Permit Application Status

PRRES20180922


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20180922
Building Permit - Residential
Certificate of Occupancy
CHAPEL RIDGE RESIDENTIAL LLC
NEW SINGLE FAMILY
NEW HOUSE FINISHED AND UNFINISHED BASEMENT COVERED DECK
04/03/2018
05/09/2018
04/29/2019
Locations
Contacts
CHAPEL RIDGE RESIDENTIAL LLC, Address:3170 NE CARNEGIE DR #400  
CAPITAL CONSTRUCTION SERVICES LLC, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ONHOME SYSTEMS LLC, Address:510 SW MISSION RD, Phone:(816) 875-3696  
A BRIGHT PLUMBING LLC, Address:18107 E 18TH TER N, Phone:(816) 215-0730  
Reviews
Review Type Outcome Est. Completion Date Completed
Residential Plan Review Approved 04/05/2018 05/02/2018
Brandon Kalwei
33 Identify braced wall locations and length of braced wall panel(s).
Corrective Action Required
04/03/2018

Identify braced wall locations and length of braced wall panel(s). (IRC Section R602.10)
Plot Plan Review Approved 04/05/2018 04/04/2018
Troy Thompson
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $917.38 $917.38 Paid 05/09/2018
9110073-Right of Way Permit Fee $75.00 $75.00 Paid 05/09/2018
8331506-EFHB Maybrook, Full $553.93 $553.93 Paid 05/09/2018
8331507-Sewer Connection Fee $390.00 $390.00 Paid 05/09/2018
8331401-Water Tap Fee $3,343.00 $3,343.00 Paid 05/09/2018
8350015-Water Meter Fee $431.83 $431.83 Paid 05/09/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 5/9/2018 at 1:40 PM 05/09/2018
Water Service Inspection - R Partial 6/5/2018 (1:00) 6/5/2018 06/05/2018
Water Service Inspection - R Passed 6/7/2018 6/7/2018 at 3:50 PM 06/06/2018
Sewer Service Inspection - R Passed 6/5/2018 (1:00) 6/5/2018 06/06/2018
Underslab Plumbing Inspection - Residential Passed 6/7/2018 6/7/2018 at 9:20 AM 06/07/2018
Piers/Caissons Inspection - Residential Passed 8/28/2018 (8:00) 8/28/2018 at 8:25 AM 08/28/2018
All Rough Inspection - Residential Failed 10/9/2018 10/9/2018 at 2:35 PM 10/09/2018
Misc
Corrective Action Required
10/09/2018
FRAMING: -Provide plan on site -Redo piers outside. The two outer piers settled -Fb wall space from soffit at front basement bedroom -Nail garage portal wall sheathing per code; install 2” washers -Anchor garage sill plate near dryer -Install beam support under stoop roof load above garage -Install security blocking for rear door 3 stud spaces out -Fb wall space at closet/master shower from roof; Fb basement rear bedroom wall from ceiling furdown space -Install 3 stud support for roof lvl beam near master bedroom door -Nail all hangers at stair -Header off cut joist at water heater b vent -Anchor sill plate near service panel MECHANICAL: -Install b vent shield in attic -Pan off return air space from front basement bedroom soffit; provide return air from front basement bedroom ELECTRICAL: -Protect wiring at bottom wall plate near range; in pantry ; at master bedroom ceiling string light circuit -Provide rear wall receptacle spacing per code -Over filled 2-gang box outside master bedroom -Staple wiring min min 1.25” from nailing surface basement bath and outside bath -Securely fasten the SE cable within 12” of meter and service disconnect ; securely fasten all NM cable at maximum 4.5 ft interval, not just resting on framing -Complete cooktop circuit -Move smoke alarm outside the soffit and install alarm minimum 4 inches from soffit wall **OK TO INSULATE
Electrical Service Inspection Passed 10/9/2018 10/9/2018 10/09/2018
Gas Service Inspection - Residential Passed 10/9/2018 10/9/2018 10/09/2018
All Rough Inspection - Residential Failed 10/12/2018 10/12/2018 at 9:10 AM 10/12/2018
Misc
Corrective Action Required
10/09/2018
FRAMING: -Provide plan on site **where is the plan? -Redo piers outside. The two outer piers settled -Anchor garage sill plate near dryer **cannot cut off the good stud and install a scab next to it. Install a full height stud please -Install beam support under stoop roof load above garage **I want to see the plan -Nail all hangers at stair **double joist hanger not nailed MECHANICAL: -Install b vent shield in attic **Need 1" space around the b-vent **OK TO INSULATE
All Rough Inspection - Residential Failed 10/16/2018 10/16/2018 at 10:40 AM 10/16/2018
Misc
Corrective Action Required
10/12/2018
FRAMING: -Provide plan on site **Install triple lvl under foyer wall per plan **Install triple 2x10 joist under the front bed closet bearing wall. I failed to catch this **Install triple 18" lvl above living rm. Provide (4)2x4 stud support at kitchen end. Make sure to solidblock unerneath point load -Redo piers outside. The two outer piers settled MECHANICAL: -Install b vent shield in attic **Need 1" space around the b-vent. **OK TO INSULATE
All Rough Inspection - Residential Partial 10/22/2018 10/22/2018 at 1:05 PM 10/22/2018
Misc
Corrective Action Required
10/16/2018
-Redo piers outside. The two outer piers settled **OK TO ROCK
Driveway Inspection Partial 1/7/2019 1/10/2019 01/10/2019
Informational
01/10/2019
Per Brice Lawson inspected sidewalks, ADA ramps and driveways approach prior to pour. 1/8/19 The contractor poured on 1/9/19 Magan Concrete. They used Dupuis ready mix. 1/8/19 Brent Dye with Water Utilities adjusted the manhole behind the ADA ramp on the coner. John Jackson 01/10/2019 3:46 PM
Sidewalk Inspection Partial 1/7/2019 1/10/2019 01/10/2019
Misc
Corrective Action Required
01/07/2019
Per Brice Lawson inspected sidewalks, ADA ramps and driveways approach prior to pour. 1/8/19 The contractor poured on 1/9/19 Magan Concrete. They used Dupuis ready mix. 1/8/19 Brent Dye with Water Utilities adjusted the manhole behind the ADA ramp on the coner. John Jackson 01/10/2019 3:50 PM
Informational
01/10/2019
Driveway Inspection Passed 1/29/2019 01/30/2019
Informational
01/10/2019
Informational
01/30/2019
Driveway meets the required specification.John Jackson 01/30/2019 9:25 AM
Sidewalk Inspection Passed 1/29/2019 01/30/2019
Informational
01/30/2019
Sidewalk passed meets required specification.
All Rough Inspection - Residential Passed 03/25/2019
Misc
Resolved
03/25/2019
-Redo piers outside. The two outer piers settled **OK TO ROCK
Occupancy Inspection - Codes Residential Failed 3/25/2019 3/25/2019 at 8:00 AM 03/25/2019
Misc
Corrective Action Required
03/25/2019
-FINAL GRADE, SOD, ROOF DRAINAGE AND SPLASHBLOCKS -LOWER WATER METER TO FLUSH WITH FINAL GRADE -SEAL EXTERIOR: PENETRATIONS, ABOVE METER AND AC DISCONNECTS, LIGHTS, ETC -COMPLETE DECK AND AC INSTALATION -FASTEN WINDOW WELL LADDER -PROVIDE ENGINEER DOCUMENT FOR GARAGE DOOR INSTALLATION. CHECK DOOR BRACKET SUPPORTS -INSTALL GARAGE DOOR SELF CLOSERS -INSTALL LAUNDRY RECEPTACLE FLUSHED WITH WALL -INSTALL SECURITY STRIKE PLATE FOR REAR EXTERIOR DOOR -ONE BREAKER NOT LABELED -MOVE WATER HEATER MIN 1" AWAY FROM WATER HEATER B-VENT
Occupancy Inspection - Codes Residential Temporary C of O 3/28/2019 3/28/2019 at 10:25 AM 03/28/2019
Misc
Corrective Action Required
03/25/2019
-FINAL GRADE, SOD, SPLASHBLOCKS -LOWER WATER METER TO FLUSH WITH FINAL GRADE -SEAL EXTERIOR: PENETRATIONS, ABOVE METER AND AC DISCONNECTS, LIGHTS, ETC
Occupancy Inspection - Codes Residential Full C of O 4/29/2019 at 10:10 AM 04/29/2019
Misc
Resolved
04/29/2019
-FINAL GRADE, SOD, SPLASHBLOCKS -LOWER WATER METER TO FLUSH WITH FINAL GRADE -SEAL EXTERIOR: PENETRATIONS, ABOVE METER AND AC DISCONNECTS, LIGHTS, ETC
Documents & Images
Date Uploaded File Type Document Name
04/03/2018 Letter Codes Residential Plan Review
05/09/2018 Receipt Receipt for transaction: 2018-002141
05/09/2018 Letter Codes Building Permit
05/09/2018 Plot Plan DOC050918-006
05/09/2018 Letter Inspection Summary
06/05/2018 Letter Inspection Summary
06/06/2018 Letter Inspection Summary
06/07/2018 Letter Inspection Summary
08/28/2018 Letter Inspection Summary
10/09/2018 Letter Inspection Summary
10/12/2018 Letter Inspection Summary
10/12/2018 Letter Inspection Summary
10/16/2018 Letter Inspection Summary
10/22/2018 Letter Inspection Summary
01/10/2019 Letter Inspection Summary
01/10/2019 Letter Inspection Summary
01/24/2019 Letter DE-Daily Inspection Summary
01/30/2019 Letter Inspection Summary
01/30/2019 Letter Inspection Summary
03/25/2019 Letter INSPECTION SUMMARY
03/25/2019 Letter INSPECTION SUMMARY
03/28/2019 Letter Codes Temporary Certificate of Occupancy
04/29/2019 Letter Codes Final Certificate of Occupancy
04/29/2019 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home