Summary
PRRES20245948
Building Permit - Residential
Temporary Occupancy
NEW SINGLE FAMILY
NEW HOUSE - ROOF TRUSSES - FINISHED AND UNFINISHED BASEMENT - UNCOVERED DECK STOP WORK ORDER generated on 12/20/2024 12:00 AM by username 'Shawn Hoffman'. STOP WORK ORDER removed on 12/23/2024 12:00 AM by username 'Shawn Hoffman'.
11/13/2024
11/14/2024
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
BRUCER@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Right of Way Permit Fee $85.00 $85.00 Paid 11/14/2024
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 11/14/2024
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 11/14/2024
Water Tap Fee $3,973.00 $3,973.00 Paid 11/14/2024
Water Meter Fee $748.03 $748.03 Paid 11/14/2024
Valuation Fee New Single Family $2,043.10 $2,043.10 Paid 11/14/2024
Temporary Occupancy Fee $50.00 $50.00 Paid 05/22/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sidewalk Inspection Pending
Misc
Informational
04/24/2025
4-24-25 DP. SW is formed aggregate compacted approved to pour
Driveway Inspection Pending
Misc
Informational
04/24/2025
4-24-25 DP. DW is formed, aggregate compacted, approve to pour
Erosion Control Inspection Residential Pending
Miscellaneous Correction
Corrective Action Required
05/22/2025
- Erosion control in place at time of inspection.
Occupancy Inspection - Codes Residential Pending 6/21/2025
Misc
Corrective Action Required
05/22/2025
- Land sewer trace wire - Provide splash pads - Final grading and sod - Sump discharge to be 36” away from foundation - Driveway and sidewalk inspection pending
Erosion Control Inspection Residential Failed 12/20/2024 12/20/2024
Misc
Corrective Action Required
12/20/2024
POST ADDRESS
Piers/Caissons Inspection - Residential Passed 12/20/2024 12/20/2024
Misc
Corrective Action Required
12/20/2024
THIRD PARTY INSPECTION ON FILE
Footing Inspection - Residential Failed - Stop Work 12/20/2024 12/20/2024
Misc
Corrective Action Required
12/20/2024
FOOTING POURED WIH NO INSPECTION - POST ADDRESS
Footing Inspection - Residential Passed 12/23/2024 12/23/2024
Misc
Resolved
12/23/2024
FOOTING POURED WIH NO INSPECTION - POST ADDRESS
Misc
Corrective Action Required
12/23/2024
Third party inspection on file
Erosion Control Inspection Residential Failed 12/23/2024 12/23/2024
Misc
Corrective Action Required
12/20/2024
POST ADDRESS
Sewer Service Inspection - R Passed 1/15/2025 1/15/2025 01/15/2025
Water Service Inspection - R Passed 1/16/2025 1/16/2025 01/16/2025
Erosion Control Inspection Residential Partial 1/23/2025 01/23/2025
Misc
Corrective Action Required
01/23/2025
- Erosion control in place at time of inspection.
Underslab Plumbing Inspection - Residential Passed 1/23/2025 1/23/2025 01/23/2025
All Rough Inspection - Residential Partial 2/25/2025 2/25/2025 02/25/2025
Misc
Informational
02/25/2025
Garage portal framing only-OK
All Rough Inspection - Residential Failed 3/13/2025 3/13/2025 03/13/2025
Misc
Informational
02/25/2025
Garage portal framing only-OK
Miscellaneous Correction
Corrective Action Required
03/13/2025
- Missing nails in LIB at bedroom 5 - Fire block penetration at top of HVAC chase in pantry - Provide hanger for truss at single bay garage at I- beam - Missing truss hold downs at primary bedroom closet and upstairs laundry - Missing truss hanger laundry near toilet
Electrical Service Inspection Passed 3/13/2025 3/13/2025 03/13/2025
Erosion Control Inspection Residential Partial 3/13/2025 03/13/2025
Misc
Corrective Action Required
01/23/2025
- Erosion control in place at time of inspection.
Gas Service Inspection - Residential Passed 3/13/2025 3/13/2025 03/13/2025
All Rough Inspection - Residential Passed 3/18/2025 3/18/2025 03/18/2025
Misc
Resolved
03/18/2025
Garage portal framing only-OK
Miscellaneous Correction
Resolved
03/18/2025
- Missing nails in LIB at bedroom 5 - Fire block penetration at top of HVAC chase in pantry - Provide hanger for truss at single bay garage at I- beam - Missing truss hold downs at primary bedroom closet and upstairs laundry - Missing truss hanger laundry near toilet
Sidewalk Inspection Partial 4/24/2025 04/24/2025
Misc
Informational
04/24/2025
4-24-25 DP. SW is formed aggregate compacted approved to pour
Driveway Inspection Partial 4/24/2025 4/24/2025 04/24/2025
Misc
Informational
04/24/2025
4-24-25 DP. DW is formed, aggregate compacted, approve to pour
Erosion Control Inspection Residential Failed 5/15/2025 05/15/2025
Misc
Resolved
05/15/2025
- Erosion control in place at time of inspection.
