Permit Application Status

PRPWFC20172853


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRPWFC20172853
Public Works Infrastructure Permit - Commercial
Final Acceptance
DEVELOPMENT COMPLETE
Full site development - Summit Eye Care
08/24/2017
05/08/2018
Locations
Contacts
SRKO LLC, Address:24 NW CHIPMAN RD, Phone:(816) 365-0100  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/24/2017 08/28/2017
Steve Robbins
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $225.66 $225.66 Paid 08/24/2017
91100C9-Water Insp Fee $90.00 $90.00 Paid 08/24/2017
9110072-Water Test Fee $200.00 $200.00 Paid 08/24/2017
9110068-Storm Fee $1,917.02 $1,917.02 Paid 08/24/2017
9110081-Paved Surface Inspection Fee $2,864.59 $2,864.59 Paid 08/24/2017
9110071-Site Grading Fee $6,667.63 $6,667.63 Paid 08/24/2017
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Miscellaneous PWORKS Inspection Partial 9/6/2017 at 8:00 AM 09/06/2017
PW-Misc
Informational
09/06/2017
I spoke with the contractor and they said they still have a couple weeks of moving dirt and grading before they get started on the sanitary.
Erosion Control Inspection Passed 8/28/2017 09/06/2017
Miscellaneous PWORKS Inspection Partial 9/11/2017 at 12:45 PM 09/11/2017
PW-Misc
Informational
09/06/2017
I spoke with the contractor and they said they still have a couple weeks of moving dirt and grading before they get started on the sanitary.
PW-Misc
Informational
09/11/2017
They are still moving dirt and grading.
Miscellaneous PWORKS Inspection Partial 9/20/2017 at 10:30 AM 09/20/2017
PW-Misc
Informational
09/11/2017
I spoke with the contractor and they said they still have a couple weeks of moving dirt and grading before they get started on the sanitary.
PW-Misc
Informational
09/11/2017
They are still moving dirt and grading.
PW-Misc
Informational
09/20/2017
This site is getting close to installing some pipe, but they do not have any on site yet.
Sanitary Sewer Construction Inspection Partial 9/25/2017 at 11:00 AM 09/25/2017
PW-Main inspection
Informational
09/25/2017
Today Redford is starting to install the sanitary. They are digging up the existing MH to get ready for a core drill.Steve Robbins 09/25/2017 11:32 AM
Sanitary Sewer Construction Inspection Partial 9/25/2017 at 2:30 PM 09/25/2017
PW-Main inspection
Informational
09/25/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
Miscellaneous PWORKS Inspection Passed 9/22/2017 09/25/2017
PW-Misc
Informational
09/20/2017
I spoke with the contractor and they said they still have a couple weeks of moving dirt and grading before they get started on the sanitary.
PW-Misc
Informational
09/20/2017
They are still moving dirt and grading.
PW-Misc
Informational
09/20/2017
This site is getting close to installing some pipe, but they do not have any on site yet.
PW-Misc
Informational
09/25/2017
Sanitary Sewer Construction Inspection Partial 9/27/2017 at 9:15 AM 09/27/2017
PW-Main inspection
Informational
09/25/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
09/27/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
Sanitary Sewer Construction Inspection Partial 9/27/2017 at 1:00 PM 09/27/2017
PW-Main inspection
Informational
09/27/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
09/27/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
09/27/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
Sanitary Sewer Construction Inspection Partial 9/28/2017 at 10:15 AM 09/28/2017
PW-Main inspection
Informational
09/27/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
09/27/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
09/27/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
09/28/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
Sanitary Sewer Construction Inspection Partial 9/29/2017 at 10:30 AM 09/29/2017
PW-Main inspection
Informational
09/28/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
09/28/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
09/28/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
09/28/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
09/29/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
Sanitary Sewer Construction Inspection Partial 10/2/2017 at 9:00 AM 10/02/2017
PW-Main inspection
Informational
09/29/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
09/29/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
09/29/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
09/29/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
09/29/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
PW-Main inspection
Informational
10/02/2017
The tester has been here and has tested everything for compaction. They are still laying pipe from MH 1-3 to 1-4, lots of rock. They are about 20 ft. from MH 1-4.Steve Robbins 10/02/2017 9:14 AM
Sanitary Sewer Construction Inspection Partial 10/2/2017 at 1:00 PM 10/02/2017
PW-Main inspection
Informational
10/02/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
10/02/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
10/02/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
10/02/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
10/02/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
PW-Main inspection
Informational
10/02/2017
The tester has been here and has tested everything for compaction. They are still laying pipe from MH 1-3 to 1-4, lots of rock. They are about 20 ft. from MH 1-4.Steve Robbins 10/02/2017 9:14 AM
PW-Main inspection
Informational
10/02/2017
The contractor is installing MH 1-4, they have the pipe in up to the MH.Steve Robbins 10/02/2017 1:20 PM
Sanitary Sewer - Invert Partial 10/2/2017 at 2:45 PM 10/02/2017
PW-Misc
Informational
10/02/2017
The inverts for MH 1-2 and 1-3 have been poured. They still have 1-1 and 1-4 to go.Steve Robbins 10/02/2017 3:15 PM
Sanitary Sewer Construction Inspection Partial 10/3/2017 at 10:15 AM 10/03/2017
PW-Main inspection
Informational
10/02/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
10/02/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
10/02/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
10/02/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
10/02/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
PW-Main inspection
Informational
10/02/2017
The tester has been here and has tested everything for compaction. They are still laying pipe from MH 1-3 to 1-4, lots of rock. They are about 20 ft. from MH 1-4.Steve Robbins 10/02/2017 9:14 AM
PW-Main inspection
Informational
10/02/2017
The contractor is installing MH 1-4, they have the pipe in up to the MH.Steve Robbins 10/02/2017 1:20 PM
PW-Main inspection
Informational
10/03/2017
No one is on site working so far today.Steve Robbins 10/03/2017 10:31 AM
Sanitary Sewer - Invert Partial 10/3/2017 at 12:45 PM 10/03/2017
PW-Misc
Informational
10/02/2017
The inverts for MH 1-2 and 1-3 have been poured. They still have 1-1 and 1-4 to go.Steve Robbins 10/02/2017 3:15 PM
PW-Misc
Informational
10/03/2017
I checked back this afternoon and still nobody is working.Steve Robbins 10/03/2017 1:10 PM
Sanitary Sewer Construction Inspection Partial 10/4/2017 at 11:00 AM 10/04/2017
PW-Main inspection
Informational
10/03/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
10/03/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
10/03/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
10/03/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
10/03/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
PW-Main inspection
Informational
10/03/2017
The tester has been here and has tested everything for compaction. They are still laying pipe from MH 1-3 to 1-4, lots of rock. They are about 20 ft. from MH 1-4.Steve Robbins 10/02/2017 9:14 AM
PW-Main inspection
Informational
10/03/2017
The contractor is installing MH 1-4, they have the pipe in up to the MH.Steve Robbins 10/02/2017 1:20 PM
PW-Main inspection
Informational
10/03/2017
No one is on site working so far today.Steve Robbins 10/03/2017 10:31 AM
PW-Main inspection
Informational
10/04/2017
They are not working today due to the rain.Steve Robbins 10/04/2017 11:09 AM
Sanitary Sewer Construction Inspection Partial 10/6/2017 at 10:30 AM 10/06/2017
PW-Main inspection
Informational
10/04/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
10/04/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
10/04/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
10/04/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
10/04/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
PW-Main inspection
Informational
10/04/2017
The tester has been here and has tested everything for compaction. They are still laying pipe from MH 1-3 to 1-4, lots of rock. They are about 20 ft. from MH 1-4.Steve Robbins 10/02/2017 9:14 AM
PW-Main inspection
Informational
10/04/2017
The contractor is installing MH 1-4, they have the pipe in up to the MH.Steve Robbins 10/02/2017 1:20 PM
PW-Main inspection
Informational
10/04/2017
No one is on site working so far today.Steve Robbins 10/03/2017 10:31 AM
PW-Main inspection
Informational
10/04/2017
They are not working today due to the rain.Steve Robbins 10/04/2017 11:09 AM
PW-Main inspection
Informational
10/06/2017
No work has been going on due to the rain the last 3 days.Steve Robbins 10/06/2017 11:54 AM
Sanitary Sewer Construction Inspection Partial 10/9/2017 at 11:00 AM 10/10/2017
PW-Main inspection
Informational
10/06/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
10/06/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
10/06/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
10/06/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
10/06/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
PW-Main inspection
Informational
10/06/2017
The tester has been here and has tested everything for compaction. They are still laying pipe from MH 1-3 to 1-4, lots of rock. They are about 20 ft. from MH 1-4.Steve Robbins 10/02/2017 9:14 AM
PW-Main inspection
Informational
10/06/2017
The contractor is installing MH 1-4, they have the pipe in up to the MH.Steve Robbins 10/02/2017 1:20 PM
PW-Main inspection
Informational
10/06/2017
No one is on site working so far today.Steve Robbins 10/03/2017 10:31 AM
PW-Main inspection
Informational
10/06/2017
They are not working today due to the rain.Steve Robbins 10/04/2017 11:09 AM
PW-Main inspection
Informational
10/06/2017
No work has been going on due to the rain the last 3 days.Steve Robbins 10/06/2017 11:54 AM
PW-Main inspection
Informational
10/10/2017
The contractors installed storm box 2-1 and the 15"pipe. They were attempting to get to the next box.
