Permit Application Status

PRRES20201094


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20201094
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW SINGLE FAMILY UNFINISHED BASEMENT
04/30/2020
05/05/2020
12/09/2020
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
PERMITTING@SUMMITHOMESKC.COM  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 05/04/2020 05/04/2020
Steve Conrick
Residential Plan Review Approved 05/04/2020 05/04/2020
Steve Conrick
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,156.65 $1,156.65 Paid 05/04/2020
8331504-EFHB Middle Big Creek, Full $502.20 $502.20 Paid 05/04/2020
8331507-Sewer Connection Fee $450.00 $450.00 Paid 05/04/2020
8331401-Water Tap Fee $3,477.00 $3,477.00 Paid 05/04/2020
8350015-Water Meter Fee $425.02 $425.02 Paid 05/04/2020
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 05/04/2020
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 05/04/2020
9110078-Valuation Fee New Single Family $48.67 $48.67 Paid 06/30/2020
$1,205.52
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 5/18/2020 (11:15) 5/18/2020 05/18/2020
Misc
Informational
05/18/2020
(1) PIER PAD 26 X 26 W/ 5 # 4 EACH WAY DETAIL H PER PLAN 16" x 36" PIER W/ (4) VERTICAL #4
Underslab Plumbing Inspection - Residential Failed 6/5/2020 6/5/2020 06/05/2020
Misc
Corrective Action Required
06/05/2020
- POST ADDRESS - - BACKFILL AROUND FOUNDATION TO ALLOW INPECTION OF COMPLETE DWV
Underslab Plumbing Inspection - Residential Passed 6/15/2020 6/15/2020 06/15/2020
Misc
Resolved
06/15/2020
Sewer Service Inspection - R Passed 6/17/2020 (11:00) 6/17/2020 06/17/2020
Water Service Inspection - R Passed 6/25/2020 (11:15) 6/25/2020 06/25/2020
Electrical Service Inspection Passed 8/31/2020 8/31/2020 08/31/2020
Gas Piping Inspection - Residential Passed 8/31/2020 8/31/2020 08/31/2020
Gas Service Inspection - Residential Failed 8/31/2020 8/31/2020 08/31/2020
Misc
Corrective Action Required
08/31/2020
- Gas pressure at 7 psi Must maintain 10 psi for 15 minutes
All Rough Inspection - Residential Failed 8/31/2020 8/31/2020 08/31/2020
Misc
Corrective Action Required
08/31/2020
- Staple plans together in order - Garage PFH per plans - Address cut floor joist at beam in garage, connect to header - Structural straps required at top and bottom plates bored 50% or more on exterior walls and interior bearing walls - Seal all top plate penetrations - Fireblock deadspace in kitchen - Nail off dbl joist hanger above front entry 1st floor - Secure all DWV 2” or less at mid point - H2.5 strap missing - 1st floor bed - Truss hangers per plans - Nail off truss hangers bedroom #2 - Connect top plates at 2nd floor, 2x6 to 2x4 wall - Great room girder truss bearing (4) 2x6 full height continuous per plans - Dbl girder truss should be bearing on (2) 2x4 studs bedroom #4 - EC#2 per plans - Ceiling 2x4 laid floor over 3’ at furred downs in basement need to be supported to the floor joists to support the ceiling load - Protection plate at DWV top, N wall basement - Dbl joist hanger required at floor joist connection to landing in basement at furred down - Address over notched floor joist for DWV, S side basement above main service panel - Permit lists basement as unfinished, add basement finish to permit and submit finished basement plans
All Rough Inspection - Residential Failed 9/17/2020 9/17/2020 09/17/2020
Misc
Corrective Action Required
09/17/2020
- Truss hangers per plans - Nail off truss hangers bedroom #2, bedroom #4 OK to Insulate
Gas Service Inspection - Residential Passed 9/17/2020 9/17/2020 09/17/2020
Misc
Resolved
09/17/2020
All Rough Inspection - Residential Passed 9/18/2020 9/18/2020 09/18/2020
Misc
Resolved
09/18/2020
Driveway Inspection Partial 10/1/2020 (P.M.) 10/1/2020 10/01/2020
Misc
Informational
10/01/2020
PRE POUR INSPECTION The forms are set and there appears to be sufficient compacted aggregate.
