Summary


PRPWFC20173611
Public Works Infrastructure Permit - Commercial
Final Acceptance
PARROT PROPERTIES INC - John Bondon
DEVELOPMENT COMPLETE
Village at View High On-Site Infrastructure for Village at View High, 1st Plat (on and off-site water, on-site sanitary sewer, street, storm, MDP, ESC)
11/03/2017
11/16/2017
11/06/2022
12/17/2021
Locations
Contacts
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
CITYSCAPE CONSTRUCTION VIEW HIGH LLC, Address:10 W CARMEL DR STE 200, Phone:(317) 574-1600 Ext:100  
PARROT PROPERTIES INC - John Bondon, Address:11303 VIEW HIGH DR, Phone:(816) 616-2208  
ARCHVIEW INVESTORS, LLC, Address:8335 KEYSTONE CROSSING, SUITE 220, Phone:(317) 574-1600  
CITY OF LEES SUMMIT, Address:220 SE GREEN ST  
CONIFER PROPERTIES LLC, Address:1010 GRAND BLVD  
NEW ORLEANS LLC, Address:PO BOX 900  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/03/2017 11/03/2017
Chris Hughey
CHRIS HUGHEY 11/03/2017 11:19 AM
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $5,034.42 $5,034.42 Paid 11/03/2017
Water Insp Fee $4,835.09 $4,835.09 Paid 11/03/2017
$4,835.08
Water Test Fee $800.00 $800.00 Paid 11/03/2017
Storm Sewer Inspection Fee $11,402.48 $11,402.48 Paid 11/03/2017
Paved Surface Inspection Fee $14,715.84 $14,715.84 Paid 11/03/2017
Site Grading Fee $6,919.92 $6,919.92 Paid 11/03/2017
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $50.00 $0.00 $50.00 Not Paid



(None of the fees owing can be paid online)
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Grading/Excavation/Fill Inspection Partial 1/2/2018 at 10:00 AM 01/02/2018
PW-Misc
Informational
01/02/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
Grading/Excavation/Fill Inspection Partial 1/5/2018 at 10:30 AM 01/05/2018
PW-Misc
Informational
01/02/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/05/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
Grading/Excavation/Fill Inspection Partial 1/10/2018 at 11:00 AM 01/10/2018
PW-Misc
Informational
01/05/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/05/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/10/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
Grading/Excavation/Fill Inspection Partial 1/11/2018 at 1:15 PM 01/11/2018
PW-Misc
Informational
01/10/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/10/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/10/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/11/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
Grading/Excavation/Fill Inspection Partial 1/19/2018 at 1:00 PM 01/19/2018
PW-Misc
Informational
01/11/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/11/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/11/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/11/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/19/2018
The final grading is not done, the contractors are moving the large pile of dirt behind the building over to the the Village View High project. They are working inside, not much going on outside.Steve Robbins 01/19/2018 3:35 PM
Grading/Excavation/Fill Inspection Partial 1/23/2018 01/19/2018
PW-Misc
Informational
01/19/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/19/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/19/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/19/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/19/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
Grading/Excavation/Fill Inspection Partial 1/23/2018 at 12:00 PM 01/23/2018
PW-Misc
Informational
01/19/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/19/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/19/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/19/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/19/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
01/23/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
Grading/Excavation/Fill Inspection Partial 1/24/2018 at 2:00 PM 01/24/2018
PW-Misc
Informational
01/23/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/23/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/23/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/23/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/23/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
01/23/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
01/24/2018
They were hauling fill-dirt today.Steve Robbins 01/24/2018 3:48 PM
Erosion Control Inspection Partial 1/26/2018 at 9:00 AM 01/26/2018
PW-Misc
Informational
01/26/2018
The silt fence is up and in good condition.Steve Robbins 01/26/2018 1:39 PM
Grading/Excavation/Fill Inspection Partial 1/26/2018 at 2:30 PM 01/26/2018
PW-Misc
Informational
01/24/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/24/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/24/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/24/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/24/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
01/24/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Corrective Action Required
01/24/2018
They were hauling more fill-dirt today.Steve Robbins 01/24/2018 3:45 PM
Corrective Action Required
01/26/2018
They were bringing in dirt for fill today.Steve Robbins 01/26/2018 2:52 PM
Grading/Excavation/Fill Inspection Partial 1/29/2018 at 11:00 AM 01/29/2018
PW-Misc
Informational
01/26/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/26/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/26/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/26/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/26/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
01/26/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
01/29/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
Grading/Excavation/Fill Inspection Partial 1/30/2018 at 1:30 PM 01/30/2018
PW-Misc
Informational
01/29/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/29/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/29/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/29/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/29/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
01/29/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
01/29/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
01/30/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
Erosion Control Inspection Partial 1/31/2018 at 2:00 PM 01/31/2018
PW-Misc
Informational
01/26/2018
The silt fence is up and in good condition.Steve Robbins 01/26/2018 1:39 PM
PW-Misc
Informational
01/31/2018
The silt fence is up and in place. I walked the entire site with the contractor for off-site sanitary. Steve Robbins 01/31/2018 2:49 PM
Grading/Excavation/Fill Inspection Partial 2/1/2018 at 1:45 PM 02/01/2018
PW-Misc
Informational
01/30/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
01/30/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
01/30/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
01/30/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
01/30/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
01/30/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
01/30/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
01/30/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/01/2018
The contractors are still bringing in dirt for fill.
Grading/Excavation/Fill Inspection Partial 2/6/2018 at 10:45 AM 02/06/2018
PW-Misc
Informational
02/01/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
02/01/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
02/01/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
02/01/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
02/01/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
02/01/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
02/01/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
02/01/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/01/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
02/06/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
Grading/Excavation/Fill Inspection Partial 2/7/2018 at 2:00 PM 02/07/2018
PW-Misc
Informational
02/06/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
02/06/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
02/06/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
02/06/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
02/06/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
02/06/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
02/06/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
02/06/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/06/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
02/06/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
02/07/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
Grading/Excavation/Fill Inspection Partial 2/9/2018 at 10:45 AM 02/09/2018
PW-Misc
Informational
02/07/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
02/07/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
02/07/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
02/07/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
02/07/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
02/07/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
02/07/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
02/07/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/07/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
02/07/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
02/07/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
02/09/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
Grading/Excavation/Fill Inspection Partial 2/14/2018 at 3:00 PM 02/14/2018
PW-Misc
Informational
02/09/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
02/09/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
02/09/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
02/09/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
02/09/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
02/09/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
02/09/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
02/09/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/09/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
02/09/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
02/09/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
02/09/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
02/14/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
Erosion Control Inspection Partial 2/21/2018 at 10:00 AM 02/21/2018
PW-Misc
Informational
01/31/2018
The silt fence is up and in good condition.Steve Robbins 01/26/2018 1:39 PM
PW-Misc
Informational
01/31/2018
The silt fence is up and in place. I walked the entire site with the contractor for off-site sanitary. Steve Robbins 01/31/2018 2:49 PM
PW-Misc
Informational
02/21/2018
The silt fence is still up and after the rain is still in good condition. I did not see any run-off.Steve Robbins 02/21/2018 11:56 AM
Grading/Excavation/Fill Inspection Partial 2/21/2018 at 11:45 AM 02/21/2018
PW-Misc
Informational
02/14/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
02/14/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
02/14/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
02/14/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
02/14/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
02/14/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
02/14/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
02/14/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/14/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
02/14/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
02/14/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
02/14/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
02/14/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
Informational
02/16/2018
PW-Misc
Informational
02/21/2018
No work was being done today because of the ice and bad weather.Steve Robbins 02/21/2018 12:02 PM
Grading/Excavation/Fill Inspection Partial 2/22/2018 at 2:15 PM 02/22/2018
PW-Misc
Informational
02/21/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
02/21/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
02/21/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
02/21/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
02/21/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
02/21/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
02/21/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
02/21/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/21/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
02/21/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
02/21/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
02/21/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
02/21/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
02/22/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
Water Line - Construction Inspection Partial 2/26/2018 at 8:30 AM 02/26/2018
PW-Main inspection
Informational
02/26/2018
Shaw Construction is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
Water Line - Construction Inspection Partial 2/26/2018 at 12:45 PM 02/26/2018
PW-Main inspection
Informational
02/26/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
02/26/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
Water Line - Construction Inspection Partial 2/27/2018 at 12:30 PM 02/27/2018
PW-Main inspection
Informational
02/26/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
02/26/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
02/27/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
Water Line - Construction Inspection Partial 2/28/2018 at 10:30 AM 02/28/2018
PW-Main inspection
Informational
02/27/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
02/27/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
02/27/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
02/28/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
Water - Material Verification Passed 2/26/2018 at 8:15 AM 02/28/2018
Informational
02/26/2018
I have checked the materials that are on-site . They did not have the spray for the bolts, but they now have it . They seem to have the correct pipe and fittings and all the pipe and fitting sizes are correct.Steve Robbins 02/28/2018 3:36 PM
Water Line - Construction Inspection Partial 3/1/2018 at 8:45 AM 03/01/2018
PW-Main inspection
Informational
02/28/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
02/28/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
02/28/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
02/28/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
03/01/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
Water - Material Verification Passed 2/26/2018 03/01/2018
Water Line - Construction Inspection Partial 3/5/2018 at 11:45 AM 03/05/2018
PW-Main inspection
Informational
03/01/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
03/01/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
03/01/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
03/01/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
03/01/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
03/05/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing.Steve Robbins 03/05/2018 3:22 PM
Grading/Excavation/Fill Inspection Partial 3/5/2018 at 1:00 PM 03/05/2018
PW-Misc
Informational
02/22/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
02/22/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
02/22/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
02/22/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
02/22/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
02/22/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
02/22/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
02/22/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
02/22/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
02/22/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
02/22/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
02/22/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
02/22/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
02/22/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
03/05/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
Grading/Excavation/Fill Inspection Partial 3/12/2018 at 11:00 AM 03/12/2018
PW-Misc
Informational
03/05/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
03/05/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
03/05/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
03/05/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
03/05/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
03/05/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
03/05/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
03/05/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
03/05/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
03/05/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
03/05/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
03/05/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
03/05/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
03/05/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
03/05/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
03/12/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
Water Line - Coliform Test 1 Partial 3/13/2018 at 10:00 AM 03/14/2018
PW-Misc
Informational
03/14/2018
On friday 3/9/18 the contractor filled up the water line on View High, we did not tie into the existing line yet they did it via a jumper hose. When they installed the water line they put chlorine in the line. On 3/12/18 I checked to make sure that we had chlorine in the line. On 3/13/18 we de-chlorinated the water line with the tablets and did a flush. I am taking the first sample this morning.
Water Line - Coliform Test 1 Partial 3/14/2018 at 8:00 AM 03/14/2018
PW-Misc
Informational
03/14/2018
On friday 3/9/18 the contractor filled up the water line on View High, we did not tie into the existing line yet they did it via a jumper hose. When they installed the water line they put chlorine in the line. On 3/12/18 I checked to make sure that we had chlorine in the line. On 3/13/18 we de-chlorinated the water line with the tablets and did a flush. I am taking the first sample this morning.
PW-Misc
Informational
03/14/2018
I took the first sample to Blue Valley Lab. I took 1 sample and 1 duplicate. I will be attending a training class on thursday and friday so i will see if John or Matt can get the second sample for me.Steve Robbins 03/14/2018 11:48 AM
Water Line - Coliform Test 2 Partial 3/15/2018 at 7:50 AM 03/15/2018
PW-Misc
Informational
03/15/2018
Matt Munger 03/15/2018 9:44 AM Casey took two samples, I deliverd the samples to Blue Valley Labs.
Water Line - Coliform Test 2 Passed 3/21/2018 at 11:00 AM 03/21/2018
PW-Misc
Informational
03/15/2018
Matt Munger 03/15/2018 9:44 AM Casey took two samples, I deliverd the samples to Blue Valley Labs.
PW-Misc
Informational
03/21/2018
I was out at classes on the 15, and 16. and I was out sick on the 19, and the 20th. While i was out the sample I took to the lab and the samlple Matt took to the lab have both passed. This completes the samples for the new water line on viewhigh. They have not tied in to the main yet.Steve Robbins 03/21/2018 11:42 AM
Water Line - Coliform Test 1 Passed 3/15/2018 03/21/2018
PW-Misc
Informational
03/14/2018
On friday 3/9/18 the contractor filled up the water line on View High, we did not tie into the existing line yet they did it via a jumper hose. When they installed the water line they put chlorine in the line. On 3/12/18 I checked to make sure that we had chlorine in the line. On 3/13/18 we de-chlorinated the water line with the tablets and did a flush. I am taking the first sample this morning.
PW-Misc
Informational
03/14/2018
I took the first sample to Blue Valley Lab. I took 1 sample and 1 duplicate. I will be attending a training class on thursday and friday so i will see if John or Matt can get the second sample for me.Steve Robbins 03/14/2018 11:48 AM
Grading/Excavation/Fill Inspection Partial 3/27/2018 at 1:00 PM 03/27/2018
PW-Misc
Informational
03/12/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
03/12/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
03/12/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
03/12/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
03/12/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
03/12/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
03/12/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
03/12/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
03/12/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
03/12/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
03/12/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
03/12/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
03/12/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
03/12/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
03/12/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
03/12/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
03/27/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
Grading/Excavation/Fill Inspection Partial 4/2/2018 at 11:30 AM 04/02/2018
PW-Misc
Informational
03/27/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
03/27/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
03/27/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
03/27/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
03/27/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
03/27/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
03/27/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
03/27/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
03/27/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
03/27/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
03/27/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
03/27/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
03/27/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
03/27/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
03/27/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
03/27/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
03/27/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
04/02/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
Erosion Control Inspection Passed 4/4/2018 at 8:45 AM 04/04/2018
PW-Misc
Informational
02/21/2018
The silt fence is up and in good condition.Steve Robbins 01/26/2018 1:39 PM
PW-Misc
Informational
02/21/2018
The silt fence is up and in place. I walked the entire site with the contractor for off-site sanitary. Steve Robbins 01/31/2018 2:49 PM
PW-Misc
Informational
02/21/2018
The silt fence is still up and after the rain is still in good condition. I did not see any run-off.Steve Robbins 02/21/2018 11:56 AM
PW-Misc
Informational
04/04/2018
The erosion control appears to be working. There has been a few days when there was mud on the street, but they always get it cleaned up in a timely mannner.Steve Robbins 04/04/2018 9:35 AM
Water Line - Hydrostatic Test Passed 4/5/2018 at 7:30 AM 04/05/2018
PW-Misc
Informational
04/05/2018
The hydrostatic pressure test has passed for the water line on view high 150psi for 2 hrs. The water samples have passed and it has been flushed, they are ready to make the tie-in to the existing main.Steve Robbins 04/05/2018 2:59 PM
Grading/Excavation/Fill Inspection Partial 4/10/2018 at 10:30 AM 04/10/2018
PW-Misc
Informational
04/02/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
04/02/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
04/02/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
04/02/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
04/02/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
04/02/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
04/02/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
04/02/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
04/02/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
04/02/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
04/02/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
04/02/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
04/02/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
04/02/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
04/02/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
04/02/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
04/02/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
04/02/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
04/10/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
Water Line - Construction Inspection Partial 4/12/2018 at 8:15 AM 04/12/2018
PW-Main inspection
Informational
03/05/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
03/05/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
03/05/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
03/05/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
03/05/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
03/05/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
04/12/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
Grading/Excavation/Fill Inspection Partial 4/13/2018 at 8:30 AM 04/13/2018
PW-Misc
Informational
04/10/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
04/10/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
04/10/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
04/10/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
04/10/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
04/10/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
04/10/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
04/10/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
04/10/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
04/10/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
04/10/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
04/10/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
04/10/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
04/10/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
04/10/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
04/10/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
04/10/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
04/10/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
04/10/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
04/13/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
Grading/Excavation/Fill Inspection Partial 4/16/2018 at 1:00 PM 04/16/2018
PW-Misc
Informational
04/13/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
04/13/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
04/13/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
04/13/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
04/13/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
04/13/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
04/13/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
04/13/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
04/13/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
04/13/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
04/13/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
04/13/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
04/13/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
04/13/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
04/13/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
04/13/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
04/13/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
04/13/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
04/13/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
04/13/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
04/16/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
Water Line - Construction Inspection Partial 4/18/2018 at 10:45 AM 04/18/2018
PW-Main inspection
Informational
04/12/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
04/12/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
04/12/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
04/12/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
04/12/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
04/12/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
04/12/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
04/18/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
Site Visit Partial 4/26/2018 at 1:40 PM 04/26/2018
PW-Misc
Informational
04/26/2018
Matt Munger 04/26/2018 2:05 PM No utility work was going on, on site. Workers had equipment on site and were trying to brake up the bedrock on the east side of the property. A neighbor to the project had stopped in and had informed of his concern with the blasting that had been going on and I spoke to him for a bit and informed him that I would send an email to Dan Harper and inform him of the concern. While on site there wasn't any blasting going on. I had called Dennis Sondgeroth (concerned neighbor) to let him know I had emailed Dan but wasn't sure what his schedule was for today just in case Dan was tied up in meetings and was not able to contact Dennis today.