Storm Sewer Construction Inspection Partial 10/10/2017 at 9:15 AM 10/10/2017
PW-Storm Sewer Inspection
Informational
10/10/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
Storm Sewer Construction Inspection Partial 10/11/2017 at 2:45 PM 10/11/2017
PW-Storm Sewer Inspection
Informational
10/10/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/11/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
Storm Sewer Construction Inspection Partial 10/12/2017 at 10:45 AM 10/12/2017
PW-Storm Sewer Inspection
Informational
10/11/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/11/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/12/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
Storm Sewer Construction Inspection Partial 10/12/2017 at 1:15 PM 10/12/2017
PW-Storm Sewer Inspection
Informational
10/12/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/12/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/12/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/12/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
Storm Sewer Construction Inspection Partial 10/13/2017 at 11:00 AM 10/13/2017
PW-Storm Sewer Inspection
Informational
10/12/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/12/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/12/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/12/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/13/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
Storm Sewer Construction Inspection Partial 10/16/2017 at 9:15 AM 10/16/2017
PW-Storm Sewer Inspection
Informational
10/13/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/13/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/13/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/13/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/13/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/16/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
Storm Sewer Construction Inspection Partial 10/16/2017 at 11:00 AM 10/16/2017
PW-Storm Sewer Inspection
Informational
10/16/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/16/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/16/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/16/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/16/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/16/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/16/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
Storm Sewer Construction Inspection Partial 10/17/2017 at 11:30 AM 10/17/2017
PW-Storm Sewer Inspection
Informational
10/16/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/16/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/16/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/16/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/16/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/16/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/16/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/17/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
Storm Sewer Construction Inspection Partial 10/17/2017 at 2:00 PM 10/17/2017
PW-Storm Sewer Inspection
Informational
10/17/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/17/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/17/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/17/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/17/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/17/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/17/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/17/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/17/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
Storm Sewer Construction Inspection Partial 10/18/2017 at 8:15 AM 10/19/2017
PW-Storm Sewer Inspection
Informational
10/17/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/17/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/17/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/17/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/17/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/17/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/17/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/17/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/17/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/19/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
Storm Sewer Construction Inspection Partial 10/19/2017 at 8:15 AM 10/19/2017
PW-Storm Sewer Inspection
Informational
10/19/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/19/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/19/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/19/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/19/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/19/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
Storm Sewer Construction Inspection Partial 10/19/2017 at 1:15 PM 10/19/2017
PW-Storm Sewer Inspection
Informational
10/19/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/19/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/19/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/19/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/19/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/19/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
Storm Sewer Construction Inspection Partial 10/20/2017 at 8:00 AM 10/23/2017
PW-Storm Sewer Inspection
Informational
10/19/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/19/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/19/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/19/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/19/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/19/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
10/19/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
10/23/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
Storm Sewer Construction Inspection Partial 10/23/2017 at 9:15 AM 10/23/2017
PW-Storm Sewer Inspection
Informational
10/23/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/23/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/23/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/23/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/23/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/23/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
10/23/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
10/23/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
Sanitary Sewer - Wye / Insert-A-Tee Installation Passed 10/24/2017 at 10:45 AM 10/24/2017
PW-Misc
Informational
10/24/2017
The service line for the building has been tied into the main with a wye connection using the fernco stainless steel strongback. The tracer wire has been installed along with the trench check. The service line goes under the road and they have had a compaction test done.They are running the tracer wire to the building , they also have the tracer box. They are working on the service line to the buildingSteve Robbins 10/24/2017 12:04 PM.
Sanitary Sewer Construction Inspection Passed 10/25/2017 at 2:00 PM 10/25/2017
PW-Main inspection
Informational
10/10/2017
The existing MH has been exposed and they took off the 2 barrells. This afternoon the core drill will take place. They took the barrells off and are trying to get the MH to grade.
PW-Main inspection
Informational
10/10/2017
The existing MH 1-1 has been core drilled and the psx direct drive boot has been installed. The contractor is laying the pipe toward MH 1-2. There is a 20ft. encasement and they are constructing the encasement with rebar now and are planning on pouring concrete at 1:00 this afternoon.Steve Robbins 09/27/2017 9:36 AM
PW-Main inspection
Informational
10/10/2017
The base for MH 1-2 has been installed and the 20ft. encasement has been built with rebar and concrete has been installed around it.Steve Robbins 09/27/2017 3:38 PM
PW-Main inspection
Informational
10/10/2017
MH 1-2 has been installed and wrapped. The pipe has been installed with rock and they are heading towards 1-3. They are coming this afternoon to do testing for the road crossing on 1-1 to 1-2.Steve Robbins 09/28/2017 10:41 AM
PW-Main inspection
Corrective Action Required
10/10/2017
The contractor has hit a lot of rock they are still going between MH 1-3 to 1-4. On 1-3 the base has been installed. The inverts have not been poured yet. The tester was out yesterday for the street crossing from MH 1-1 to 1-2l.Steve Robbins 09/29/2017 11:01 AM
PW-Main inspection
Informational
10/10/2017
The tester has been here and has tested everything for compaction. They are still laying pipe from MH 1-3 to 1-4, lots of rock. They are about 20 ft. from MH 1-4.Steve Robbins 10/02/2017 9:14 AM
PW-Main inspection
Informational
10/10/2017
The contractor is installing MH 1-4, they have the pipe in up to the MH.Steve Robbins 10/02/2017 1:20 PM
PW-Main inspection
Informational
10/10/2017
No one is on site working so far today.Steve Robbins 10/03/2017 10:31 AM
PW-Main inspection
Informational
10/10/2017
They are not working today due to the rain.Steve Robbins 10/04/2017 11:09 AM
PW-Main inspection
Informational
10/10/2017
No work has been going on due to the rain the last 3 days.Steve Robbins 10/06/2017 11:54 AM
PW-Main inspection
Informational
10/10/2017
The contractors installed storm box 2-1 and the 15"pipe. They were attempting to get to the next box.
