Permit Application Status

PRPWFC20173605


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRPWFC20173605
Public Works Infrastructure Permit - Commercial
Final Acceptance
RUF DEVELOPMENT INC
DEVELOPMENT COMPLETE
Village at View High - Off-Site Sanitary Sewer from the northeast corner of the project headed in a northeasterly directon to the Cedar Creek Interceptor Main
11/03/2017
11/06/2017
10/28/2019
Locations
Contacts
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
CITYSCAPE CONSTRUCTION VIEW HIGH LLC, Address:10 W CARMEL DR STE 200, Phone:(317) 574-1600 Ext:100  
RUF DEVELOPMENT INC, Address:604 NW RIVEN ROCK TRL  
WEINEL CAREY H & SHERRY A-TRUSTEES, Address:345 NW VIEW HIGH DR  
WEINEL CAREY H JR & SHERRY A TRUST, Address:345 NW VIEW HIGH DR  
WEINEL CINDY S, Address:10903 VIEW HIGH DR  
RICHARD FAULKNER LLC, Address:10825 VIEW HIGH DR  
WOHLLEBER WILLIAM, Address:2807 NW CHIPMAN RD  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/03/2017 11/03/2017
Chris Hughey
CHRIS HUGHEY 11/03/2017 11:19 AM
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $11,533.68 $11,533.68 Paid 11/03/2017
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Site Visit Partial 1/22/2018 at 9:15 AM 01/22/2018
PW-Misc
Informational
01/22/2018
Jeremy Young 01/22/2018 9:15 AM No work being done today because of weather.
Erosion Control Inspection Partial 1/25/2018 at 2:00 PM 01/25/2018
PW-Misc
Informational
01/25/2018
The silt-fence is up and everything looks good.Steve Robbins 01/25/2018 3:18 PM
Sanitary - Material Verification Partial 2/1/2018 at 10:45 AM 02/01/2018
Informational
02/01/2018
The materials have not been delivered yet. Steve Robbins 02/01/2018 11:15 AM
Erosion Control Inspection Partial 2/7/2018 at 1:15 PM 02/07/2018
PW-Misc
Informational
01/25/2018
The silt-fence is up and everything looks good.Steve Robbins 01/25/2018 3:18 PM
PW-Misc
Informational
02/07/2018
The silt fence is up and in good shape.Steve Robbins 02/07/2018 3:45 PM
Sanitary Sewer Construction Inspection Partial 2/9/2018 at 1:00 PM 02/09/2018
PW-Main inspection
Informational
02/09/2018
Today the contractors are building the encasement for the ductile iron pipe that is going across the stream. We discussed that they need to have 8 inches of concrete all the way around the pipe and the re-bar needs to be in the middle of the concrete. On both sides of the pipe the concrete gets higher with the highest point reaching 20''. When it is finished it will look like a swale. Fine Cut drilling and sawing is also here and doing the core drill for the existing MH 27-189. They have exposed that MH and are going to install the A-lok when they are finished core drilling. They are not planning on installing any pipe today.Steve Robbins 02/09/2018 2:23 PM
Sanitary Sewer Construction Inspection Partial 2/12/2018 at 9:00 AM 02/12/2018
PW-Main inspection
Informational
02/12/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
Sanitary Sewer Construction Inspection Partial 2/12/2018 at 11:15 AM 02/12/2018
PW-Main inspection
Informational
02/12/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/12/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
Sanitary Sewer Construction Inspection Partial 2/12/2018 at 2:00 PM 02/12/2018
PW-Main inspection
Informational
02/12/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/12/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/12/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
Sanitary Sewer Construction Inspection Partial 2/13/2018 at 10:35 AM 02/13/2018
PW-Main inspection
Informational
02/12/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/12/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/12/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/13/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
Sanitary Sewer Construction Inspection Partial 2/13/2018 at 1:15 PM 02/13/2018
PW-Main inspection
Informational
02/13/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/13/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/13/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/13/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/13/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
Sanitary Sewer Construction Inspection Partial 2/14/2018 at 11:45 AM 02/14/2018
PW-Main inspection
Informational
02/13/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/13/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/13/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/13/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/13/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/14/2018
I came by this morning on my way to a water sample and they were starting to install the ductile iron pipe in MH 1-1, they are now are putting the rebar encasement around the pipe, they are putting 8" of concrete around the pipe with it gradually going up to 20 " on the far end of each side of the creek. Steve Robbins 02/14/2018 12:24 PM
Sanitary Sewer Construction Inspection Partial 2/14/2018 at 1:30 PM 02/14/2018
PW-Main inspection
Informational
02/14/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/14/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/14/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/14/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/14/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/14/2018
I came by this morning on my way to a water sample and they were starting to install the ductile iron pipe in MH 1-1, they are now are putting the rebar encasement around the pipe, they are putting 8" of concrete around the pipe with it gradually going up to 20 " on the far end of each side of the creek. Steve Robbins 02/14/2018 12:24 PM
Informational
02/14/2018
The contractors put approximately 120' of ductile iron pipe in and encased about 80' of it in rebar with kcmmb mix. They are close to the stream .Steve Robbins 02/14/2018 3:51 PM
Sanitary Sewer Construction Inspection Partial 2/15/2018 at 8:15 AM 02/15/2018
PW-Main inspection
Informational
02/14/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/14/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/14/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/14/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/14/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/15/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
Sanitary Sewer Construction Inspection Partial 2/15/2018 at 1:50 PM 02/15/2018
PW-Main inspection
Informational
02/15/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/15/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/15/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/15/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/15/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/15/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/15/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
Sanitary Sewer Construction Inspection Partial 2/16/2018 at 1:15 PM 02/16/2018
PW-Main inspection
Informational
02/15/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/15/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/15/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/15/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/15/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/15/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/15/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/16/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
Erosion Control Inspection Failed 2/16/2018 at 3:00 PM 02/16/2018
PW-Misc
Informational
02/07/2018
The silt-fence is up and everything looks good.Steve Robbins 01/25/2018 3:18 PM
PW-Misc
Informational
02/07/2018
The silt fence is up and in good shape.Steve Robbins 02/07/2018 3:45 PM
PW-Devices for Erosion and Sediment Control
Informational
02/16/2018
I put this on the wrong permit last time, this project does not have the silt fence up yet. I talked with Chad and he has assured me he is pushing the company to install the silt fence. I talked with the P.M. for cityscapes and he was asking about the erosino control also. They silt fence companty came out last week and could not do it because of the ground being froze. If it is not in by tuesday feb. 20 I will have to take firmer action , but I do think they are trying to get it in .Steve Robbins 02/16/2018 4:06 PM
Erosion Control Inspection Partial 2/20/2018 at 10:30 AM 02/20/2018
PW-Misc
Informational
02/16/2018
The silt-fence is up and everything looks good.Steve Robbins 01/25/2018 3:18 PM
PW-Misc
Informational
02/16/2018
The silt fence is up and in good shape.Steve Robbins 02/07/2018 3:45 PM
PW-Devices for Erosion and Sediment Control
Informational
02/16/2018
I put this on the wrong permit last time, this project does not have the silt fence up yet. I talked with Chad and he has assured me he is pushing the company to install the silt fence. I talked with the P.M. for cityscapes and he was asking about the erosino control also. They silt fence companty came out last week and could not do it because of the ground being froze. If it is not in by tuesday feb. 20 I will have to take firmer action , but I do think they are trying to get it in .Steve Robbins 02/16/2018 4:06 PM
PW-Erosion and Sediment Control
Resolved
02/20/2018
The silt fence has been instlled, we were off yesterday and it looks like the silt fence has been installed. I will re-examine the silt fence in the next few days to make sure they have enough silt fence up where it needs to go.Steve Robbins 02/20/2018 2:50 PM
Sanitary Sewer Construction Inspection Partial 2/21/2018 at 12:00 PM 02/21/2018
PW-Main inspection
Informational
02/16/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/16/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/16/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/16/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/16/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/16/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/16/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/16/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/21/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
Sanitary Sewer Construction Inspection Partial 2/22/2018 at 1:45 PM 02/22/2018
PW-Main inspection
Informational
02/21/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/21/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/21/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/21/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/21/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/21/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/21/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/21/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/21/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
02/22/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
Sanitary Sewer Construction Inspection Partial 2/23/2018 at 2:00 PM 02/23/2018
PW-Main inspection
Informational
02/22/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/22/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/22/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/22/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/22/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/22/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/22/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/22/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/22/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
02/22/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
02/23/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
Sanitary Sewer Construction Inspection Partial 2/26/2018 at 9:00 AM 02/26/2018
PW-Main inspection
Informational
02/23/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/23/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/23/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/23/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/23/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/23/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/23/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/23/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/23/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
02/23/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
02/23/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
02/26/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
Erosion Control Inspection Partial 2/26/2018 at 9:45 AM 02/26/2018
PW-Misc
Informational
02/20/2018
The silt-fence is up and everything looks good.Steve Robbins 01/25/2018 3:18 PM
PW-Misc
Informational
02/20/2018
The silt fence is up and in good shape.Steve Robbins 02/07/2018 3:45 PM
PW-Devices for Erosion and Sediment Control
Informational
02/20/2018
I put this on the wrong permit last time, this project does not have the silt fence up yet. I talked with Chad and he has assured me he is pushing the company to install the silt fence. I talked with the P.M. for cityscapes and he was asking about the erosino control also. They silt fence companty came out last week and could not do it because of the ground being froze. If it is not in by tuesday feb. 20 I will have to take firmer action , but I do think they are trying to get it in .Steve Robbins 02/16/2018 4:06 PM
PW-Misc
Informational
02/26/2018
The silt fence has been installed. I will be checking periodically to make sure the fence is still up and working properly. Steve Robbins 02/26/2018 11:32 AM
Sanitary Sewer Construction Inspection Partial 2/26/2018 at 2:15 PM 02/26/2018
PW-Main inspection
Informational