Water Line - Construction Inspection Partial 4/30/2018 at 8:00 AM 04/30/2018
PW-Main inspection
Informational
04/18/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
04/18/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
04/18/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
04/18/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
04/18/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
04/18/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
04/18/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
04/18/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
04/30/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
Grading/Excavation/Fill Inspection Partial 5/4/2018 at 9:00 AM 05/04/2018
PW-Misc
Informational
04/16/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
04/16/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
04/16/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
04/16/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
04/16/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
04/16/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
04/16/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
04/16/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
04/16/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
04/16/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
04/16/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
04/16/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
04/16/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
04/16/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
04/16/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
04/16/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
04/16/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
04/16/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
04/16/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
04/16/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
04/16/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
05/04/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
Water Line - Construction Inspection Partial 5/4/2018 at 10:00 AM 05/04/2018
PW-Main inspection
Informational
04/30/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
04/30/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
04/30/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
04/30/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
04/30/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
04/30/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
04/30/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
04/30/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
04/30/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
05/04/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
Water Line - Construction Inspection Partial 5/7/2018 at 8:45 AM 05/07/2018
PW-Main inspection
Informational
05/04/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
05/04/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
05/04/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
05/04/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
05/04/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
05/04/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
05/04/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
05/04/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
05/04/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
05/04/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
05/07/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
Grading/Excavation/Fill Inspection Partial 5/8/2018 at 11:00 AM 05/08/2018
PW-Misc
Informational
05/04/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
05/04/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
05/04/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
05/04/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
05/04/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
05/04/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
05/04/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
05/04/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
05/04/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
05/04/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
05/04/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
05/04/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
05/04/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
05/04/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
05/04/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
05/04/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
05/04/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
05/04/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
05/04/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
05/04/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
05/04/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
05/04/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
05/08/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
Water Line - Construction Inspection Partial 5/9/2018 at 8:30 AM 05/10/2018
PW-Main inspection
Informational
05/07/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
05/07/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
05/07/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
05/07/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
05/07/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
05/07/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
05/07/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
05/07/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
05/07/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
05/07/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
05/07/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
05/10/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
Grading/Excavation/Fill Inspection Partial 5/11/2018 at 8:30 AM 05/11/2018
PW-Misc
Informational
05/08/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
05/08/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
05/08/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
05/08/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
05/08/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
05/08/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
05/08/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
05/08/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
05/08/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
05/08/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
05/08/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
05/08/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
05/08/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
05/08/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
05/08/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
05/08/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
05/08/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
05/08/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
05/08/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
05/08/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
05/08/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
05/08/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
05/08/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
05/11/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
Grading/Excavation/Fill Inspection Partial 5/15/2018 at 12:45 PM 05/15/2018
PW-Misc
Informational
05/11/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
05/11/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
05/11/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
05/11/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
05/11/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
05/11/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
05/11/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
05/11/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
05/11/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
05/11/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
05/11/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
05/11/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
05/11/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
05/11/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
05/11/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
05/11/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
05/11/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
05/11/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
05/11/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
05/11/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
05/11/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
05/11/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
05/11/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
05/11/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
05/15/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
Grading/Excavation/Fill Inspection Partial 5/17/2018 at 11:15 AM 05/17/2018
PW-Misc
Informational
05/15/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
05/15/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
05/15/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
05/15/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
05/15/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
05/15/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
05/15/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
05/15/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
05/15/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
05/15/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
05/15/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
05/15/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
05/15/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
05/15/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
05/15/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
05/15/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
05/15/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
05/15/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
05/15/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
05/15/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
05/15/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
05/15/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
05/15/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
05/15/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
05/15/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
05/17/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
Water Line - Construction Inspection Partial 5/18/2018 at 9:00 AM 05/18/2018
PW-Main inspection
Informational
05/10/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
05/10/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
05/10/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
05/10/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
05/10/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
05/10/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
05/10/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
05/10/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
05/10/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
05/10/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
05/10/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
05/10/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
05/18/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
Grading/Excavation/Fill Inspection Partial 5/30/2018 at 10:00 AM 05/30/2018
PW-Misc
Informational
05/17/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
05/17/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
05/17/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
05/17/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
05/17/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
05/17/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
05/17/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
05/17/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
05/17/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
05/17/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
05/17/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
05/17/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
05/17/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
05/17/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
05/17/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
05/17/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
05/17/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
05/17/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
05/17/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
05/17/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
05/17/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
05/17/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
05/17/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
05/17/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
05/17/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
05/17/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
PW-Misc
Informational
05/30/2018
I was out of town all last week. While I was out Jeremy Young checked on this project. There was not much going on, there was alot of rain. Today i observed dirt and rock being moved and being compacted. I also spoke with Bair Excavating and they are planning on starting the private infrastructure for the apartments next week.Steve Robbins 05/30/2018 2:54 PM
Grading/Excavation/Fill Inspection Partial 6/1/2018 at 10:45 AM 06/01/2018
PW-Misc
Informational
05/30/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
05/30/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
05/30/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
05/30/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
05/30/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
05/30/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
05/30/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
05/30/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
05/30/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
05/30/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
05/30/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
05/30/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
05/30/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
05/30/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
05/30/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
05/30/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
05/30/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
05/30/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
05/30/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
05/30/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
05/30/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
05/30/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
05/30/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
05/30/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
05/30/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
05/30/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
PW-Misc
Informational
05/30/2018
I was out of town all last week. While I was out Jeremy Young checked on this project. There was not much going on, there was alot of rain. Today i observed dirt and rock being moved and being compacted. I also spoke with Bair Excavating and they are planning on starting the private infrastructure for the apartments next week.Steve Robbins 05/30/2018 2:54 PM
PW-Misc
Informational
06/01/2018
Today they are moving rock and dirt and grading.Steve Robbins 06/01/2018 2:56 PM
Grading/Excavation/Fill Inspection Partial 6/6/2018 at 1:30 PM 06/06/2018
PW-Misc
Informational
06/01/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
06/01/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
06/01/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
06/01/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
06/01/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
06/01/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
06/01/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
06/01/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
06/01/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
06/01/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
06/01/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
06/01/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
06/01/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
06/01/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
06/01/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
06/01/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
06/01/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
06/01/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
06/01/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
06/01/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
06/01/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
06/01/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
06/01/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
06/01/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
06/01/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
06/01/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
PW-Misc
Informational
06/01/2018
I was out of town all last week. While I was out Jeremy Young checked on this project. There was not much going on, there was alot of rain. Today i observed dirt and rock being moved and being compacted. I also spoke with Bair Excavating and they are planning on starting the private infrastructure for the apartments next week.Steve Robbins 05/30/2018 2:54 PM
PW-Misc
Informational
06/01/2018
Today they are moving rock and dirt and grading.Steve Robbins 06/01/2018 2:56 PM
Corrective Action Required
06/06/2018
Shaw is working on the detention basin today down by MH a-15 .Steve Robbins 06/06/2018 3:16 PM
Retention Basin Partial 6/8/2018 at 10:30 AM 06/08/2018
PW-Misc
Informational
06/08/2018
The last 3 days Shaw Construction has been excavating and grading the retention basin on the back side of the property, they have not installed any storm structures yet.Steve Robbins 06/08/2018 3:30 PM
Retention Basin Partial 6/11/2018 at 9:20 AM 06/11/2018
PW-Misc
Informational
06/08/2018
The last 3 days Shaw Construction has been excavating and grading the retention basin on the back side of the property, they have not installed any storm structures yet.Steve Robbins 06/08/2018 3:30 PM
PW-Misc
Informational
06/11/2018
Shaw is still working on getting the retention basin excavated.Steve Robbins 06/11/2018 9:33 AM
Sanitary Sewer Construction Inspection Partial 6/12/2018 at 10:06 AM 06/12/2018
PW-Main inspection
Informational
06/12/2018
Brice Lawson 06/12/2018 5:01 PM Larry Bair Construction was installing the 8" SDR 26 private sanitary main between MH a6 and C1. The pipe is being bedded in clean rock the trench appeared to be more than the minumum req. width.
Sanitary Sewer Construction Inspection Partial 6/12/2018 at 1:51 PM 06/12/2018
PW-Main inspection
Informational
06/12/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
Retention Basin Partial 6/18/2018 at 10:15 AM 06/18/2018
PW-Misc
Informational
06/11/2018
The last 3 days Shaw Construction has been excavating and grading the retention basin on the back side of the property, they have not installed any storm structures yet.Steve Robbins 06/08/2018 3:30 PM
PW-Misc
Informational
06/11/2018
Shaw is still working on getting the retention basin excavated.Steve Robbins 06/11/2018 9:33 AM
PW-Misc
Informational
06/18/2018
Blue Nile Construction has been working on the retention basin the last few working days. Shaw was gong ot install the storm structures but decided to start on the sanitary instead.Steve Robbins 06/18/2018 12:19 PM
Sanitary Sewer Construction Inspection Partial 6/18/2018 at 11:45 AM 06/18/2018
PW-Main inspection
Informational
06/12/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
06/18/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
Sanitary Sewer Construction Inspection Partial 6/21/2018 at 10:30 AM 06/21/2018
PW-Main inspection
Informational
06/18/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
06/18/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
06/21/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
Grading/Excavation/Fill Inspection Partial 6/22/2018 at 1:15 PM 06/22/2018
PW-Misc
Informational
06/06/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
06/06/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
06/06/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
06/06/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
06/06/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
06/06/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
06/06/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
06/06/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
06/06/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
06/06/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
06/06/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
06/06/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
06/06/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
06/06/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
06/06/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
06/06/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
06/06/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
06/06/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
06/06/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
06/06/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
06/06/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
06/06/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
06/06/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
06/06/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
06/06/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
06/06/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
PW-Misc
Informational
06/06/2018
I was out of town all last week. While I was out Jeremy Young checked on this project. There was not much going on, there was alot of rain. Today i observed dirt and rock being moved and being compacted. I also spoke with Bair Excavating and they are planning on starting the private infrastructure for the apartments next week.Steve Robbins 05/30/2018 2:54 PM
PW-Misc
Informational
06/22/2018
There was no work being done on the retention basin today. It appears that they are almost finished with grading it out.Steve Robbins 06/22/2018 3:12 PM
Sanitary Sewer Construction Inspection Partial 6/22/2018 at 2:00 PM 06/22/2018
PW-Main inspection
Informational
06/21/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
06/21/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
06/21/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
06/22/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
Sanitary Sewer Construction Inspection Partial 6/25/2018 at 11:30 AM 06/25/2018
PW-Main inspection
Informational
06/22/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
06/22/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
06/22/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
06/22/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
06/25/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
Sanitary Sewer Construction Inspection Partial 7/2/2018 at 9:00 AM 07/02/2018
PW-Main inspection
Informational
06/25/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
06/25/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
06/25/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
06/25/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
06/25/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/02/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
Retention Basin Partial 7/2/2018 at 9:30 AM 07/02/2018
PW-Misc
Informational
06/18/2018
The last 3 days Shaw Construction has been excavating and grading the retention basin on the back side of the property, they have not installed any storm structures yet.Steve Robbins 06/08/2018 3:30 PM
PW-Misc
Informational
06/18/2018
Shaw is still working on getting the retention basin excavated.Steve Robbins 06/11/2018 9:33 AM
PW-Misc
Informational
06/18/2018
Blue Nile Construction has been working on the retention basin the last few working days. Shaw was gong ot install the storm structures but decided to start on the sanitary instead.Steve Robbins 06/18/2018 12:19 PM
Informational
07/02/2018
Shaw construction has the basin graded out for the most part, Bair is installing the structure but shaw hit the structure with a truck and they have to order a new one that was coming from the private side. The grading of the basin has pretty much been completed.Steve Robbins 07/02/2018 2:30 PM
Sanitary Sewer Construction Inspection Partial 7/5/2018 at 2:00 PM 07/05/2018
PW-Main inspection
Informational
07/02/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/02/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/02/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/02/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/02/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/02/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/05/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
Sanitary Sewer Construction Inspection Partial 7/10/2018 at 1:00 PM 07/10/2018
PW-Main inspection
Informational
07/05/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/05/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/05/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/05/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/05/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/05/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/05/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/10/2018
Blue Nile has set MH A-1 and are working toward A-2. They were not working today. They have still not core drill for line D out of existiong MH A-15.Steve Robbins 07/10/2018 3:39 PM
Sanitary Sewer Construction Inspection Partial 7/11/2018 at 11:30 AM 07/11/2018
PW-Main inspection
Informational
07/10/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/10/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/10/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/10/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/10/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/10/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/10/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/10/2018
Blue Nile has set MH A-1 and are working toward A-2. They were not working today. They have still not core drill for line D out of existing MH A-15.Steve Robbins 07/10/2018 3:39 PM
Informational
07/11/2018
No one working today.Steve Robbins 07/11/2018 3:53 PM
Sanitary Sewer Construction Inspection Partial 7/13/2018 at 1:15 PM 07/12/2018
PW-Main inspection
Informational
07/11/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/11/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/11/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/11/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/11/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/11/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/11/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/12/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
Sanitary Sewer Construction Inspection Partial 7/13/2018 at 12:45 PM 07/13/2018
PW-Main inspection
Informational
07/12/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/12/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/12/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/12/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/12/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/12/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/12/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/12/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
07/13/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
Sanitary Sewer Construction Inspection Partial 7/16/2018 at 11:00 AM 07/16/2018
PW-Main inspection
Informational
07/13/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/13/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/13/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/13/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/13/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/13/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/13/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/13/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
07/13/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
07/16/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
Sanitary Sewer Construction Inspection Partial 7/17/2018 at 1:50 PM 07/17/2018
PW-Main inspection
Informational
07/16/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/16/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/16/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/16/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/16/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/16/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/16/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/16/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
07/16/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
07/16/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
07/17/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
Sanitary Sewer Construction Inspection Partial 7/23/2018 at 12:30 PM 07/23/2018
PW-Main inspection
Informational
07/17/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/17/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/17/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/17/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/17/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/17/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/17/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/17/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
07/17/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
07/17/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
07/17/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
07/23/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
Sanitary Sewer Construction Inspection Partial 7/30/2018 at 8:45 AM 07/30/2018
PW-Main inspection
Informational
07/23/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/23/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/23/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/23/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/23/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/23/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/23/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/23/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
07/23/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
07/23/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
07/23/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
07/23/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
07/30/2018
While I was gone last week, Jerry Smith filled in for me, they are still working toward MH a-3, they have hit even more rock. They are close to installing MH a-3.Steve Robbins 07/30/2018 2:06 PM
Storm - Outlet Structure Passed 7/30/2018 at 9:15 AM 07/30/2018
PW-Misc
Informational
07/30/2018
Outlet Structure 1-1 has been installed on the retention basin. Today they were having some of the storm surveyed so they can start installing the road crossings . They may be installing some storm structures tomorrow The outlet structure has passed..Steve Robbins 07/30/2018 2:30 PM
Grading/Excavation/Fill Inspection Partial 7/30/2018 at 9:45 AM 07/30/2018
PW-Misc
Informational
06/22/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
06/22/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
06/22/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
06/22/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
06/22/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
06/22/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
06/22/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
06/22/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
06/22/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
06/22/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
06/22/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
06/22/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
06/22/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
06/22/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
06/22/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
06/22/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
06/22/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
06/22/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
06/22/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
06/22/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
06/22/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
06/22/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
06/22/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
06/22/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
06/22/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
06/22/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
PW-Misc
Informational
06/22/2018
I was out of town all last week. While I was out Jeremy Young checked on this project. There was not much going on, there was alot of rain. Today i observed dirt and rock being moved and being compacted. I also spoke with Bair Excavating and they are planning on starting the private infrastructure for the apartments next week.Steve Robbins 05/30/2018 2:54 PM
PW-Misc
Informational
06/22/2018
There was no work being done on the retention basin today. It appears that they are almost finished with grading it out.Steve Robbins 06/22/2018 3:12 PM
PW-Misc
Informational
07/30/2018
The grading appears to be getting done correctly, and this will be ongoing for while out here.Steve Robbins 07/30/2018 2:37 PM
Sanitary Sewer Construction Inspection Partial 8/1/2018 at 1:30 PM 08/01/2018
PW-Main inspection
Informational
07/30/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
07/30/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
07/30/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
07/30/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
07/30/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
07/30/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
07/30/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
07/30/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
07/30/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
07/30/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
07/30/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
07/30/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
07/30/2018
While I was gone last week, Jerry Smith filled in for me, they are still working toward MH a-3, they have hit even more rock. They are close to installing MH a-3.Steve Robbins 07/30/2018 2:06 PM
PW-Main inspection
Informational
08/01/2018
MH A-3 has been installed ,they have started 1 stick of pipe coming out of the MH. They have pulled off sanitary today to start on some storm work.Steve Robbins 08/01/2018 2:49 PM
Storm - Pipe Partial 8/1/2018 at 1:50 PM 08/01/2018
PW-Misc
Informational
08/01/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
Storm - Pipe Partial 8/2/2018 at 1:15 PM 08/02/2018
PW-Misc
Informational
08/01/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/02/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
Storm - Pipe Partial 8/10/2018 at 2:00 PM 08/10/2018
PW-Misc
Informational
08/02/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/02/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
08/10/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
Water Line - Construction Inspection Partial 8/10/2018 at 2:20 PM 08/10/2018
PW-Main inspection
Informational
05/18/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
05/18/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
05/18/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
05/18/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
05/18/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
05/18/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
05/18/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
05/18/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
05/18/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
05/18/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
05/18/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
05/18/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
05/18/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
08/10/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
Water Line - Construction Inspection Partial 8/13/2018 at 1:00 PM 08/13/2018
PW-Main inspection
Informational
08/10/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
08/10/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
08/10/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
08/10/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
08/10/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
08/10/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
08/10/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
08/10/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
08/10/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
08/10/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
08/10/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
08/10/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
08/10/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
08/10/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
PW-Main inspection
Informational
08/13/2018
Blue Nile has installed the fire hydrant at station 3+08.73 along with the valve, they have also installed the thrust block. They have not installed fire hydrant at station 7+51.63 . They have also installed all the bends and thrust blocks going down kessler. They stopped when they got to the fire hydrant and now have jumped over to storm.Steve Robbins 08/13/2018 1:23 PM
Storm - Pipe Partial 8/13/2018 at 1:15 PM 08/13/2018
PW-Misc
Informational
08/10/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/10/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
08/10/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
08/13/2018
Structure 5-6 and 5-7 have been installed at the top of kessler. They have now moved down to village park and kessler and have installed 2-3 and 2-4 which is a road crossing, psi is out here doing the testing in lifts. The other crew is working on storm line 1 going toward field inlet 1-2, they are still hitting alot of rock.Steve Robbins 08/13/2018 1:38 PM
Storm - Pipe Partial 8/15/2018 at 3:15 PM 08/15/2018
PW-Misc
Informational
08/13/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/13/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
08/13/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
08/13/2018
Structure 5-6 and 5-7 have been installed at the top of kessler. They have now moved down to village park and kessler and have installed 2-3 and 2-4 which is a road crossing, psi is out here doing the testing in lifts. The other crew is working on storm line 1 going toward field inlet 1-2, they are still hitting alot of rock.Steve Robbins 08/13/2018 1:38 PM
PW-Misc
Informational
08/15/2018
They had a rain day yesterday, they are now installing pipe going toward structure 5-1. they also poured some collars for structures 2-3 and 2-4.Steve Robbins 08/15/2018 3:58 PM
Storm - Pipe Partial 8/22/2018 at 9:30 AM 08/22/2018
PW-Misc
Informational
08/15/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/15/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
08/15/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
08/15/2018
Structure 5-6 and 5-7 have been installed at the top of kessler. They have now moved down to village park and kessler and have installed 2-3 and 2-4 which is a road crossing, psi is out here doing the testing in lifts. The other crew is working on storm line 1 going toward field inlet 1-2, they are still hitting alot of rock.Steve Robbins 08/13/2018 1:38 PM
PW-Misc
Informational
08/15/2018
They had a rain day yesterday, they are now installing pipe going toward structure 5-1. they also poured some collars for structures 2-3 and 2-4.Steve Robbins 08/15/2018 3:58 PM
PW-Misc
Informational
08/22/2018
The structures of 5-1, 5-2,5-3, 5-4 and 6-1 have been installed. They are doing the compaction testing for all road crossing. They have also poured all the collars and inverts for these structures.Steve Robbins 08/22/2018 10:14 AM
Storm - Pipe Partial 8/29/2018 at 9:30 AM 08/29/2018
PW-Misc
Informational
08/22/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/22/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
08/22/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
08/22/2018
Structure 5-6 and 5-7 have been installed at the top of kessler. They have now moved down to village park and kessler and have installed 2-3 and 2-4 which is a road crossing, psi is out here doing the testing in lifts. The other crew is working on storm line 1 going toward field inlet 1-2, they are still hitting alot of rock.Steve Robbins 08/13/2018 1:38 PM
PW-Misc
Informational
08/22/2018
They had a rain day yesterday, they are now installing pipe going toward structure 5-1. they also poured some collars for structures 2-3 and 2-4.Steve Robbins 08/15/2018 3:58 PM
PW-Misc
Informational
08/22/2018
The structures of 5-1, 5-2,5-3, 5-4 and 6-1 have been installed. They are doing the compaction testing for all road crossing. They have also poured all the collars and inverts for these structures.Steve Robbins 08/22/2018 10:14 AM
Informational
08/29/2018
All the storm on Kessler dr . has been installed.They have run into an issue with the width of the road on village dr. They are on hold for now.Steve Robbins 08/29/2018 4:04 PM
Retention Basin Passed 8/30/2018 at 7:30 AM 08/30/2018
PW-Misc
Informational
07/02/2018
The last 3 days Shaw Construction has been excavating and grading the retention basin on the back side of the property, they have not installed any storm structures yet.Steve Robbins 06/08/2018 3:30 PM
PW-Misc
Informational
07/02/2018
Shaw is still working on getting the retention basin excavated.Steve Robbins 06/11/2018 9:33 AM
Informational
08/30/2018
The retention basin has been completed and appears to be built correctly. All the storm lines for the public and private have been tied into the retention basin.Steve Robbins 08/30/2018 8:47 AM
Water Line - Construction Inspection Partial 8/30/2018 at 7:45 AM 08/30/2018
PW-Main inspection
Informational
08/13/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
08/13/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
08/13/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
08/13/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
08/13/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
08/13/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
08/13/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
08/13/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
08/13/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
08/13/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
08/13/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
08/13/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
08/13/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
08/13/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
PW-Main inspection
Informational
08/13/2018
Blue Nile has installed the fire hydrant at station 3+08.73 along with the valve, they have also installed the thrust block. They have not installed fire hydrant at station 7+51.63 . They have also installed all the bends and thrust blocks going down kessler. They stopped when they got to the fire hydrant and now have jumped over to storm.Steve Robbins 08/13/2018 1:23 PM
PW-Main inspection
Informational
08/30/2018
I am waiting on the contractor to do the hydrostatic pressure test on this partial water line so we can get to the water sampling.Steve Robbins 08/30/2018 8:51 AM
Storm - Pipe Partial 8/30/2018 at 8:00 AM 08/30/2018
PW-Misc
Informational
08/29/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/29/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
08/29/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
08/29/2018
Structure 5-6 and 5-7 have been installed at the top of kessler. They have now moved down to village park and kessler and have installed 2-3 and 2-4 which is a road crossing, psi is out here doing the testing in lifts. The other crew is working on storm line 1 going toward field inlet 1-2, they are still hitting alot of rock.Steve Robbins 08/13/2018 1:38 PM
PW-Misc
Informational
08/29/2018
They had a rain day yesterday, they are now installing pipe going toward structure 5-1. they also poured some collars for structures 2-3 and 2-4.Steve Robbins 08/15/2018 3:58 PM
Informational
08/30/2018
The other crew from Blue Nile is working on Sanitary and Storm at the same time in part becuase they are running close to each other. We are sure to keep them a minimum of 10 ft of separation. The flared end section 1-1 and the field inlet 1-2 and they are working toward field inlet 1-3. They are also doing the sanitary at the same time.Steve Robbins 08/30/2018 9:05 AM
Sanitary Sewer Construction Inspection Partial 8/29/2018 08/30/2018
PW-Main inspection
Informational
08/01/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
08/01/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
08/01/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
08/01/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
08/01/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
08/01/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
08/01/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
08/01/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
08/01/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
08/01/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
08/01/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
08/01/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
08/01/2018
While I was gone last week, Jerry Smith filled in for me, they are still working toward MH a-3, they have hit even more rock. They are close to installing MH a-3.Steve Robbins 07/30/2018 2:06 PM
PW-Main inspection
Informational
08/01/2018
MH A-3 has been installed ,they have started 1 stick of pipe coming out of the MH. They have pulled off sanitary today to start on some storm work.Steve Robbins 08/01/2018 2:49 PM
Informational
08/30/2018
The Blue Nile has installed MH A-4 and is laying pipe toward A-5 as they are also installing the storm pipe at the same time.Steve Robbins 08/30/2018 9:33 AM
Grading/Excavation/Fill Inspection Partial 9/4/2018 at 7:00 AM 09/04/2018
PW-Misc
Informational
07/30/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
07/30/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
07/30/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
07/30/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
07/30/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
07/30/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
07/30/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
07/30/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
07/30/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
07/30/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
07/30/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
07/30/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
07/30/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
07/30/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
07/30/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
07/30/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
07/30/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
07/30/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
07/30/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
07/30/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
07/30/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
07/30/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
07/30/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
07/30/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
07/30/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
07/30/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
PW-Misc
Informational
07/30/2018
I was out of town all last week. While I was out Jeremy Young checked on this project. There was not much going on, there was alot of rain. Today i observed dirt and rock being moved and being compacted. I also spoke with Bair Excavating and they are planning on starting the private infrastructure for the apartments next week.Steve Robbins 05/30/2018 2:54 PM
PW-Misc
Informational
07/30/2018
There was no work being done on the retention basin today. It appears that they are almost finished with grading it out.Steve Robbins 06/22/2018 3:12 PM
PW-Misc
Informational
07/30/2018
The grading appears to be getting done correctly, and this will be ongoing for while out here.Steve Robbins 07/30/2018 2:37 PM
Informational
09/04/2018
The contractors are continuing to do grading on this site.Steve Robbins 09/04/2018 7:20 AM
Storm - Pipe Partial 9/4/2018 at 10:40 AM 09/04/2018
PW-Misc
Informational
08/30/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
08/30/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
08/30/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
08/30/2018
Structure 5-6 and 5-7 have been installed at the top of kessler. They have now moved down to village park and kessler and have installed 2-3 and 2-4 which is a road crossing, psi is out here doing the testing in lifts. The other crew is working on storm line 1 going toward field inlet 1-2, they are still hitting alot of rock.Steve Robbins 08/13/2018 1:38 PM
Informational
09/04/2018
Field inlet 1-3 has been installed and the other crew is working on connecting 2-5 toward 2-6 . They have also been pouring the collars around the pipes on the storm box structures.Steve Robbins 09/04/2018 11:31 AM
Sanitary Sewer Construction Inspection Partial 9/4/2018 at 10:55 AM 09/04/2018
PW-Main inspection
Informational
08/30/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
08/30/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
08/30/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
08/30/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
08/30/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
08/30/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
08/30/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
08/30/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
08/30/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
08/30/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
08/30/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
08/30/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
08/30/2018
While I was gone last week, Jerry Smith filled in for me, they are still working toward MH a-3, they have hit even more rock. They are close to installing MH a-3.Steve Robbins 07/30/2018 2:06 PM
Corrective Action Required
09/04/2018
The contractors are working and going toward a-5. The storm and sanitary are runing parallel with each other and appear to be 10 ft. apart. When I spot check it is good.Steve Robbins 09/04/2018 11:54 AM
Storm - Pipe Partial 9/11/2018 at 1:40 PM 09/11/2018
PW-Misc
Informational
09/04/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
09/04/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
09/04/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
09/11/2018
Storm structure 2-6, 2-7 and 4-1 structure has been installed. 4-1 flared end section has not been installed yet.. The collars have been poured for everything up to 4-1. The other crew is working on coming off of structure 1-3, today they have hit rock.Steve Robbins 09/11/2018 2:50 PM
Sanitary Sewer Construction Inspection Partial 9/11/2018 at 1:50 PM 09/11/2018
PW-Main inspection
Informational
09/04/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
09/04/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
09/04/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
09/04/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
09/04/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
09/04/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
09/04/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
09/04/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
09/04/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
09/04/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
09/04/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
09/04/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
09/11/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
Sanitary Sewer Construction Inspection Partial 9/11/2018 at 2:50 PM 09/11/2018
PW-Main inspection
Informational
09/11/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
09/11/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
09/11/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
09/11/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
09/11/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
09/11/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
09/11/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
09/11/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
09/11/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
09/11/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
Fire Line - Hydrostatic Test Partial 9/10/2018 at 9:00 AM 09/13/2018
PW-Misc
Informational
09/12/2018
This is a partial test, this starts on Kessler at the top of the hill on view high dr. at the valve and goes to the first fire hydrant on the south side of the street. They used granuales to chlorinate. They filled the line with water and did a hydrostatic test , he kept it at 190 for 2 hrs. After we took the test we dechlorinated and flushed the line so it could sit 24 hours.Steve Robbins 09/12/2018 11:51 AM
Storm - Pipe Partial 9/14/2018 at 9:00 AM 09/14/2018
PW-Misc
Informational
09/11/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
09/11/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
09/11/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
09/11/2018
Storm structure 2-6, 2-7 and 4-1 structure has been installed. 4-1 flared end section has not been installed yet.. The collars have been poured for everything up to 4-1. The other crew is working on coming off of structure 1-3, today they have hit rock.Steve Robbins 09/11/2018 2:50 PM
PW-Misc
Informational
09/14/2018
Structure 1-4 has been installed. All the collars have been installed. They are working toward structure 1-5.Steve Robbins 09/14/2018 11:23 AM
Sanitary Sewer Construction Inspection Partial 9/14/2018 at 10:30 AM 09/14/2018
PW-Main inspection
Informational
09/11/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
09/11/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
09/11/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
09/11/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
09/11/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
09/11/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
09/11/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
09/11/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
09/11/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
09/11/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
09/11/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
PW-Main inspection
Informational
09/14/2018
The Blue Nile crew is still working towards MH A-6, they have hit some rock and have slowed down again. They were not working today.Steve Robbins 09/14/2018 3:52 PM
Water Line - Coliform Test 1 Partial 9/14/2018 at 2:30 PM 09/14/2018
PW-Misc
Informational
09/14/2018
Casey from Blue Nile chlroinated the water line coming down kessler and we dechlorinated and flushed today. On Monday we will take the first sample.Steve Robbins 09/14/2018 4:01 PM
Storm - Pipe Partial 9/18/2018 at 11:00 AM 09/18/2018
PW-Misc
Informational
09/14/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
09/14/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
09/14/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
09/14/2018
Storm structure 2-6, 2-7 and 4-1 structure has been installed. 4-1 flared end section has not been installed yet.. The collars have been poured for everything up to 4-1. The other crew is working on coming off of structure 1-3, today they have hit rock.Steve Robbins 09/11/2018 2:50 PM
PW-Misc
Informational
09/14/2018
Structure 1-4 has been installed. All the collars have been installed. They are working toward structure 1-5.Steve Robbins 09/14/2018 11:23 AM
PW-Misc
Informational
09/18/2018
As of today they have installed all the storm structures, all the pipes have been connected. They are planning on finishing the collars and pouring the inverts and then they are going to flush the line because it has some mudd in it.Steve Robbins 09/18/2018 3:56 PM
Sanitary Sewer Construction Inspection Partial 9/21/2018 at 11:15 AM 09/21/2018
PW-Main inspection
Informational
09/14/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
09/14/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
09/14/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
09/14/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
09/14/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
09/14/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
09/14/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
09/14/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
09/14/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
09/14/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
09/14/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
09/14/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
09/14/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
09/14/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
PW-Main inspection
Informational
09/14/2018
The Blue Nile crew is still working towards MH A-6, they have hit some rock and have slowed down again. They were not working today.Steve Robbins 09/14/2018 3:52 PM
PW-Main inspection
Informational
09/21/2018
they will start working toward A-6 again next week. Yesterday they were finishing up D-line, They has to replace to cone on MH D-1 because it was cracked and chipped up.. I watched them back-fill and everything seems to be up to standards.Steve Robbins 09/21/2018 3:54 PM
Storm - Pipe Partial 9/21/2018 at 11:30 AM 09/21/2018
PW-Misc
Informational
09/18/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
09/18/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
09/18/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
09/18/2018
Storm structure 2-6, 2-7 and 4-1 structure has been installed. 4-1 flared end section has not been installed yet.. The collars have been poured for everything up to 4-1. The other crew is working on coming off of structure 1-3, today they have hit rock.Steve Robbins 09/11/2018 2:50 PM
PW-Misc
Informational
09/18/2018
Structure 1-4 has been installed. All the collars have been installed. They are working toward structure 1-5.Steve Robbins 09/14/2018 11:23 AM
PW-Misc
Informational
09/18/2018
As of today they have installed all the storm structures, all the pipes have been connected. They are planning on finishing the collars and pouring the inverts and then they are going to flush the line because it has some mudd in it.Steve Robbins 09/18/2018 3:56 PM
PW-Misc
Informational
09/21/2018
They have completed all the storm structures and installed all the collars and they have tested all the road crossings. They still have to pour all the inverts for the storm boxes.Steve Robbins 09/21/2018 3:58 PM
Sanitary Sewer Construction Inspection Partial 9/25/2018 at 8:45 AM 09/25/2018
PW-Main inspection
Informational
09/21/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
09/21/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
09/21/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
09/21/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
09/21/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
09/21/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
09/21/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
09/21/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
09/21/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
09/21/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
09/21/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
09/21/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
09/21/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
09/21/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
PW-Main inspection
Informational
09/21/2018
The Blue Nile crew is still working towards MH A-6, they have hit some rock and have slowed down again. They were not working today.Steve Robbins 09/14/2018 3:52 PM
PW-Main inspection
Informational
09/21/2018
they will start working toward A-6 again next week. Yesterday they were finishing up D-line, They has to replace to cone on MH D-1 because it was cracked and chipped up.. I watched them back-fill and everything seems to be up to standards.Steve Robbins 09/21/2018 3:54 PM
PW-Main inspection
Informational
09/25/2018
MH A-6 has been installed, it has been wrapped and backfilled. None of the inverts have been poured yet. The A-line is 12" . They are working toward A-7, they will set that MH today. A-7 to A-8 will reduce down to 8".Steve Robbins 09/25/2018 10:02 AM
PW-Main inspection
Informational
09/27/2018
The blue nile is working on MH A-8, they are also working on the crossing for b-line and c -line MH"s. They are installing rock and backfilling with dirt.Steve Robbins 09/27/2018 1:00 PM
Pavement-Stabilized Subgrade Partial 9/24/2018 at 11:11 AM 09/25/2018
PW-Misc
Informational
09/25/2018
Shaw Construction has installed portland cement for the road on Kessler, They till in 9 inches of portlandl, they used a tiller and they had a water truck connected. They are letting it set up over the weekenc. They are planning on finishing grading on tuesday and doing a proofroll on tuesday afternoo.
Water Line - Construction Inspection Partial 9/25/2018 at 9:30 AM 09/25/2018
PW-Main inspection
Informational
08/30/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
08/30/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
08/30/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
08/30/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
08/30/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
08/30/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
08/30/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
08/30/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
08/30/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
08/30/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
08/30/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
08/30/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
08/30/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
08/30/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
PW-Main inspection
Informational
08/30/2018
Blue Nile has installed the fire hydrant at station 3+08.73 along with the valve, they have also installed the thrust block. They have not installed fire hydrant at station 7+51.63 . They have also installed all the bends and thrust blocks going down kessler. They stopped when they got to the fire hydrant and now have jumped over to storm.Steve Robbins 08/13/2018 1:23 PM
PW-Main inspection
Informational
08/30/2018
I am waiting on the contractor to do the hydrostatic pressure test on this partial water line so we can get to the water sampling.Steve Robbins 08/30/2018 8:51 AM
PW-Main inspection
Informational
09/25/2018
They are continuing to install the water line, they are at the corner kessler dr. The plans only showed 2 valves, i spoke with Gene and he said we needed 3. Blue Nile agreed to install the other. We are at the end where we have an in- line fire hydrant. That has been installed at the end of kessler.Steve Robbins 09/25/2018 10:21 AM
Sanitary Sewer Construction Inspection Partial 9/27/2018 at 12:45 PM 09/27/2018
PW-Main inspection
Informational
09/25/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
09/25/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
09/25/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
09/25/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
09/25/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
09/25/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
09/25/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
09/25/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
09/25/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
09/25/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
09/25/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
09/25/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
09/25/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
09/25/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
PW-Main inspection
Informational
09/25/2018
The Blue Nile crew is still working towards MH A-6, they have hit some rock and have slowed down again. They were not working today.Steve Robbins 09/14/2018 3:52 PM
PW-Main inspection
Informational
09/25/2018
they will start working toward A-6 again next week. Yesterday they were finishing up D-line, They has to replace to cone on MH D-1 because it was cracked and chipped up.. I watched them back-fill and everything seems to be up to standards.Steve Robbins 09/21/2018 3:54 PM
PW-Main inspection
Informational
09/25/2018
MH A-6 has been installed, it has been wrapped and backfilled. None of the inverts have been poured yet. The A-line is 12" . They are working toward A-7, they will set that MH today. A-7 to A-8 will reduce down to 8".Steve Robbins 09/25/2018 10:02 AM
PW-Main inspection
Informational
09/27/2018
-------------------------------------- The blue nile is working on MH A-8, they are also working on the crossing for b-line and c -line MH"s. They are installing rock and backfilling with dirt.Steve Robbins 09/27/2018 1:00 PM
Curb - Proof Roll Partial 9/27/2018 at 12:30 PM 09/27/2018
PW-Misc
Informational
09/27/2018
The proof roll for the curbs on Kessler has been completed and has passed.Steve Robbins 09/27/2018 1:10 PM
Water Line - Construction Inspection Partial 9/27/2018 at 2:00 PM 09/27/2018
PW-Main inspection
Informational
09/25/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
09/25/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
09/25/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
09/25/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
09/25/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
09/25/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
09/25/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
09/25/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
09/25/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
09/25/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
09/25/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
09/25/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
09/25/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
09/25/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
PW-Main inspection
Informational
09/25/2018
Blue Nile has installed the fire hydrant at station 3+08.73 along with the valve, they have also installed the thrust block. They have not installed fire hydrant at station 7+51.63 . They have also installed all the bends and thrust blocks going down kessler. They stopped when they got to the fire hydrant and now have jumped over to storm.Steve Robbins 08/13/2018 1:23 PM
PW-Main inspection
Informational
09/25/2018
I am waiting on the contractor to do the hydrostatic pressure test on this partial water line so we can get to the water sampling.Steve Robbins 08/30/2018 8:51 AM
PW-Main inspection
Informational
09/25/2018
They are continuing to install the water line, they are at the corner kessler dr. The plans only showed 2 valves, i spoke with Gene and he said we needed 3. Blue Nile agreed to install the other. We are at the end where we have an in- line fire hydrant. That has been installed at the end of kessler.Steve Robbins 09/25/2018 10:21 AM
PW-Main inspection
Informational
09/27/2018
the blue nile has been working on the 12" waterline going down village park dr. They are working toward the fire hydrant with the in-line valve. They are also going to install a road crossing for the connection of the back-flow preventer and water meter vault.Steve Robbins 09/27/2018 1:22 PM
Curb - Proof Roll Partial 9/27/2018 at 1:00 PM 09/27/2018
PW-Misc
Informational
09/27/2018
The proof roll for the curbs on Kessler has been completed and has passed.Steve Robbins 09/27/2018 1:10 PM
Sanitary Sewer Construction Inspection Partial 10/1/2018 at 9:45 AM 10/01/2018
PW-Main inspection
Informational
09/27/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
09/27/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
09/27/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
09/27/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
09/27/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
09/27/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
09/27/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
09/27/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
09/27/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
09/27/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
09/27/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
09/27/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
09/27/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
09/27/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
PW-Main inspection
Informational
09/27/2018
The Blue Nile crew is still working towards MH A-6, they have hit some rock and have slowed down again. They were not working today.Steve Robbins 09/14/2018 3:52 PM
PW-Main inspection
Informational
09/27/2018
they will start working toward A-6 again next week. Yesterday they were finishing up D-line, They has to replace to cone on MH D-1 because it was cracked and chipped up.. I watched them back-fill and everything seems to be up to standards.Steve Robbins 09/21/2018 3:54 PM
PW-Main inspection
Informational
09/27/2018
MH A-6 has been installed, it has been wrapped and backfilled. None of the inverts have been poured yet. The A-line is 12" . They are working toward A-7, they will set that MH today. A-7 to A-8 will reduce down to 8".Steve Robbins 09/25/2018 10:02 AM
PW-Main inspection
Informational
09/27/2018
-------------------------------------- The blue nile is working on MH A-8, they are also working on the crossing for b-line and c -line MH"s. They are installing rock and backfilling with dirt.Steve Robbins 09/27/2018 1:00 PM
PW-Main inspection
Informational
10/01/2018
All of A-line has been installed and backfilled as of9/26. They are working on b-line and c-line today and tomorrow.Steve Robbins 10/01/2018 11:30 AM
Water Line - Construction Inspection Partial 10/1/2018 at 10:00 AM 10/01/2018
PW-Main inspection
Informational
09/27/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
09/27/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
09/27/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
09/27/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
09/27/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
09/27/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
09/27/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
09/27/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
09/27/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
09/27/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
09/27/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
09/27/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
09/27/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
09/27/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
PW-Main inspection
Informational
09/27/2018
Blue Nile has installed the fire hydrant at station 3+08.73 along with the valve, they have also installed the thrust block. They have not installed fire hydrant at station 7+51.63 . They have also installed all the bends and thrust blocks going down kessler. They stopped when they got to the fire hydrant and now have jumped over to storm.Steve Robbins 08/13/2018 1:23 PM
PW-Main inspection
Informational
09/27/2018
I am waiting on the contractor to do the hydrostatic pressure test on this partial water line so we can get to the water sampling.Steve Robbins 08/30/2018 8:51 AM
PW-Main inspection
Informational
09/27/2018
They are continuing to install the water line, they are at the corner kessler dr. The plans only showed 2 valves, i spoke with Gene and he said we needed 3. Blue Nile agreed to install the other. We are at the end where we have an in- line fire hydrant. That has been installed at the end of kessler.Steve Robbins 09/25/2018 10:21 AM
PW-Main inspection
Informational
09/27/2018
the blue nile has been working on the 12" waterline going down village park dr. They are working toward the fire hydrant with the in-line valve. They are also going to install a road crossing for the connection of the back-flow preventer and water meter vault.Steve Robbins 09/27/2018 1:22 PM
PW-Main inspection
Informational
10/01/2018
The fire hydrant for station 7+51.63 has been installed and the temorary in line fire hydrand on station 9+21.12. They have also installed the in-line fire hydrand for station 10+16.45. The 12" water line for the temp in line fire hydrant has been installed. Steve Robbins 10/01/2018 11:42 AM
Sanitary Sewer Construction Inspection Partial 10/2/2018 at 9:00 AM 10/03/2018
PW-Main inspection
Informational
10/01/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
10/01/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
10/01/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
10/01/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
10/01/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
10/01/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
10/01/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
10/01/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
10/01/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
10/01/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
10/01/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
10/01/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
10/01/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
10/01/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
PW-Main inspection
Informational
10/01/2018
The Blue Nile crew is still working towards MH A-6, they have hit some rock and have slowed down again. They were not working today.Steve Robbins 09/14/2018 3:52 PM
PW-Main inspection
Informational
10/01/2018
they will start working toward A-6 again next week. Yesterday they were finishing up D-line, They has to replace to cone on MH D-1 because it was cracked and chipped up.. I watched them back-fill and everything seems to be up to standards.Steve Robbins 09/21/2018 3:54 PM
PW-Main inspection
Informational
10/01/2018
MH A-6 has been installed, it has been wrapped and backfilled. None of the inverts have been poured yet. The A-line is 12" . They are working toward A-7, they will set that MH today. A-7 to A-8 will reduce down to 8".Steve Robbins 09/25/2018 10:02 AM
PW-Main inspection
Informational
10/01/2018
-------------------------------------- The blue nile is working on MH A-8, they are also working on the crossing for b-line and c -line MH"s. They are installing rock and backfilling with dirt.Steve Robbins 09/27/2018 1:00 PM
PW-Main inspection
Informational
10/01/2018
All of A-line has been installed and backfilled as of9/26. They are working on b-line and c-line today and tomorrow.Steve Robbins 10/01/2018 11:30 AM
PW-Main inspection
Informational
10/03/2018
Testing can begin with existing MH a-15 to MH a-1 and a-1 to a-6. These have all been in for 30 days. A-6 to A-8. On my plans I have A-6 going in on 9/3, i had the numbers of the MH confused in cityview. Everything is good to test up[ to A-6.Steve Robbins 10/03/2018 11:21 AM
Water Line - Construction Inspection Partial 10/3/2018 at 11:45 AM 10/03/2018
PW-Main inspection
Informational
10/01/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
10/01/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
10/01/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
10/01/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
10/01/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
10/01/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
10/01/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
10/01/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
10/01/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
10/01/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
10/01/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
10/01/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
10/01/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
10/01/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
PW-Main inspection
Informational
10/01/2018
Blue Nile has installed the fire hydrant at station 3+08.73 along with the valve, they have also installed the thrust block. They have not installed fire hydrant at station 7+51.63 . They have also installed all the bends and thrust blocks going down kessler. They stopped when they got to the fire hydrant and now have jumped over to storm.Steve Robbins 08/13/2018 1:23 PM
PW-Main inspection
Informational
10/01/2018
I am waiting on the contractor to do the hydrostatic pressure test on this partial water line so we can get to the water sampling.Steve Robbins 08/30/2018 8:51 AM
PW-Main inspection
Informational
10/01/2018
They are continuing to install the water line, they are at the corner kessler dr. The plans only showed 2 valves, i spoke with Gene and he said we needed 3. Blue Nile agreed to install the other. We are at the end where we have an in- line fire hydrant. That has been installed at the end of kessler.Steve Robbins 09/25/2018 10:21 AM
PW-Main inspection
Informational
10/01/2018
the blue nile has been working on the 12" waterline going down village park dr. They are working toward the fire hydrant with the in-line valve. They are also going to install a road crossing for the connection of the back-flow preventer and water meter vault.Steve Robbins 09/27/2018 1:22 PM
PW-Main inspection
Informational
10/01/2018
The fire hydrand for station 7+51.63 has been installed and the temorary in line fire hydrand on station 9+21.12. They have also installed the in-line fire hydrand for station 10+16.45. The 12" water line for the temp in line fire hydrant has been installed. Steve Robbins 10/01/2018 11:42 AM
PW-Main inspection
Informational
10/03/2018
The water line has been installed except for the crossing on village park dr. We are also waiting for 2 butterfly valves. Steve Robbins 10/03/2018 11:51 AM
Sanitary Sewer - Air Test Partial 10/3/2018 10/04/2018
PW-Misc
Informational
10/04/2018
We are doing air testing MH A-6 to A-5, A-5 to A-4, and A-4 to A-3 have all passed the air test.Steve Robbins 10/04/2018 8:24 AM
Pavement-Proof Roll Partial 10/5/2018 at 7:30 AM 10/08/2018
PW-Misc
Informational
10/08/2018
The proofroll passed and they had 2 trucks full of asphalt that they put down, it rained and we had to call it off for the day. It rained alot over the weekend so we will have to do another proofroll when it drys out.Steve Robbins 10/08/2018 8:01 AM
Pavement-Curb Construction Passed 9/28/2018 10/08/2018
PW-Curb Construction
Informational
10/08/2018
The new curbs for kessler has been installed and have passed all the tests. This will be a partial because we still have the other main road to do and cant start yet because of sanitary testing .Steve Robbins 10/08/2018 8:09 AM
Sanitary Sewer - Air Test Partial 10/4/2018 at 2:30 PM 10/10/2018
PW-Misc
Informational
10/04/2018
We are doing air testing MH A-6 to A-5, A-5 to A-4, and A-4 to A-3 have all passed the air test.Steve Robbins 10/04/2018 8:24 AM
PW-Sanitary Sewer Testing
Informational
10/10/2018
Sanitary Sewer Testing needs to be completed. Joe Starlin stayed late and finished the testing. Everything from A-6 to existing MH A-15 has been air tested and has passed.Steve Robbins 10/10/2018 3:11 PM
Storm - Material Verification Passed 10/12/2018
Pavement-Surface Partial 10/5/2018 at 8:00 AM 10/12/2018
PW-Misc
Informational
10/12/2018
The contractors were able to install 2 truck loads of asphalt. It started raining so they had to stop installing. Steve Robbins 10/12/2018 1:54 PM
Pavement-Surface Partial 10/17/2018 10/22/2018
PW-Misc
Informational
10/12/2018
The contractors were able to install 2 truck loads of asphalt. It started raining so they had to stop installing. Steve Robbins 10/12/2018 1:54 PM
Pavement-Proof Roll Partial 10/22/2018 10/24/2018
PW-Misc
Informational
10/08/2018
The proofroll passed and they had 2 trucks full of asphalt that they put down, it rained and we had to call it off for the day. It rained alot over the weekend so we will have to do another proofroll when it drys out.Steve Robbins 10/08/2018 8:01 AM
PW-Misc
Informational
10/24/2018
A proofroll for kessler dr. Was completed for me while i was off on friday 10/19/18. They also did a string line test . This was the second proofroll done , they were not able to get asphalt in after the first proof roll. This proofroll passed and they are putting in ashphalt today. This is a partial proofroll as we will need to proofroll the other street that connects to Kessler.Steve Robbins 10/24/2018 2:48 PM
Pavement-Surface Partial 10/22/2018 at 8:00 AM 10/24/2018
PW-Misc
Informational
10/22/2018
The contractors were able to install 2 truck loads of asphalt. It started raining so they had to stop installing. Steve Robbins 10/12/2018 1:54 PM
PW-Misc
Informational
10/24/2018
The base asphal of 7.5 " has been installed, it was installed in 2 lifts of 3.5 and 4". This was done after a proofroll was completed and they filled in some ruts after the rain with Mo-type 5. They also had one section of curb that the rock was washed out underneath the curb. The contractor installed flow-fill under the curb. This is for kessler st.
Sanitary Sewer Construction Inspection Passed 10/24/2018 at 3:00 PM 10/24/2018
PW-Main inspection
Informational
10/03/2018
Brice Lawson 06/12/2018 5:05 PM Larry Bair Construction continued installing the 8" SDR 26 sewer main between MH A6 and MH C1. The service wye has been installed. I informed them that a trench check will be required on the stub. The 8" main was installed to point approx. 18' upstream of the serice wye.
PW-Main inspection
Informational
10/03/2018
Blue Nile has exposed the existing MH a-15, and are planning on doing the core driill this afternoon. I have checked the pipe that is on site. This is public sanitary.Steve Robbins 06/18/2018 12:31 PM
PW-Main inspection
Informational
10/03/2018
Blue Nile did not appear to be working today.Steve Robbins 06/21/2018 3:57 PM
PW-Main inspection
Corrective Action Required
10/03/2018
They have done a core drill for the A-line coming out of MH A-15. They did not do the core drill fo the D-line coming out of MH A-15,. The contractors -(Blue Nile) were not working today.Steve Robbins 06/22/2018 3:17 PM
PW-Main inspection
Informational
10/03/2018
No work today due to the rain this morning.Steve Robbins 06/25/2018 3:45 PM
PW-Main inspection
Informational
10/03/2018
Blue Nile was not working today, they are still laying pipe starting from existing MH A-15.Steve Robbins 07/02/2018 2:23 PM
PW-Main inspection
Informational
10/03/2018
Blue Nile is not working for the rest of the week, it appears that they have installed 1 stick of pipe from existing MH A-15.Steve Robbins 07/05/2018 3:13 PM
PW-Main inspection
Informational
10/03/2018
MH A-1 has been installed, they forgot to install sanitary sewer tape, they will bring it tomorrow and install . They are hitting rock and moving slow, they are heading toward MH A-2. MH A-3 that is on-site has a drop set up, I talked with Brian, it does not show this on the plans. He is looking into it.Steve Robbins 07/12/2018 2:06 PM
PW-Main inspection
Informational
10/03/2018
It appears that Blue Nile is not working today.Steve Robbins 07/13/2018 1:14 PM
PW-Main inspection
Informational
10/03/2018
It appears that Blue Nile is not working today.Steve Robbins 07/16/2018 3:01 PM
PW-Main inspection
Informational
10/03/2018
They are working today installing pipe, they also have the sanitary tape. They are hitting alot of rock.Steve Robbins 07/17/2018 3:59 PM
PW-Main inspection
Informational
10/03/2018
Blue Nile did not work on friday, they are working today heading toward MH a-3 , they are hitting alot of rock , they have installed 2 sticks of pipe today.Steve Robbins 07/23/2018 2:02 PM
PW-Main inspection
Informational
10/03/2018
The blue nile crew has been installing sanitary along side the storm, they are keeping the 10 feet distance between them. They are now on MH A-5 and are working toward A-6. This is public and they are installing sewer tape and rock around the pipe.Steve Robbins 09/11/2018 2:59 PM
PW-Main inspection
Informational
10/03/2018
Bair has core drill into the public sanitary A-4 MH. They have connected to the city public line and are installing and 8" private main. There are 3 wyes on this main.Steve Robbins 09/11/2018 3:07 PM
PW-Main inspection
Informational
10/03/2018
The Blue Nile crew is still working towards MH A-6, they have hit some rock and have slowed down again. They were not working today.Steve Robbins 09/14/2018 3:52 PM
PW-Main inspection
Informational
10/03/2018
they will start working toward A-6 again next week. Yesterday they were finishing up D-line, They has to replace to cone on MH D-1 because it was cracked and chipped up.. I watched them back-fill and everything seems to be up to standards.Steve Robbins 09/21/2018 3:54 PM
PW-Main inspection
Informational
10/03/2018
MH A-6 has been installed, it has been wrapped and backfilled. None of the inverts have been poured yet. The A-line is 12" . They are working toward A-7, they will set that MH today. A-7 to A-8 will reduce down to 8".Steve Robbins 09/25/2018 10:02 AM
PW-Main inspection
Informational
10/03/2018
-------------------------------------- The blue nile is working on MH A-8, they are also working on the crossing for b-line and c -line MH"s. They are installing rock and backfilling with dirt.Steve Robbins 09/27/2018 1:00 PM
PW-Main inspection
Informational
10/03/2018
All of A-line has been installed and backfilled as of9/26. They are working on b-line and c-line today and tomorrow.Steve Robbins 10/01/2018 11:30 AM
PW-Main inspection
Informational
10/03/2018
Testing can begin with existing MH a-15 to MH a-1 and a-1 to a-6. These have all been in for 30 days. A-6 to A-8. On my plans I have A-6 going in on 9/3, i had the numbers of the MH confused in cityview. Everything is good to test up[ to A-6.Steve Robbins 10/03/2018 11:21 AM
Misc
Informational
10/24/2018
All the sanitary lines have been installed as of 10/3/18. The testing for the remainder of the sanitary lines can be tested on friday 11/2/18. Steve Robbins 10/24/2018 3:21 PM
Pavement-Stabilized Subgrade Partial 10/24/2018 10/24/2018
PW-Misc
Informational
09/25/2018
Shaw Construction has installed portland cement for the road on Kessler, They till in 9 inches of portlandl, they used a tiller and they had a water truck connected. They are letting it set up over the weekenc. They are planning on finishing grading on tuesday and doing a proofroll on tuesday afternoo.
PW-Misc
Informational
10/24/2018
They are not going to stabilize the other streets subgrade until the sanitary passes all the road crossings.Steve Robbins 10/24/2018 3:28 PM
Pavement-Stabilized Subgrade Partial 11/1/2018 at 7:00 AM 11/01/2018
PW-Misc
Informational
10/24/2018
Shaw Construction has installed portland cement for the road on Kessler, They till in 9 inches of portlandl, they used a tiller and they had a water truck connected. They are letting it set up over the weekenc. They are planning on finishing grading on tuesday and doing a proofroll on tuesday afternoo.
PW-Misc
Informational
10/24/2018
They are not going to stabilize the other streets subgrade until the sanitary passes all the road crossings.Steve Robbins 10/24/2018 3:28 PM
Misc
Informational
11/01/2018
Shaw Construction is out grading for the road on Village Park Dr, they are plannig on using portland for their subgrade stabilization.Steve Robbins 11/01/2018 7:19 AM
Water Line - Coliform Test 1 Failed 11/1/2018 at 1:00 PM 11/01/2018
PW-Misc
Informational
09/14/2018
Casey from Blue Nile chlroinated the water line coming down kessler and we dechlorinated and flushed today. On Monday we will take the first sample.Steve Robbins 09/14/2018 4:01 PM
Miscellaneous Correction
Corrective Action Required
11/01/2018
The first round of samples has failed, the contractor flushed and we started over. I took the first second round and the first samples failed. I was already there with the second set of samples and found out they failed so blue nile just had me have them try anyway. I will find out this afternoon if they passed or failed.Steve Robbins 11/01/2018 8:06 AM
Grading/Excavation/Fill Inspection Partial 10/23/2018 at 1:00 PM 11/01/2018
PW-Misc
Informational
09/04/2018
No work going on here today.Steve Robbins 01/02/2018 3:33 PM
PW-Misc
Informational
09/04/2018
The contractors are working on fill dirt today.Steve Robbins 01/05/2018 3:57 PM
PW-Misc
Informational
09/04/2018
They are doing some grading and brought in some dirt.Steve Robbins 01/10/2018 11:29 AM
PW-Misc
Informational
09/04/2018
No work today.Steve Robbins 01/11/2018 2:08 PM
PW-Misc
Informational
09/04/2018
The the contractors are moving the large pile of dirt behind the B&B Theater over to the the Village View High project. They said they are getting compaction tests as they go while they are filling in.Steve Robbins 01/19/2018 3:39 PM
PW-Misc
Informational
09/04/2018
Not much was going on today, I spoke with the owner who just happened to be out on site, they are having compaction tests done on the fill dirt going in. I let him know I will need the results when they are finished.Steve Robbins 01/23/2018 3:48 PM
PW-Misc
Informational
09/04/2018
The contractors are working on grading and fill- dirt today.Steve Robbins 01/29/2018 11:13 AM
PW-Misc
Informational
09/04/2018
The contractors are bringing in dirt for fill today.Steve Robbins 01/30/2018 3:30 PM
PW-Misc
Informational
09/04/2018
The contractors are still bringing in dirt for fill.
PW-Misc
Informational
09/04/2018
No work is going on here today, Steve Robbins 02/06/2018 11:50 AM
PW-Misc
Informational
09/04/2018
No grading was going on today.Steve Robbins 02/07/2018 3:50 PM
PW-Misc
Informational
09/04/2018
The contractors are bringing in more fill dirt today.Steve Robbins 02/09/2018 2:04 PM
PW-Misc
Corrective Action Required
09/04/2018
The contractors are doing grading and bringing in fill dirt, they are also getting compaction tests.Steve Robbins 02/14/2018 3:44 PM
PW-Misc
Informational
09/04/2018
No work has been going on due to the weather. I talked with the contractor and they are planning on starting the water line on monday as they have dropped off some of the pipe.Steve Robbins 02/22/2018 3:17 PM
PW-Misc
Informational
09/04/2018
The contractors were bringing in more fill dirt today, they have not been able to work all last week.Steve Robbins 03/05/2018 3:34 PM
PW-Misc
Informational
09/04/2018
They are spreading fill dirt and also bringing more in. They are also doing compaction tests for the fill-dirt.Steve Robbins 03/12/2018 12:23 PM
PW-Misc
Informational
09/04/2018
The last few weeks they have been bringing in fill-dirt and doing compaction tests for it. It rained hard yesterday so no work has gone on this week yet.Steve Robbins 03/27/2018 3:49 PM
PW-Misc
Informational
09/04/2018
Nothing was going on today due to the snow and rain. I talked with Rob about a complaint that came from the golf course last week about the road being damaged due to the work going on at this site. The only problem I could see was at the entrance there is a small area in the road on View High that could have been caused by all the trucks going in and out of the work site. The contractor said that they would take care of the pot hole. Steve Robbins 04/02/2018 3:16 PM
PW-Misc
Informational
09/04/2018
I was off yesterday but they said nothing was going on . Today it appears that they are bringing in some dirt, Bair Excavating was on site. Steve Robbins 04/10/2018 1:50 PM
PW-Misc
Informational
09/04/2018
The contractors are working this morning bringing in fill dirt and doing grading. I talked with Rob yesterday about the complaints from the golf course about the trucks from this site making wide turns in their driveway in order to make a u-turn. I did not witness this happening but I did witness a dump truck coming out of the golf course that was doing work there. When I talked with Rob he said he was going to have his office get in contact with the golf course. They are willing to put cold patch down to take care of the problem now.Steve Robbins 04/13/2018 9:38 AM
PW-Misc
Informational
09/04/2018
The contractors are still hauling dirt for fill and doing compaction tests for the site. I spoke with Rob today and he said there continues to be several concrete trucks turning into the golf course where they say trucks from this job site damaged the entry to golf course. He is taking pictures and has contacted his office. They do not think they did the damage to the street on that side of the road. Steve Robbins 04/16/2018 4:07 PM
PW-Misc
Informational
09/04/2018
Due to the rain there has not been much work going on the last 2 days.Steve Robbins 05/04/2018 3:22 PM
PW-Misc
Informational
09/04/2018
The contractors are still bringing in dirt , grading and doing testing.Steve Robbins 05/08/2018 2:35 PM
PW-Misc
Informational
09/04/2018
It has been raining on and off this morning, it apprears to be close to clearing up. There is a few trucks moving dirt right now. They will probably be working more as the day goes on.Steve Robbins 05/11/2018 9:34 AM
PW-Misc
Informational
09/04/2018
There is rock crushing, grading and testing going on today. They are getting close to starting some of the foundations for the apartments. They also have sanitary and storm pipes dropped off for the infrastructure of the apartments.Steve Robbins 05/15/2018 3:04 PM
PW-Misc
Informational
09/04/2018
The contractors are bringing in fill for the road on Kessler, the new 12" water main is installed and going across the road. They have been doing compaction tests over the water main in lifts as they have been bringing in the fill. Steve Robbins 05/17/2018 2:24 PM
PW-Misc
Informational
09/04/2018
I was out of town all last week. While I was out Jeremy Young checked on this project. There was not much going on, there was alot of rain. Today i observed dirt and rock being moved and being compacted. I also spoke with Bair Excavating and they are planning on starting the private infrastructure for the apartments next week.Steve Robbins 05/30/2018 2:54 PM
PW-Misc
Informational
09/04/2018
There was no work being done on the retention basin today. It appears that they are almost finished with grading it out.Steve Robbins 06/22/2018 3:12 PM
PW-Misc
Informational
11/01/2018
The grading and excavation is pretty much completed, it is starting to take shape now.Steve Robbins 11/01/2018 8:37 AM
Sanitary Sewer - Mandrel Partial 11/9/2018 at 11:00 AM 11/09/2018
Misc
Informational
11/09/2018
We have done the mandrel testing for all the lines except A-6 to A-7 which is a 12 in line. Steve Robbins 11/09/2018 8:42 AM
Water Line - Construction Inspection Passed 11/8/2018 at 1:30 PM 11/09/2018
PW-Main inspection
Informational
10/03/2018
The contractor is on site and are starting the 12" public water line. They are planning on building the waterline first and then doing the tie-in to the existing 8" water line. They are planning on laying pipe today.Steve Robbins 02/26/2018 10:19 AM
PW-Main inspection
Informational
10/03/2018
They have installed the 12x12 tee, no thrust block yet. also have installed the 12x8 reducer and 2- 12" valves. They will install the 45 when they tie in to the 8" line. Tehy are working there way up to the fire hydrant at station 43.73. Steve Robbins 02/26/2018 2:54 PM
PW-Main inspection
Informational
10/03/2018
The 12" butterfly valve and 8" gate valve has been installed at station 16.49 and the tee for the fire hydrant at station 34.73 has also been installed. They are planning on installing thrust blocks and straddle block this afternoon.Steve Robbins 02/27/2018 1:45 PM
PW-Main inspection
Informational
10/03/2018
The water line has been installed up to station 34.73. . The fire hydrants for station 34.73 has not been installed yet. Steve Robbins 02/28/2018 11:51 AM
PW-Main inspection
Informational
10/03/2018
They are continuing the 12" waterline. They have 3 fire hydrants to install. The contractors are working on the end of the water line. Steve Robbins 03/01/2018 12:22 PM
PW-Main inspection
Informational
10/03/2018
All the valves and fire hydrants have been installed. All straddle blocks and thrust blocks have also been installed. They still have alot of fill to bring in so the water line is covered with rock right now. They still have to bring in 4-5 feet of cover and then they will do the compaction tests for the 2 road crossings and every 300 ft. in the row. I was told they have a tie in crew and they will get in touch with me to do the tie in and water testing. They will continue with the installation of the water line when the fill is in place.Steve Robbins 03/05/2018 3:22 PM
PW-Main inspection
Informational
10/03/2018
The 12" water line has been installed, the water samples have passed, and the hydrostatic pressure test has also passed. They are ready to do the tie in to the existing 8" line. The water line going to the east will not be able to be finished until all the fill has been brought in.
PW-Main inspection
Informational
10/03/2018
The water dept. came out and did a test shut-down , but i havent heard back from them yet. The next step is for the contractors to do the tie in.Steve Robbins 04/18/2018 3:03 PM
PW-Main inspection
Informational
10/03/2018
The new water main running along view high has been exposed to the rock, they will start bringing in the fill dirt and doing the compaction tests across the road-Kessler.Steve Robbins 04/30/2018 8:48 AM
PW-Main inspection
Informational
10/03/2018
I talked with Casey from Blue Nile, they are planning on doing the water tie-in for both sides on view high dr. on wednesday morning at 9 a.m. The water dept. has done a test shutdown already, I am sending them an e-mail to make them aware of the tie-in of wednesday May 9.Steve Robbins 05/04/2018 3:28 PM
PW-Main inspection
Informational
10/03/2018
The water tie-in on view high dr. will effect only 2 houses. I put fliers on the doors this morning to make sure they have 48 hrs. notice before the shutdown. I have notified the water dept. , they will send a crew out on Wednesday at 9 am to shut the water down. I have spoke with blue nile about having bleach and a mop to clean the pipes for the tie-in. Steve Robbins 05/07/2018 3:01 PM
PW-Main inspection
Informational
10/03/2018
Yesterday on May 9 we did a tie in on both sides of the existing 8" water line on viewhigh. The water dept. came out and turned the water back on at around 2:30. The contractors, (blue Nile ) did not have the valves turned on for the new 12" line. The water dept. had to turn them on, because of this they did not get the fire hydrants flushed, so I did the flush for the hydrants. When i flushed them the water run-off washed away some of the cover for the new 12" line. This morning Blue Nile put a couple of feet of cover over the exposed water line. Shaw Construction is working on getting fill in for the future roads that are going in. The water line tie-in has been completed. Everything on View High DR. has now passed. When the fill has been completed they can install the remainder of the water line that goes along the 2 future roads.Steve Robbins 05/10/2018 10:01 AM
PW-Main inspection
Informational
10/03/2018
I noted in the grading section that this water line has now been covered with fill and they have done the compaction tests for the crossing of the road on Kessler.Steve Robbins 05/18/2018 3:55 PM
PW-Main inspection
Informational
10/03/2018
one of the Blue Nile crews has connected to the existing valve on the main that has been installed already on View High Dr. They have installed 5 bends with the 5 thrust blocks for the 8" water main all the way down to village park dr.They did not install the fire hydrant yet, it will be a road crossing. It is not on the plans but they are going to install a crossing for the water line so they can connect for the private .Steve Robbins 08/10/2018 4:01 PM
PW-Main inspection
Informational
10/03/2018
Blue Nile has installed the fire hydrant at station 3+08.73 along with the valve, they have also installed the thrust block. They have not installed fire hydrant at station 7+51.63 . They have also installed all the bends and thrust blocks going down kessler. They stopped when they got to the fire hydrant and now have jumped over to storm.Steve Robbins 08/13/2018 1:23 PM
PW-Main inspection
Informational
10/03/2018
I am waiting on the contractor to do the hydrostatic pressure test on this partial water line so we can get to the water sampling.Steve Robbins 08/30/2018 8:51 AM
PW-Main inspection
Informational
10/03/2018
They are continuing to install the water line, they are at the corner kessler dr. The plans only showed 2 valves, i spoke with Gene and he said we needed 3. Blue Nile agreed to install the other. We are at the end where we have an in- line fire hydrant. That has been installed at the end of kessler.Steve Robbins 09/25/2018 10:21 AM
PW-Main inspection
Informational
10/03/2018
the blue nile has been working on the 12" waterline going down village park dr. They are working toward the fire hydrant with the in-line valve. They are also going to install a road crossing for the connection of the back-flow preventer and water meter vault.Steve Robbins 09/27/2018 1:22 PM
PW-Main inspection
Informational
10/03/2018
The fire hydrand for station 7+51.63 has been installed and the temorary in line fire hydrand on station 9+21.12. They have also installed the in-line fire hydrand for station 10+16.45. The 12" water line for the temp in line fire hydrant has been installed. Steve Robbins 10/01/2018 11:42 AM
PW-Main inspection
Informational
10/03/2018
The water line has been installed except for the crossing on village park dr. We are also waiting for 2 butterfly valves. Steve Robbins 10/03/2018 11:51 AM
Misc
Informational
11/09/2018
The water line has been completed. They have installed the crossing for the road that will be for the backflow and fire line. We still have to do the pressure test. The entire water line has now been installed.Steve Robbins 11/09/2018 1:15 PM
Pavement-Stabilized Subgrade Partial 10/30/2018 at 2:00 PM 11/09/2018
PW-Misc
Informational
11/01/2018
Shaw Construction has installed portland cement for the road on Kessler, They till in 9 inches of portlandl, they used a tiller and they had a water truck connected. They are letting it set up over the weekenc. They are planning on finishing grading on tuesday and doing a proofroll on tuesday afternoo.
PW-Misc
Informational
11/01/2018
They are not going to stabilize the other streets subgrade until the sanitary passes all the road crossings.Steve Robbins 10/24/2018 3:28 PM
Misc
Informational
11/01/2018
Shaw Construction is out grading for the road on Village Park Dr, they are plannig on using portland for their subgrade stabilization.Steve Robbins 11/01/2018 7:19 AM
PW-Misc
Informational
11/09/2018
Shaw has tilled in the portland for Village Park Dr., this now completes all the roads for the city of lees summit that will have a subgrade of portland. They are still working on the turn lanes for kansas city. This completes the subgrade stabilization for the portland. After this passes a proofroll we will move onto the MO-type5.
Pavement-Stabilized Subgrade Partial 10/31/2018 at 7:45 AM 11/21/2018
PW-Misc
Informational
11/09/2018
Shaw Construction has installed portland cement for the road on Kessler, They till in 9 inches of portlandl, they used a tiller and they had a water truck connected. They are letting it set up over the weekenc. They are planning on finishing grading on tuesday and doing a proofroll on tuesday afternoo.
PW-Misc
Informational
11/09/2018
They are not going to stabilize the other streets subgrade until the sanitary passes all the road crossings.Steve Robbins 10/24/2018 3:28 PM
Misc
Informational
11/09/2018
Shaw Construction is out grading for the road on Village Park Dr, they are plannig on using portland for their subgrade stabilization.Steve Robbins 11/01/2018 7:19 AM
PW-Misc
Informational
11/09/2018
Shaw has tilled in the portland for Village Park Dr., this now completes all the roads for the city of lees summit that will have a subgrade of portland. They are still working on the turn lanes for kansas city. This completes the subgrade stabilization for the portland. After this passes a proofroll we will move onto the MO-type5.
PW-Misc
Informational
11/21/2018
9 inches of portland cement was tilled into the subgrade using a tiller. After a proofroll we can then install the 6" of Mo-type 5.
Pavement-Proof Roll Failed 11/19/2018 at 1:00 PM 11/21/2018
PW-Misc
Informational
10/24/2018
The proofroll passed and they had 2 trucks full of asphalt that they put down, it rained and we had to call it off for the day. It rained alot over the weekend so we will have to do another proofroll when it drys out.Steve Robbins 10/08/2018 8:01 AM
PW-Misc
Informational
10/24/2018
A proofroll for kessler dr. Was completed for me while i was off on friday 10/19/18. They also did a string line test . This was the second proofroll done , they were not able to get asphalt in after the first proof roll. This proofroll passed and they are putting in ashphalt today. This is a partial proofroll as we will need to proofroll the other street that connects to Kessler.Steve Robbins 10/24/2018 2:48 PM
PW-Misc
Corrective Action Required
11/21/2018
A proofroll on the subgrade of portland has not passed, there were aproximately 5 areas of concern, mostly in front of storm boxes. I allowed them to dig down 18-24" to a stable area and install Mo-type 5. They have completed this yesterday and we are waiting for it to cure out for a proofroll.Steve Robbins 11/21/2018 7:11 AM
Sanitary Sewer - Mandrel Passed 11/15/2018 at 9:00 AM 11/21/2018
Misc
Informational
11/09/2018
We have done the mandrel testing for all the lines except A-6 to A-7 which is a 12 in line. Steve Robbins 11/09/2018 8:42 AM
Misc
Informational
11/21/2018
All the mandrel testing has been completed and all has passed.Steve Robbins 11/21/2018 7:14 AM
Storm - Pipe Passed 11/9/2018 at 9:00 AM 11/26/2018
PW-Misc
Informational
09/21/2018
Storm structure 5-5 and 5-6 have been installed with 24" hdpe storm pipe. They are working on 5-6 to 5-7 which is a road crossing. Shawn will be out to do the testing in lifts.Steve Robbins 08/01/2018 2:57 PM
PW-Misc
Informational
09/21/2018
Structure 5-7 has been installed. This is a road crossing, psi was out doing the testing in lifts for the road crossing. They are not doing any more storm right now.Steve Robbins 08/02/2018 2:55 PM
PW-Misc
Informational
09/21/2018
The other blue nile crew has started working on the outlet structure going into the retention basin. They have hit a lot of rock so they are moving very slow.Steve Robbins 08/10/2018 3:39 PM
PW-Misc
Informational
09/21/2018
Storm structure 2-6, 2-7 and 4-1 structure has been installed. 4-1 flared end section has not been installed yet.. The collars have been poured for everything up to 4-1. The other crew is working on coming off of structure 1-3, today they have hit rock.Steve Robbins 09/11/2018 2:50 PM
PW-Misc
Informational
09/21/2018
Structure 1-4 has been installed. All the collars have been installed. They are working toward structure 1-5.Steve Robbins 09/14/2018 11:23 AM
PW-Misc
Informational
09/21/2018
As of today they have installed all the storm structures, all the pipes have been connected. They are planning on finishing the collars and pouring the inverts and then they are going to flush the line because it has some mudd in it.Steve Robbins 09/18/2018 3:56 PM
PW-Misc
Informational
09/21/2018
They have completed all the storm structures and installed all the collars and they have tested all the road crossings. They still have to pour all the inverts for the storm boxes.Steve Robbins 09/21/2018 3:58 PM
PW-Misc
Informational
11/26/2018
All the inverts have been poured for the storm.This now completes all the public storm.
Water Line - Coliform Test 1 Failed 11/26/2018 at 10:30 AM 11/26/2018
PW-Misc
Informational
11/01/2018
Casey from Blue Nile chlroinated the water line coming down kessler and we dechlorinated and flushed today. On Monday we will take the first sample.Steve Robbins 09/14/2018 4:01 PM
Miscellaneous Correction
Corrective Action Required
11/01/2018
The first round of samples has failed, the contractor flushed and we started over. I took the first second round and the first samples failed. I was already there with the second set of samples and found out they failed so blue nile just had me have them try anyway. I will find out this afternoon if they passed or failed.Steve Robbins 11/01/2018 8:06 AM
Misc
Corrective Action Required
11/26/2018
I have not heard anything, Blue nile was considering if the citys water wasn't passing the test. I told them they were free to test our water and get back with me. The next time we test they will need to chlorinate again and flush before we take more samples. Steve Robbins 11/26/2018 10:52 AM
Pavement-Stabilized Subgrade Passed 11/20/2018 at 10:00 AM 11/26/2018
PW-Misc
Informational
11/21/2018
Shaw Construction has installed portland cement for the road on Kessler, They till in 9 inches of portlandl, they used a tiller and they had a water truck connected. They are letting it set up over the weekenc. They are planning on finishing grading on tuesday and doing a proofroll on tuesday afternoo.
PW-Misc
Informational
11/21/2018
They are not going to stabilize the other streets subgrade until the sanitary passes all the road crossings.Steve Robbins 10/24/2018 3:28 PM
Misc
Informational
11/21/2018
Shaw Construction is out grading for the road on Village Park Dr, they are plannig on using portland for their subgrade stabilization.Steve Robbins 11/01/2018 7:19 AM
PW-Misc
Informational
11/21/2018
Shaw has tilled in the portland for Village Park Dr., this now completes all the roads for the city of lees summit that will have a subgrade of portland. They are still working on the turn lanes for kansas city. This completes the subgrade stabilization for the portland. After this passes a proofroll we will move onto the MO-type5.
PW-Misc
Informational
11/21/2018
9 inches of portland cement was tilled into the subgrade using a tiller. After a proofroll we can then install the 6" of Mo-type 5.
PW-Misc
Informational
11/26/2018
The portland has cured and the suggrade has been stabilized.
Pavement-Proof Roll Partial 11/20/2018 at 9:00 AM 11/26/2018
PW-Misc
Informational
11/21/2018
The proofroll passed and they had 2 trucks full of asphalt that they put down, it rained and we had to call it off for the day. It rained alot over the weekend so we will have to do another proofroll when it drys out.Steve Robbins 10/08/2018 8:01 AM
PW-Misc
Informational
11/21/2018
A proofroll for kessler dr. Was completed for me while i was off on friday 10/19/18. They also did a string line test . This was the second proofroll done , they were not able to get asphalt in after the first proof roll. This proofroll passed and they are putting in ashphalt today. This is a partial proofroll as we will need to proofroll the other street that connects to Kessler.Steve Robbins 10/24/2018 2:48 PM
PW-Misc
Corrective Action Required
11/21/2018
A proofroll on the subgrade of portland has not passed, there were aproximately 5 areas of concern, mostly in front of storm boxes. I allowed them to dig down 18-24" to a stable area and install Mo-type 5. They have completed this yesterday and we are waiting for it to cure out for a proofroll.Steve Robbins 11/21/2018 7:11 AM
PW-Misc
Informational
11/26/2018
The proofroll for the subgrade where portland has been installed has now passed. The contractors dug up the wet spots and installed Mo-type 5 about 18-24" deep which is how deep the wet spots were.The entire subgrade has passed a proofroll and has been covered by Mo-type 5 base rock. It has snow 3-4" over the weekend so they will not be installing curbs for now.Steve Robbins 11/26/2018 11:05 AM
Sanitary Sewer - Vacuum Partial 11/26/2018 at 11:15 AM 11/26/2018
Corrective Action Required
11/26/2018
Partial Correction
11/26/2018
All the sanitary MH vacuum testing is complete and have passed except for Mh D-1. We have tried 2 times and it has not passed yet. A-1 to A-8 and B-1 and C-1.Steve Robbins 11/26/2018 2:31 PM
Sanitary Sewer - Air Test Passed 11/13/2018 at 9:00 AM 11/26/2018
PW-Misc
Informational
10/10/2018
We are doing air testing MH A-6 to A-5, A-5 to A-4, and A-4 to A-3 have all passed the air test.Steve Robbins 10/04/2018 8:24 AM
PW-Sanitary Sewer Testing
Informational
10/10/2018
Sanitary Sewer Testing needs to be completed. Joe Starlin stayed late and finished the testing. Everything from A-6 to existing MH A-15 has been air tested and has passed.Steve Robbins 10/10/2018 3:11 PM
PW-Misc
Informational
11/26/2018
The air testing from MH A-6 to existiing MH A-15 has been completed and passed. A-7 to B-1 and A-8 to C-1 and existing MH A-15 to MH D-1 has all been tested and has passed.Steve Robbins 11/26/2018 2:37 PM
Site Visit Complete 11/26/2018
PW-Misc
Informational
04/26/2018
Matt Munger 04/26/2018 2:05 PM No utility work was going on, on site. Workers had equipment on site and were trying to brake up the bedrock on the east side of the property. A neighbor to the project had stopped in and had informed of his concern with the blasting that had been going on and I spoke to him for a bit and informed him that I would send an email to Dan Harper and inform him of the concern. While on site there wasn't any blasting going on. I had called Dennis Sondgeroth (concerned neighbor) to let him know I had emailed Dan but wasn't sure what his schedule was for today just in case Dan was tied up in meetings and was not able to contact Dennis today.
Sanitary Sewer - Invert Passed 11/26/2018 11/26/2018
Misc
Informational
11/26/2018
All the inverts for the MH's have been poured.
Water Line - Coliform Test 1 Partial 12/3/2018 at 12:00 PM 12/04/2018
PW-Misc
Informational
11/26/2018
Casey from Blue Nile chlroinated the water line coming down kessler and we dechlorinated and flushed today. On Monday we will take the first sample.Steve Robbins 09/14/2018 4:01 PM
Miscellaneous Correction
Corrective Action Required
11/26/2018
The first round of samples has failed, the contractor flushed and we started over. I took the first second round and the first samples failed. I was already there with the second set of samples and found out they failed so blue nile just had me have them try anyway. I will find out this afternoon if they passed or failed.Steve Robbins 11/01/2018 8:06 AM
Misc
Corrective Action Required
11/26/2018
I have not heard anything, Blue nile was considering if the citys water wasn't passing the test. I told them they were free to test our water and get back with me. The next time we test they will need to chlorinate again and flush before we take more samples. Steve Robbins 11/26/2018 10:52 AM
Misc
Informational
12/04/2018
Casey flushed the line on friday and we took a sample on monday the 3rd. i did not here if it passed yet.Steve Robbins 12/04/2018 3:58 PM
Water Line - Coliform Test 1 Partial 12/26/2018 at 10:00 AM 12/26/2018
PW-Misc
Informational
12/04/2018
Casey from Blue Nile chlroinated the water line coming down kessler and we dechlorinated and flushed today. On Monday we will take the first sample.Steve Robbins 09/14/2018 4:01 PM
Miscellaneous Correction
Corrective Action Required
12/04/2018
The first round of samples has failed, the contractor flushed and we started over. I took the first second round and the first samples failed. I was already there with the second set of samples and found out they failed so blue nile just had me have them try anyway. I will find out this afternoon if they passed or failed.Steve Robbins 11/01/2018 8:06 AM
Misc
Corrective Action Required
12/04/2018
I have not heard anything, Blue nile was considering if the citys water wasn't passing the test. I told them they were free to test our water and get back with me. The next time we test they will need to chlorinate again and flush before we take more samples. Steve Robbins 11/26/2018 10:52 AM
Misc
Informational
12/04/2018
Casey flushed the line on friday and we took a sample on monday the 3rd. i did not here if it passed yet.Steve Robbins 12/04/2018 3:58 PM
PW-Misc
Informational
12/26/2018
We had failing samples from blue valley lab. We have switched to Keystone Labs. The public water line on Kessler and Village Park Dr has had 2 passes in a row. Because of different contractors installing the water lines we also had to get a test from the main to the backflow on kessler and on the backflow on Villlage Park. Dr. We have the passing tests for Kessler but did not take the one for Village Park Dr.Steve Robbins 12/26/2018 10:12 AM
Sanitary Sewer - Vacuum Passed 12/4/2018 at 10:00 AM 01/02/2019
Misc
Resolved
01/02/2019
MH D-1 has now passed the vacuum test. The vacuum testing for all the MH"s have been completed.
Pavement-Surface Partial 2/11/2019 at 9:00 AM 02/12/2019
PW-Misc
Informational
10/24/2018
The contractors were able to install 2 truck loads of asphalt. It started raining so they had to stop installing. Steve Robbins 10/12/2018 1:54 PM
PW-Misc
Informational
10/24/2018
The base asphal of 7.5 " has been installed, it was installed in 2 lifts of 3.5 and 4". This was done after a proofroll was completed and they filled in some ruts after the rain with Mo-type 5. They also had one section of curb that the rock was washed out underneath the curb. The contractor installed flow-fill under the curb. This is for kessler st.
PW-Misc
Informational
02/12/2019
It will be a while before we get to the base on Village Park Dr.Steve Robbins 02/12/2019 4:25 PM
Curb - Proof Roll Failed 2/13/2019 at 1:00 PM 02/13/2019
PW-Misc
Informational
09/27/2018
The proof roll for the curbs on Kessler has been completed and has passed.Steve Robbins 09/27/2018 1:10 PM
PW-Misc
Informational
02/13/2019
The proofroll for the curbs on village park dr. still needs to be done.Steve Robbins 02/13/2019 2:29 PM
Fire Line - Hydrostatic Test Passed 12/10/2018 at 8:00 AM 02/13/2019
PW-Misc
Informational
09/13/2018
This is a partial test, this starts on Kessler at the top of the hill on view high dr. at the valve and goes to the first fire hydrant on the south side of the street. They used granuales to chlorinate. They filled the line with water and did a hydrostatic test , he kept it at 190 for 2 hrs. After we took the test we dechlorinated and flushed the line so it could sit 24 hours.Steve Robbins 09/12/2018 11:51 AM
PW-Misc
Informational
02/13/2019
The hydrostatic pressure test for the entire line has been completed. This includes kessler dr. and village park dr. all the way up to the backflow preventers. They have not yet connected to the main after the passing samples and they also have not removed the construction taps.
Erosion Control Inspection Failed 4/12/2019 at 3:00 PM 04/12/2019
PW-Erosion and Sediment Control
Corrective Action Required
04/12/2019
Your project is in violation of the Erosion and Sediment control policy.There needs to be silt fence installed by Kessler and View Park Dr. , the silt is coming down the hill and onto the street and going down the storm box. We also need gutter buddys on all the stom boxes on the street on Kessler. The Storm Boxes need to be flushed. The whole sight in general needs to be cleaned up. There seems to be sufficient silt fence around the basin, but we also need to get started with vegetation on the sight, it has been several months since any work has been done in some area's. Steve Robbins 04/12/2019 5:27 PM
Erosion Control Inspection Failed 7/17/2019 at 10:00 AM 07/17/2019
PW-Erosion and Sediment Control
Corrective Action Required
04/12/2019
Your project is in violation of the Erosion and Sediment control policy.There needs to be silt fence installed by Kessler and View Park Dr. , the silt is coming down the hill and onto the street and going down the storm box. We also need gutter buddys on all the stom boxes on the street on Kessler. The Storm Boxes need to be flushed. The whole sight in general needs to be cleaned up. There seems to be sufficient silt fence around the basin, but we also need to get started with vegetation on the sight, it has been several months since any work has been done in some area's. Steve Robbins 04/12/2019 5:27 PM
PW-Erosion and Sediment Control
Corrective Action Required
07/17/2019
Your project is in violation of the Erosion and Sediment control policy. There has been no work on the off-site of the this project almost 8 months. All erosion control is in violaton and the entire site needs to be cleaned up. They are continuing to do work on the on-site /Meridian Development but will soon have to stop if the off-site does not get finished.
Curb - Proof Roll Passed 8/29/2019 09/12/2019
PW-Misc
Informational
02/13/2019
The proof roll for the curbs on Kessler has been completed and has passed.Steve Robbins 09/27/2018 1:10 PM
PW-Misc
Informational
02/13/2019
The proofroll for the curbs on village park dr. still needs to be done.Steve Robbins 02/13/2019 2:29 PM
Misc
Informational
09/12/2019
The proofroll for the curbs on village park dr. has been completed and passed.
Pavement-Curb Construction Passed 9/3/2019 09/12/2019
Misc
Informational
09/12/2019
The curbs on village park dr. have been installed with a curb machine and curbs and throats for the curb inlets have all been installed and have been cure with white cure.
Pavement-Proof Roll Passed 9/12/2019 09/13/2019
PW-Misc
Informational
11/26/2018
The proofroll passed and they had 2 trucks full of asphalt that they put down, it rained and we had to call it off for the day. It rained alot over the weekend so we will have to do another proofroll when it drys out. We will need to do another proofroll for the curbs and the road.Steve Robbins 10/08/2018 8:01 AM
PW-Misc
Informational
11/26/2018
A proofroll for kessler dr. Was completed for me while i was off on friday 10/19/18. They also did a string line test . This was the second proofroll done , they were not able to get asphalt in after the first proof roll. This proofroll passed and they are putting in ashphalt today. This is a partial proofroll as we will need to proofroll the other street that connects to Kessler.Steve Robbins 10/24/2018 2:48 PM
PW-Misc
Corrective Action Required
11/26/2018
A proofroll on the subgrade of portland has not passed, there were aproximately 5 areas of concern, mostly in front of storm boxes. I allowed them to dig down 18-24" to a stable area and install Mo-type 5. They have completed this yesterday and we are waiting for it to cure out for a proofroll.Steve Robbins 11/21/2018 7:11 AM
PW-Misc
Informational
11/26/2018
The proofroll for the subgrade where portland has been installed has now passed. The contractors dug up the wet spots and installed Mo-type 5 about 18-24" deep which is how deep the wet spots were.The entire subgrade has passed a proofroll and has been covered by Mo-type 5 base rock. It has snow 3-4" over the weekend so they will not be installing curbs for now.Steve Robbins 11/26/2018 11:05 AM
Misc
Informational
09/13/2019
The proof-roll for view park drive has passed and is now ready for asphalt. We had a truck with a 20 ton load.
Storm Sewer Construction Inspection Partial 9/13/2019 09/13/2019
Misc
Informational
09/13/2019
Blue Nile Construction was out today grouting in the curb inlets that were not finished last summer. They were hoping to finish all of them up today, if not they will finish on Monday.
Pavement-Surface Partial 9/14/2019 09/23/2019
PW-Misc
Informational
02/12/2019
The contractors were able to install 2 truck loads of asphalt. It started raining so they had to stop installing. Steve Robbins 10/12/2018 1:54 PM
PW-Misc
Informational
02/12/2019
The base asphal of 7.5 " has been installed, it was installed in 2 lifts of 3.5 and 4". This was done after a proofroll was completed and they filled in some ruts after the rain with Mo-type 5. They also had one section of curb that the rock was washed out underneath the curb. The contractor installed flow-fill under the curb. This is for kessler st.
PW-Misc
Informational
02/12/2019
It will be a while before we get to the base on Village Park Dr.Steve Robbins 02/12/2019 4:25 PM
Misc
Informational
09/23/2019
The first lift of base was installed 4" . PSI was out doing the testing. John Jackson was on site doing the inspecting.
Pavement-Surface Passed 9/20/2019 09/23/2019
PW-Misc
Informational
09/23/2019
The contractors were able to install 2 truck loads of asphalt. It started raining so they had to stop installing. Steve Robbins 10/12/2018 1:54 PM
PW-Misc
Informational
09/23/2019
The base asphal of 7.5 " has been installed, it was installed in 2 lifts of 3.5 and 4". This was done after a proofroll was completed and they filled in some ruts after the rain with Mo-type 5. They also had one section of curb that the rock was washed out underneath the curb. The contractor installed flow-fill under the curb. This is for kessler st.
PW-Misc
Informational
09/23/2019
It will be a while before we get to the base on Village Park Dr.Steve Robbins 02/12/2019 4:25 PM
Misc
Informational
09/23/2019
The first lift of base was installed 4" . PSI was out doing the testing. John Jackson was on site doing the inspecting.
Misc
Informational
09/23/2019
O'donnel way has finished installing the second lift of base-3 1/2". PSI was out doing the testing on site. I had a concern at the bottom of village park dr. where the pond to the south overflows after a rain. Shaw Construction built a berm to divert the water flowing from the pond over the hill so it will go across and into the storm box. The subgrade and the base seemed to be dry at the time of installation.
Street - Surface Course Passed 9/24/2019 09/24/2019
Misc
Informational
09/24/2019
The 2" of surface has been installed for kessler and village at view park.About a month ago we went out to the site Dawn Bell, Ryan Elam and met with John Davis , the realtor and Rachel Rowland to discuss what was needed for a substantial completion. The pond that is to the south of village park dr has water that comes down the hill and is running onto village park dr. We decided that if they put in a berm and divert the water to go into the curb inlet/stormbox this would take care of the problem. This appears to have resolved the problem, after a significant rain over the weekend the water seems to be going into the storm box. I am not 100% convinced that it is still not going under the curb and coming up under the road but it did not appear to be at this point. I just want to note that the surface is in and the road is complete but i will be checking on this reguarlily to see if there is any change in the sub-grade or road conditions.
Water Line - Construction Inspection Partial 9/30/2019 09/30/2019
Misc
Corrective Action Required
09/30/2019
The water samples passe last december for this water line but the new main on village park dr. was never connected to view high dr. and the construction taps were never removed. On friday 9/27 the main was chlorinated again so we will dechlorinate and take samples on line 2 of the water main going down village park dr.
Water Line - Construction Inspection Passed 10/21/2019 10/28/2019
Misc
Corrective Action Required
09/30/2019
The water samples passe last december for this water line but the new main on village park dr. was never connected to view high dr. and the construction taps were never removed. On friday 9/27 the main was chlorinated again so we will dechlorinate and take samples on line 2 of the water main going down village park dr.
Misc
Resolved
10/28/2019
The water line has been re-tested and has recieved passing tests from Keystone Lab. The water line at View High and Village Park has been tied in and is in full service. The fire hydrants have all been turned toward the street and raised if they needed it. This now completes all the water for this permit.
Water Line - Construction Taps Removed Passed 10/24/2019 10/28/2019
Misc
Informational
10/28/2019
The construction taps have been removed and repalaced with repair clamps.
Storm Sewer Construction Inspection Partial 10/28/2019 10/28/2019
Misc
Informational
09/13/2019
Blue Nile Construction was out today grouting in the curb inlets that were not finished last summer. They were hoping to finish all of them up today, if not they will finish on Monday.
Misc
Informational
10/28/2019
The curb inlets have all been grouted and the storm line has been flushed but they still have some of the hooks to take off the storm box lids.
Sidewalk Inspection Failed 10/28/2019 10/28/2019
Misc
Informational
10/28/2019
As per the agreement they are only installiing sidewalks on the east side of kessler dr. The sidewalks have all been formed and rock was installed and compacted. I spoke with Ryan and we are letting them keep about 25-30 ft. open on the ease side of kessler so they can get their heavy equipment across the road without breaking the sidewalk. The sidewalk has all been poured down kessler and down the portion of village park dr. to the dead end. They also poured ADA ramps at the corner of kessler and village park dr. 2 of the ramps have failed and are not in compliance. Everything else seems to be in compliance.
Sidewalk Inspection Partial 11/4/2019 11/05/2019
Misc
Informational
10/28/2019
As per the agreement they are only installiing sidewalks on the east side of kessler dr. The sidewalks have all been formed and rock was installed and compacted. I spoke with Ryan and we are letting them keep about 25-30 ft. open on the ease side of kessler so they can get their heavy equipment across the road without breaking the sidewalk. The sidewalk has all been poured down kessler and down the portion of village park dr. to the dead end. They also poured ADA ramps at the corner of kessler and village park dr. 2 of the ramps have failed and are not in compliance. Everything else seems to be in compliance.
Misc
Informational
11/05/2019
All the sidewalk has been accepted and has passed. We are allowing cityscapes to drive accross where the sidewalk would be on Kessler Dr. When Cityscapes is finished working on that area the remaining 30-40ft of sidewalk will be installed.
Sidewalk Inspection Partial 11/05/2019
Misc
Informational
11/05/2019
As per the agreement they are only installiing sidewalks on the east side of kessler dr. The sidewalks have all been formed and rock was installed and compacted. I spoke with Ryan and we are letting them keep about 25-30 ft. open on the ease side of kessler so they can get their heavy equipment across the road without breaking the sidewalk. The sidewalk has all been poured down kessler and down the portion of village park dr. to the dead end. They also poured ADA ramps at the corner of kessler and village park dr. 2 of the ramps have failed and are not in compliance. Everything else seems to be in compliance.
Misc
Informational
11/05/2019
All the sidewalk has been accepted and has passed. We are allowing cityscapes to drive accross where the sidewalk would be on Kessler Dr. When Cityscapes is finished working on that area the remaining 30-40ft of sidewalk will be installed. The plans called for sidewalk on both sides of the road on kessler and villagepark dr. The city has agreed to allow them to only install on sidewalk on the east side of kessler and north side of village park dr.
ADA Inspection Failed 11/4/2019 11/05/2019
Misc
Corrective Action Required
11/05/2019
The ADA ramps on kessler by the approach into the appartments has been completed . The 2 ADA ramps at the kessler and village park intersection have failed, they are not compliant and will need to be repaired.
Sanitary Sewer Construction Inspection Partial 11/5/2019 11/05/2019
Misc
Informational
11/05/2019
The water dept. ran the camera test and found a sag and an invert that needed to be corrected. The sag was between MH 27-259 and MH 27-260. The Sag has been repaired and the water dept. agreed to inspect it before the 30 days and then inspect after 30 again so we will be able to give them substantial completion for the off-site project. I spoke with Brent today and they will come out again is 30 day to inspect, if it is not good they will have to make corrections again. If they do not fix the problem we will hold up TCO on any buildings that do not have one yet.
Curb - Compression Strength Passed 11/05/2019
Street - Wedge Lift Passed 10/7/2019 11/05/2019
Water Line - Valve Passed 11/05/2019
Water Line - Fire Hydrant Passed 11/5/2019 11/05/2019
Misc
Informational
11/05/2019
All the hydrants have been installed and turned the right direction.
Water Line - Thrust Restraint Passed 11/05/2019
Water Line - Construction Taps Removed Passed 11/05/2019
Sanitary - Material Verification Passed 11/05/2019
Sanitary Sewer Construction Inspection Passed 11/05/2019
Storm - Pipe Passed 11/05/2019
Storm - Inlets Clean Partial 11/05/2019
Storm - Swales Partial 11/5/2019 11/05/2019
Misc
Corrective Action Required
11/05/2019
The swales that are on the east side of the property that drain to the field inlets have been installed but need some attention as the construction of the apartments has filled them in some and they will need to be shot to grade.
Storm - Inlets Clean Passed 10/10/2019 11/06/2019
Misc
Informational
11/06/2019
The storm intlets and pipes were jetted and cleaned out.
Sanitary Sewer Construction Inspection Passed 12/5/2019 01/06/2020
Misc
Informational
11/05/2019
The water dept. ran the camera test and found a sag and an invert that needed to be corrected. The sag was between MH 27-259 and MH 27-260. The Sag has been repaired and the water dept. agreed to inspect it before the 30 days and then inspect after 30 again so we will be able to give them substantial completion for the off-site project. I spoke with Brent today and they will come out again is 30 day to inspect, if it is not good they will have to make corrections again. If they do not fix the problem we will hold up TCO on any buildings that do not have one yet.
Misc
Resolved
01/06/2020
The water dept. ran their camer through again and they said everything is good. I am passing all the sanitary as of now.
Install Street and Stop Signs Passed 11/5/2019 01/14/2020
Retention Basin Partial 3/19/2020 03/19/2020
Misc
Informational
03/19/2020
The contractor has dug the silt out of the retention basin. They will still need to stabilize the slopes and stabilize the outlet structure . There has been some progress made but still needs some work.
ESC - (Vegetation/Ground Cover) Passed 12/17/2021
Water Line - Coliform Test 1 Passed 12/17/2021
PW-Misc
Informational
12/26/2018
Casey from Blue Nile chlroinated the water line coming down kessler and we dechlorinated and flushed today. On Monday we will take the first sample. We will now be able to have fire protection for the building of the apartments.Steve Robbins 09/14/2018 4:01 PM
Miscellaneous Correction
Corrective Action Required
12/26/2018
The first round of samples has failed, the contractor flushed and we started over. I took the first second round and the first samples failed. I was already there with the second set of samples and found out they failed so blue nile just had me have them try anyway. I will find out this afternoon if they passed or failed.Steve Robbins 11/01/2018 8:06 AM
Misc
Corrective Action Required
12/26/2018
I have not heard anything, Blue nile was considering if the citys water wasn't passing the test. I told them they were free to test our water and get back with me. The next time we test they will need to chlorinate again and flush before we take more samples. Steve Robbins 11/26/2018 10:52 AM
Misc
Informational
12/26/2018
Casey flushed the line on friday and we took a sample on monday the 3rd. i did not here if it passed yet.Steve Robbins 12/04/2018 3:58 PM
PW-Misc
Informational
12/26/2018
We had failing samples from blue valley lab. We have switched to Keystone Labs. The public water line on Kessler and Village Park Dr has had 2 passes in a row. Because of different contractors installing the water lines we also had to get a test from the main to the backflow on kessler and on the backflow on Villlage Park. Dr. We have the passing tests for Kessler but did not take the one for Village Park Dr.Steve Robbins 12/26/2018 10:12 AM
Storm - Swales Passed 4/22/2020 12/17/2021
Misc
Corrective Action Required
11/05/2019
The swales that are on the east side of the property that drain to the field inlets have been installed but need some attention as the construction of the apartments has filled them in some and they will need to be shot to grade.
Record Drawing Review Passed 8/13/2021 12/17/2021
Documents & Images
Date Uploaded File Type Document Name
01/19/2018 Letter DE-Daily Inspection Summary
01/26/2018 Letter DE-Daily Inspection Summary
01/26/2018 Letter DE-Daily Inspection Summary
01/30/2018 Letter DE-Daily Inspection Summary
01/31/2018 Letter DE-Daily Inspection Summary
02/06/2018 Letter DE-Daily Inspection Summary
02/21/2018 Letter DE-Daily Inspection Summary
02/21/2018 Letter DE-Daily Inspection Summary
02/22/2018 Letter DE-Daily Inspection Summary
02/26/2018 Letter DE-Daily Inspection Summary
02/14/2018 Letter DE-Daily Inspection Summary
02/12/2018 Village At View High Infrastructure Permit
02/09/2018 Letter DE-Daily Inspection Summary
02/08/2018 Letter DE-Permit
02/07/2018 Letter DE-Daily Inspection Summary
02/01/2018 Letter DE-Daily Inspection Summary
04/02/2018 Letter DE-Daily Inspection Summary
01/29/2018 Letter DE-Daily Inspection Summary
01/24/2018 Letter DE-Daily Inspection Summary
01/23/2018 Letter DE-Daily Inspection Summary
01/11/2018 Letter DE-Daily Inspection Summary
04/13/2018 Letter DE-Daily Inspection Summary
01/10/2018 Letter DE-Daily Inspection Summary
01/05/2018 Letter DE-Daily Inspection Summary
01/02/2018 Letter DE-Daily Inspection Summary
11/16/2017 Letter DE-Permit (signed)
11/16/2017 Letter DE-Permit
11/03/2017 Receipt Receipt for transaction: 2017-007108
05/07/2018 Letter DE-Daily Inspection Summary
05/08/2018 Letter DE-Daily Inspection Summary
03/14/2018 Letter DE-Daily Inspection Summary
03/12/2018 Letter DE-Daily Inspection Summary
03/05/2018 Letter DE-Daily Inspection Summary
03/05/2018 Letter DE-Daily Inspection Summary
03/01/2018 Letter DE-Daily Inspection Summary
02/28/2018 Letter DE-Daily Inspection Summary
02/28/2018 Letter DE-Daily Inspection Summary
02/27/2018 Letter DE-Daily Inspection Summary
02/26/2018 Letter DE-Daily Inspection Summary
03/14/2018 Letter DE-Daily Inspection Summary
06/12/2018 Letter DE-Daily Inspection Summary
03/14/2018 Letter DE-Daily Inspection Summary
03/15/2018 Letter DE-Daily Inspection Summary
03/21/2018 Letter DE-Daily Inspection Summary
05/11/2018 Letter DE-Daily Inspection Summary
03/27/2018 Letter DE-Daily Inspection Summary
04/04/2018 Letter DE-Daily Inspection Summary
04/05/2018 Letter DE-Daily Inspection Summary
04/10/2018 Letter DE-Daily Inspection Summary
04/12/2018 Letter DE-Daily Inspection Summary
04/16/2018 Letter DE-Daily Inspection Summary
04/18/2018 Letter DE-Daily Inspection Summary
07/12/2018 Letter DE-Daily Inspection Summary
04/26/2018 Letter DE-Site Visit Inspection
04/30/2018 Letter DE-Daily Inspection Summary
05/04/2018 Letter DE-Daily Inspection Summary
05/04/2018 Letter DE-Daily Inspection Summary
05/10/2018 Letter DE-Daily Inspection Summary
06/22/2018 Letter DE-Daily Inspection Summary
05/15/2018 Letter DE-Daily Inspection Summary
05/17/2018 Letter DE-Daily Inspection Summary
05/18/2018 Letter DE-Daily Inspection Summary
08/02/2018 Letter DE-Daily Inspection Summary
05/30/2018 Letter DE-Daily Inspection Summary
06/01/2018 Letter DE-Daily Inspection Summary
06/06/2018 Letter DE-Daily Inspection Summary
06/08/2018 Letter DE-Daily Inspection Summary
06/11/2018 Letter DE-Daily Inspection Summary
06/18/2018 Letter DE-Daily Inspection Summary
06/18/2018 Letter DE-Daily Inspection Summary
06/21/2018 Letter DE-Daily Inspection Summary
06/22/2018 Letter DE-Daily Inspection Summary
06/25/2018 Letter DE-Daily Inspection Summary
07/02/2018 Letter DE-Daily Inspection Summary
07/02/2018 Letter DE-Daily Inspection Summary
07/05/2018 Letter DE-Daily Inspection Summary
07/10/2018 Letter DE-Daily Inspection Summary
07/11/2018 Letter DE-Daily Inspection Summary
07/30/2018 Letter DE-Daily Inspection Summary
08/01/2018 Letter DE-Daily Inspection Summary
08/01/2018 Letter DE-Daily Inspection Summary
08/10/2018 Letter DE-Daily Inspection Summary
08/10/2018 Letter DE-Daily Inspection Summary
08/13/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
08/13/2018 Letter DE-Daily Inspection Summary
08/15/2018 Letter DE-Daily Inspection Summary
08/22/2018 Letter DE-Daily Inspection Summary
07/13/2018 Letter DE-Daily Inspection Summary
07/16/2018 Letter DE-Daily Inspection Summary
07/17/2018 Letter DE-Daily Inspection Summary
07/23/2018 Letter DE-Daily Inspection Summary
07/30/2018 Letter DE-Daily Inspection Summary
07/30/2018 Letter DE-Daily Inspection Summary
10/04/2018 Letter DE-Daily Inspection Summary
08/29/2018 Letter DE-Daily Inspection Summary
08/30/2018 Letter DE-Daily Inspection Summary
08/30/2018 Letter DE-Daily Inspection Summary
08/30/2018 Letter DE-Daily Inspection Summary
08/30/2018 Letter DE-Daily Inspection Summary
09/04/2018 Letter DE-Daily Inspection Summary
09/04/2018 Letter DE-Daily Inspection Summary
09/04/2018 Letter DE-Daily Inspection Summary
09/13/2018 Letter DE-Daily Inspection Summary
09/14/2018 Letter DE-Daily Inspection Summary
09/14/2018 Letter DE-Daily Inspection Summary
09/14/2018 Letter DE-Daily Inspection Summary
10/01/2018 Letter DE-Daily Inspection Summary
11/12/2018 Letter Inspection Summary
11/12/2018 Letter Inspection Summary
11/12/2018 Letter Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
09/27/2018 Letter DE-Daily Inspection Summary
09/27/2018 Letter DE-Daily Inspection Summary
10/08/2018 Letter DE-Daily Inspection Summary
10/10/2018 Letter DE-Daily Inspection Summary
10/12/2018 Letter DE-Daily Inspection Summary
10/24/2018 Letter DE-Daily Inspection Summary
10/24/2018 Letter DE-Daily Inspection Summary
10/24/2018 Letter DE-Daily Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
09/11/2018 Letter DE-Daily Inspection Summary
09/11/2018 Letter DE-Daily Inspection Summary
09/27/2018 Letter DE-Daily Inspection Summary
10/01/2018 Letter DE-Daily Inspection Summary
10/03/2018 Letter DE-Daily Inspection Summary
09/12/2019 Letter DE-Daily Inspection Summary
09/13/2019 Letter DE-Daily Inspection Summary
10/03/2018 Letter DE-Daily Inspection Summary
09/23/2019 Letter DE-Daily Inspection Summary
09/23/2019 Letter DE-Daily Inspection Summary
09/27/2019 Letter DE-Daily Inspection Summary
10/08/2018 Letter DE-Daily Inspection Summary
11/09/2018 Letter DE-Daily Inspection Summary
11/09/2018 Letter DE-Daily Inspection Summary
11/09/2018 Letter DE-Daily Inspection Summary
09/18/2018 Letter DE-Daily Inspection Summary
11/05/2019 Letter DE-Daily Inspection Summary
11/05/2019 Letter DE-Daily Inspection Summary
11/05/2019 Letter DE-Daily Inspection Summary
11/05/2019 Letter DE-Daily Inspection Summary
11/05/2019 Letter DE-Daily Inspection Summary
11/06/2019 Letter DE-Daily Inspection Summary
11/07/2019 Letter DE-Punch List
11/07/2019 Substanial Completion and Punch List for Village At View High On-Site Infrastructure
09/25/2018 Letter DE-Daily Inspection Summary
01/06/2020 Letter DE-Daily Inspection Summary
09/25/2018 Letter DE-Daily Inspection Summary
11/21/2018 Letter DE-Daily Inspection Summary
11/21/2018 Letter DE-Daily Inspection Summary
10/30/2020 Letter DE-Daily Inspection Summary
10/30/2020 Letter DE-Daily Inspection Summary
10/30/2020 Letter DE-Daily Inspection Summary
10/30/2020 Letter DE-Daily Inspection Summary
10/30/2020 Letter DE-Daily Inspection Summary
10/30/2020 Letter DE-Daily Inspection Summary
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter DE-Daily Inspection Summary
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter DE-Daily Inspection Summary
12/02/2020 Letter DE-Daily Inspection Summary
11/26/2018 Letter DE-Daily Inspection Summary
11/26/2018 Letter DE-Daily Inspection Summary
11/26/2018 Letter DE-Daily Inspection Summary
11/26/2018 Letter DE-Daily Inspection Summary
11/26/2018 Letter DE-Daily Inspection Summary
11/26/2018 Letter DE-Daily Inspection Summary
12/04/2018 Letter DE-Daily Inspection Summary
10/28/2019 Letter DE-Daily Inspection Summary
10/28/2019 Letter DE-Daily Inspection Summary
10/28/2019 Letter DE-Daily Inspection Summary
11/20/2019 Village at View High on_Site Infrastructure Signed Substantial Completion
03/19/2020 Letter DE-Daily Inspection Summary
12/26/2018 Letter DE-Daily Inspection Summary
01/02/2019 Letter DE-Daily Inspection Summary
02/12/2019 Letter DE-Daily Inspection Summary
02/13/2019 Letter DE-Daily Inspection Summary
02/13/2019 Letter DE-Daily Inspection Summary
04/12/2019 Letter DE-Daily Inspection Summary
09/12/2019 Letter DE-Daily Inspection Summary
09/13/2019 Letter DE-Daily Inspection Summary
09/30/2019 Letter DE-Daily Inspection Summary
10/28/2019 Letter DE-Daily Inspection Summary
08/17/2020 SANITARY ASBUILTS
08/17/2020 8.17.20 WATER as- builts
08/02/2021 Plans STREET AND STORM ASBUILT
08/30/2021 Security Document Final Affidavit
12/02/2020 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/02/2020 Letter DE-Daily Inspection Summary
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter DE-Daily Inspection Summary
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter DE-Daily Inspection Summary
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
07/26/2021 Security Document Village at View High LOC - 3 yr maintenance bond
12/17/2021 Letter DE-Certificate of Final Acceptance (Commercial)
12/07/2020 C_206
01/11/2021 Letter DE-Punch List
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home