Summary
PRRES20201498
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW SINGLE FAMILY UNFINISHED BASEMENT COVERED DECK DEFERRED FLOOR SYSTEM BERM/SWALE TO BE CONSTRUCTURED IN CONJUNCTION WITH LOT 1470***
06/04/2020
07/14/2020
01/06/2021
06/10/2021
Locations
Contacts
GALE HOMES II INC, Address:400 SW LONGVIEW BLVD, Unit 109, Phone:(816) 761-9292  
MFAULKNER@GALECOMMUNITIES.COM  
APEX HEATING & AIR CONDITIONING INC, Address:1202 NW EAGLE RIDGE BLVD, Phone:(816) 228-2739  
MC ELECTRICAL SERVICES INC, Address:1502 N VANSANT RD, Phone:(816) 392-3970  
R & R PLUMBING INC, Address:2001 GASLIGHT DR, Phone:(816) 772-5431  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 07/15/2020 07/13/2020
Steve Conrick
Signed and sealed
Corrective Action Required
07/13/2020

Plot plan must drawn, signed, and sealed by a licensed surveyor or engineer.
As-graded plot plan
Corrective Action Required
07/13/2020

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Residential Plan Review Approved 07/15/2020 07/13/2020
Steve Conrick
Plot Plan Review Rejected 07/10/2020 07/10/2020
Steve Conrick
Signed and sealed
Corrective Action Required
07/10/2020

Plot plan must drawn, signed, and sealed by a licensed surveyor or engineer.
As-graded plot plan
Corrective Action Required
07/10/2020

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Residential Plan Review Approved 07/13/2020 07/09/2020
Steve Conrick
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $1,421.12 $1,421.12 Paid 07/14/2020
Right of Way Permit Fee $80.00 $80.00 Paid 07/14/2020
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 07/14/2020
8331507-Sewer Connection Fee $570.00 $570.00 Paid 07/14/2020
Water Tap Fee $3,581.00 $3,581.00 Paid 07/14/2020
Water Meter Fee $455.54 $455.54 Paid 07/14/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Failed 8/24/2020 (9:45) 8/24/2020 08/24/2020
Misc
Corrective Action Required
08/24/2020
- PLANS ON SITE ARE FLOPPED PLAN WITH NO CITY STAMP - - PROVIDE 3RD PARTY INSPECTION FOR DRILLED PIERS - - COLUMN PAD E 54 X 54 W/ (8) #4 E W - - COLUMN PAD B MISSING BEHIND FRONT STOOP - - UFER GARAGE WALL NEAR FURNACE -
Piers/Caissons Inspection - Residential Passed 8/11/2020 09/08/2020
Misc
Informational
09/08/2020
- 3RD PARTY PIERS BY KEVIN MILLER @ APEX SIGNED & SEALED BY CLAYTON HESS - - DECK PIERS & PIERS AT PADS FOR SCH 40 COLUMNS -
Footing Inspection - Residential Passed 9/17/2020 (8:30) 9/17/2020 09/17/2020
Misc
Corrective Action Required
08/24/2020
- UFER GARAGE WALL NEAR FURNACE - - (2) DECK PIERS POURED WITH DRILLED PIERS -
Erosion Control Inspection Residential Failed 9/17/2020 09/17/2020
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
09/17/2020
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Sewer Service Inspection - R Passed 10/15/2020 (10:15) 10/15/2020 10/15/2020
Water Service Inspection - R Partial 10/15/2020 (10:15) 10/15/2020 10/15/2020
Misc
Informational
10/15/2020
Water service approved from structure to metallic/non-metallic connection on customer side of meter
Water Service Inspection - R Passed 10/16/2020 (10:15) 10/16/2020 10/16/2020
Misc
Resolved
10/16/2020
Water service approved from structure to metallic/non-metallic connection on customer side of meter
Underslab Plumbing Inspection - Residential Passed 10/21/2020 10/21/2020 10/20/2020
Erosion Control Inspection Residential Failed 12/31/2020
DCM2 ESC DEFICIENT INSTALLATION
Resolved
10/26/2020
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Misc
Resolved
12/31/2020
Provide and maintain gravel filter at driveway
Misc
Corrective Action Required
12/31/2020
-Erosion control requires continuous maintenance. Repair damage sections within two business days and remove debris from street. No further inspections until complete