02/26/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/26/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/26/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/26/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/26/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/26/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/26/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/26/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/26/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
02/26/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
02/26/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
02/26/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
02/26/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
Sanitary Sewer Construction Inspection Partial 2/27/2018 at 2:00 PM 02/27/2018
PW-Main inspection
Informational
02/26/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/26/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/26/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/26/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/26/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/26/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/26/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/26/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/26/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
02/26/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
02/26/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
02/26/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
02/26/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
02/27/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
Sanitary Sewer Construction Inspection Partial 2/28/2018 at 12:50 PM 02/28/2018
PW-Main inspection
Informational
02/27/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/27/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/27/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/27/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/27/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/27/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/27/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/27/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/27/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
02/27/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
02/27/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
02/27/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
02/27/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
02/27/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
02/28/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
Sanitary Sewer Construction Inspection Partial 3/1/2018 at 12:30 PM 03/01/2018
PW-Main inspection
Informational
02/28/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
02/28/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
02/28/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
02/28/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
02/28/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
02/28/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
02/28/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
02/28/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
02/28/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
02/28/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
02/28/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
02/28/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
02/28/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
02/28/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
02/28/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/01/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
Sanitary Sewer Construction Inspection Partial 3/2/2018 at 10:30 AM 03/02/2018
PW-Main inspection
Informational
03/01/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/01/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/01/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/01/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/01/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/01/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/01/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/01/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/01/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/01/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/01/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/01/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/01/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/01/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/01/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/01/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/02/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
Sanitary Sewer Construction Inspection Partial 3/6/2018 at 1:30 PM 03/06/2018
PW-Main inspection
Informational
03/02/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/02/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/02/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/02/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/02/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/02/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/02/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/02/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/02/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/02/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/02/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/02/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/02/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/02/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/02/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/02/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/02/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/06/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
Sanitary Sewer Construction Inspection Partial 3/7/2018 at 1:30 PM 03/07/2018
PW-Main inspection
Informational
03/06/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/06/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/06/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/06/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/06/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/06/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/06/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/06/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/06/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/06/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/06/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/06/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/06/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/06/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/06/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/06/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/06/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/06/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/07/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
Sanitary Sewer Construction Inspection Partial 3/9/2018 at 10:00 AM 03/09/2018
PW-Main inspection
Informational
03/07/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/07/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/07/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/07/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/07/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/07/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/07/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/07/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/07/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/07/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/07/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/07/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/07/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/07/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/07/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/07/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/07/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/07/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/07/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/09/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
Sanitary Sewer Construction Inspection Partial 3/12/2018 at 1:30 PM 03/12/2018
PW-Main inspection
Informational
03/09/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/09/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/09/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/09/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/09/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/09/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/09/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/09/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/09/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/09/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/09/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/09/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/09/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/09/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/09/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/09/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/09/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/09/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/09/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/09/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
PW-Main inspection
Informational
03/12/2018
This morning they set MH A-9 and this afternoon they set -10. They were putting in the first stick of pipe going g toward A-11 when i left. Steve Robbins 03/12/2018 3:17 PM
Sanitary Sewer Construction Inspection Partial 3/13/2018 at 8:45 AM 03/13/2018
PW-Main inspection
Informational
03/12/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/12/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/12/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/12/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/12/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/12/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/12/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/12/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/12/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/12/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/12/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/12/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/12/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/12/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/12/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/12/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/12/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/12/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/12/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/12/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
PW-Main inspection
Informational
03/12/2018
This morning they set MH A-9 and this afternoon they set -10. They were putting in the first stick of pipe going g toward A-11 when i left. Steve Robbins 03/12/2018 3:17 PM
PW-Main inspection
Informational
03/13/2018
This morning the contractors installed MH A-11 and were laying pipe toward A-12. Steve Robbins 03/13/2018 1:44 PM
Sanitary Sewer Construction Inspection Partial 3/13/2018 at 1:45 PM 03/13/2018
PW-Main inspection
Informational
03/13/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/13/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/13/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/13/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/13/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/13/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/13/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/13/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/13/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/13/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/13/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/13/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/13/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/13/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/13/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/13/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/13/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/13/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/13/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/13/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
PW-Main inspection
Informational
03/13/2018
This morning they set MH A-9 and this afternoon they set -10. They were putting in the first stick of pipe going g toward A-11 when i left. Steve Robbins 03/12/2018 3:17 PM
PW-Main inspection
Informational
03/13/2018
This morning the contractors installed MH A-11 and were laying pipe toward A-12. Steve Robbins 03/13/2018 1:44 PM
PW-Main inspection
Informational
03/13/2018
MH A-12 has been installed this afternoon with the barrel sections and the rock. From MH A-12 to A-13 there is 27 LF of Ductile Iron with and encasement.They are planning on doing that in the morning.Steve Robbins 03/13/2018 3:55 PM
Sanitary Sewer Construction Inspection Partial 3/14/2018 at 10:00 AM 03/14/2018
PW-Main inspection
Informational
