Permit Application Status

PRRES20243237


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20243237
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - ROOF TRUSSES
06/24/2024
06/27/2024
04/09/2025
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
BRUCER@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $2,159.00 $2,159.00 Paid 06/27/2024
Right of Way Permit Fee $85.00 $85.00 Paid 06/27/2024
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 06/27/2024
Water Tap Fee $3,760.00 $3,760.00 Paid 06/27/2024
Water Meter Fee $680.46 $680.46 Paid 06/27/2024
Valuation Fee New Single Family $1,743.63 $1,743.63 Paid 06/27/2024
Not Ready Inspection Fee $75.00 $75.00 Paid 12/04/2024
Not Ready Inspection Fee $75.00 $75.00 Paid 12/04/2024
Not Ready Inspection Fee $75.00 $75.00 Paid 12/04/2024
3rd and Subsequent Inspection Fee (Per Hour) $75.00 $75.00 Paid 12/04/2024
3rd and Subsequent Inspection Fee (Per Hour) $75.00 $75.00 Paid 12/04/2024
Temporary Occupancy Fee $50.00 $50.00 Paid 01/07/2025
Temporary Occupancy Fee $50.00 $50.00 Paid 01/07/2025
Temporary Occupancy Fee $50.00 $50.00 Paid 01/30/2025
Temporary Occupancy Fee $50.00 $50.00 Paid 02/24/2025
Temporary Occupancy Fee $50.00 $50.00 Paid 03/19/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Partial 7/5/2024 07/05/2024
Miscellaneous Correction
Informational
07/05/2024
Erosion control measures are in place and needs to be maintained until CofO
Footing Inspection - Residential Passed 7/5/2024 07/05/2024
Miscellaneous Correction
Informational
07/05/2024
Footing was passed by a third party. Piers were not mentioned in the footing report
Sewer Service Inspection - R Passed 7/11/2024 07/11/2024
Water Service Inspection - R Partial 7/11/2024 07/11/2024
Miscellaneous Correction
Informational
07/11/2024
PEX pipe ran out 20 feet from foundation Okay to cover This is a partial pass only
Erosion Control Inspection Residential Partial 7/11/2024 07/11/2024
Miscellaneous Correction
Resolved
07/11/2024
Erosion control measures are in place and needs to be maintained until CofO
Miscellaneous Correction
Informational
07/11/2024
Erosion control measures are in place and needs to be maintained until CofO
Water Service Inspection - R Passed 7/12/2024 07/12/2024
Miscellaneous Correction
Resolved
07/12/2024
PEX pipe ran out 20 feet from foundation Okay to cover This is a partial pass only
Underslab Plumbing Inspection - Residential Passed 7/23/2024 7/23/2024 07/23/2024
Erosion Control Inspection Residential Partial 7/23/2024 07/23/2024
Miscellaneous Correction
Informational
07/11/2024
Erosion control measures are in place and needs to be maintained until CofO
Misc
Informational
07/23/2024
Erosion control measures are in place and needs to be maintained until CofO
Erosion Control Inspection Residential Partial 8/13/2024 08/13/2024
Miscellaneous Correction
Resolved
08/13/2024
Erosion control measures are in place and needs to be maintained until CofO
Misc
Resolved
08/13/2024
Erosion control measures are in place and needs to be maintained until CofO
Miscellaneous Correction
Informational
08/13/2024
Full erosion control measures are in place and must be maintained until CofO
Erosion Control Inspection Residential Partial 9/11/2024 09/11/2024
Miscellaneous Correction
Informational
08/13/2024
Full erosion control measures are in place and must be maintained until CofO
Erosion Control Inspection Residential Partial 9/25/2024 09/25/2024
Miscellaneous Correction
Informational
09/11/2024
Full erosion control measures are in place and must be maintained until CofO
Miscellaneous Inspection Passed 9/25/2024 09/25/2024
Miscellaneous Correction
Informational
09/25/2024
Talked to the on site superintendent about portal inspections
All Rough Inspection - Residential Failed 9/27/2024 9/27/2024 09/27/2024
Miscellaneous Correction
Informational
09/27/2024
Exterior garage portal sheeting passed only. Okay to cover exterior garage sheeting only This is a partial pass only
Erosion Control Inspection Residential Partial 9/27/2024 09/27/2024
Miscellaneous Correction
Informational
09/25/2024
Full erosion control measures are in place and must be maintained until CofO
Electrical Service Inspection Failed 10/21/2024 10/21/2024
Miscellaneous Correction
Corrective Action Required
10/21/2024
Attach electrical above panel to code
Electrical Service Inspection Passed 10/21/2024 10/21/2024
Miscellaneous Correction
Resolved
10/21/2024
Attach electrical above panel to code
All Rough Inspection - Residential Not Ready 10/21/2024 10/21/2024 10/21/2024
Miscellaneous Correction
Informational
09/27/2024