All Rough Inspection - Residential Failed 12/31/2020 12/31/2020 12/31/2020
Misc
Corrective Action Required
12/31/2020
-This is a non-inclusive inspection due to not all systems are installed at the time of rough in -Method PFH exterior fastening per plan, third car -NM Conductors prohibited in exterior raceway. Conductors must be wet location rated, condensing unit whip -complete fire blocking throughout -several locations in where headered floor joists require joist hangers, garage & basement -two rows 16D at 3” oc PFH top plate fastening -Furr out supply duct in garage for insulation -Provide bearing for floor joist above entry area -Ensure steel LIB bracing is properly fastened -12 inch OC fastening brace wall intersections stud to stud and abutting studs -Proper fastening of structural straps -exterior receptacles cannot be from kitchen/dining room circuits -Protect NM conductors minimum 6 inches AFF at floor penetrations -braced wall method CS-PF exterior fastening per detail 1/S1.4, both sides of cantilevered wall sections dining/master bedroom -Seal penetrations in all stud cavities used as return air Plenum -Complete electrical installation -Overbored/notched interior loadbearing top plates require structural strap spanning minimum 6 inches beyond either side of penetration with four 8D fasteners each side, Garage/dwelling separation wall and bedroom three closet -Nail plate protection Conductor top plate penetration garage/dwelling separation wall -Nail plate protection conductor stud penetrations master bath -Bond gas piping Between gas meter outlet and upstream of the first CSST connection -provide solid blocking between floor joists where required by approved plans -damaged I-joist top cord, conductor installation below kitchen island -Cap and label future basement bath group dry vent -Nail plate protection bedroom four, conductor stud penetration -Three 2 x 4 for roof support, bedroom three door
Electrical Service Inspection Failed 12/31/2020 12/31/2020 12/31/2020
Misc
Corrective Action Required
12/31/2020
Service equipment not installed
Gas Service Inspection - Residential Failed 12/31/2020
Misc
Corrective Action Required
12/31/2020
Use of non-shielded CSST requires the gas piping system to be bonded
Gas Piping Inspection - Residential Passed 12/31/2020 12/31/2020 12/31/2020
All Rough Inspection - Residential Failed 1/5/2021 1/5/2021 01/05/2021
Misc
Corrective Action Required
01/05/2021
-This is a non-inclusive inspection due to not all systems are installed at the time of rough in -Method PFH exterior fastening per plan, third car -NM Conductors prohibited in exterior raceway. Conductors must be wet location rated, condensing unit whip -complete fire blocking throughout -several locations in where headered floor joists require joist hangers, garage & basement -two rows 16D at 3” oc PFH top plate fastening -Furr out supply duct in garage for insulation -Provide bearing for floor joist above entry area -Ensure steel LIB bracing is properly fastened -12 inch OC fastening brace wall intersections stud to stud and abutting studs -Proper fastening of structural straps -exterior receptacles cannot be from kitchen/dining room circuits -Protect NM conductors minimum 6 inches AFF at floor penetrations -braced wall method CS-PF exterior fastening per detail 1/S1.4, both sides of cantilevered wall sections dining/master bedroom -Seal penetrations in all stud cavities used as return air Plenum -Complete electrical installation -Overbored/notched interior loadbearing top plates require structural strap spanning minimum 6 inches beyond either side of penetration with four 8D fasteners