03/13/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/13/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/13/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/13/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/13/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/13/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/13/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/13/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/13/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/13/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/13/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/13/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/13/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/13/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/13/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/13/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/13/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/13/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/13/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/13/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
PW-Main inspection
Informational
03/13/2018
This morning they set MH A-9 and this afternoon they set -10. They were putting in the first stick of pipe going g toward A-11 when i left. Steve Robbins 03/12/2018 3:17 PM
PW-Main inspection
Informational
03/13/2018
This morning the contractors installed MH A-11 and were laying pipe toward A-12. Steve Robbins 03/13/2018 1:44 PM
PW-Main inspection
Informational
03/13/2018
MH A-12 has been installed this afternoon with the barrel sections and the rock. From MH A-12 to A-13 there is 27 LF of Ductile Iron with and encasement.They are planning on doing that in the morning.Steve Robbins 03/13/2018 3:55 PM
PW-Main inspection
Informational
03/14/2018
MH a-12 and MH a-13 and the ductile iron pipe between the 2 MH"s have been instaled. The contractors also installed the re-bar encasement and the concrete from MH to MH.Steve Robbins 03/14/2018 11:59 AM
Sanitary Sewer Construction Inspection Partial 3/14/2018 at 1:30 PM 03/14/2018
PW-Main inspection
Informational
03/14/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/14/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/14/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/14/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/14/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/14/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/14/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/14/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/14/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/14/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/14/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/14/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/14/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/14/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/14/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/14/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/14/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/14/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/14/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/14/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
PW-Main inspection
Informational
03/14/2018
This morning they set MH A-9 and this afternoon they set -10. They were putting in the first stick of pipe going g toward A-11 when i left. Steve Robbins 03/12/2018 3:17 PM
PW-Main inspection
Informational
03/14/2018
This morning the contractors installed MH A-11 and were laying pipe toward A-12. Steve Robbins 03/13/2018 1:44 PM
PW-Main inspection
Informational
03/14/2018
MH A-12 has been installed this afternoon with the barrel sections and the rock. From MH A-12 to A-13 there is 27 LF of Ductile Iron with and encasement.They are planning on doing that in the morning.Steve Robbins 03/13/2018 3:55 PM
PW-Main inspection
Informational
03/14/2018
MH a-12 and MH a-13 and the ductile iron pipe between the 2 MH"s have been instaled. The contractors also installed the re-bar encasement and the concrete from MH to MH.Steve Robbins 03/14/2018 11:59 AM
PW-Main inspection
Corrective Action Required
03/14/2018
The contractors are working from MH A-13 toward MH A-14. Steve Robbins 03/14/2018 4:02 PM
Sanitary Sewer Construction Inspection Partial 3/15/2018 at 2:40 PM 03/16/2018
PW-Main inspection
Informational
03/14/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/14/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/14/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/14/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/14/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/14/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/14/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/14/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/14/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/14/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/14/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/14/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/14/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/14/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/14/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/14/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/14/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/14/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/14/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/14/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
PW-Main inspection
Informational
03/14/2018
This morning they set MH A-9 and this afternoon they set -10. They were putting in the first stick of pipe going g toward A-11 when i left. Steve Robbins 03/12/2018 3:17 PM
PW-Main inspection
Informational
03/14/2018
This morning the contractors installed MH A-11 and were laying pipe toward A-12. Steve Robbins 03/13/2018 1:44 PM
PW-Main inspection
Informational
03/14/2018
MH A-12 has been installed this afternoon with the barrel sections and the rock. From MH A-12 to A-13 there is 27 LF of Ductile Iron with and encasement.They are planning on doing that in the morning.Steve Robbins 03/13/2018 3:55 PM
PW-Main inspection
Informational
03/14/2018
MH a-12 and MH a-13 and the ductile iron pipe between the 2 MH"s have been instaled. The contractors also installed the re-bar encasement and the concrete from MH to MH.Steve Robbins 03/14/2018 11:59 AM
PW-Main inspection
Corrective Action Required
03/14/2018
The contractors are working from MH A-13 toward MH A-14. Steve Robbins 03/14/2018 4:02 PM
PW-Main inspection
Informational
03/16/2018
Matt Munger 03/16/2018 2:40 PM I spoke with the foreman on site and he stated they had installed 100ft of sanitary sewer line and installed MH A-14. I observed an adequate amount of gravel above the pipe. They also had wrapped the lower barrel section and I did see there was mastic used when setting the cone section on top of the barrel section. They had also placed utility marker tape on top of the gravel as well. The pipe that was onsite was 15" SDR-26.
Sanitary Sewer Construction Inspection Partial 3/16/2018 at 1:45 PM 03/16/2018
PW-Main inspection
Informational
03/16/2018
Matt Munger 03/16/2018 2:05 PM I spoke with the foreman and he stated they installed approximately 100ft of sanitary main. There was an adequate amount of gravel above and below the pipe. They also were putting down the green utility marker tape as well.
Sanitary Sewer Construction Inspection Partial 3/21/2018 at 11:15 AM 03/21/2018
PW-Main inspection
Informational
03/16/2018
The core drill was done on the existing MH on friday. Today the contractors are pumping the water out and are getting ready to start on MH 0. They are not working right now.Steve Robbins 02/12/2018 9:49 AM
PW-Main inspection
Informational
03/16/2018
The have installed the A-lok boot after the core drill has been completed. They are going to start on the MH o after lunch.Steve Robbins 02/12/2018 11:47 AM
PW-Main inspection
Informational
03/16/2018
MH A-o has been installed, the base has been installed, it has not been wrapped yet and the cone has not been put on yet. The 15" SDR pipe has been connected to the existing MH.Steve Robbins 02/12/2018 3:24 PM
PW-Main inspection
Informational
03/16/2018
The contractors are laying pipe from MH A-0 going towards A-1, they are using a vibrater to compact the rock under the 15" pipe.Steve Robbins 02/13/2018 11:11 AM
PW-Main inspection
Informational
03/16/2018
They are finishing up the 85 ft. of pipe being laid to MH 1-1. They are getting ready to install MH 1-1, the rock is being installed now. Steve Robbins 02/13/2018 2:15 PM
PW-Main inspection
Informational
03/16/2018
They have started the pipe encasement with rebar around the pipe , they are getting 8" all the way around the pipe with kcmmb 5k as called out in the plans. They are using ductile iron as called out in the plans. They have aproximately 80-100 feet encased now. They are digging across the stream right now.Steve Robbins 02/15/2018 8:45 AM
PW-Main inspection
Informational
03/16/2018
The ductile iron pipe has been laid for the entire length of the encasement, the rebar has been installed and tied together. The concrete has been installed for about 3/4 of the encasement. They are back-filling the part of the encasement that has cured. Another truck just got here and that will be close to finishing to concrete. They have maintained at least 8" around the encasement and are gradually working toward the end where it will be 20" on the top.Steve Robbins 02/15/2018 3:18 PM
PW-Main inspection
Informational
03/16/2018
The contractors have laid all the ductile iron pipe from MH A-1 to A-2 and the concrete encasement has been finished and backfilled. This afternoon they installed MH A-2 and about 80' of sdr 26 15" pipe heading toward MH A-3. Steve Robbins 02/16/2018 3:57 PM
PW-Main inspection
Informational
03/16/2018
The contractors tried to work today but it was too muddy and icy. They are planning on trying again tomorrow.
PW-Main inspection
Informational
03/16/2018
The contractors have not worked all week due to the ice and rain.Steve Robbins 02/22/2018 3:12 PM
PW-Main inspection
Informational
03/16/2018
Jeremy Young 02/23/2018 3:39 PM Contractor set MH A-4 and ran the sanitary line toward MH A-5. The rock bedding looked to be sufficient and there was locate tape installed.
PW-Main inspection
Informational
03/16/2018
MH A-3 has been installed and the pipe going to MH A-4 was put in on friday while I was out. They will set MH A-4 this afternoon. Steve Robbins 02/26/2018 10:40 AM
PW-Main inspection
Informational
03/16/2018
They have not made it to MH A-4, about 2 sticks of pipe away.Steve Robbins 02/26/2018 3:02 PM
PW-Main inspection
Informational
03/16/2018
The contractors are installing MH A-4 . They are hoping to get all the sections installed today.Steve Robbins 02/27/2018 4:17 PM
PW-Main inspection
Informational
03/16/2018
MH A-4 has been installed, all the sections and the cone. One stick of pipe was laid coming out of MH A-4 going toward A-5. They are also fixing some silt fence that was knocked down.Steve Robbins 02/28/2018 2:08 PM
PW-Main inspection
Informational
03/16/2018
They have laid the pipe up to MH A-5. This afternoon the base for A-5 has been installed, I have asked them about compaction testing every 300. The last 2 days I have not seen anyone testing.Steve Robbins 03/01/2018 3:22 PM
PW-Main inspection
Informational
03/16/2018
The contractors have finished MH A-5 , all sections are in and taped. They are now laying pipe to MH A-6. Steve Robbins 03/02/2018 11:16 AM
PW-Main inspection
Informational
03/16/2018
Yesterday on 3/5 the contractors installed MH A-6 and all the sections and the cone. Today they laid pipe up to MH A-7 and installed A-7. This afternoon they were going toward A-8.Steve Robbins 03/06/2018 3:41 PM
PW-Main inspection
Informational
03/16/2018
They have backfilled A-7 and this afternoon they had about 3 sticks of pipe coming out of A-7 going toward A-8.Steve Robbins 03/07/2018 4:03 PM
PW-Main inspection
Informational
03/16/2018
This morning they set MH A-8. They are heading toward A-9. Steve Robbins 03/09/2018 11:12 AM
PW-Main inspection
Informational
03/16/2018
This morning they set MH A-9 and this afternoon they set -10. They were putting in the first stick of pipe going g toward A-11 when i left. Steve Robbins 03/12/2018 3:17 PM
PW-Main inspection
Informational
03/16/2018
This morning the contractors installed MH A-11 and were laying pipe toward A-12. Steve Robbins 03/13/2018 1:44 PM
PW-Main inspection
Informational
03/16/2018
MH A-12 has been installed this afternoon with the barrel sections and the rock. From MH A-12 to A-13 there is 27 LF of Ductile Iron with and encasement.They are planning on doing that in the morning.Steve Robbins 03/13/2018 3:55 PM
PW-Main inspection
Informational
03/16/2018
MH a-12 and MH a-13 and the ductile iron pipe between the 2 MH"s have been instaled. The contractors also installed the re-bar encasement and the concrete from MH to MH.Steve Robbins 03/14/2018 11:59 AM
PW-Main inspection
Corrective Action Required
03/16/2018
The contractors are working from MH A-13 toward MH A-14. Steve Robbins 03/14/2018 4:02 PM
PW-Main inspection
Informational
03/16/2018
Matt Munger 03/16/2018 2:40 PM I spoke with the foreman on site and he stated they had installed 100ft of sanitary sewer line and installed MH A-14. I observed an adequate amount of gravel above the pipe. They also had wrapped the lower barrel section and I did see there was mastic used when setting the cone section on top of the barrel section. They had also placed utility marker tape on top of the gravel as well. The pipe that was onsite was 15" SDR-26.