PW-Main inspection
Informational
10/25/2017
The contractors have finished the tie in for the service line. They had 2 clean-outs that have been installed to the building. The connection to the building has been completed.The tracer wire went all the way to the building.Steve Robbins 10/25/2017 2:33 PM
Storm Sewer Construction Inspection Partial 10/26/2017 at 9:30 AM 10/26/2017
PW-Storm Sewer Inspection
Informational
10/23/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/23/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/23/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/23/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/23/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/23/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
10/23/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
10/23/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
10/23/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
Structures 8-1 and 8-2 have been installed, they are working on getting the pipe installed and collars so they can backfill.Steve Robbins 10/26/2017 10:21 AM
Sanitary Sewer - Invert Passed 10/26/2017 at 2:00 PM 10/26/2017
PW-Misc
Informational
10/03/2017
The inverts for MH 1-2 and 1-3 have been poured. They still have 1-1 and 1-4 to go.Steve Robbins 10/02/2017 3:15 PM
PW-Misc
Informational
10/03/2017
I checked back this afternoon and still nobody is working.Steve Robbins 10/03/2017 1:10 PM
PW-Misc
Informational
10/26/2017
All the inverts have been poured MH 1-1 to MH 1-4 have all been completed.Steve Robbins 10/26/2017 3:38 PM
Storm Sewer Construction Inspection Partial 10/26/2017 at 2:30 PM 10/26/2017
PW-Storm Sewer Inspection
Informational
10/26/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/26/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/26/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/26/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/26/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/26/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
10/26/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
10/26/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
Structures 8-1 and 8-2 have been installed, they are working on getting the pipe installed and collars so they can backfill.Steve Robbins 10/26/2017 10:21 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are backfilling and getting compaction tests on the part that crosses the road.Steve Robbins 10/26/2017 3:43 PM
Storm Sewer Construction Inspection Partial 10/27/2017 at 9:15 AM 10/27/2017
PW-Storm Sewer Inspection
Informational
10/26/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/26/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/26/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/26/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/26/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/26/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
10/26/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
10/26/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
Structures 8-1 and 8-2 have been installed, they are working on getting the pipe installed and collars so they can backfill.Steve Robbins 10/26/2017 10:21 AM
PW-Storm Sewer Inspection
Informational
10/26/2017
The contractors are backfilling and getting compaction tests on the part that crosses the road.Steve Robbins 10/26/2017 3:43 PM
PW-Storm Sewer Inspection
Informational
10/27/2017
Struture 8-1, 8-2 and 5-1 have been installed. That finishes the road crossing, They still have more storm to do but they are going to do water now.Steve Robbins 10/27/2017 9:45 AM
Water - Material Verification Passed 10/27/2017 at 10:00 AM 10/27/2017
Informational
10/27/2017
I checked the material and they have everything on site .Steve Robbins 10/27/2017 10:11 AM
Storm - Material Verification Passed 9/13/2017 10/27/2017
Sanitary - Material Verification Passed 9/4/2017 10/27/2017
Water Line - Construction Inspection Partial 10/27/2017 at 1:00 PM 10/27/2017
PW-Main inspection
Informational
10/27/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
Water Line - Construction Inspection Partial 10/30/2017 at 8:30 AM 10/30/2017
PW-Main inspection
Informational
10/27/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
Water Line - Construction Inspection Partial 10/30/2017 at 1:45 PM 10/30/2017
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
Sanitary Sewer Construction Inspection Passed 10/31/2017 at 7:00 AM 10/31/2017
PW-Main inspection
Informational
10/31/2017
All the sanitary sewer was installed and backfilled on 10/2/17 and will be ready for testing on 11/2/17Steve Robbins 10/31/2017 7:21 AM
Water Line - Construction Inspection Partial 10/31/2017 at 1:30 PM 10/31/2017
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/31/2017
They are planning on pouring the thrust blocks this afternoon, they also installed a valve and are working on the fire hydrant at the end of the road.Steve Robbins 10/31/2017 2:52 PM
Water Line - Fire Hydrant Partial 11/1/2017 at 8:30 AM 11/01/2017
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Misc
Informational
11/01/2017
The fire hydrant at station 11+42.77 has been installed with valve and backing block. The backing block for station 11+06.63 has been installed by the 90* bend. and the straddle block for the tee on station 14+65.82 has been installed, but the fire hydrand has not been installed yet.Steve Robbins 11/01/2017 9:17 AM
Storm Sewer Construction Inspection Partial 11/1/2017 at 10:30 AM 11/01/2017
PW-Storm Sewer Inspection
Informational
10/27/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
10/27/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
10/27/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
10/27/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
10/27/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
10/27/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
10/27/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
10/27/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
10/27/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
10/27/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
10/27/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
10/27/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
10/27/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
10/27/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
PW-Storm Sewer Inspection
Informational
10/27/2017
Structures 8-1 and 8-2 have been installed, they are working on getting the pipe installed and collars so they can backfill.Steve Robbins 10/26/2017 10:21 AM
PW-Storm Sewer Inspection
Informational
10/27/2017
The contractors are backfilling and getting compaction tests on the part that crosses the road.Steve Robbins 10/26/2017 3:43 PM
PW-Storm Sewer Inspection
Informational
10/27/2017
Struture 8-1, 8-2 and 5-1 have been installed. That finishes the road crossing, They still have more storm to do but they are going to do water now.Steve Robbins 10/27/2017 9:45 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
The storm structures 6-1 and 6-2 have been installed, the collars and inverts have been poured.They are now working on structure 7-1.Steve Robbins 11/01/2017 11:01 AM
Pavement-Stabilized Subgrade Partial 11/1/2017 at 11:15 AM 11/01/2017
PW-Misc
Informational
11/01/2017
The contractors have finished grading the subgrade, they are using flyash- portland cement, but they havent shown up yet.Steve Robbins 11/01/2017 12:08 PM
Pavement-Stabilized Subgrade Partial 11/1/2017 at 2:00 PM 11/01/2017
PW-Misc
Informational
11/01/2017
The contractors have finished grading the subgrade, they are using flyash- portland cement, but they havent shown up yet.Steve Robbins 11/01/2017 12:08 PM
PW-Misc
Corrective Action Required
11/01/2017
Supperior has installed the portland on the subgrade, in the morning they are going to till it in. They are spreading it out now .Steve Robbins 11/01/2017 2:41 PM
Water Line - Fire Hydrant Passed 11/2/2017 at 10:00 AM 11/02/2017
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Misc
Informational
11/01/2017
The fire hydrant at station 11+42.77 has been installed with valve and backing block. The backing block for station 11+06.63 has been installed by the 90* bend. and the straddle block for the tee on station 14+65.82 has been installed, but the fire hydrand has not been installed yet.Steve Robbins 11/01/2017 9:17 AM
PW-Misc
Corrective Action Required
11/02/2017
The fire hydrant for station 14+65.82 has been installed and wrapped. Both fire hydrants have been completed.Steve Robbins 11/02/2017 4:13 PM
Pavement-Stabilized Subgrade Partial 11/2/2017 at 7:30 AM 11/02/2017
PW-Misc
Informational
11/01/2017
The contractors have finished grading the subgrade, they are using flyash- portland cement, but they havent shown up yet.Steve Robbins 11/01/2017 12:08 PM
PW-Misc
Corrective Action Required
11/01/2017
Supperior has installed the portland on the subgrade, in the morning they are going to till it in. They are spreading it out now .Steve Robbins 11/01/2017 2:41 PM
PW-Misc
Informational
11/02/2017
This morning the contractors tilled in the portland mix and added water, they had testing done while they were doing it. This afternoon they were grading and rolling it in.Steve Robbins 11/02/2017 4:16 PM
Storm Sewer Construction Inspection Partial 11/2/2017 at 11:00 AM 11/02/2017
PW-Storm Sewer Inspection
Informational
11/01/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
11/01/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
11/01/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
11/01/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
11/01/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
11/01/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
11/01/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
11/01/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
11/01/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
11/01/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
Structures 8-1 and 8-2 have been installed, they are working on getting the pipe installed and collars so they can backfill.Steve Robbins 10/26/2017 10:21 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
The contractors are backfilling and getting compaction tests on the part that crosses the road.Steve Robbins 10/26/2017 3:43 PM
PW-Storm Sewer Inspection
Informational
11/01/2017
Struture 8-1, 8-2 and 5-1 have been installed. That finishes the road crossing, They still have more storm to do but they are going to do water now.Steve Robbins 10/27/2017 9:45 AM
PW-Storm Sewer Inspection
Informational
11/01/2017
The storm structures 6-1 and 6-2 have been installed, the collars and inverts have been poured.They are now working on structure 7-1.Steve Robbins 11/01/2017 11:01 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
Today they tied into structure 11-1 and installed structure 11-2. They also did structure 7-1 in the detention basin and were working toward 7-2.Steve Robbins 11/02/2017 4:20 PM
Sanitary Sewer Construction Inspection Passed 11/2/2017 at 7:15 AM 11/03/2017
PW-Sanitary Sewer Testing
Informational
11/03/2017
Existing MH 1-1 to 1-2, 1-2 to 1-3, and 1-3 to 1-4 have all passed the air test of 7:34.Steve Robbins 11/03/2017 9:13 AM
Sanitary Sewer - Mandrel Passed 11/2/2017 at 8:15 AM 11/03/2017
PW-Misc
Informational
11/03/2017
The mandrel has passed from MH 1-1 to 1-2, a-2 to 1-3 and 1-3 to 1-4. That completes mandrel testing.Steve Robbins 11/03/2017 9:40 AM
Pavement-Stabilized Subgrade Partial 11/3/2017 at 10:00 AM 11/06/2017
PW-Misc
Informational
11/02/2017
