Permit Application Status

PRRES20201648


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20201648
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - PARTIAL FINISHED BASEMENT - COVERED PATIO
06/18/2020
06/30/2020
12/28/2020
Locations
Contacts
SAB CONSTRUCTION INC, Address:PO BOX 942, Phone:(816) 524-3855  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
C-R ELECTRICAL LLC, Address:4539 RIDGEWAY, Phone:(816) 803-3500  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
JIM@SABHOMES.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Residential Plan Review Approved 06/22/2020 06/26/2020
Kim Brennan
05 Provide square footage of living area, garage area, unfinished basement
Corrective Action Required
06/18/2020

Provide square footage of living area, garage area, unfinished basement area, etc (IRC Section R304) Please provide total square footage for both garages and square footage for the finished and unfinished basement
21 Foundation wall thickness and height and reinforcement.
Corrective Action Required
06/18/2020

Foundation wall thickness and height and reinforcement. (IRC Section R404)
Plot Plan Review Approved 06/22/2020 06/23/2020
Kim Brennan
Deck location
Corrective Action Required
06/19/2020

Deck location, with dimensions to property lines must be provided on the plot plan. Please show this as a covered patio
Front building line
Corrective Action Required
06/19/2020

Front building line and dimension to front of building must be provided on the plot plan. The front building line along Carson Dr. has a 30' bulding line and not a 25' building line per the recorded plat.
Drainage swales
Corrective Action Required
06/19/2020

Drainage swales (where required); show spot elevations within the swale as required to conform to the approved master drainage plan (if applicable), must be provided
As-graded plot plan
Corrective Action Required
06/19/2020