PW-Main inspection
Informational
03/21/2018
The contractors have laid the pipe up to MH A-15. Right now they are at lunch and they will install the MH A-15 after lunch. It appears they have used the proper amount of rock to cover the pipe.Steve Robbins 03/21/2018 11:50 AM
Sanitary Sewer Construction Inspection Passed 3/22/2018 at 11:30 AM 03/22/2018
PW-Main inspection
Informational
03/22/2018
MH A-15 has been installed and completed. They are gong to start pouring the inverts tomorrow. This completes the sanitary sewer construction.Steve Robbins 03/22/2018 1:25 PM
Sanitary Sewer - Invert Partial 3/23/2018 at 1:30 PM 03/23/2018
PW-Misc
Informational
03/23/2018
Today the contractors poured all the inverts for the 15 MH's. I still have a few more to look at but they appear to be good. MH A-0 was holding some water but I talked with Kent and Gene and they said it is because they had to come in below the flow line. They did it according to the plans because it is all that could be done.Steve Robbins 03/23/2018 3:52 PM
Sanitary Sewer - Vacuum Partial 3/29/2018 at 2:00 PM 03/30/2018
PW-Misc
Informational
03/30/2018
We did the vacuum testing for MH A-0, A-1 and A-2. The test was for 2.5 minutes and they all passed. They are planning on doing the rest of the MH on April 22, when it is 30 days for everything.Steve Robbins 03/30/2018 8:33 AM
Sanitary Sewer - Air Test Partial 3/29/2018 at 12:30 PM 03/30/2018
PW-Sanitary Sewer Testing
Informational
03/30/2018
We did the air test from existing Mh to A-o , A-o to A-1, and A-1 to A-2. The testing passed up to MH A-2. They are going to do the rest on april 23.Steve Robbins 03/30/2018 9:04 AM
Sanitary Sewer - Mandrel Partial 3/29/2018 at 3:00 PM 03/30/2018
PW-Misc
Informational
03/30/2018
The mandrel test was completed from the existing MH to A-o-10 ft. A-0 to A-1 which is 85 ft. These tests all passed. A-1 to A-2 is all ductile so there is no mandrel test.Steve Robbins 03/30/2018 9:08 AM
Erosion Control Inspection Passed 3/30/2018 at 9:30 AM 03/30/2018
PW-Misc
Informational
02/26/2018
The silt-fence is up and everything looks good.Steve Robbins 01/25/2018 3:18 PM
PW-Misc
Informational
02/26/2018
The silt fence is up and in good shape.Steve Robbins 02/07/2018 3:45 PM
PW-Devices for Erosion and Sediment Control
Informational
02/26/2018
I put this on the wrong permit last time, this project does not have the silt fence up yet. I talked with Chad and he has assured me he is pushing the company to install the silt fence. I talked with the P.M. for cityscapes and he was asking about the erosino control also. They silt fence companty came out last week and could not do it because of the ground being froze. If it is not in by tuesday feb. 20 I will have to take firmer action , but I do think they are trying to get it in .Steve Robbins 02/16/2018 4:06 PM
PW-Misc
Informational
02/26/2018
The silt fence has been installed. I will be checking periodically to make sure the fence is still up and working properly. Steve Robbins 02/26/2018 11:32 AM
PW-Misc
Informational
03/30/2018
The erosion control appears to be working properly.Steve Robbins 03/30/2018 11:17 AM
Sanitary Sewer - Invert Passed 4/6/2018 at 10:30 AM 04/06/2018
PW-Misc
Informational
03/23/2018
Today the contractors poured all the inverts for the 15 MH's. I still have a few more to look at but they appear to be good. MH A-0 was holding some water but I talked with Kent and Gene and they said it is because they had to come in below the flow line. They did it according to the plans because it is all that could be done.Steve Robbins 03/23/2018 3:52 PM
PW-Misc
Informational
04/06/2018
The contractors have poured all the inverts for the MH's, they all appear to be done properly.Steve Robbins 04/06/2018 11:29 AM
Sanitary Sewer Construction Inspection Partial 4/17/2018 at 2:00 PM 04/17/2018
PW-Main inspection
Informational
03/16/2018
Matt Munger 03/16/2018 2:05 PM I spoke with the foreman and he stated they installed approximately 100ft of sanitary main. There was an adequate amount of gravel above and below the pipe. They also were putting down the green utility marker tape as well.
PW-Main inspection
Informational
04/17/2018
The testing has been completed for MH A-0 to A-2 . I e-mailed Josh Roach on 4/4/18 for a camera inspection. The water dept. came out yesterday and put dye into MH a-15 and let it run down to MH a-0. This afternoon they came out and did the camera test for A-0 to A-2.Steve Robbins 04/17/2018 3:50 PM
ESC - (Vegetation/Ground Cover) Partial 4/17/2018 at 3:00 PM 04/17/2018
PW-Misc
Informational
04/17/2018
The seeding company came in yesterday and today and installed the Coir Log and J-Hook. They did this on the enbankment of the stream. They installed all the seed and straw around MH A-0 to A-2 . Steve Robbins 04/17/2018 4:01 PM
Sanitary Sewer Construction Inspection Partial 4/18/2018 at 9:00 AM 04/18/2018
PW-Main inspection
Informational
04/18/2018
The contractors were planning on doing testing today but they called and cancelled for today.I spoke with the camera crew yesterday while they were at the site, they said they were not able to put the camera in the MH A-0 because the water was too high for the camera. They were taking the results back to their bosses for review. I am waiting to hear what the results of the camera test was.Steve Robbins 04/18/2018 2:22 PM
Sanitary Sewer Construction Inspection Partial 4/20/2018 at 9:45 AM 04/20/2018
PW-Sanitary Sewer Testing
Informational
04/20/2018
Matt Munger 04/20/2018 10:50 AM Observed the sanitary testing with Steve Robbins.
Sanitary Sewer Construction Inspection Partial 4/20/2018 at 1:40 PM 04/20/2018
PW-Sanitary Sewer Testing
Informational
04/20/2018
Matt Munger 04/20/2018 2:30 PM I observed the sanitary sewer testing with Steve Robbins.