The contractors have finished grading the subgrade, they are using flyash- portland cement, but they havent shown up yet.Steve Robbins 11/01/2017 12:08 PM
PW-Misc
Corrective Action Required
11/02/2017
Supperior has installed the portland on the subgrade, in the morning they are going to till it in. They are spreading it out now .Steve Robbins 11/01/2017 2:41 PM
PW-Misc
Informational
11/02/2017
This morning the contractors tilled in the portland mix and added water, they had testing done while they were doing it. This afternoon they were grading and rolling it in.Steve Robbins 11/02/2017 4:16 PM
Informational
11/06/2017
The public road on rosemary dr. has been graded and is ready for 6"of MO-dot -5. They also tilled in 7" of portland for the private drive leading up to the parking lot.Steve Robbins 11/06/2017 2:30 PM
Storm Sewer Construction Inspection Partial 11/6/2017 at 9:00 AM 11/07/2017
PW-Storm Sewer Inspection
Informational
11/02/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
11/02/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
11/02/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
11/02/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
11/02/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
11/02/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
11/02/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
11/02/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
11/02/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
11/02/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
Structures 8-1 and 8-2 have been installed, they are working on getting the pipe installed and collars so they can backfill.Steve Robbins 10/26/2017 10:21 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
The contractors are backfilling and getting compaction tests on the part that crosses the road.Steve Robbins 10/26/2017 3:43 PM
PW-Storm Sewer Inspection
Informational
11/02/2017
Struture 8-1, 8-2 and 5-1 have been installed. That finishes the road crossing, They still have more storm to do but they are going to do water now.Steve Robbins 10/27/2017 9:45 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
The storm structures 6-1 and 6-2 have been installed, the collars and inverts have been poured.They are now working on structure 7-1.Steve Robbins 11/01/2017 11:01 AM
PW-Storm Sewer Inspection
Informational
11/02/2017
Today they tied into structure 11-1 and installed structure 11-2. They also did structure 7-1 in the detention basin and were working toward 7-2.Steve Robbins 11/02/2017 4:20 PM
PW-Storm Sewer Inspection
Informational
11/07/2017
The contractors installed the storm pipe to the building for the roof drains. The also worked on structure 7-2 in the detention basin
Roof Drain Passed 11/7/2017 at 7:00 AM 11/07/2017
Informational
11/07/2017
All the roof drains and pipe has been installed for the building, they are backfilling this morning.Steve Robbins 11/07/2017 7:07 AM
Pavement-Stabilized Subgrade Partial 11/7/2017 at 9:00 AM 11/07/2017
PW-Misc
Informational
11/07/2017
Today they are installing the 6" of MO-Type 5 on Rosemary .Steve Robbins 11/07/2017 9:30 AM
Water Line - Construction Inspection Partial 11/8/2017 at 11:00 AM 11/08/2017
PW-Main inspection
Informational
10/31/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
10/31/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
10/31/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
10/31/2017
They are planning on pouring the thrust blocks this afternoon, they also installed a valve and are working on the fire hydrant at the end of the road.Steve Robbins 10/31/2017 2:52 PM
PW-Main inspection
Informational
11/08/2017
The contractors are digging up the fire hydrant and are going to connect to the existing 8"line connecting to the fire hydrant. We are going to bleach and swabb the connection when they are connecting. The fire hydrant will be re-used and will be moved moved about 10 feet from its current location. They still need to install a straddle block and a thrust block for the 90 degree pipe.Steve Robbins 11/08/2017 11:45 AM
Storm Sewer Construction Inspection Passed 11/8/2017 at 12:00 PM 11/08/2017
PW-Storm Sewer Inspection
Informational
11/07/2017
Storm box 2-1 and 1-2 have been installed with collars and inverts. They have also been backfilled because of the rain coming.Steve Robbins 10/10/2017 9:44 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
No work is being done today.Steve Robbins 10/11/2017 2:45 PM
PW-Storm Sewer Inspection
Informational
11/07/2017
The contractors are installing storm box 1-3. They are going accross the road to 3-1. They will need to get compaction tests for the road crossSteve Robbins 10/12/2017 11:31 AMing.
PW-Storm Sewer Inspection
Informational
11/07/2017
Structures 1-3 and 3-1 has been installed along with the 15" hdpe pipe. The contractors are planning on installing the collars and inverts this afternoon at 3:30. Steve Robbins 10/12/2017 1:47 PM
PW-Grout storm boxes
Informational
11/07/2017
This morning the inverts and collars were poured on the 3 storm boxes that have been installed.
PW-Storm Sewer Inspection
Corrective Action Required
11/07/2017
The contractors are not working yet.Steve Robbins 10/16/2017 9:25 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
The contractors are not going to work today, they do not have the right size pipe.Steve Robbins 10/16/2017 11:24 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
Storm box 1-4 and 4-1 has been installed, the pipe has been installed from 1-4 to 4-1 , they are going to have a compaction tests for the road crossings this afternoon. They are also going to install the collars this afternoon. They are still waiting on the 36" pipe to show up..
PW-Storm Sewer Inspection
Informational
11/07/2017
The compaction tester is here and they are beginning to test. They are still planning on pouring the collars this afternoon. The 36" pipe has not yet showed up.Steve Robbins 10/17/2017 2:38 PM
PW-Storm Sewer Inspection
Informational
11/07/2017
They are working on the 36" storm pipe from structure 1-4 to 1-5.
PW-Storm Sewer Inspection
Informational
11/07/2017
The contractors are still working on the 36" pipe heading toward structure existing structure 1-5 where they will tie into the structure.Steve Robbins 10/19/2017 8:58 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
The contractors are close to 1-5, there are several utility lines by the structure so it is taking a little time the get done.Steve Robbins 10/19/2017 1:43 PM
PW-Storm Sewer Inspection
Informational
11/07/2017
The storm pipe has been connected to the existing storm box 1-5, the collar has been installed and this line is complete.
PW-Storm Sewer Inspection
Informational
11/07/2017
No one is working today, it is very wet.Steve Robbins 10/23/2017 9:42 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
Structures 8-1 and 8-2 have been installed, they are working on getting the pipe installed and collars so they can backfill.Steve Robbins 10/26/2017 10:21 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
The contractors are backfilling and getting compaction tests on the part that crosses the road.Steve Robbins 10/26/2017 3:43 PM
PW-Storm Sewer Inspection
Informational
11/07/2017
Struture 8-1, 8-2 and 5-1 have been installed. That finishes the road crossing, They still have more storm to do but they are going to do water now.Steve Robbins 10/27/2017 9:45 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
The storm structures 6-1 and 6-2 have been installed, the collars and inverts have been poured.They are now working on structure 7-1.Steve Robbins 11/01/2017 11:01 AM
PW-Storm Sewer Inspection
Informational
11/07/2017
Today they tied into structure 11-1 and installed structure 11-2. They also did structure 7-1 in the detention basin and were working toward 7-2.Steve Robbins 11/02/2017 4:20 PM
PW-Storm Sewer Inspection
Informational
11/07/2017
The contractors installed the storm pipe to the building for the roof drains. The also worked on structure 7-2 in the detention basin
PW-Storm Sewer Inspection
Informational
11/08/2017
All the storm structures and storm pipe have been insalled . All the inverts and collars have been installed in all the storm boxes and has passed instection.Steve Robbins 11/08/2017 12:12 PM
Pavement-Stabilized Subgrade Partial 11/8/2017 at 12:30 PM 11/08/2017
PW-Misc
Informational
11/07/2017
Today they are installing the 6" of MO-Type 5 on Rosemary .Steve Robbins 11/07/2017 9:30 AM
PW-Misc
Informational
11/08/2017
The contractors are still installing the MO-type-5 , they have done the public road on Rosemary ct., the rock is not complete yet for the private road leading up to the building. All the portland has been installed by tilling the subgraded up and installing the portland.
Water Line - Construction Inspection Partial 11/9/2017 at 8:30 AM 11/09/2017
PW-Main inspection
Informational
11/08/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/08/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/08/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/08/2017
They are planning on pouring the thrust blocks this afternoon, they also installed a valve and are working on the fire hydrant at the end of the road.Steve Robbins 10/31/2017 2:52 PM
PW-Main inspection
Informational
11/08/2017
The contractors are digging up the fire hydrant and are going to connect to the existing 8"line connecting to the fire hydrant. We are going to bleach and swabb the connection when they are connecting. The fire hydrant will be re-used and will be moved moved about 10 feet from its current location. They still need to install a straddle block and a thrust block for the 90 degree pipe.Steve Robbins 11/08/2017 11:45 AM
PW-Main inspection
Informational
11/09/2017
The water line has been connected to the existing valve. The pipes are all connected. we are ready for the compression test.Steve Robbins 11/09/2017 12:05 PM
Water Line - Construction Inspection Partial 11/10/2017 at 9:00 AM 11/10/2017
PW-Main inspection
Informational
11/09/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/09/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/09/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/09/2017
They are planning on pouring the thrust blocks this afternoon, they also installed a valve and are working on the fire hydrant at the end of the road.Steve Robbins 10/31/2017 2:52 PM
PW-Main inspection
Informational
11/09/2017
The contractors are digging up the fire hydrant and are going to connect to the existing 8"line connecting to the fire hydrant. We are going to bleach and swabb the connection when they are connecting. The fire hydrant will be re-used and will be moved moved about 10 feet from its current location. They still need to install a straddle block and a thrust block for the 90 degree pipe.Steve Robbins 11/08/2017 11:45 AM
PW-Main inspection
Informational
11/09/2017
The water line has been connected to the existing valve. The pipes are all connected. we are ready for the compression test.Steve Robbins 11/09/2017 12:05 PM
PW-Main inspection
Informational
11/10/2017
The 8" public water main has been installed and completed. We still need to do the service line tap.Steve Robbins 11/10/2017 9:26 AM
Pavement-Stabilized Subgrade Partial 11/10/2017 at 8:45 AM 11/10/2017
PW-Misc
Informational
11/08/2017
Today they are installing the 6" of MO-Type 5 on Rosemary .Steve Robbins 11/07/2017 9:30 AM
PW-Misc
Informational
11/08/2017
The contractors are still installing the MO-type-5 , they have done the public road on Rosemary ct., the rock is not complete yet for the private road leading up to the building. All the portland has been installed by tilling the subgraded up and installing the portland.