Misc
Corrective Action Required
05/15/2025
NO EROSION CONTROL IN FRONT LOT LOT.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
05/15/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Occupancy Inspection - Codes Residential Failed 5/15/2025 5/15/2025 05/15/2025
Miscellaneous Correction
Corrective Action Required
05/15/2025
INSPECION DENIDE EROSION CONTROL AT FRONT OF LOT NOT IN COMPLIENCE
Occupancy Inspection - Codes Residential Failed 5/19/2025 5/19/2025 05/19/2025
Miscellaneous Correction
Resolved
05/19/2025
INSPECION DENIDE EROSION CONTROL AT FRONT OF LOT NOT IN COMPLIENCE
Misc
Corrective Action Required
05/19/2025
- cover attic’s access in garage - Provide handrails for basement stairs - Provide landing for back door - Provide landing for deck stairs at bottom - Open electrical box out side at A/C compressor - Land sewer trace wire - Provide splash pads - Final grading and sod - Sump discharge to be 36” away from foundation - Driveway and sidewalk inspection pending - Erosion control needs corrected
Plot Plan Inspection Passed 5/19/2025 05/19/2025
Erosion Control Inspection Residential Failed 5/19/2025 05/19/2025
Misc
Corrective Action Required
05/15/2025
NO EROSION CONTROL IN FRONT LOT LOT.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
05/15/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Partial 5/22/2025 05/22/2025
Misc
Resolved
05/22/2025
NO EROSION CONTROL IN FRONT LOT LOT.
DCM3 ESC REQUIRED 2 DAY
Resolved
05/22/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Miscellaneous Correction
Corrective Action Required
05/22/2025
- Erosion control in place at time of inspection.
Occupancy Inspection - Codes Residential Ready for Temp CO 5/22/2025 5/22/2025 05/22/2025
Misc
Corrective Action Required
05/19/2025
- Land sewer trace wire - Provide splash pads - Final grading and sod - Sump discharge to be 36” away from foundation - Driveway and sidewalk inspection pending
Documents & Images
Date Uploaded File Type Document Name
11/13/2024 Application Form HM #204 - PERMIT APP
11/14/2024 Approved Plans APPROVED PLANS
11/14/2024 Plot Plan APPROVED PLOT PLAN
11/14/2024 Approved Plans APPROVED TRUSS LAYOUT
11/14/2024 Approved Plans APPROVED TRUSS PACKAGE
11/14/2024 Permit Codes Residential Plan Review
11/14/2024 Receipt Receipt for transaction:2024-008968
12/20/2024 204 Highland Meadows - Drilled Pier INSP-signed-stamped
12/20/2024 Letter INSPECTION SUMMARY
12/20/2024 Letter INSPECTION SUMMARY
12/23/2024 3RD Party Insp Report M L Crose 1071 Fiord Dr LSMO Footing Inspection Report 12-20-24
12/23/2024 Letter INSPECTION SUMMARY
12/23/2024 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
01/15/2025 Letter Stop Work Order
01/16/2025 Letter INSPECTION SUMMARY
01/23/2025 Letter INSPECTION SUMMARY
01/23/2025 Letter INSPECTION SUMMARY
02/25/2025 Letter INSPECTION SUMMARY
03/05/2025 Engineer Report/Study HM 204 - Alternate HDR Letter
03/12/2025 Engineer Report/Study HM204 truss repair
03/13/2025 Letter INSPECTION SUMMARY
03/13/2025 Letter INSPECTION SUMMARY
03/13/2025 Letter INSPECTION SUMMARY
03/13/2025 Letter INSPECTION SUMMARY
03/18/2025 Letter INSPECTION SUMMARY
04/24/2025 Letter INSPECTION SUMMARY
04/24/2025 Letter INSPECTION SUMMARY
05/15/2025 Letter INSPECTION SUMMARY
05/19/2025 Letter INSPECTION SUMMARY
05/19/2025 Letter INSPECTION SUMMARY
05/19/2025 Letter INSPECTION SUMMARY
05/19/2025 Letter INSPECTION SUMMARY
05/20/2025 Letter DS Building Permit
05/22/2025 Letter INSPECTION SUMMARY
05/22/2025 Letter INSPECTION SUMMARY
05/22/2025 Certificate/License Codes Temporary Certificate of Occupancy
05/22/2025 Receipt Receipt for transaction:2025-003721
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home