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $1,137.67 $1,137.67 Paid 06/30/2020
Right of Way Permit Fee $80.00 $80.00 Paid 06/30/2020
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 06/30/2020
8331507-Sewer Connection Fee $420.00 $420.00 Paid 06/30/2020
Water Tap Fee $3,477.00 $3,477.00 Paid 06/30/2020
Water Meter Fee $425.02 $425.02 Paid 06/30/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sewer Service Inspection - R Passed 7/21/2020 (10:00) 7/21/2020 at 10:33 AM 07/21/2020
Misc
Informational
07/21/2020
- NO FOOTING INSPECTION ON RECORD - Michael Harkins 07/21/2020 10:42 AM
Water Service Inspection - R Passed 7/22/2020 (9:45) 7/22/2020 at 10:40 AM 07/22/2020
Underslab Plumbing Inspection - Residential Passed 7/23/2020 7/23/2020 at 7:35 AM 07/23/2020
Footing Inspection - Residential Passed 7/9/2020 at 2:00 PM 07/27/2020
Misc
Informational
07/27/2020
- 3RD PARTY FOOTING SIGNED & STAMPED BY DAVID P AINSWORTH - - COMMENTS: UFER ROD LOCATED IN REAR FOUNDATION WALL ABOUT 22' SOUTHEAST OF SOUTHWEST CORNER -
Piers/Caissons Inspection - Residential Passed 8/3/2020 (1:00) 8/3/2020 08/03/2020
Misc
Informational
08/03/2020
(2) 24 X 36 D (2) 24 X 96 C
Suspended Slab Inspection Passed 8/12/2020 (8:45) 8/12/2020 08/12/2020
Gas Piping Inspection - Residential Passed 9/15/2020 9/15/2020 09/15/2020
Electrical Service Inspection Passed 9/15/2020 9/15/2020 09/15/2020
Gas Service Inspection - Residential Failed 9/15/2020 9/15/2020 09/15/2020
Misc
Corrective Action Required
09/15/2020
Complete gas vent installation
Erosion Control Inspection Residential Failed 9/15/2020 9/15/2020 09/15/2020
Misc
Corrective Action Required
09/15/2020
Erosion control methods require continuous maintenance. Please repair damaged sections of silt fence.
Gas Service Inspection - Residential Passed 9/18/2020 9/18/2020 09/18/2020
Misc
Resolved
09/18/2020
All Rough Inspection - Residential Passed 9/18/2020 9/18/2020 09/18/2020
Sidewalk Inspection Partial 11/3/2020 11/03/2020
Misc
Informational
11/03/2020
Forms were placed and aggregate was present and compacted. Talked to Roy about no picture framing the sidewalks. RP 11-3-20
Sidewalk Inspection Passed 11/13/2020 11/13/2020 11/13/2020
Misc
Informational
11/03/2020
Forms were placed and aggregate was present and compacted. Talked to Roy about no picture framing the sidewalks. RP 11-3-20
Misc
Informational
11/13/2020
Finished sidewalk meets LS and ADA specs. RP 11-13-20
Driveway Inspection Partial 11/17/2020 (P.M.) 11/17/2020 11/17/2020
Misc
Informational
11/17/2020
Forms were placed and aggregate was present and compacted. RP 11-17-20
Driveway Inspection Passed 11/25/2020 11/25/2020 11/25/2020
Misc
Informational
11/17/2020
Forms were placed and aggregate was present and compacted. RP 11-17-20
Misc
Informational
11/25/2020
Finished driveway meets LS specs. RP 11-25-20
Occupancy Inspection - Codes Residential Failed 12/9/2020 12/9/2020 12/09/2020
Misc
Corrective Action Required
12/09/2020
-provide as graded plot plan for review -Final grade and sod per approved as graded plot plan, ensure public utility valve boxes are accessible at grade -Repair damage sections of erosion control -Remove debris from sidewalk, Street, curb/gutter and storm inlet boxes -Sump piping to discharge minimum 36” from foundation -Seal all exterior penetrations -Provide ladders at basement egress window wells -Remove trash and construction debris -Remove paint covers from smoke/carbon monoxide alarms -Complete cooktop installation -Remove paper from batt insulation in unfinished basement area -Branch circuits that supply 120-volt, single-phase, 15 and 20 amp circuits installed in kitchens, family rooms, dining rooms, living rooms, parlors, libraries, dens, bedrooms, sun- rooms, recreations rooms, closets, hallways, laundry areas and similar rooms or areas require AFCI protection -provide building address on the front side of structure, fronting the street the property is addressed to.
Erosion Control Inspection Residential Failed 12/09/2020
Misc
Partial Correction
12/16/2020
-Repair damage sections of erosion control -Remove debris from sidewalk, Street, curb/gutter and storm inlet boxes
Misc
Corrective Action Required
12/16/2020
-remove debris from street, curb/gutter and storm inlet boxes at sediment control devices
Erosion Control Inspection Residential Failed 12/16/2020
Misc
Partial Correction
12/16/2020
-Repair damage sections of erosion control -Remove debris from sidewalk, Street, curb/gutter and storm inlet boxes
Misc
Corrective Action Required
12/16/2020
Remove debris from street, curb/gutter and storm inlets at sediment control devices
Plot Plan Inspection Failed 12/16/2020 12/16/2020
Misc
Corrective Action Required
12/16/2020
Water valve box lids to be accessible at finished grade
Plot Plan Inspection Failed 12/17/2020 12/17/2020
Misc
Corrective Action Required
12/16/2020
Water valve box lids to be accessible at finished grade
Occupancy Inspection - Codes Residential Failed 12/23/2020 12/23/2020 12/23/2020
Misc
Corrective Action Required
12/09/2020
-Branch circuits that supply 120-volt, single-phase, 15 and 20 amp circuits installed in kitchens require AFCI protection, kitchen island and microwave circuits
Plot Plan Inspection Passed 12/23/2020
Misc
Resolved
12/23/2020
Water valve box lids to be accessible at finished grade
All Rough Inspection - Residential Passed 9/15/2020 9/15/2020 12/23/2020
Misc
Resolved
09/18/2020
Occupancy Inspection - Codes Residential Full C of O 12/28/2020 12/28/2020 12/28/2020
Misc
Resolved
12/28/2020
-Branch circuits that supply 120-volt, single-phase, 15 and 20 amp circuits installed in kitchens require AFCI protection, kitchen island and microwave circuits
Documents & Images
Date Uploaded File Type Document Name
06/18/2020 WV1438 - Gas combustion 6_18_2020
06/18/2020 Letter Permit Application
06/18/2020 Letter License Tax Form
06/19/2020 Letter Codes Residential Plan Review
06/23/2020 Plot Plan Approved Plot Plan
06/26/2020 Drawing Approved Drawings
06/30/2020 Receipt Receipt for transaction:2020-003806
06/30/2020 Letter DS Building Permit
07/22/2020 Letter INSPECTION SUMMARY
07/22/2020 Letter INSPECTION SUMMARY
07/23/2020 Letter INSPECTION SUMMARY
07/24/2020 M L Crose 161 NW Carson Dr LSMO Winterset Valley Lot 1438 SAB Homes P 2020-1007 3rd Party Footing Inspection Report 7-9-20
07/27/2020 Letter INSPECTION SUMMARY
08/03/2020 Letter INSPECTION SUMMARY
08/12/2020 Letter INSPECTION SUMMARY
09/15/2020 Letter INSPECTION SUMMARY
09/15/2020 Letter INSPECTION SUMMARY
09/15/2020 Letter INSPECTION SUMMARY
09/15/2020 Letter INSPECTION SUMMARY
09/15/2020 Letter INSPECTION SUMMARY
09/17/2020 DW Framing Inspection Item WV1438 Avere 2+2 Split Garage Winterset Valley 161 NW Carson Dr
09/18/2020 Letter INSPECTION SUMMARY
09/18/2020 Letter INSPECTION SUMMARY
09/18/2020 Letter INSPECTION SUMMARY
11/03/2020 Letter INSPECTION SUMMARY
11/13/2020 Letter INSPECTION SUMMARY
11/13/2020 Letter INSPECTION SUMMARY
11/13/2020 Letter INSPECTION SUMMARY
11/17/2020 Letter INSPECTION SUMMARY
11/25/2020 Letter INSPECTION SUMMARY
12/09/2020 Letter INSPECTION SUMMARY
12/09/2020 Letter INSPECTION SUMMARY
12/15/2020 Plot Plan As Graded Plot Plan
12/16/2020 Letter INSPECTION SUMMARY
12/16/2020 Letter INSPECTION SUMMARY
12/16/2020 Letter INSPECTION SUMMARY
12/17/2020 Letter INSPECTION SUMMARY
12/23/2020 Letter INSPECTION SUMMARY
12/23/2020 Letter INSPECTION SUMMARY
12/23/2020 Letter INSPECTION SUMMARY
12/28/2020 Letter Codes Final Certificate of Occupancy
12/28/2020 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home