Exterior garage portal sheeting passed only. Okay to cover exterior garage sheeting only This is a partial pass only
Miscellaneous Correction
Corrective Action Required
10/21/2024
Gas service lines are not installed Trash and debris need to be cleaned up as they are a hazard to walk around House is not ready for inspection
All Rough Inspection - Residential Not Ready 10/24/2024 10/24/2024 10/24/2024
Miscellaneous Correction
Informational
10/21/2024
Exterior garage portal sheeting passed only. Okay to cover exterior garage sheeting only This is a partial pass only
Miscellaneous Correction
Resolved
10/24/2024
Gas service lines are not installed Trash and debris need to be cleaned up as they are a hazard to walk around House is not ready for inspection
Miscellaneous Correction
Corrective Action Required
10/24/2024
3812 SW Ravengate. All rough •Garage anchor bolts are not PFH approved •Garage anchor bolts need to be in the middle 1/3 of sole plate •Garage jack stud at overhead header needs a electrical nail guard S/W corner •Garage jack studs at N/W corner are over cut •Garage trusses above overhead door do not have truss hangers installed •Truss tie down screw is missing in truss above garage overhead door •Nail garage upper S/W corner to code •Nail garage upper N/W corner to code •Garage walls are missing 2 2x6 and 3 2x4 king studs •Garage LIB is not installed to length •Top of garage chase needs fire blocking to be tightly packed •Fire block horizontal furr down in powder bathroom and pantry House is not ready for inspection Framer is still working inside This is not a complete list
Erosion Control Inspection Residential Partial 10/24/2024 10/24/2024
Miscellaneous Correction
Informational
09/27/2024
Full erosion control measures are in place and must be maintained until CofO
Erosion Control Inspection Residential Failed 10/25/2024 10/25/2024
Miscellaneous Correction
Resolved
10/25/2024
Full erosion control measures are in place and must be maintained until CofO
Miscellaneous Correction
Corrective Action Required
10/25/2024
Replace missing erosion control at the front of the property Full erosion control measures must be in place and properly maintained until CofO
All Rough Inspection - Residential Not Ready 10/25/2024 10/25/2024 10/25/2024
Miscellaneous Correction
Informational
10/24/2024
Exterior garage portal sheeting passed only. Okay to cover exterior garage sheeting only This is a partial pass only
Miscellaneous Correction
Resolved
10/25/2024
3812 SW Ravengate. All rough •Garage anchor bolts are not PFH approved •Garage anchor bolts need to be in the middle 1/3 of sole plate •Garage jack stud at overhead header needs a electrical nail guard S/W corner •Garage jack studs at N/W corner are over cut •Garage trusses above overhead door do not have truss hangers installed •Truss tie down screw is missing in truss above garage overhead door •Nail garage upper S/W corner to code •Nail garage upper N/W corner to code •Garage walls are missing 2 2x6 and 3 2x4 king studs •Garage LIB is not installed to length •Top of garage chase needs fire blocking to be tightly packed •Fire block horizontal furr down in powder bathroom and pantry House is not ready for inspection Framer is still working inside This is not a complete list
Miscellaneous Correction
Corrective Action Required
10/25/2024
3812 SW Ravengate. All rough (2) •Garage anchor bolts are not PFH approved •Garage anchor bolts need to be in the middle 1/3 of sole plate •Garage jack stud at overhead header needs a electrical nail guard S/W corner •Garage jack studs at N/W corner are over cut •Garage trusses above overhead door do not have truss hangers installed •Truss tie down screw is missing in truss above garage overhead door •Nail garage upper S/W corner to code •Nail garage upper N/W corner to code •Garage walls are missing 2 2x6 and 3 2x4 king studs •Garage LIB is not installed to length •Top of garage chase needs fire blocking to be tightly packed •Fire block horizontal furr down in powder bathroom and pantry •Electrical nail guard is needed in powder bathroom south wall •Nail corner of pantry to code •Nail is missing in joist hanger at Ibeam between kitchen/great room •Straighten joist hanger nail at I beam between kitchen/great room •Nail great room corner to code •Nail great room and patio headers to king studs •Nail entry header to window 2x6 above window header •Nails missing in joist hangers in foyer area •Roof jacket is not installed for plumbing above bedroom 2 •Roof jacket is not installed for plumbing above learning lounge •Fire block top of chase upstairs above HVAC •LGT2 brackets are not installed •Tightly install fire blocking at top plate in chase of primary bathroom •Nail all headers to king studs to code throughout •Provide blocking for snow flashing at gable ends •Inside corners of primary bedroom at the windows are not properly tied in at the top plate List is not complete Walk your property before scheduling any more inspections House is not ready for inspection KBEARD 10/25/24