PW-Misc
Informational
11/10/2017
The subgrade of portland has been installed on the private road, rosemary ct. has been completed. Today they are putting the MO-Dot type-5 down and grading and rolling it.Steve Robbins 11/10/2017 9:32 AM
Curb - Proof Roll Passed 11/9/2017 at 2:00 PM 11/10/2017
PW-Misc
Informational
11/10/2017
We did a proof roll in the morning and there was a few soft spots for the curb. We did another one in the afternoon aftrer it dried out some and it was good to go.They also dug out some areas on the main road that need to dry out before a street proofroll.Steve Robbins 11/10/2017 9:39 AM
Sanitary Sewer - Vacuum Passed 11/2/2017 at 8:45 AM 11/10/2017
PW-Sanitary Sewer Testing
Informational
11/10/2017
We also did a flush for the 8" line.Steve Robbins 11/10/2017 9:43 AM
Water Line - Thrust Restraint Passed 11/10/2017 at 8:30 AM 11/10/2017
PW-Misc
Informational
11/10/2017
All the hydrants and thrust blocks and straddle blocks have been installed and completed.Steve Robbins 11/10/2017 9:51 AM
Pavement-Stabilized Subgrade Passed 11/13/2017 at 8:45 AM 11/13/2017
PW-Misc
Informational
11/10/2017
Today they are installing the 6" of MO-Type 5 on Rosemary .Steve Robbins 11/07/2017 9:30 AM
PW-Misc
Informational
11/10/2017
The contractors are still installing the MO-type-5 , they have done the public road on Rosemary ct., the rock is not complete yet for the private road leading up to the building. All the portland has been installed by tilling the subgraded up and installing the portland.
PW-Misc
Informational
11/10/2017
The subgrade of portland has been installed on the private road, rosemary ct. has been completed. Today they are putting the MO-Dot type-5 down and grading and rolling it.Steve Robbins 11/10/2017 9:32 AM
Corrective Action Required
11/13/2017
The private road has the MO-dot -5 installed and is all graded out, ready for a Steve Robbins 11/13/2017 10:15 AMproofroll.
Pavement-Curb Construction Failed 11/13/2017 at 11:00 AM 11/13/2017
PW-Curb Construction
Informational
11/13/2017
They have started constructing the curbs with the curb machine on Rosemary. When they finish this they will start on the private street.Steve Robbins 11/13/2017 12:27 PM
Water Line - Hydrostatic Test Passed 11/13/2017 at 12:15 PM 11/13/2017
PW-Misc
Informational
11/13/2017
The hydrostatic pressure test passed for the water line.Steve Robbins 11/13/2017 3:46 PM
Pavement-Curb Construction Failed 11/14/2017 at 10:00 AM 11/14/2017
PW-Curb Construction
Informational
11/13/2017
They have started constructing the curbs with the curb machine on Rosemary. When they finish this they will start on the private street.Steve Robbins 11/13/2017 12:27 PM
PW-Curb Construction
Informational
11/14/2017
The contractors are now forming the curbs by the storm inlets and the storm throats. They will pour this afternoon if weather permits. They are finished with the curb machine for the public street rosemary.Steve Robbins 11/14/2017 11:20 AM
Pavement-Curb Construction Failed 11/14/2017 at 1:30 PM 11/14/2017
PW-Curb Construction
Informational
11/14/2017
They have started constructing the curbs with the curb machine on Rosemary. When they finish this they will start on the private street.Steve Robbins 11/13/2017 12:27 PM
PW-Curb Construction
Informational
11/14/2017
The contractors are now forming the curbs by the storm inlets and the storm throats. They will pour this afternoon if weather permits. They are finished with the curb machine for the public street rosemary.Steve Robbins 11/14/2017 11:20 AM
PW-Backfill curb
Informational
11/14/2017
They are backfilling the curbs that have been completed. We have some that have honeycombs so they will have to grout them. They are also finishing the curbs in the island on rosemary ct.Steve Robbins 11/14/2017 2:32 PM
Pavement-Curb Construction Passed 11/15/2017 at 7:45 AM 11/15/2017
PW-Curb Construction
Informational
11/14/2017
They have started constructing the curbs with the curb machine on Rosemary. When they finish this they will start on the private street.Steve Robbins 11/13/2017 12:27 PM
PW-Curb Construction
Informational
11/14/2017
The contractors are now forming the curbs by the storm inlets and the storm throats. They will pour this afternoon if weather permits. They are finished with the curb machine for the public street rosemary.Steve Robbins 11/14/2017 11:20 AM
PW-Backfill curb
Informational
11/14/2017
They are backfilling the curbs that have been completed. We have some that have honeycombs so they will have to grout them. They are also finishing the curbs in the island on rosemary ct.Steve Robbins 11/14/2017 2:32 PM
PW-Backfill curb
Corrective Action Required
11/15/2017
The contractors have grouted all the curbs that I pointed out for honeycombing. They will finish backfilling this afternoon.Steve Robbins 11/15/2017 9:49 AM
Detention Basin Partial 11/16/2017 at 9:45 AM 11/16/2017
Informational
11/16/2017
The contractors are constructing the detention basin , they are installing the 4" perforated pipe wrapped in silt and covered in clean rock. This basin also gets a special dirt and sand mix.Steve Robbins 11/16/2017 2:36 PM
Pavement-Proof Roll Passed 11/17/2017 at 9:00 AM 11/17/2017
PW-Misc
Informational
11/17/2017
The proofroll has passed and they are ready for asphalt. There may be a problem with the sanitary sewer line that goes under the road, They are planning on asphalt on Monday morning.Steve Robbins 11/17/2017 10:21 AM
Sanitary Sewer Construction Inspection Failed 11/20/2017 at 7:00 AM 11/20/2017
PW-Sanitary Sewer Testing
Corrective Action Required
11/20/2017
The water dept. did the camera test and found 3 sags which was pointed out in the email sent out. There was also concerns by Josh Roach that there were no wyes installed on this main. Ryan Elam pointed out that this was meant to be that way. Also , MH 22a-008 to existing MH 22a003 the grade is called out in the plans at .6 fall. I told the contractor when the surveyer comes out for the as-builds that it needs to be at least .6. The contractor said it was installed at .6. The contractors are planning on digging up the 3 sags and correcting them today.Steve Robbins 11/20/2017 11:50 AM
Sanitary Sewer Construction Inspection Partial 11/21/2017 at 10:00 AM 11/20/2017
PW-Sanitary Sewer Testing
Corrective Action Required
11/20/2017
The water dept. did the camera test and found 3 sags which was pointed out in the email sent out. There was also concerns by Josh Roach that there were no wyes installed on this main. Ryan Elam pointed out that this was meant to be that way. Also , MH 22a-008 to existing MH 22a003 the grade is called out in the plans at .6 fall. I told the contractor when the surveyer comes out for the as-builds that it needs to be at least .6. The contractor said it was installed at .6. The contractors are planning on digging up the 3 sags and correcting them today.Steve Robbins 11/20/2017 11:50 AM
PW-Sanitary Sewer Testing
Informational
11/20/2017
The contractors have corrected the 3 sags that have been identified by the water dept. The 30 day wait starts today for the camera test again.Steve Robbins 11/20/2017 4:36 PM
Pavement-Surface Passed 11/20/2017 at 3:00 PM 11/20/2017
PW-Misc
Informational
11/20/2017
The contractors have installed the base lift type 2 ashphalt and now are installing a wedge lift to get it ready for a 2 inch surface lift next week. They are doing public road at roaemary ct.and private.Steve Robbins 11/20/2017 4:42 PM
Water Line - Coliform Test 1 Partial 11/20/2017 at 1:00 PM 11/20/2017
PW-Misc
Informational
11/20/2017
The line has been chlorinated and flushed , we took the first sample to the lab this afternoon. John DiMarro will take the second one tomorrow.Steve Robbins 11/20/2017 4:49 PM
Water Line - Coliform Test 2 Partial 11/21/2017 at 12:30 PM 11/21/2017
PW-Misc
Informational
11/21/2017
John DiMauro 11/21/2017 4:20 PM I collected samples today at the fire hydrant for Rosemary Ct. and delivered them to Blue Valley Labs. The tech at the lab told me that the day #1 samples failed so she is not going to run tests on the samples that I delivered.
Street - Wedge Lift Partial 11/27/2017 at 8:00 AM 11/27/2017
PW-Misc
Informational
11/27/2017
The wedge lift is not completed. It got dark last week and they did not finish. They have the right lane on rosemary ct. to finish and they will be done.Steve Robbins 11/27/2017 11:03 AM
Water Line - Coliform Test 1 Failed 11/27/2017 at 11:30 AM 11/27/2017
PW-Misc
Informational
11/20/2017
The line has been chlorinated and flushed , we took the first sample to the lab this afternoon. John DiMarro will take the second one tomorrow.Steve Robbins 11/20/2017 4:49 PM
PW-Misc
Corrective Action Required
11/27/2017
The first sample that I took on 11/20 failed, the duplicate passed but that does not count. The sample John took to the lab on the 21, did not get sampled. The contractor thought it did , but blue valley lab does not have record of it. Today on the 11/27 we took another sample to the lab, Nick is going to take it for me tomorrow if the one from today passes.Steve Robbins 11/27/2017 2:46 PM
Detention Basin Partial 11/27/2017 at 10:00 AM 11/27/2017
Corrective Action Required
11/17/2017
Informational
11/27/2017
The detention basin has been completed , they are now installing the rock-check damns. They are also getting some of the grading finished.Steve Robbins 11/27/2017 2:52 PM
Water Line - Coliform Test 1 Partial 11/28/2017 at 1:10 PM 11/28/2017
PW-Misc
Informational
11/27/2017
The line has been chlorinated and flushed , we took the first sample to the lab this afternoon. John DiMarro will take the second one tomorrow.Steve Robbins 11/20/2017 4:49 PM
PW-Misc
Corrective Action Required
11/27/2017
The first sample that I took on 11/20 failed, the duplicate passed but that does not count. The sample John took to the lab on the 21, did not get sampled. The contractor thought it did , but blue valley lab does not have record of it. Today on the 11/27 we took another sample to the lab, Nick is going to take it for me tomorrow if the one from today passes.Steve Robbins 11/27/2017 2:46 PM
PW-Misc
Informational
11/28/2017
Took two samples down to the lab. Nick Lightner 11/28/2017 3:31 PM
Water Line - Coliform Test 2 Passed 11/30/2017 at 1:00 PM 11/30/2017
PW-Misc
Informational
11/21/2017
John DiMauro 11/21/2017 4:20 PM I collected samples today at the fire hydrant for Rosemary Ct. and delivered them to Blue Valley Labs. The tech at the lab told me that the day #1 samples failed so she is not going to run tests on the samples that I delivered.
PW-Misc
Informational
11/30/2017
I took a new sample on Monday the 27th and it passed. I was off on the 28th and Nick took the sample for me and it passed. The water samples are now complete.Steve Robbins 11/30/2017 7:24 AM
Detention Basin Passed 11/30/2017 at 10:00 AM 11/30/2017
Informational
11/30/2017
The detention basin has been completed, all the pipe has been laid and the rip - rap has all been installed.Steve Robbins 11/30/2017 1:43 PM
Water Line - Construction Inspection Partial 11/30/2017 at 10:45 AM 11/30/2017
PW-Main inspection
Informational
11/10/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/10/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/10/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/10/2017
They are planning on pouring the thrust blocks this afternoon, they also installed a valve and are working on the fire hydrant at the end of the road.Steve Robbins 10/31/2017 2:52 PM
PW-Main inspection
Informational
11/10/2017
The contractors are digging up the fire hydrant and are going to connect to the existing 8"line connecting to the fire hydrant. We are going to bleach and swabb the connection when they are connecting. The fire hydrant will be re-used and will be moved moved about 10 feet from its current location. They still need to install a straddle block and a thrust block for the 90 degree pipe.Steve Robbins 11/08/2017 11:45 AM
PW-Main inspection
Informational
11/10/2017
The water line has been connected to the existing valve. The pipes are all connected. we are ready for the compression test.Steve Robbins 11/09/2017 12:05 PM
PW-Main inspection
Informational
11/10/2017
The 8" public water main has been installed and completed. We still need to do the service line tap.Steve Robbins 11/10/2017 9:26 AM
PW-Main inspection
Informational
11/30/2017
The 2 inch domestic line has been installed up to the building. Tomorrow the water dept is coming out to do a tap. When this is done the water line will be complete.Steve Robbins 11/30/2017 1:50 PM
Water Line - Construction Inspection Partial 12/1/2017 at 11:00 AM 12/01/2017
PW-Main inspection
Informational
11/30/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
11/30/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
11/30/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
11/30/2017
They are planning on pouring the thrust blocks this afternoon, they also installed a valve and are working on the fire hydrant at the end of the road.Steve Robbins 10/31/2017 2:52 PM
PW-Main inspection
Informational
11/30/2017
The contractors are digging up the fire hydrant and are going to connect to the existing 8"line connecting to the fire hydrant. We are going to bleach and swabb the connection when they are connecting. The fire hydrant will be re-used and will be moved moved about 10 feet from its current location. They still need to install a straddle block and a thrust block for the 90 degree pipe.Steve Robbins 11/08/2017 11:45 AM
PW-Main inspection
Informational
11/30/2017
The water line has been connected to the existing valve. The pipes are all connected. we are ready for the compression test.Steve Robbins 11/09/2017 12:05 PM
PW-Main inspection
Informational
11/30/2017
The 8" public water main has been installed and completed. We still need to do the service line tap.Steve Robbins 11/10/2017 9:26 AM
PW-Main inspection
Informational
11/30/2017
The 2 inch domestic line has been installed up to the building. Tomorrow the water dept is coming out to do a tap. When this is done the water line will be complete.Steve Robbins 11/30/2017 1:50 PM
PW-Main inspection
Informational
12/01/2017
The domestic water line for the building has been installed, the water dept. came out and did the tap and brought the meter and the pit. They are working on installing it this afternoon.Steve Robbins 12/01/2017 2:42 PM
Street - Wedge Lift Passed 12/4/2017 at 10:00 AM 12/06/2017
PW-Misc
Informational
11/27/2017
The wedge lift is not completed. It got dark last week and they did not finish. They have the right lane on rosemary ct. to finish and they will be done.Steve Robbins 11/27/2017 11:03 AM
PW-Misc
Informational
12/06/2017
The wedge lift has been completed and the surface was almost done, I had to leave early on monday , but the a asphalt equipment broke down so they were not able to finist the surface.
Water Line - Construction Inspection Passed 12/7/2017 at 9:00 AM 12/07/2017
PW-Main inspection
Informational
12/01/2017
The contractors started the water line today, they started at station 14+65.82 , they installed the 8x6 tee and then started laying pipe. They stopped at station 11+42.77 and installed the 8x6 tee. Thats where they were stopping for the day.Steve Robbins 10/27/2017 3:04 PM
PW-Main inspection
Informational
12/01/2017
The contractors have installed the fire hydrant in front of the building, its a Mueller, they have also installed the 90 degree bend that connects to the road crossing. They have not poured the thrust blocks yet, probably this afternoon.Steve Robbins 10/30/2017 11:57 AM
PW-Main inspection
Informational
12/01/2017
All the fittings are wrapped, but they have not poured the thrust blocks. Greg and Chuck came out and did a water test shut-down. Steve Robbins 10/30/2017 3:07 PM
PW-Main inspection
Informational
12/01/2017
They are planning on pouring the thrust blocks this afternoon, they also installed a valve and are working on the fire hydrant at the end of the road.Steve Robbins 10/31/2017 2:52 PM
PW-Main inspection
Informational
12/01/2017
The contractors are digging up the fire hydrant and are going to connect to the existing 8"line connecting to the fire hydrant. We are going to bleach and swabb the connection when they are connecting. The fire hydrant will be re-used and will be moved moved about 10 feet from its current location. They still need to install a straddle block and a thrust block for the 90 degree pipe.Steve Robbins 11/08/2017 11:45 AM
PW-Main inspection
Informational
12/01/2017
The water line has been connected to the existing valve. The pipes are all connected. we are ready for the compression test.Steve Robbins 11/09/2017 12:05 PM
PW-Main inspection
Informational
12/01/2017
The 8" public water main has been installed and completed. We still need to do the service line tap.Steve Robbins 11/10/2017 9:26 AM
PW-Main inspection
Informational
12/01/2017
The 2 inch domestic line has been installed up to the building. Tomorrow the water dept is coming out to do a tap. When this is done the water line will be complete.Steve Robbins 11/30/2017 1:50 PM
PW-Main inspection
Informational
12/01/2017
The domestic water line for the building has been installed, the water dept. came out and did the tap and brought the meter and the pit. They are working on installing it this afternoon.Steve Robbins 12/01/2017 2:42 PM
PW-Main inspection
Informational
12/07/2017
The domestic water line 2" copper has been tapped by the water dept. and is now installed with the meter and pit. The public water line is completed and has passed the water bacteria test and the private domestic line has also been completed..Steve Robbins 12/07/2017 11:06 AM
Street - Surface Course Passed 12/7/2017 at 10:30 AM 12/07/2017
PW-Misc
Informational
12/07/2017
The surface for the parking lot and the public street (Rosemary Ct.) have been installed and is now completed.The surface was installed on 12/5/17.