Driveway Inspection Passed 10/8/2020 10/8/2020 10/12/2020
Misc
Informational
10/01/2020
PRE POUR INSPECTION The forms are set and there appears to be sufficient compacted aggregate.
Piers/Caissons Inspection - Residential Passed 11/20/2020
Occupancy Inspection - Codes Residential Failed 11/20/2020 11/20/2020 11/20/2020
Misc
Corrective Action Required
11/20/2020
-Complete final grade and sod -Complete stone/siding at garage -Splash blocks at all sump pump and downspout discharge locations, minimum 36” clearance from foundation -Seal around exterior light fixtures -Seal all penetrations in siding, seal along top of AC disconnect and meter can
Occupancy Inspection - Codes Residential Temporary C of O 11/25/2020 11/25/2020 11/25/2020
Misc
Corrective Action Required
11/20/2020
-Complete final grade and sod -Complete stone/siding at garage -Splash blocks at all sump pump and downspout discharge locations, minimum 36” clearance from foundation -Seal around exterior light fixtures -Seal all penetrations in siding, seal along top of AC disconnect and meter can -Install handle/lock at sliding patio door -two locking devices required at sliding patio door -Remove all paint covers from smokes -Label dedicated outlets in garage and unfinished basement as not GFCI protected
Plot Plan Inspection Passed 12/09/2020
Occupancy Inspection - Codes Residential Full C of O 12/9/2020 12/9/2020 12/09/2020
Misc
Resolved
12/09/2020
Documents & Images
Date Uploaded File Type Document Name
04/30/2020 MN #106 - PERMIT APP
04/30/2020 LOT 106 FINAL
04/30/2020 106 manor at stoney creek roof layout- signed
04/30/2020 2319678 SEALED ROOF TRUSS DWGS 04202020
04/30/2020 MN #106 - Bayfield - Prairie - Sheets- signed
04/30/2020 APPROVED 2319678 SEALED ROOF TRUSS DWGS 04202020
04/30/2020 APPROVED 106 manor at stoney creek roof layout- signed
05/04/2020 APRROVED LOT 106 FINAL
05/04/2020 APPROVED MN #106 - Bayfield - Prairie - Sheets- signed
05/04/2020 Receipt Receipt for transaction:2020-001890
05/05/2020 Letter DS Building Permit
05/18/2020 Letter INSPECTION SUMMARY
06/05/2020 Letter INSPECTION SUMMARY
06/15/2020 Letter INSPECTION SUMMARY
06/17/2020 Letter INSPECTION SUMMARY
06/25/2020 Letter INSPECTION SUMMARY
06/30/2020 Scope of Work Scope of Work
06/30/2020 Drawing Basement Finish Plan
06/30/2020 Letter DS Building Permit
06/30/2020 Receipt Receipt for transaction:2020-003807
08/31/2020 Letter INSPECTION SUMMARY
08/31/2020 Letter INSPECTION SUMMARY
08/31/2020 Letter INSPECTION SUMMARY
08/31/2020 Letter INSPECTION SUMMARY
09/17/2020 Letter INSPECTION SUMMARY
09/17/2020 Letter INSPECTION SUMMARY
09/18/2020 Letter INSPECTION SUMMARY
10/01/2020 Letter INSPECTION SUMMARY
10/12/2020 Letter INSPECTION SUMMARY
11/20/2020 Letter INSPECTION SUMMARY
11/20/2020 Letter INSPECTION SUMMARY
11/25/2020 Letter Codes Temporary Certificate of Occupancy
12/09/2020 Letter INSPECTION SUMMARY
12/09/2020 Letter Field Certificate of Occupancy
12/09/2020 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home