Gas Service Inspection - Residential Failed 10/28/2024 10/28/2024
Miscellaneous Correction
Corrective Action Required
10/28/2024
Gas pressure is below 10 PSI at the time of inspection
Erosion Control Inspection Residential Partial 10/28/2024 10/28/2024
Miscellaneous Correction
Resolved
10/28/2024
Replace missing erosion control at the front of the property Full erosion control measures must be in place and properly maintained until CofO
Miscellaneous Correction
Informational
10/28/2024
Full erosion control measures must be in place and properly maintained until CofO
All Rough Inspection - Residential Failed 10/28/2024 10/28/2024 10/28/2024
Miscellaneous Correction
Informational
10/25/2024
Exterior garage portal sheeting passed only. Okay to cover exterior garage sheeting only This is a partial pass only
Miscellaneous Correction
Resolved
10/28/2024
3812 SW Ravengate. All rough (2) •Garage anchor bolts are not PFH approved •Garage anchor bolts need to be in the middle 1/3 of sole plate •Garage jack stud at overhead header needs a electrical nail guard S/W corner •Garage jack studs at N/W corner are over cut •Garage trusses above overhead door do not have truss hangers installed •Truss tie down screw is missing in truss above garage overhead door •Nail garage upper S/W corner to code •Nail garage upper N/W corner to code •Garage walls are missing 2 2x6 and 3 2x4 king studs •Garage LIB is not installed to length •Top of garage chase needs fire blocking to be tightly packed •Fire block horizontal furr down in powder bathroom and pantry •Electrical nail guard is needed in powder bathroom south wall •Nail corner of pantry to code •Nail is missing in joist hanger at Ibeam between kitchen/great room •Straighten joist hanger nail at I beam between kitchen/great room •Nail great room corner to code •Nail great room and patio headers to king studs •Nail entry header to window 2x6 above window header •Nails missing in joist hangers in foyer area •Roof jacket is not installed for plumbing above bedroom 2 •Roof jacket is not installed for plumbing above learning lounge •Fire block top of chase upstairs above HVAC •LGT2 brackets are not installed •Tightly install fire blocking at top plate in chase of primary bathroom •Nail all headers to king studs to code throughout •Provide blocking for snow flashing at gable ends •Inside corners of primary bedroom at the windows are not properly tied in at the top plate List is not complete Walk your property before scheduling any more inspections House is not ready for inspection KBEARD 10/25/24
Miscellaneous Correction
Corrective Action Required
10/28/2024
3812 SW Ravengate. All rough (3) •Garage anchor bolts are not PFH approved •Garage anchor bolts need to be in the middle 1/3 of sole plate •Garage jack stud at overhead header needs a electrical nail guard S/W corner •Garage jack studs at N/W corner are over cut •Garage trusses above overhead door do not have truss hangers installed •Truss tie down screw is missing in truss above garage overhead door •Nail garage upper S/W corner to code •Nail garage upper N/W corner to code •Garage walls are missing 2 2x6 and 3 2x4 king studs •Garage LIB is not installed to length •Top of garage chase needs fire blocking to be tightly packed •Fire block horizontal furr down in powder bathroom and pantry •Electrical nail guard is needed in powder bathroom south wall •Nail corner of pantry to code •Nail is missing in joist hanger at Ibeam between kitchen/great room •Straighten joist hanger nail at I beam between kitchen/great room •Nail great room corner to code •Nail great room and patio headers to king studs •Nail entry header to window 2x6 above window header •Nails missing in joist hangers in foyer area •Roof jacket is not installed for plumbing above bedroom 2 •Roof jacket is not installed for plumbing above learning lounge •Fire block top of chase upstairs above HVAC •LGT2 brackets are not installed •Tightly install fire blocking at top plate in chase of primary bathroom •Nail all headers to king studs to code throughout •Provide blocking for snow flashing at gable ends •Inside corners of primary bedroom at the windows are not properly tied in at