Sanitary Sewer - Air Test Partial 4/20/2018 at 8:00 AM 04/20/2018
PW-Sanitary Sewer Testing
Informational
03/30/2018
We did the air test from existing Mh to A-o , A-o to A-1, and A-1 to A-2. The testing passed up to MH A-2. They are going to do the rest on april 23.Steve Robbins 03/30/2018 9:04 AM
PW-Sanitary Sewer Testing
Informational
04/20/2018
Today we did the air test on MH A2-A-7. After today everything passsed up to A-7.Steve Robbins 04/20/2018 3:52 PM
Sanitary Sewer - Vacuum Partial 4/20/2018 at 1:00 PM 04/20/2018
PW-Misc
Informational
03/30/2018
We did the vacuum testing for MH A-0, A-1 and A-2. The test was for 2.5 minutes and they all passed. They are planning on doing the rest of the MH on April 22, when it is 30 days for everything.Steve Robbins 03/30/2018 8:33 AM
PW-Misc
Informational
04/20/2018
Today we did the vacuum test on MH A-3 to MH A-6. I did all the tests for 2.5 mins. Everything is passed up to A-6.Steve Robbins 04/20/2018 3:57 PM
Sanitary Sewer - Mandrel Partial 4/20/2018 at 2:00 PM 04/20/2018
PW-Misc
Informational
03/30/2018
The mandrel test was completed from the existing MH to A-o-10 ft. A-0 to A-1 which is 85 ft. These tests all passed. A-1 to A-2 is all ductile so there is no mandrel test.Steve Robbins 03/30/2018 9:08 AM
PW-Misc
Informational
04/20/2018
The mandrel has passed up to A-6.Steve Robbins 04/20/2018 4:00 PM
Sanitary Sewer - Air Test Partial 4/23/2018 at 8:20 AM 04/24/2018
PW-Sanitary Sewer Testing
Informational
04/20/2018
We did the air test from existing Mh to A-o , A-o to A-1, and A-1 to A-2. The testing passed up to MH A-2. They are going to do the rest on april 23.Steve Robbins 03/30/2018 9:04 AM
PW-Sanitary Sewer Testing
Informational
04/20/2018
Today we did the air test on MH A2-A-7. After today everything passsed up to A-7.Steve Robbins 04/20/2018 3:52 PM
PW-Sanitary Sewer Testing
Corrective Action Required
04/24/2018
Today we did the air test from a-6 to a-10. Everything passed.Steve Robbins 04/24/2018 8:30 AM
Sanitary Sewer - Vacuum Partial 4/23/2018 at 12:45 PM 04/24/2018
PW-Misc
Informational
04/20/2018
We did the vacuum testing for MH A-0, A-1 and A-2. The test was for 2.5 minutes and they all passed. They are planning on doing the rest of the MH on April 22, when it is 30 days for everything.Steve Robbins 03/30/2018 8:33 AM
PW-Misc
Informational
04/20/2018
Today we did the vacuum test on MH A-3 to MH A-6. I did all the tests for 2.5 mins. Everything is passed up to A-6.Steve Robbins 04/20/2018 3:57 PM
PW-Misc
Informational
04/24/2018
We did the vacuum test from a-6 to a-10. A-8 failed the first time, then they wrapped the top riser rings again and then it passed. Everything is now passed up to A-10.Steve Robbins 04/24/2018 8:36 AM
Sanitary Sewer - Mandrel Partial 4/23/2018 at 2:00 PM 04/24/2018
PW-Misc
Informational
04/20/2018
The mandrel test was completed from the existing MH to A-o-10 ft. A-0 to A-1 which is 85 ft. These tests all passed. A-1 to A-2 is all ductile so there is no mandrel test.Steve Robbins 03/30/2018 9:08 AM
PW-Misc
Informational
04/20/2018
The mandrel has passed up to A-6.Steve Robbins 04/20/2018 4:00 PM
PW-Misc
Informational
04/24/2018
The mandrel has passed from A-6 to A-10.Steve Robbins 04/24/2018 9:41 AM
Sanitary Sewer - Air Test Passed 4/24/2018 at 8:30 AM 04/25/2018
PW-Sanitary Sewer Testing
Informational
04/24/2018
We did the air test from existing Mh to A-o , A-o to A-1, and A-1 to A-2. The testing passed up to MH A-2. They are going to do the rest on april 23.Steve Robbins 03/30/2018 9:04 AM
PW-Sanitary Sewer Testing
Informational
04/24/2018
Today we did the air test on MH A2-A-7. After today everything passsed up to A-7.Steve Robbins 04/20/2018 3:52 PM
PW-Sanitary Sewer Testing
Corrective Action Required
04/24/2018
Today we did the air test from a-6 to a-10. Everything passed.Steve Robbins 04/24/2018 8:30 AM
PW-Sanitary Sewer Testing
Informational
04/25/2018
The air testing from A-10 to A-15 has been completed. This completes the testing from A-0 to A-15. Everything has passed for the air test.Steve Robbins 04/25/2018 1:27 PM
Sanitary Sewer - Vacuum Failed 4/24/2018 at 11:00 AM 04/25/2018
PW-Misc
Informational
04/24/2018
We did the vacuum testing for MH A-0, A-1 and A-2. The test was for 2.5 minutes and they all passed. They are planning on doing the rest of the MH on April 22, when it is 30 days for everything.Steve Robbins 03/30/2018 8:33 AM
PW-Misc
Informational
04/24/2018
Today we did the vacuum test on MH A-3 to MH A-6. I did all the tests for 2.5 mins. Everything is passed up to A-6.Steve Robbins 04/20/2018 3:57 PM
PW-Misc
Informational
04/24/2018
We did the vacuum test from a-6 to a-10. A-8 failed the first time, then they wrapped the top riser rings again and then it passed. Everything is now passed up to A-10.Steve Robbins 04/24/2018 8:36 AM
PW-Misc
Corrective Action Required
04/25/2018
We did the vacuum test on A-10 -A-15. A-13 failed, they then re-wrapped the cone on top and it then passed. A-12 failed, the contractors re-wrapped and it failed again. They then grouted around the barrell on the inside. They can re-test after 24 hrs. All the MH's have passed except A-12.Steve Robbins 04/25/2018 1:35 PM
Sanitary Sewer - Mandrel Passed 4/24/2018 at 12:00 PM 04/25/2018
PW-Misc
Informational
04/24/2018
The mandrel test was completed from the existing MH to A-o-10 ft. A-0 to A-1 which is 85 ft. These tests all passed. A-1 to A-2 is all ductile so there is no mandrel test.Steve Robbins 03/30/2018 9:08 AM
PW-Misc
Informational
04/24/2018
The mandrel has passed up to A-6.Steve Robbins 04/20/2018 4:00 PM
PW-Misc
Informational
04/24/2018
The mandrel has passed from A-6 to A-10.Steve Robbins 04/24/2018 9:41 AM
PW-Misc
Informational
04/25/2018
The mandrel has been tested from A-10 - A-15 and it all passed. This completes the mandrel testing from the existing MH to MH A-15.Steve Robbins 04/25/2018 1:42 PM
Sanitary Sewer Construction Inspection Partial 4/30/2018 04/30/2018
PW-Main inspection
Informational
04/18/2018
The contractors were planning on doing testing today but they called and cancelled for today.I spoke with the camera crew yesterday while they were at the site, they said they were not able to put the camera in the MH A-0 because the water was too high for the camera. They were taking the results back to their bosses for review. I am waiting to hear what the results of the camera test was.Steve Robbins 04/18/2018 2:22 PM
PW-Sanitary Sewer Testing
Informational
04/30/2018
Sanitary Sewer Testing needs to be completed. The camera test for the first 3 MH has passed. The testing has been completed on all the MH up to A-15. One MH vacuum test failed, when that one passes I will call for a camera test for the remaining MH's.Steve Robbins 04/30/2018 2:19 PM
Sanitary Sewer - Vacuum Failed 5/2/2018 at 10:30 AM 05/02/2018
PW-Misc
Informational
04/25/2018
We did the vacuum testing for MH A-0, A-1 and A-2. The test was for 2.5 minutes and they all passed. They are planning on doing the rest of the MH on April 22, when it is 30 days for everything.Steve Robbins 03/30/2018 8:33 AM
PW-Misc
Informational
04/25/2018
Today we did the vacuum test on MH A-3 to MH A-6. I did all the tests for 2.5 mins. Everything is passed up to A-6.Steve Robbins 04/20/2018 3:57 PM
PW-Misc
Informational
04/25/2018
We did the vacuum test from a-6 to a-10. A-8 failed the first time, then they wrapped the top riser rings again and then it passed. Everything is now passed up to A-10.Steve Robbins 04/24/2018 8:36 AM
PW-Misc
Corrective Action Required
04/25/2018
We did the vacuum test on A-10 -A-15. A-13 failed, they then re-wrapped the cone on top and it then passed. A-12 failed, the contractors re-wrapped and it failed again. They then grouted around the barrell on the inside. They can re-test after 24 hrs. All the MH's have passed except A-12.Steve Robbins 04/25/2018 1:35 PM
PW-Sanitary Sewer Testing
Corrective Action Required
05/02/2018
Sanitary Sewer Testing needs to be completed.The contractors still need to do the vacuum test on MH A-12.Steve Robbins 05/02/2018 10:44 AM
ESC - (Vegetation/Ground Cover) Partial 5/8/2018 at 9:15 AM 05/08/2018
PW-Misc
Informational
04/17/2018
The seeding company came in yesterday and today and installed the Coir Log and J-Hook. They did this on the enbankment of the stream. They installed all the seed and straw around MH A-0 to A-2 . Steve Robbins 04/17/2018 4:01 PM
PW-Misc
Informational
05/08/2018
The seed and straw for the side where the horse stable is on the east side of the creek is installed but not yet coming up.Steve Robbins 05/08/2018 2:07 PM
Sanitary Sewer - Vacuum Failed 5/10/2018 at 9:30 AM 05/10/2018
PW-Misc
Informational
05/02/2018
We did the vacuum testing for MH A-0, A-1 and A-2. The test was for 2.5 minutes and they all passed. They are planning on doing the rest of the MH on April 22, when it is 30 days for everything.Steve Robbins 03/30/2018 8:33 AM
PW-Misc
Informational
05/02/2018
Today we did the vacuum test on MH A-3 to MH A-6. I did all the tests for 2.5 mins. Everything is passed up to A-6.Steve Robbins 04/20/2018 3:57 PM
PW-Misc
Informational
05/02/2018
We did the vacuum test from a-6 to a-10. A-8 failed the first time, then they wrapped the top riser rings again and then it passed. Everything is now passed up to A-10.Steve Robbins 04/24/2018 8:36 AM
PW-Misc
Corrective Action Required
05/02/2018
We did the vacuum test on A-10 -A-15. A-13 failed, they then re-wrapped the cone on top and it then passed. A-12 failed, the contractors re-wrapped and it failed again. They then grouted around the barrell on the inside. They can re-test after 24 hrs. All the MH's have passed except A-12.Steve Robbins 04/25/2018 1:35 PM
PW-Sanitary Sewer Testing
Corrective Action Required
05/02/2018
Sanitary Sewer Testing needs to be completed.The contractors still need to do the vacuum test on MH A-12.Steve Robbins 05/02/2018 10:44 AM
PW-Sanitary Sewer Testing
Corrective Action Required
05/10/2018
Sanitary Sewer Testing needs to be completed. I spoke with Chad from Holthouse and he said they will be probably be coming out soon to finish this last vacuum test so we can get the camera test started.Steve Robbins 05/10/2018 3:41 PM
ESC - (Vegetation/Ground Cover) Partial 5/15/2018 at 2:30 PM 05/15/2018
PW-Misc
Informational
05/08/2018
The seeding company came in yesterday and today and installed the Coir Log and J-Hook. They did this on the enbankment of the stream. They installed all the seed and straw around MH A-0 to A-2 . Steve Robbins 04/17/2018 4:01 PM
PW-Misc
Informational
05/08/2018
The seed and straw for the side where the horse stable is on the east side of the creek is installed but not yet coming up.Steve Robbins 05/08/2018 2:07 PM
PW-Misc
Informational
05/15/2018
The contractors are grading from MH A-3 to A-15 and bringing top soil so they get get seed and straw down.Steve Robbins 05/15/2018 2:58 PM
Sanitary Sewer - Vacuum Passed 5/18/2018 at 11:45 AM 05/18/2018
PW-Misc
Informational
05/10/2018
We did the vacuum testing for MH A-0, A-1 and A-2. The test was for 2.5 minutes and they all passed. They are planning on doing the rest of the MH on April 22, when it is 30 days for everything.Steve Robbins 03/30/2018 8:33 AM
PW-Misc
Informational
05/10/2018
Today we did the vacuum test on MH A-3 to MH A-6. I did all the tests for 2.5 mins. Everything is passed up to A-6.Steve Robbins 04/20/2018 3:57 PM
PW-Misc
Informational
05/10/2018
We did the vacuum test from a-6 to a-10. A-8 failed the first time, then they wrapped the top riser rings again and then it passed. Everything is now passed up to A-10.Steve Robbins 04/24/2018 8:36 AM
PW-Misc
Corrective Action Required
05/10/2018
We did the vacuum test on A-10 -A-15. A-13 failed, they then re-wrapped the cone on top and it then passed. A-12 failed, the contractors re-wrapped and it failed again. They then grouted around the barrell on the inside. They can re-test after 24 hrs. All the MH's have passed except A-12.Steve Robbins 04/25/2018 1:35 PM
PW-Sanitary Sewer Testing
Corrective Action Required
05/10/2018
Sanitary Sewer Testing needs to be completed.The contractors still need to do the vacuum test on MH A-12.Steve Robbins 05/02/2018 10:44 AM
PW-Sanitary Sewer Testing
Corrective Action Required
05/10/2018
Sanitary Sewer Testing needs to be completed. I spoke with Chad from Holthouse and he said they will be probably be coming out soon to finish this last vacuum test so we can get the camera test started.Steve Robbins 05/10/2018 3:41 PM
Resolved
05/18/2018
MH A-12 has passed the vacuum test. After they flush the entire line I can call the water dept. for a camera inspection.Steve Robbins 05/18/2018 2:11 PM
Sanitary Sewer Construction Inspection Partial 5/31/2018 at 2:45 PM 05/31/2018
PW-Main inspection
Informational
05/31/2018
I spoke with Chad today about getting the sanitary line flushed so we can get the camera crew out. It looks like it will be difficult for the camera crew to get their van on site to do the video. I spoke with Brent and he is going to try and come out on site and give us some suggestions as to how we can get this taken care of.Steve Robbins 05/31/2018 2:54 PM
Sanitary Sewer Construction Inspection Partial 6/1/2018 at 12:00 PM 06/01/2018
PW-Main inspection
Informational
05/31/2018
I spoke with Chad today about getting the sanitary line flushed so we can get the camera crew out. It looks like it will be difficult for the camera crew to get their van on site to do the video. I spoke with Brent and he is going to try and come out on site and give us some suggestions as to how we can get this taken care of.Steve Robbins 05/31/2018 2:54 PM
PW-Main inspection
Informational
06/01/2018
I met with Brent today and after walking the site i am going to let the contractor know we need to get some dirt in to cross the creek, there is no water running through it. We need to get the van for the camera crew across the creek.Steve Robbins 06/01/2018 3:51 PM
Sanitary Sewer Construction Inspection Partial 6/5/2018 at 8:30 AM 06/05/2018
PW-Main inspection
Informational
06/01/2018
I spoke with Chad today about getting the sanitary line flushed so we can get the camera crew out. It looks like it will be difficult for the camera crew to get their van on site to do the video. I spoke with Brent and he is going to try and come out on site and give us some suggestions as to how we can get this taken care of.Steve Robbins 05/31/2018 2:54 PM
PW-Main inspection
Informational
06/01/2018
I met with Brent today and after walking the site i am going to let the contractor know we need to get some dirt in to cross the creek, there is no water running through it. We need to get the van for the camera crew across the creek.Steve Robbins 06/01/2018 3:51 PM
PW-Sanitary Sewer Testing
Informational
06/05/2018
Holthouse came out yesterday and filled in the creek crossing with dirt so the camera van will be able to get across and complete the camera testing. I spoke with Brent and he is having them come out this afternoon to start the camera testing. If they dont finish this afternoon they will in the morning.Steve Robbins 06/05/2018 10:52 AM
ESC - (Vegetation/Ground Cover) Partial 6/7/2018 at 7:15 AM 06/07/2018
PW-Misc
Informational
05/15/2018
The seeding company came in yesterday and today and installed the Coir Log and J-Hook. They did this on the enbankment of the stream. They installed all the seed and straw around MH A-0 to A-2 . Steve Robbins 04/17/2018 4:01 PM
PW-Misc
Informational
05/15/2018
The seed and straw for the side where the horse stable is on the east side of the creek is installed but not yet coming up.Steve Robbins 05/08/2018 2:07 PM
PW-Misc
Informational
05/15/2018
The contractors are grading from MH A-3 to A-15 and bringing top soil so they get get seed and straw down.Steve Robbins 05/15/2018 2:58 PM
PW-Misc
Informational
06/07/2018
The seeding company was here yesterday installing seed and straw. I am going to check today to make sure they finished.Steve Robbins 06/07/2018 7:23 AM
Sanitary Sewer Construction Inspection Partial 6/7/2018 at 11:30 AM 06/07/2018
PW-Main inspection
Informational
06/05/2018
I spoke with Chad today about getting the sanitary line flushed so we can get the camera crew out. It looks like it will be difficult for the camera crew to get their van on site to do the video. I spoke with Brent and he is going to try and come out on site and give us some suggestions as to how we can get this taken care of.Steve Robbins 05/31/2018 2:54 PM
PW-Main inspection
Informational
06/05/2018
I met with Brent today and after walking the site i am going to let the contractor know we need to get some dirt in to cross the creek, there is no water running through it. We need to get the van for the camera crew across the creek.Steve Robbins 06/01/2018 3:51 PM
PW-Sanitary Sewer Testing
Informational
06/05/2018
Holthouse came out yesterday and filled in the creek crossing with dirt so the camera van will be able to get across and complete the camera testing. I spoke with Brent and he is having them come out this afternoon to start the camera testing. If they dont finish this afternoon they will in the morning.Steve Robbins 06/05/2018 10:52 AM
PW-Sanitary Sewer Testing
Informational
06/07/2018
The camera test has been comleted. I spoke with Brent Dye and he said he would finish looking at it tomorrow and then send it on to Josh and hopefully get some results at the beginning of next week.Steve Robbins 06/07/2018 3:47 PM
Sanitary Sewer Construction Inspection Partial 6/14/2018 at 7:15 AM 06/14/2018
PW-Main inspection
Informational
06/07/2018
I spoke with Chad today about getting the sanitary line flushed so we can get the camera crew out. It looks like it will be difficult for the camera crew to get their van on site to do the video. I spoke with Brent and he is going to try and come out on site and give us some suggestions as to how we can get this taken care of.Steve Robbins 05/31/2018 2:54 PM
PW-Main inspection
Informational
06/07/2018
I met with Brent today and after walking the site i am going to let the contractor know we need to get some dirt in to cross the creek, there is no water running through it. We need to get the van for the camera crew across the creek.Steve Robbins 06/01/2018 3:51 PM
PW-Sanitary Sewer Testing
Informational
06/07/2018
Holthouse came out yesterday and filled in the creek crossing with dirt so the camera van will be able to get across and complete the camera testing. I spoke with Brent and he is having them come out this afternoon to start the camera testing. If they dont finish this afternoon they will in the morning.Steve Robbins 06/05/2018 10:52 AM
PW-Sanitary Sewer Testing
Informational
06/07/2018
The camera test has been comleted. I spoke with Brent Dye and he said he would finish looking at it tomorrow and then send it on to Josh and hopefully get some results at the beginning of next week.Steve Robbins 06/07/2018 3:47 PM
PW-Sanitary Sewer Testing
Corrective Action Required
06/14/2018
I have the results from the camera test from Josh Roach, MH 27-269 and 27-271 have inverts that are too high going upstream. There is also debris throughout the entire and needs to be flushed again.Steve Robbins 06/14/2018 11:30 AM
ESC - (Vegetation/Ground Cover) Partial 6/15/2018 at 2:00 PM 06/15/2018
PW-Misc
Informational
06/07/2018
The seeding company came in yesterday and today and installed the Coir Log and J-Hook. They did this on the enbankment of the stream. They installed all the seed and straw around MH A-0 to A-2 . Steve Robbins 04/17/2018 4:01 PM
PW-Misc
Informational
06/07/2018
The seed and straw for the side where the horse stable is on the east side of the creek is installed but not yet coming up.Steve Robbins 05/08/2018 2:07 PM
PW-Misc
Informational
06/07/2018
The contractors are grading from MH A-3 to A-15 and bringing top soil so they get get seed and straw down.Steve Robbins 05/15/2018 2:58 PM
PW-Misc
Informational
06/07/2018
The seeding company was here yesterday installing seed and straw. I am going to check today to make sure they finished.Steve Robbins 06/07/2018 7:23 AM
PW-Misc
Informational
06/15/2018
They have installed seed and straw throughout the site.Steve Robbins 06/15/2018 3:55 PM
Sanitary Sewer Construction Inspection Partial 7/5/2018 at 2:40 PM 07/05/2018
PW-Main inspection
Informational
06/14/2018
I spoke with Chad today about getting the sanitary line flushed so we can get the camera crew out. It looks like it will be difficult for the camera crew to get their van on site to do the video. I spoke with Brent and he is going to try and come out on site and give us some suggestions as to how we can get this taken care of.Steve Robbins 05/31/2018 2:54 PM
PW-Main inspection
Informational
06/14/2018
I met with Brent today and after walking the site i am going to let the contractor know we need to get some dirt in to cross the creek, there is no water running through it. We need to get the van for the camera crew across the creek.Steve Robbins 06/01/2018 3:51 PM
PW-Sanitary Sewer Testing
Informational
06/14/2018
Holthouse came out yesterday and filled in the creek crossing with dirt so the camera van will be able to get across and complete the camera testing. I spoke with Brent and he is having them come out this afternoon to start the camera testing. If they dont finish this afternoon they will in the morning.Steve Robbins 06/05/2018 10:52 AM
PW-Sanitary Sewer Testing
Informational
06/14/2018
The camera test has been comleted. I spoke with Brent Dye and he said he would finish looking at it tomorrow and then send it on to Josh and hopefully get some results at the beginning of next week.Steve Robbins 06/07/2018 3:47 PM
PW-Sanitary Sewer Testing
Corrective Action Required
06/14/2018
I have the results from the camera test from Josh Roach, MH 27-269 and 27-271 have inverts that are too high going upstream. There is also debris throughout the entire line and needs to be flushed again.Steve Robbins 06/14/2018 11:30 AM
PW-Main inspection
Informational
07/05/2018
Holthouse has came in and fixed the inverts in the 2 MHs that were in questiion. I have not yet been able to see the corections yet, they still have to do a flush but are having trouble getting back there because of the other contractors working.Steve Robbins 07/05/2018 3:47 PM
Sanitary Sewer Construction Inspection Passed 7/24/2018 at 2:15 PM 07/24/2018
PW-Main inspection
Informational
07/05/2018
I spoke with Chad today about getting the sanitary line flushed so we can get the camera crew out. It looks like it will be difficult for the camera crew to get their van on site to do the video. I spoke with Brent and he is going to try and come out on site and give us some suggestions as to how we can get this taken care of.Steve Robbins 05/31/2018 2:54 PM
PW-Main inspection
Informational
07/05/2018
I met with Brent today and after walking the site i am going to let the contractor know we need to get some dirt in to cross the creek, there is no water running through it. We need to get the van for the camera crew across the creek.Steve Robbins 06/01/2018 3:51 PM
PW-Sanitary Sewer Testing
Informational
07/05/2018
Holthouse came out yesterday and filled in the creek crossing with dirt so the camera van will be able to get across and complete the camera testing. I spoke with Brent and he is having them come out this afternoon to start the camera testing. If they dont finish this afternoon they will in the morning.Steve Robbins 06/05/2018 10:52 AM
PW-Sanitary Sewer Testing
Informational
07/05/2018
The camera test has been comleted. I spoke with Brent Dye and he said he would finish looking at it tomorrow and then send it on to Josh and hopefully get some results at the beginning of next week.Steve Robbins 06/07/2018 3:47 PM
PW-Sanitary Sewer Testing
Corrective Action Required
07/05/2018
I have the results from the camera test from Josh Roach, MH 27-269 and 27-271 have inverts that are too high going upstream. There is also debris throughout the entire line and needs to be flushed again.Steve Robbins 06/14/2018 11:30 AM
PW-Main inspection
Informational
07/05/2018
Holthouse has came in and fixed the inverts in the 2 MHs that were in questiion. I have not yet been able to see the corections yet, they still have to do a flush but are having trouble getting back there because of the other contractors working.Steve Robbins 07/05/2018 3:47 PM
PW-Main inspection
Informational
07/24/2018
Holthouse has done the flush of the sanitary lines and have corrected the 2 inverts that were high. I spoke with jeremy at the water dept. and they are considering this project to be completed from their end.Steve Robbins 07/24/2018 2:28 PM
Sanitary Sewer Construction Inspection Passed 7/24/2018 07/24/2018
PW-Sanitary Sewer Testing
Informational
04/20/2018
Matt Munger 04/20/2018 2:30 PM I observed the sanitary sewer testing with Steve Robbins.