each side, Garage/dwelling separation wall and bedroom three closet -Nail plate protection Conductor top plate penetration garage/dwelling separation wall -Nail plate protection conductor stud penetrations master bath -Bond gas piping Between gas meter outlet and upstream of the first CSST connection -provide solid blocking between floor joists where required by approved plans -damaged I-joist top cord, conductor installation below kitchen island -Cap and label future basement bath group dry vent -Nail plate protection bedroom four, conductor stud penetration -Three 2 x 4 for roof support, bedroom three door
Misc
Corrective Action Required
01/05/2021
01/05/2021 Inspection denied due to lack of compliance with erosion control report from 12/31/2020
Erosion Control Inspection Residential Failed 01/05/2021
Misc
Corrective Action Required
10/26/2020
Non compliant with erosion control inspection report dated 12/31/2020 -Erosion control requires continuous maintenance, repair damaged sections and remove debris from street
Erosion Control Inspection Residential Passed 01/08/2021
Misc
Resolved
01/08/2021
Non compliant with erosion control inspection report dated 12/31/2020 -Erosion control requires continuous maintenance, repair damaged sections and remove debris from street
Gas Service Inspection - Residential Passed 01/08/2021
Misc
Resolved
01/08/2021
Use of non-shielded CSST requires the gas piping system to be bonded
Electrical Service Inspection Passed 01/08/2021
Misc
Resolved
01/08/2021
Service equipment not installed
All Rough Inspection - Residential Failed 1/8/2021 1/8/2021 01/08/2021
Misc
Corrective Action Required
01/05/2021
-Method PFH exterior fastening per plan, third car -braced wall method CS-PF exterior fastening per detail 1/S1.4, both sides of cantilevered wall sections dining/master Reschedule for portal frame exterior fastening inspection. Ok to insulate and rock
Misc
Resolved
01/08/2021
01/05/2021 Inspection denied due to lack of compliance with erosion control report from 12/31/2020
Driveway Inspection Partial 1/21/2021 1/21/2021 01/21/2021
Misc
Informational
01/21/2021
Forms were placed and aggregate was present and compacted. Left a voicemail informing them that they needed to cover the approach to prevent freezing. RP 1-21-21
Erosion Control Inspection Residential Failed 01/21/2021
Misc
Corrective Action Required
01/21/2021
-Erosion control requires continuous maintenance. Repair damaged sections within two business days -immediate street cleanup required -no further inspections until issues are resolved
All Rough Inspection - Residential Passed 01/21/2021
Misc
Resolved
01/21/2021
-Method PFH exterior fastening per plan, third car -braced wall method CS-PF exterior fastening per detail 1/S1.4, both sides of cantilevered wall sections dining/master Reschedule for portal frame exterior fastening inspection. Ok to insulate and rock
Erosion Control Inspection Residential Failed 01/22/2021
Misc
Partial Correction
01/22/2021
-Erosion control requires continuous maintenance. Repair damaged sections at front curb line either side of driveway
Driveway Inspection Passed 1/29/2021 1/29/2021 01/29/2021
Misc
Informational
01/21/2021
Forms were placed and aggregate was present and compacted. Left a voicemail informing them that they needed to cover the approach to prevent freezing. RP 1-21-21
Misc
Informational
01/29/2021
Finished driveway meets LS specs. RP 1-29-21
Erosion Control Inspection Residential Passed 05/18/2021
Misc
Resolved
05/18/2021
-Erosion control requires continuous maintenance. Repair damaged sections at front curb line either side of driveway
Plot Plan Inspection Failed 5/25/2021 05/25/2021
Misc
Corrective Action Required