the top plate •Front porch soffit is installed and joist hold downs can not be inspected •Stair stringer beam going up from the main floor to upstairs is not supported by 1 1/2 inches on the 2x10 floor platform •HDU14-SDS2.5 does not hold down the 2x6 bottom plate of the first floor •Top of the bottom set of stair stringer beams do not bear 1 1/2 inches against the 2x10 platform •Joist hangers are not installed in the basement above the stairs for 2x10 floor •Basement wall at the stairs, needs to be vertically fire blocked at 10 feet on center •Basement stair platform needs to be vertically supported under 2x10 platform joist •Nails are missing for double 2x10 beam under basement stairs •Joists above electrical panel has holes drilled closer than 2 inches together •Joist hangers are not installed at blocked out floor joist 2x10’s above basement window •Secure all electrical from sagging to code 334.30 throughout the basement Truss diagram plans are not located in the structure This is not a complete list KBEARD 10/28/24
Erosion Control Inspection Residential Failed 11/1/2024 11/01/2024
Miscellaneous Correction
Resolved
11/01/2024
Full erosion control measures must be in place and properly maintained until CofO
Miscellaneous Correction
Corrective Action Required
11/01/2024
Spread gravel in driveway for proper erosion control Full erosion control measures must be in place and properly maintained until CofO
Erosion Control Inspection Residential Failed 11/1/2024 11/1/2024 11/01/2024
Miscellaneous Correction
Corrective Action Required
11/01/2024
Spread gravel in driveway for proper erosion control Full erosion control measures must be in place and properly maintained until CofO
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
11/01/2024
11-1-24 Dustin A, Clean road of gravel and mud. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Gas Service Inspection - Residential Passed 11/4/2024 11/04/2024
Miscellaneous Correction
Resolved
11/04/2024
Gas pressure is below 10 PSI at the time of inspection
All Rough Inspection - Residential Failed 11/4/2024 11/4/2024 11/04/2024
Miscellaneous Correction
Resolved
11/04/2024
Exterior garage portal sheeting passed only. Okay to cover exterior garage sheeting only This is a partial pass only
Miscellaneous Correction
Resolved
11/04/2024
3812 SW Ravengate. All rough (3) •Garage anchor bolts are not PFH approved •Garage anchor bolts need to be in the middle 1/3 of sole plate •Garage jack stud at overhead header needs a electrical nail guard S/W corner •Garage jack studs at N/W corner are over cut •Garage trusses above overhead door do not have truss hangers installed •Truss tie down screw is missing in truss above garage overhead door •Nail garage upper S/W corner to code •Nail garage upper N/W corner to code •Garage walls are missing 2 2x6 and 3 2x4 king studs •Garage LIB is not installed to length •Top of garage chase needs fire blocking to be tightly packed •Fire block horizontal furr down in powder bathroom and pantry •Electrical nail guard is needed in powder bathroom south wall •Nail corner of pantry to code •Nail is missing in joist hanger at Ibeam between kitchen/great room •Straighten joist hanger nail at I beam between kitchen/great room •Nail great room corner to code •Nail great room and patio headers to king studs •Nail entry header to window 2x6 above window header •Nails missing in joist hangers in foyer area •Roof jacket is not installed for plumbing above bedroom 2 •Roof jacket is not installed for plumbing above learning lounge •Fire block top of chase upstairs above HVAC •LGT2 brackets are not installed •Tightly install fire blocking at top plate in chase of primary bathroom •Nail all headers to king studs to code throughout •Provide blocking for snow flashing at gable ends •Inside corners of primary bedroom at the windows are not properly tied in at the top plate •Front porch soffit is installed and joist hold downs can not be inspected •Stair stringer beam going up from the main floor to upstairs is not supported by 1 1/2 inches on the 2x10 floor platform •HDU14-SDS2.5 does not hold down the 2x6 bottom plate of the first floor •Top of the bottom set of stair stringer beams do not bear 1 1/2 inches against the 2x10 platform •Joist hangers are not installed in the basement above the stairs for 2x10 floor •Basement wall at the stairs, needs to be vertically fire blocked at 10 feet on center •Basement stair platform needs to be vertically supported under 2x10 platform joist •Nails are missing for double 2x10 beam under basement stairs •Joists above electrical panel has holes drilled closer than 2 inches together •Joist hangers are not installed at blocked out floor joist 2x10’s above basement window •Secure all electrical from sagging to code 334.30 throughout the basement Truss diagram plans are not located in the structure This is not a complete list KBEARD 10/28/24
Miscellaneous Correction
Corrective Action Required
11/04/2024
3812 SW Ravengate. All rough (4) Garage anchor bolts need to be in the middle 1/3 of sole plate Garage jack stud at overhead garage door header needs a electrical nail guard S/W corner Garage jack studs at N/W corner are over cut at electrical Truss tie down screw is missing in truss above garage overhead door Garage walls are missing 2 2x6 and 3 2x4 king studs Garage LIB is not installed to length Electrical nail guard is needed in powder bathroom south wall Nail great room SW corner to code Nail great room and patio headers to king studs Fire block top of chase upstairs above HVAC (new fire blocking must be 3/4 of an inch or more) LGT2 brackets are not installed Provide blocking for snow flashing at gable ends Inside corners of primary bedroom by the windows are not properly tied in at the top plate Front porch soffit is installed and joist hold downs can not be inspected (reinstall crooked joist hanger as per manufacturers recommendation) HDU14-SDS2.5 does not hold down the 2x6 bottom plate of the first floor Joist hangers are not installed in the basement above the stairs for 2x10 floor ( straighten out bent over nails at installed joist hanger) Basement wall at the stairs, needs to be vertically fire blocked at 10 feet on center
Erosion Control Inspection Residential Partial 11/5/2024 11/5/2024 11/05/2024
Miscellaneous Correction
Corrective Action Required
11/01/2024
Spread gravel in driveway for proper erosion control Full erosion control measures must be in place and properly maintained until CofO
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
11/01/2024
11-1-24 Dustin A, Clean road of gravel and mud. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 11-5-24 Dustin A. road cleaned
All Rough Inspection - Residential Failed 11/8/2024 11/8/2024 11/08/2024
Miscellaneous Correction
Resolved
11/08/2024
3812 SW Ravengate. All rough (4) Garage anchor bolts need to be in the middle 1/3 of sole plate Garage jack stud at overhead garage door header needs a electrical nail guard S/W corner Garage jack studs at N/W corner are over cut at electrical Truss tie down screw is missing in truss above garage overhead door Garage walls are missing 2 2x6 and 3 2x4 king studs Garage LIB is not installed to length Electrical nail guard is needed in powder bathroom south wall Nail great room SW corner to code Nail great room and patio headers to king studs Fire block top of chase upstairs above HVAC (new fire blocking must be 3/4 of an inch or more) LGT2 brackets are not installed Provide blocking for snow flashing at gable ends Inside corners of primary bedroom by the windows are not properly tied in at the top plate Front porch soffit is installed and joist hold downs can not be inspected (reinstall crooked joist hanger as per manufacturers recommendation) HDU14-SDS2.5 does not hold down the 2x6 bottom plate of the first floor Joist hangers are not installed in the basement above the stairs for 2x10 floor ( straighten out bent over nails at installed joist hanger) Basement wall at the stairs, needs to be vertically fire blocked at 10 feet on center
Miscellaneous Correction
Corrective Action Required
11/08/2024
3812 SW Ravengate. All rough (5) Garage anchor bolts need to be in the middle 1/3 of sole plate Garage jack stud at overhead garage door header needs a electrical nail guard S/W corner Garage jack studs at N/W corner are over cut at electrical Garage walls are missing 2 2x6 and 3 2x4 king studs Garage LIB is not installed to length Electrical nail guard is needed in powder bathroom south wall Fire block top of chase upstairs above HVAC (new fire blocking must be 3/4 of an inch or more) Provide blocking for snow flashing at gable ends Joist hangers are not installed in the basement above the stairs for 2x10 floor ( straighten out bent over nails at installed joist hanger) Basement wall at the stairs, needs to be vertically fire blocked at 10 feet on center
Driveway Inspection Partial 11/12/2024 11/12/2024
Misc
Informational
11/12/2024
11-12-24 Dustin A. Dw is formed and compacted. Approved to pour.
Sidewalk Inspection Partial 11/12/2024 11/12/2024
Misc
Informational
11/12/2024
11-12-24 Dustin A, Sw is formed and compacted. Slopes are in compliance. Approved to pour.
All Rough Inspection - Residential Failed 11/12/2024 11/12/2024 11/12/2024
Miscellaneous Correction
Corrective Action Required
11/08/2024
3812 SW Ravengate. All rough (5) Garage anchor bolts need to be in the middle 1/3 of sole plate Garage jack stud at overhead garage door header needs a electrical nail guard S/W corner Garage jack studs at N/W corner are over cut at electrical Garage walls are missing 2 2x6 and 3 2x4 king studs Garage LIB is not installed to length Electrical nail guard is needed in powder bathroom south wall Fire block top of chase upstairs above HVAC (new fire blocking must be 3/4 of an inch or more) Provide blocking for snow flashing at gable ends Joist hangers are not installed in the basement above the stairs for 2x10 floor ( straighten out bent over nails at installed joist hanger) Basement wall at the stairs, needs to be vertically fire blocked at 10 feet on center No access provided. Concrete was poured and still wet
All Rough Inspection - Residential Passed 11/13/2024 11/13/2024 11/13/2024
Miscellaneous Correction
Resolved
11/13/2024
3812 SW Ravengate. All rough (5) Garage anchor bolts need to be in the middle 1/3 of sole plate Garage jack stud at overhead garage door header needs a electrical nail guard S/W corner Garage jack studs at N/W corner are over cut at electrical Garage walls are missing 2 2x6 and 3 2x4 king studs Garage LIB is not installed to length Electrical nail guard is needed in powder bathroom south wall Fire block top of chase upstairs above HVAC (new fire blocking must be 3/4 of an inch or more) Provide blocking for snow flashing at gable ends Joist hangers are not installed in the basement above the stairs for 2x10 floor ( straighten out bent over nails at installed joist hanger) Basement wall at the stairs, needs to be vertically fire blocked at 10 feet on center No access provided. Concrete was poured and still wet
Driveway Inspection Partial 11/19/2024 11/19/2024 11/19/2024
Misc
Informational
11/12/2024
11-12-24 Dustin A. Dw is formed and compacted. Approved to pour. 11-19-24 Dustin A, DW is poured to city specs. Slopes are in compliance. Cannot pass until forms pulled
Sidewalk Inspection Partial 11/19/2024 11/19/2024 11/19/2024
Misc
Informational
11/12/2024
11-12-24 Dustin A, Sw is formed and compacted. Slopes are in compliance. Approved to pour. 11-19-24 Dustin A, Sw is poured to city specs. Slopes are in compliance. Cannot pass until forms are pulled
Erosion Control Inspection Residential Failed 12/31/2024 12/31/2024
Miscellaneous Correction
Resolved
12/31/2024
Spread gravel in driveway for proper erosion control Full erosion control measures must be in place and properly maintained until CofO
DCM3 ESC REQUIRED 2 DAY
Resolved
12/31/2024
11-1-24 Dustin A, Clean road of gravel and mud. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 11-5-24 Dustin A. road cleaned
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
12/31/2024
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE. -Erosion control measures are not in place at the time of inspection -Install full erosion control before scheduling any inspections -Remove all trash from the lot
Occupancy Inspection - Codes Residential Failed 12/31/2024 12/31/2024 12/31/2024
Miscellaneous Correction
Corrective Action Required
12/31/2024
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE. -Erosion control measures are not in place at the time of inspection -Install full erosion control before scheduling any inspections -Remove all trash from the lot Occupancy inspection denied until erosion control inspection passes 12/31/2024. KBEARD 9:00am Letter sent to brucer@summithomeskc.com
Driveway Inspection Passed 01/03/2025
Misc
Informational
11/19/2024
11-12-24 Dustin A. Dw is formed and compacted. Approved to pour. 11-19-24 Dustin A, DW is poured to city specs. Slopes are in compliance. Cannot pass until forms pulled 1-3-24 Dustin A, forms pulled . Passed
Plot Plan Inspection Failed 1/3/2025 01/03/2025
Miscellaneous Correction
Corrective Action Required
01/03/2025
Plot has been graded but an as graded plot plan is required before sodding
Erosion Control Inspection Residential Partial 1/3/2025 1/3/2025 01/03/2025
DCM1 ESC REQUIRED NO FURTHER INSP
Resolved
01/03/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE. -Erosion control measures are not in place at the time of inspection -Install full erosion control before scheduling any inspections -Remove all trash from the lot
Miscellaneous Correction
Informational
01/03/2025
Erosion control measures are in place at the time of inspection
Occupancy Inspection - Codes Residential Ready for Temp CO 1/3/2025 1/3/2025 01/07/2025
Miscellaneous Correction
Resolved
01/03/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE. -Erosion control measures are not in place at the time of inspection -Install full erosion control before scheduling any inspections -Remove all trash from the lot Occupancy inspection denied until erosion control inspection passes 12/31/2024. KBEARD 9:00am Letter sent to brucer@summithomeskc.com
Miscellaneous Correction
Partial Correction
01/07/2025
3812 SW Ravengate Occupancy Exterior garage lights are not installed Front porch steps have a greater than 3/8 of an inch in riser height difference Front porch guard rail has more than the code allowance of 4 inches from the porch surface to the bottom of the guard rail Return air grill in hallway is missing Garage to house self closing door is not functioning correctly Garage to house steps are missing a grip able handrail Air vent grill is missing upstairs in the common area Vent pipe for Heater condensation line is leaking in the basement Sod and splash pads are not installed A/C anti siphon valves are not installed As graded plot plan is not uploaded Sidewalk final needs to pass
Miscellaneous Correction
Corrective Action Required
01/07/2025
- Exterior garage lights are not installed - Front porch steps have a greater than 3/8 of an inch in riser height difference -Front porch guard rail has more than the code allowance of 4 inches from the porch surface to the bottom of the guard rail -Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass
Occupancy Inspection - Codes Residential Ready for Temp CO 1/7/2025 1/7/2025 01/07/2025
Miscellaneous Correction
Resolved
01/13/2025
3812 SW Ravengate Occupancy - Exterior garage lights are not installed - Front porch steps have a greater than 3/8 of an inch in riser height difference -Front porch guard rail has more than the code allowance of 4 inches from the porch surface to the bottom of the guard rail -Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass
Miscellaneous Correction
Corrective Action Required
01/13/2025
- Exterior garage lights are not installed - Front porch steps have a greater than 3/8 of an inch in riser height difference -Front porch guard rail has more than the code allowance of 4 inches from the porch surface to the bottom of the guard rail -Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass
Occupancy Inspection - Codes Residential Failed 1/13/2025 01/13/2025
Miscellaneous Correction
Corrective Action Required
01/07/2025
3812 SW Ravengate Occupancy
Occupancy Inspection - Codes Residential Failed 2/3/2025 01/14/2025
Miscellaneous Correction
Corrective Action Required
01/13/2025
- Exterior garage lights are not installed - Front porch steps have a greater than 3/8 of an inch in riser height difference -Front porch guard rail has more than the code allowance of 4 inches from the porch surface to the bottom of the guard rail -Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass
Occupancy Inspection - Codes Residential Ready for Temp CO 1/30/2025 01/30/2025
Miscellaneous Correction
Resolved
01/30/2025
- Exterior garage lights are not installed - Front porch steps have a greater than 3/8 of an inch in riser height difference -Front porch guard rail has more than the code allowance of 4 inches from the porch surface to the bottom of the guard rail -Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass
Miscellaneous Correction
Corrective Action Required
01/30/2025
-Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass TCO extension request sent in by builder
Erosion Control Inspection Residential Partial 1/30/2025 01/30/2025
Miscellaneous Correction
Informational
01/03/2025
Erosion control measures are in place at the time of inspection
Occupancy Inspection - Codes Residential Ready for Temp CO 2/24/2025 02/24/2025
Miscellaneous Correction
Resolved
02/24/2025
-Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass TCO extension request sent in by builder
Miscellaneous Correction
Corrective Action Required
02/24/2025
-Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass TCO extension request sent in by builder
Erosion Control Inspection Residential Partial 2/24/2025 02/24/2025
Miscellaneous Correction
Informational
01/30/2025
Erosion control measures are in place at the time of inspection
Occupancy Inspection - Codes Residential Ready for Temp CO 3/19/2025 03/19/2025
Miscellaneous Correction
Corrective Action Required
02/24/2025
-Sod and splash pads are not installed -A/C anti siphon valves are not installed -As graded plot plan is not uploaded -Sidewalk final needs to pass TCO extension request sent in by builder TCO extension approved for 30days MARK HARDING 03/19/2025 9:17 AM
Occupancy Inspection - Codes Residential Failed 3/26/2025 3/26/2025 03/26/2025
Miscellaneous Correction