Sanitary Sewer Construction Inspection Passed 7/24/2018 07/24/2018
PW-Sanitary Sewer Testing
Informational
04/20/2018
Matt Munger 04/20/2018 10:50 AM Observed the sanitary testing with Steve Robbins.
Site Visit Complete 07/24/2018
PW-Misc
Informational
01/22/2018
Jeremy Young 01/22/2018 9:15 AM No work being done today because of weather.
Grading/Excavation/Fill Inspection Passed 07/24/2018
ESC - (Vegetation/Ground Cover) Partial 8/31/2018 at 8:00 AM 08/31/2018
PW-Misc
Informational
06/15/2018
The seeding company came in yesterday and today and installed the Coir Log and J-Hook. They did this on the enbankment of the stream. They installed all the seed and straw around MH A-0 to A-2 . Steve Robbins 04/17/2018 4:01 PM
PW-Misc
Informational
06/15/2018
The seed and straw for the side where the horse stable is on the east side of the creek is installed but not yet coming up.Steve Robbins 05/08/2018 2:07 PM
PW-Misc
Informational
06/15/2018
The contractors are grading from MH A-3 to A-15 and bringing top soil so they get get seed and straw down.Steve Robbins 05/15/2018 2:58 PM
PW-Misc
Informational
06/15/2018
The seeding company was here yesterday installing seed and straw. I am going to check today to make sure they finished.Steve Robbins 06/07/2018 7:23 AM
PW-Misc
Informational
06/15/2018
They have installed seed and straw throughout the site.Steve Robbins 06/15/2018 3:55 PM
Informational
08/31/2018
I walked the site with the contractor and it is pretty much establed with vegetation. I can give a final acceptance.Steve Robbins 08/31/2018 3:51 PM
ESC - (Vegetation/Ground Cover) Passed 5/29/2019 10/28/2019
PW-Misc
Informational
08/31/2018
The seeding company came in yesterday and today and installed the Coir Log and J-Hook. They did this on the enbankment of the stream. They installed all the seed and straw around MH A-0 to A-2 . Steve Robbins 04/17/2018 4:01 PM
PW-Misc
Informational
08/31/2018
The seed and straw for the side where the horse stable is on the east side of the creek is installed but not yet coming up.Steve Robbins 05/08/2018 2:07 PM
PW-Misc
Informational
08/31/2018
The contractors are grading from MH A-3 to A-15 and bringing top soil so they get get seed and straw down.Steve Robbins 05/15/2018 2:58 PM
PW-Misc
Informational
08/31/2018
The seeding company was here yesterday installing seed and straw. I am going to check today to make sure they finished.Steve Robbins 06/07/2018 7:23 AM
PW-Misc
Informational
08/31/2018
They have installed seed and straw throughout the site.Steve Robbins 06/15/2018 3:55 PM|I walked the site with the contractor and it is pretty much establed with vegetation. There are just a few spots that are a little weak but for the most part it is all good.Steve Robbins 08/31/2018 3:49 PM
Documents & Images
Date Uploaded File Type Document Name
11/03/2017 Receipt Receipt for transaction: 2017-007108
11/06/2017 Letter DE-Permit
11/07/2017 Letter DE-Permit (signed)
01/22/2018 Letter DE-Site Visit Inspection
01/25/2018 Letter DE-Daily Inspection Summary
02/01/2018 Letter DE-Daily Inspection Summary
02/07/2018 Letter DE-Daily Inspection Summary
02/09/2018 Letter DE-Daily Inspection Summary
02/12/2018 Letter DE-Daily Inspection Summary
02/12/2018 Letter DE-Daily Inspection Summary
02/12/2018 Letter DE-Daily Inspection Summary
02/13/2018 Letter DE-Daily Inspection Summary
02/13/2018 Letter DE-Daily Inspection Summary
02/14/2018 Letter DE-Daily Inspection Summary
02/14/2018 Letter DE-Daily Inspection Summary
02/15/2018 Letter DE-Daily Inspection Summary
02/15/2018 Letter DE-Daily Inspection Summary
02/16/2018 Letter DE-Daily Inspection Summary
02/16/2018 Letter DE-Daily Inspection Summary
02/20/2018 Letter DE-Daily Inspection Summary
02/21/2018 Letter DE-Daily Inspection Summary
02/22/2018 Letter DE-Daily Inspection Summary
02/23/2018 Letter DE-Daily Inspection Summary
02/26/2018 Letter DE-Daily Inspection Summary
02/26/2018 Letter DE-Daily Inspection Summary
02/26/2018 Letter DE-Daily Inspection Summary
02/27/2018 Letter DE-Daily Inspection Summary
03/01/2018 Letter DE-Daily Inspection Summary
03/02/2018 Letter DE-Daily Inspection Summary
03/06/2018 Letter DE-Daily Inspection Summary
03/07/2018 Letter DE-Daily Inspection Summary
03/09/2018 Letter DE-Daily Inspection Summary
03/12/2018 Letter DE-Daily Inspection Summary
03/13/2018 Letter DE-Daily Inspection Summary
03/13/2018 Letter DE-Daily Inspection Summary
03/14/2018 Letter DE-Daily Inspection Summary
03/14/2018 Letter DE-Daily Inspection Summary
03/16/2018 Letter DE-Daily Inspection Summary
03/16/2018 Letter DE-Daily Inspection Summary
03/16/2018 IMG_1836
03/16/2018 IMG_1827
03/21/2018 Letter DE-Daily Inspection Summary
03/22/2018 Letter DE-Daily Inspection Summary
03/23/2018 Letter DE-Daily Inspection Summary
03/30/2018 Letter DE-Daily Inspection Summary
03/30/2018 Letter DE-Daily Inspection Summary
03/30/2018 Letter DE-Daily Inspection Summary
03/30/2018 Letter DE-Daily Inspection Summary
04/06/2018 Letter DE-Daily Inspection Summary
04/17/2018 Letter DE-Daily Inspection Summary
04/17/2018 Letter DE-Daily Inspection Summary
04/18/2018 Letter DE-Daily Inspection Summary
04/20/2018 Letter DE-Daily Inspection Summary
04/20/2018 Letter DE-Daily Inspection Summary
04/20/2018 Letter DE-Daily Inspection Summary
04/20/2018 Letter DE-Daily Inspection Summary
04/20/2018 Letter DE-Daily Inspection Summary
04/24/2018 Letter DE-Daily Inspection Summary
04/24/2018 Letter DE-Daily Inspection Summary
04/24/2018 Letter DE-Daily Inspection Summary
04/25/2018 Letter DE-Daily Inspection Summary
04/25/2018 Letter DE-Daily Inspection Summary
04/25/2018 Letter DE-Daily Inspection Summary
04/30/2018 Letter DE-Daily Inspection Summary
05/02/2018 Letter DE-Daily Inspection Summary
05/08/2018 Letter DE-Daily Inspection Summary
05/10/2018 Letter DE-Daily Inspection Summary
05/15/2018 Letter DE-Daily Inspection Summary
05/18/2018 Letter DE-Daily Inspection Summary
05/31/2018 Letter DE-Daily Inspection Summary
06/01/2018 Letter DE-Daily Inspection Summary
06/05/2018 Letter DE-Daily Inspection Summary
06/07/2018 Letter DE-Daily Inspection Summary
06/07/2018 Letter DE-Daily Inspection Summary
06/14/2018 Letter DE-Daily Inspection Summary
06/15/2018 Letter DE-Daily Inspection Summary
07/05/2018 Letter DE-Daily Inspection Summary
07/24/2018 Letter DE-Daily Inspection Summary
07/24/2018 Letter DE-Certificate of Substantial Completion Multiple Lot
07/24/2018 Letter DE-Punch List
07/31/2018 Village at View High Off-Site Sanitary
08/31/2018 Letter DE-Daily Inspection Summary
10/28/2019 View High-Off-site Sanitary -Affidavit
10/28/2019 Village at View High Off-Site Sanitary Final Acceptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home