Water Line - Valve Passed 12/7/2017 at 2:00 PM 12/07/2017
PW-Misc
Informational
12/07/2017
The gate valve at the end of rosemary ct. has been installed and is complete.Steve Robbins 12/07/2017 3:20 PM
Grading/Excavation/Fill Inspection Partial 12/19/2017 at 12:30 PM 12/19/2017
PW-Misc
Informational
12/19/2017
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
Sanitary Sewer Construction Inspection Passed 12/27/2017 at 9:30 AM 12/27/2017
PW-Sanitary Sewer Testing
Corrective Action Required
11/20/2017
The water dept. did the camera test and found 3 sags which was pointed out in the email sent out. There was also concerns by Josh Roach that there were no wyes installed on this main. Ryan Elam pointed out that this was meant to be that way. Also , MH 22a-008 to existing MH 22a003 the grade is called out in the plans at .6 fall. I told the contractor when the surveyer comes out for the as-builds that it needs to be at least .6. The contractor said it was installed at .6. The contractors are planning on digging up the 3 sags and correcting them today.Steve Robbins 11/20/2017 11:50 AM
PW-Sanitary Sewer Testing
Informational
11/20/2017
The contractors have corrected the 3 sags that have been identified by the water dept. The 30 day wait starts today for the camera test again.Steve Robbins 11/20/2017 4:36 PM
PW-Sanitary Sewer Testing
Informational
12/27/2017
The sanitary testing has all been completed and the camera test has passed after they fixed the sags as per the water dept. standards.Steve Robbins 12/27/2017 1:40 PM
Grading/Excavation/Fill Inspection Partial 1/3/2018 at 2:15 PM 01/03/2018
PW-Misc
Informational
12/19/2017
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
01/03/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
Grading/Excavation/Fill Inspection Partial 1/8/2018 at 2:30 PM 01/08/2018
PW-Misc
Informational
01/03/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
01/03/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
01/08/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
Grading/Excavation/Fill Inspection Partial 1/11/2018 at 11:00 AM 01/11/2018
PW-Misc
Informational
01/08/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
01/08/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
01/08/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
PW-Misc
Informational
01/11/2018
No work is going on today, the weather is cold and wet.Steve Robbins 01/11/2018 11:13 AM
Water Line - Construction Taps Removed Passed 1/18/2018 01/18/2018
Install Street and Stop Signs Partial 1/18/2018 at 8:00 AM 01/18/2018
Corrective Action Required
01/18/2018
The street name signs have been installed for the private side , but the stop and street name and the 3 object markers at the end of Rosemary Ct. has not been installed yet. I talked with D.J. and he said he would take care of it.Steve Robbins 01/18/2018 8:07 AM
Site Visit Partial 1/22/2018 at 1:15 PM 01/22/2018
PW-Misc
Informational
01/22/2018
Jeremy Young 01/22/2018 1:15 PM No outside work going on because of weather.
Install Street and Stop Signs Passed 1/24/2018 at 1:30 PM 01/24/2018
Resolved
01/24/2018
The stop signs and street signs have been installed, the 4 object markers have been installed too.Steve Robbins 01/24/2018 3:36 PM
Site Visit Partial 1/25/2018 at 2:45 PM 01/25/2018
PW-Misc
Informational
01/22/2018
Jeremy Young 01/22/2018 1:15 PM No outside work going on because of weather.
PW-Misc
Informational
01/25/2018
Nothing going on outside today.Steve Robbins 01/25/2018 3:45 PM
Grading/Excavation/Fill Inspection Partial 1/31/2018 at 10:00 AM 01/31/2018
PW-Misc
Informational
01/11/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
01/11/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
01/11/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
PW-Misc
Informational
01/11/2018
No work is going on today, the weather is cold and wet.Steve Robbins 01/11/2018 11:13 AM
PW-Misc
Informational
01/31/2018
The contractors are still grading and getting it ready for seed and straw.Steve Robbins 01/31/2018 2:16 PM
Site Visit Complete 2/2/2018 at 2:45 PM 02/02/2018
PW-Misc
Informational
01/25/2018
Jeremy Young 01/22/2018 1:15 PM No outside work going on because of weather.
PW-Misc
Informational
01/25/2018
Nothing going on outside today.Steve Robbins 01/25/2018 3:45 PM
Grading/Excavation/Fill Inspection Partial 2/6/2018 at 1:35 PM 02/06/2018
PW-Misc
Informational
01/31/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
01/31/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
01/31/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
PW-Misc
Informational
01/31/2018
No work is going on today, the weather is cold and wet.Steve Robbins 01/11/2018 11:13 AM
PW-Misc
Informational
01/31/2018
The contractors are still grading and getting it ready for seed and straw.Steve Robbins 01/31/2018 2:16 PM
PW-Misc
Informational
02/06/2018
Steve Robbins 02/06/2018 3:23 PM No work going on today.
Grading/Excavation/Fill Inspection Partial 2/8/2018 at 8:45 AM 02/08/2018
PW-Misc
Informational
02/06/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
02/06/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
02/06/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
PW-Misc
Informational
02/06/2018
No work is going on today, the weather is cold and wet.Steve Robbins 01/11/2018 11:13 AM
PW-Misc
Informational
02/06/2018
The contractors are still grading and getting it ready for seed and straw.Steve Robbins 01/31/2018 2:16 PM
PW-Misc
Informational
02/06/2018
Steve Robbins 02/06/2018 3:23 PM No work going on today.
PW-Misc
Informational
02/08/2018
No work going on outside today.Steve Robbins 02/08/2018 3:42 PM
Grading/Excavation/Fill Inspection Partial 2/12/2018 at 10:30 AM 02/12/2018
PW-Misc
Informational
02/08/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
02/08/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
02/08/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
PW-Misc
Informational
02/08/2018
No work is going on today, the weather is cold and wet.Steve Robbins 01/11/2018 11:13 AM
PW-Misc
Informational
02/08/2018
The contractors are still grading and getting it ready for seed and straw.Steve Robbins 01/31/2018 2:16 PM
PW-Misc
Informational
02/08/2018
Steve Robbins 02/06/2018 3:23 PM No work going on today.
PW-Misc
Informational
02/08/2018
No work going on outside today.Steve Robbins 02/08/2018 3:42 PM
PW-Misc
Informational
02/12/2018
No work is going on today.Steve Robbins 02/12/2018 11:02 AM
Grading/Excavation/Fill Inspection Partial 2/20/2018 at 11:00 AM 02/20/2018
PW-Misc
Informational
02/12/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
02/12/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
02/12/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
PW-Misc
Informational
02/12/2018
No work is going on today, the weather is cold and wet.Steve Robbins 01/11/2018 11:13 AM
PW-Misc
Informational
02/12/2018
The contractors are still grading and getting it ready for seed and straw.Steve Robbins 01/31/2018 2:16 PM
PW-Misc
Informational
02/12/2018
Steve Robbins 02/06/2018 3:23 PM No work going on today.
PW-Misc
Informational
02/12/2018
No work going on outside today.Steve Robbins 02/08/2018 3:42 PM
PW-Misc
Informational
02/12/2018
No work is going on today.Steve Robbins 02/12/2018 11:02 AM
PW-Misc
Informational
02/20/2018
I talked with Dean Kirby, they are going to relocate the at&t cable line and then they will re-grade behind the building backing up to blue-parkway.Steve Robbins 02/20/2018 2:30 PM
Storm - Pipe Passed 3/7/2018 03/07/2018
Storm - Inlets Clean Passed 3/7/2018 03/07/2018
Storm - Outlet Structure Passed 3/7/2018 03/07/2018
Storm - Rip Rap Passed 3/7/2018 03/07/2018
Storm - Swales Passed 3/7/2018 03/07/2018
Grading/Excavation/Fill Inspection Passed 3/2/2018 03/07/2018
PW-Misc
Informational
02/20/2018
The contractors seem to be done with the grading, I will look at the plans to make sure everything is looking good.Steve Robbins 12/19/2017 3:36 PM
PW-Misc
Informational
02/20/2018
No work is being done outside today.Steve Robbins 01/03/2018 2:24 PM
PW-Misc
Informational
02/20/2018
There is no work going on outside today. The contractors are continuing to work inside the building.Steve Robbins 01/08/2018 3:58 PM
PW-Misc
Informational
02/20/2018
No work is going on today, the weather is cold and wet.Steve Robbins 01/11/2018 11:13 AM
PW-Misc
Informational
02/20/2018
The contractors are still grading and getting it ready for seed and straw.Steve Robbins 01/31/2018 2:16 PM
PW-Misc
Informational
02/20/2018
Steve Robbins 02/06/2018 3:23 PM No work going on today.
PW-Misc
Informational
02/20/2018
No work going on outside today.Steve Robbins 02/08/2018 3:42 PM
PW-Misc
Informational
02/20/2018
No work is going on today.Steve Robbins 02/12/2018 11:02 AM
PW-Misc
Informational
02/20/2018
I talked with Dean Kirby, they are going to relocate the at&t cable line and then they will re-grade behind the building backing up to blue-parkway.Steve Robbins 02/20/2018 2:30 PM
ESC - (Vegetation/Ground Cover) Partial 5/1/2018 at 10:15 AM 05/01/2018
PW-Misc
Informational
05/01/2018
There has been sod installed around the building and they iinstalled hydro-seed around the site.Steve Robbins 05/01/2018 2:42 PM
ESC - (Vegetation/Ground Cover) Passed 5/23/2018 at 2:00 PM 05/07/2018
PW-Misc
Informational
05/01/2018
There has been sod installed around the building and they iinstalled hydro-seed around the site.Steve Robbins 05/01/2018 2:42 PM
PW-Misc
Informational
05/07/2018
The sod around the building has been all installed and the punch list has been completed. Ready for final acceptance on Summit Eye Care.Steve Robbins 05/07/2018 3:43 PM
Water Line - Coliform Test 1 Passed 05/08/2018
PW-Misc
Informational
11/28/2017
The line has been chlorinated and flushed , we took the first sample to the lab this afternoon. John DiMarro will take the second one tomorrow.Steve Robbins 11/20/2017 4:49 PM
PW-Misc
Corrective Action Required
11/28/2017
The first sample that I took on 11/20 failed, the duplicate passed but that does not count. The sample John took to the lab on the 21, did not get sampled. The contractor thought it did , but blue valley lab does not have record of it. Today on the 11/27 we took another sample to the lab, Nick is going to take it for me tomorrow if the one from today passes.Steve Robbins 11/27/2017 2:46 PM
Documents & Images
Date Uploaded File Type Document Name
08/24/2017 Receipt Receipt for transaction: 2017-005948
08/28/2017 Letter PW-Permit
09/06/2017 DOC090617-09062017071114
09/11/2017 Letter DE-Daily Inspection Summary
09/25/2017 Letter DE-Daily Inspection Summary
09/25/2017 Letter DE-Daily Inspection Summary
09/25/2017 Letter DE-Daily Inspection Summary
09/27/2017 Letter DE-Daily Inspection Summary
09/27/2017 Letter DE-Daily Inspection Summary
09/28/2017 Letter DE-Daily Inspection Summary
09/29/2017 Letter DE-Daily Inspection Summary
10/02/2017 Letter DE-Daily Inspection Summary
10/03/2017 Letter DE-Daily Inspection Summary
10/03/2017 Letter DE-Daily Inspection Summary
10/04/2017 Letter DE-Daily Inspection Summary
10/06/2017 Letter DE-Daily Inspection Summary
10/10/2017 Letter DE-Daily Inspection Summary
10/10/2017 Letter DE-Daily Inspection Summary
10/11/2017 Letter DE-Daily Inspection Summary
10/12/2017 Letter DE-Daily Inspection Summary
10/12/2017 Letter DE-Daily Inspection Summary
10/13/2017 Letter DE-Daily Inspection Summary
10/16/2017 Letter DE-Daily Inspection Summary
10/16/2017 Letter DE-Daily Inspection Summary
10/17/2017 Letter DE-Daily Inspection Summary
10/17/2017 Letter DE-Daily Inspection Summary
10/19/2017 Letter DE-Daily Inspection Summary
10/19/2017 Letter DE-Daily Inspection Summary
10/19/2017 Letter DE-Daily Inspection Summary
10/23/2017 Letter DE-Daily Inspection Summary
10/23/2017 Letter DE-Daily Inspection Summary
10/24/2017 Letter DE-Daily Inspection Summary
10/25/2017 Letter DE-Daily Inspection Summary
10/26/2017 Letter DE-Daily Inspection Summary
10/26/2017 Letter DE-Daily Inspection Summary
10/26/2017 Letter DE-Daily Inspection Summary
10/27/2017 Letter DE-Daily Inspection Summary
10/27/2017 Letter DE-Daily Inspection Summary
10/27/2017 Letter DE-Daily Inspection Summary
10/30/2017 Letter DE-Daily Inspection Summary
10/31/2017 Letter DE-Daily Inspection Summary
10/31/2017 Letter DE-Daily Inspection Summary
11/01/2017 Letter DE-Daily Inspection Summary
11/01/2017 Letter DE-Daily Inspection Summary
11/01/2017 Letter DE-Daily Inspection Summary
11/01/2017 Letter DE-Daily Inspection Summary
11/02/2017 Letter DE-Daily Inspection Summary
11/02/2017 Letter DE-Daily Inspection Summary
11/02/2017 Letter DE-Daily Inspection Summary
11/03/2017 Letter DE-Daily Inspection Summary
11/03/2017 Letter DE-Daily Inspection Summary
11/07/2017 Letter DE-Daily Inspection Summary
11/07/2017 Letter DE-Daily Inspection Summary
11/07/2017 Letter DE-Daily Inspection Summary
11/08/2017 Letter DE-Daily Inspection Summary
11/08/2017 Letter DE-Daily Inspection Summary
11/08/2017 Letter DE-Daily Inspection Summary
11/10/2017 Letter DE-Daily Inspection Summary
11/10/2017 Letter DE-Daily Inspection Summary
11/10/2017 Letter DE-Daily Inspection Summary
11/10/2017 Letter DE-Daily Inspection Summary
11/10/2017 Letter DE-Daily Inspection Summary
11/13/2017 Letter DE-Daily Inspection Summary
11/13/2017 Letter DE-Daily Inspection Summary
11/13/2017 Letter DE-Daily Inspection Summary
11/14/2017 Letter DE-Daily Inspection Summary
11/14/2017 Letter DE-Daily Inspection Summary
11/15/2017 Letter DE-Daily Inspection Summary
11/17/2017 Letter DE-Daily Inspection Summary
11/20/2017 Letter DE-Daily Inspection Summary
11/20/2017 Letter DE-Daily Inspection Summary
11/20/2017 Letter DE-Daily Inspection Summary
11/20/2017 Letter DE-Daily Inspection Summary
11/21/2017 Letter DE-Daily Inspection Summary
11/27/2017 Letter DE-Daily Inspection Summary
11/27/2017 Letter DE-Daily Inspection Summary
11/27/2017 Letter DE-Daily Inspection Summary
11/30/2017 Letter DE-Daily Inspection Summary
11/30/2017 Letter DE-Daily Inspection Summary
12/01/2017 Letter DE-Daily Inspection Summary
12/07/2017 Letter DE-Daily Inspection Summary
12/07/2017 Letter DE-Daily Inspection Summary
12/07/2017 Letter DE-Daily Inspection Summary
12/19/2017 Letter DE-Daily Inspection Summary
01/03/2018 Letter DE-Daily Inspection Summary
01/08/2018 Letter DE-Daily Inspection Summary
01/11/2018 Letter DE-Daily Inspection Summary
01/18/2018 Letter DE-Daily Inspection Summary
01/22/2018 Letter DE-Daily Inspection Summary
01/24/2018 Letter DE-Daily Inspection Summary
01/25/2018 Letter DE-Daily Inspection Summary
01/31/2018 Letter DE-Daily Inspection Summary
02/02/2018 Letter DE-Daily Inspection Summary
02/06/2018 Letter DE-Daily Inspection Summary
02/08/2018 Letter DE-Daily Inspection Summary
02/12/2018 Letter DE-Daily Inspection Summary
02/20/2018 Letter DE-Daily Inspection Summary
03/07/2018 Letter DE-Certificate of Substantial Completion Multiple Lot
03/07/2018 Letter DE-Punch List
03/07/2018 Summit Eye Care Substantial and Punch List
03/09/2018 Summit Eye Care Substantial and Punch List
05/01/2018 Letter DE-Daily Inspection Summary
05/07/2018 Letter DE-Daily Inspection Summary
05/08/2018 Letter DE-Certificate of Final Acceptance (Commercial)
05/08/2018 Summit Eye Care Final Acceptance
11/16/2017 Letter DE-Daily Inspection Summary
11/09/2017 Letter DE-Daily Inspection Summary
10/30/2017 Letter DE-Daily Inspection Summary
10/02/2017 Letter DE-Daily Inspection Summary
10/02/2017 Letter DE-Daily Inspection Summary
09/20/2017 Letter DE-Daily Inspection Summary
09/06/2017 Letter DE-Daily Inspection Summary
12/06/2017 Letter DE-Daily Inspection Summary
12/27/2017 Letter DE-Daily Inspection Summary
11/30/2017 Letter DE-Daily Inspection Summary
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home