Corrective Action Required
03/19/2025
-As graded plot plan is not uploaded -Sidewalk final needs to pass TCO extension request sent in by builder TCO extension approved for 30days MARK HARDING 03/19/2025 9:17 AM
Plot Plan Inspection Failed 3/27/2025 03/27/2025
Miscellaneous Correction
Corrective Action Required
01/03/2025
Plot has been graded but an as graded plot plan is required before sodding
Misc
Corrective Action Required
03/27/2025
A NEW AS GRADED PLOT PLAN REQUIRED THE ONR UPLOADED IS FROM 5/24
Sidewalk Inspection Passed 3/27/2025 03/27/2025
Misc
Informational
11/19/2024
11-12-24 Dustin A, Sw is formed and compacted. Slopes are in compliance. Approved to pour. 11-19-24 Dustin A, Sw is poured to city specs. Slopes are in compliance. Cannot pass until forms are pulled 3-27-25 Dustin A, forms pulled passed
Erosion Control Inspection Residential Passed 4/9/2025 04/09/2025
Miscellaneous Correction
Resolved
04/09/2025
Erosion control measures are in place at the time of inspection
Plot Plan Inspection Passed 4/9/2025 04/09/2025
Miscellaneous Correction
Resolved
04/09/2025
Plot has been graded but an as graded plot plan is required before sodding
Misc
Resolved
04/09/2025
A NEW AS GRADED PLOT PLAN REQUIRED THE ONR UPLOADED IS FROM 5/24
Occupancy Inspection - Codes Residential Full C of O 4/9/2025 4/9/2025 04/09/2025
Miscellaneous Correction
Resolved
04/09/2025
-As graded plot plan is not uploaded -Sidewalk final needs to pass TCO extension request sent in by builder TCO extension approved for 30days MARK HARDING 03/19/2025 9:17 AM
Documents & Images
Date Uploaded File Type Document Name
06/24/2024 OS #62 - PERMIT APP
06/27/2024 Approved Plans APPROVED PLANS
06/27/2024 Plot Plan APPROVED PLOT PLAN
06/27/2024 Approved Plans APPROVED TRUSS LAYOUT
06/27/2024 Approved Plans APPROVED TRUSS PACKAGE
06/27/2024 Permit Codes Residential Plan Review
06/27/2024 Permit DS Building Permit
06/27/2024 Receipt Receipt for transaction:2024-005245
07/04/2024 3RD Party Insp Report 3rd Party Footing Inspection Report 7-3-24
07/05/2024 Letter INSPECTION SUMMARY
07/05/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/12/2024 Letter INSPECTION SUMMARY
07/23/2024 Letter INSPECTION SUMMARY
07/23/2024 Letter INSPECTION SUMMARY
08/13/2024 Letter INSPECTION SUMMARY
09/11/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
10/21/2024 Letter INSPECTION SUMMARY
10/21/2024 Letter INSPECTION SUMMARY
10/21/2024 Letter INSPECTION SUMMARY
10/24/2024 Letter INSPECTION SUMMARY
10/24/2024 Letter INSPECTION SUMMARY
10/24/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/28/2024 Letter INSPECTION SUMMARY
10/28/2024 Letter INSPECTION SUMMARY
10/28/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/04/2024 Letter INSPECTION SUMMARY
11/04/2024 Letter INSPECTION SUMMARY
11/05/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
11/12/2024 Letter INSPECTION SUMMARY
11/12/2024 Letter INSPECTION SUMMARY
11/12/2024 Letter INSPECTION SUMMARY
11/13/2024 Letter INSPECTION SUMMARY
11/19/2024 Letter INSPECTION SUMMARY
11/19/2024 Letter INSPECTION SUMMARY
12/04/2024 Receipt Receipt for transaction:2024-009325
12/31/2024 Letter INSPECTION SUMMARY
12/31/2024 Letter INSPECTION SUMMARY
01/03/2025 Letter INSPECTION SUMMARY
01/03/2025 Letter INSPECTION SUMMARY
01/03/2025 Letter INSPECTION SUMMARY
01/03/2025 Letter INSPECTION SUMMARY
01/03/2025 Letter INSPECTION SUMMARY
01/07/2025 Letter INSPECTION SUMMARY
01/07/2025 Letter INSPECTION SUMMARY
01/07/2025 Certificate/License Codes Temporary Certificate of Occupancy
01/07/2025 Certificate/License Codes Temporary Certificate of Occupancy
01/07/2025 Receipt Receipt for transaction:2025-000067
01/13/2025 Letter INSPECTION SUMMARY
01/14/2025 Letter INSPECTION SUMMARY
01/29/2025 Application Form TCO EXTENSION APPLICATION
01/30/2025 Letter INSPECTION SUMMARY
01/30/2025 Letter INSPECTION SUMMARY
01/30/2025 Certificate/License Codes Temporary Certificate of Occupancy
01/30/2025 Receipt Receipt for transaction:2025-000587
02/19/2025 OS #62 - TCO Extension 2_19_25
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Certificate/License Codes Temporary Certificate of Occupancy
02/24/2025 Receipt Receipt for transaction:2025-001057
03/19/2025 OS #62 - TCO Extension 3_19_25
03/19/2025 Certificate/License Codes Temporary Certificate of Occupancy
03/19/2025 Receipt Receipt for transaction:2025-001651
03/26/2025 Letter INSPECTION SUMMARY
03/26/2025 Plot Plan APPROVED AS GRADED PLOT PLAN
03/27/2025 Letter INSPECTION SUMMARY
03/27/2025 Letter INSPECTION SUMMARY
04/09/2025 Letter INSPECTION SUMMARY
04/09/2025 Letter Codes Final Certificate of Occupancy
04/09/2025 Letter Field Certificate of Occupancy
04/09/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home