05/25/2021
-Locate and expose manhole, ensure lid is accessible at grade. Between driveway and transformer
Occupancy Inspection - Codes Residential Failed 5/26/2021 5/26/2021 05/26/2021
Misc
Corrective Action Required
05/26/2021
-Address failed plot plan inspection report -Seal Exterior Penetration, sump discharge piping -Seal top and sides of exterior lighting exposed to the elements -Laundry circuit requires GFCI protection -Smoke/carbon monoxide alarm required in the immediate vicinity outside of sleeping area, main floor front bedroom -Identify circuit 16 in panel -AFCI protection at required locations per code -Provide breaker lockout device for hardwired appliances not in sight of panel -Cap and identify future vent for basement bathroom group -Locate and expose grounding electrode conductor connection to concrete encased electrode -Provide sprinkler signage at water shut off
Occupancy Inspection - Codes Residential Failed 6/4/2021 6/4/2021 06/04/2021
Misc
Corrective Action Required
05/26/2021
-Seal Exterior Penetrations -AFCI Circuits 9, 11, 13, 19, 10, 18, 23 -GFCI and AFCI circuits 10 & 16 -Provide sprinkler signage at water shut off
Plot Plan Inspection Passed 06/04/2021
Misc
Resolved
06/04/2021
-Locate and expose manhole, ensure lid is accessible at grade. Between driveway and transformer
Occupancy Inspection - Codes Residential Full C of O 6/10/2021 6/10/2021 06/10/2021
Misc
Resolved
06/10/2021
-Seal Exterior Penetrations -AFCI Circuits 9, 11, 13, 19, 10, 18, 23 -GFCI and AFCI circuits 10 & 16 -Provide sprinkler signage at water shut off
Documents & Images
Date Uploaded File Type Document Name
06/05/2020 Gale Homes Lot 1471 Permit Application Form
06/05/2020 Gale Homes Lot 1471 License Tax Application Form
06/08/2020 2020_06_02_Gale Homes_Lot 1471 Winterset Valley_Sealed
06/25/2020 LOT 1471 CON 6-16-20
06/25/2020 2020_06_22 17-134 MDP SPOT ELEVATIONS AS BUILT
07/10/2020 APPROVED 2020_06_02_Gale Homes_Lot 1471 Winterset Valley_Sealed
07/10/2020 Letter Codes Residential Plan Review
07/13/2020 APPROVED LOT 1471
07/14/2020 Receipt Receipt for transaction:2020-004431
07/14/2020 Letter DS Building Permit
07/29/2020 Engineer Report/Study Final_2020.07.23_SiteObv PierDes_LSMO_Gale Homes
08/18/2020 Letter Final_2020.08.11_HPier_LSMO_Gale Homes
08/24/2020 Letter INSPECTION SUMMARY
09/03/2020 Approved Plans Approved Revised Drawings
09/08/2020 Final_2020_08_11_HPier_LSMO_Gale Homes
09/08/2020 Letter INSPECTION SUMMARY
09/17/2020 Letter INSPECTION SUMMARY
09/17/2020 Letter INSPECTION SUMMARY
10/15/2020 Letter INSPECTION SUMMARY
10/15/2020 Letter INSPECTION SUMMARY
10/16/2020 Letter INSPECTION SUMMARY
10/20/2020 Letter INSPECTION SUMMARY
10/26/2020 Letter INSPECTION SUMMARY
12/31/2020 Letter INSPECTION SUMMARY
12/31/2020 Letter INSPECTION SUMMARY
12/31/2020 Letter INSPECTION SUMMARY
12/31/2020 Letter INSPECTION SUMMARY
12/31/2020 Letter INSPECTION SUMMARY
12/31/2020 Letter INSPECTION SUMMARY
01/05/2021 Letter INSPECTION SUMMARY
01/05/2021 Letter INSPECTION SUMMARY
01/07/2021 GALE
01/07/2021 20210106_165142
01/08/2021 Letter INSPECTION SUMMARY
01/08/2021 Letter INSPECTION SUMMARY
01/08/2021 Letter INSPECTION SUMMARY
01/08/2021 Letter INSPECTION SUMMARY
01/21/2021 Letter INSPECTION SUMMARY
01/21/2021 Letter INSPECTION SUMMARY
01/21/2021 Letter INSPECTION SUMMARY
01/22/2021 Letter INSPECTION SUMMARY
01/29/2021 Letter INSPECTION SUMMARY
05/18/2021 Letter INSPECTION SUMMARY
05/24/2021 Plot Plan Approved As Graded Plot Plan
05/25/2021 Letter INSPECTION SUMMARY
05/26/2021 Letter INSPECTION SUMMARY
06/04/2021 Letter INSPECTION SUMMARY
06/04/2021 Letter INSPECTION SUMMARY
06/10/2021 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents