Summary


PRPWFC20161619
Public Works Infrastructure Permit - Commercial
Final Acceptance
LEES SUMMIT UNITED METHODIST CHURCH
DEVELOPMENT COMPLETE
The Summit Church (NW Ashurst Dr. & NW Edgewood Dr.) Sanitary Sewer (offsite)
07/05/2016
07/08/2016
10/11/2017
Locations
Contacts
A L HUBER INC, Address:10770 EL MONTE, Phone:(913) 341-4880  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
LEES SUMMIT UNITED METHODIST CHURCH, Address:114 SE DOUGLAS  
THE UNITED METHODIST CHURCH OF LEES SUMM, Address:114 SE DOUGLAS ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 07/05/2016 07/05/2016
Dawn Bell
True
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $2,743.89 $2,743.89 Paid 07/07/2016
9110081-Paved Surface Inspection Fee $371.25 $371.25 Paid 07/07/2016
9110071-Site Grading Fee $128.34 $128.34 Paid 07/07/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
ESC Devices Installed Complete 7/11/2016 07/11/2016
Site Visit Partial 7/11/2016 07/11/2016
PW-Misc
Informational
07/11/2016
Delivered the permit and talked to Mark, he said they will be starting soon on the sanitary.Steve Robbins 07/11/2016 9:21 AM
Site Visit Complete 8/30/2016 08/30/2016
PW-Misc
Informational
08/30/2016
They are probably going to finist the storm and then start on the sanitary, so it could still be a few more weeks before they get started. Steve Robbins 08/30/2016 7:40 AM
ESC Devices Installed Complete 8/30/2016 08/30/2016
Site Visit Complete 7/25/2016 08/31/2016
PW-Misc
Informational
07/11/2016
Delivered the permit and talked to Mark, he said they will be starting soon on the sanitary.Steve Robbins 07/11/2016 9:21 AM
ESC Devices Installed Complete 8/31/2016 08/31/2016
Sanitary Sewer Construction Inspection Partial 11/10/2016 11/10/2016
PW-Misc
Informational
11/10/2016
The last 2 days they have started on the MH drop on ashurst dr. Today they made the tie in to the sanitary main line and MH drop in the road. They had to dig up the road and they are putting steel plates on the road over night.Steve Robbins 11/10/2016 4:29 PM
Sanitary Sewer Construction Inspection Partial 11/11/2016 11/11/2016
PW-Misc
Informational
11/11/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
Sanitary Sewer Construction Inspection Partial 11/14/2016 11/14/2016
PW-Misc
Informational
11/11/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/14/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
Sanitary Sewer Construction Inspection Partial 11/15/2016 11/15/2016
PW-Misc
Informational
11/14/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/14/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
PW-Misc
Informational
11/15/2016
Today they finished stacking the MH and wrapping it, and continued to backfill the hole in the street.Steve Robbins 11/15/2016 4:23 PM
Sanitary Sewer - Vacuum Partial 11/15/2016 11/16/2016
PW-Misc
Informational
11/16/2016
MH 1-1 has been installed and we did a vaccum test so they can get this backfilled and tested and get the road back open. It passed the test 2.5 minutes. We will continue with the others after they are installed.Steve Robbins 11/16/2016 2:14 PM
Sanitary Sewer Construction Inspection Partial 11/16/2016 11/17/2016
PW-Misc
Informational
11/15/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/17/2016
Today they continued on with the sanitary pipe, they went around several utilitiy lines and then at the end of the day they hit rock. They backfilled the hole in the street with 3/4 " rock and then had 8" of KCCMB mix with 2" left for surface after they finish the rest.Steve Robbins 11/17/2016 4:21 PM
PW-Misc
Informational
11/15/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
PW-Misc
Informational
11/15/2016
Today they finished stacking the MH and wrapping it, and continued to backfill the hole in the street.Steve Robbins 11/15/2016 4:23 PM
Sanitary Sewer Construction Inspection Partial 11/18/2016 11/23/2016
PW-Misc
Informational
11/17/2016
Today they continued on with the sanitary pipe, they went around several utilitiy lines and then at the end of the day they hit rock. They backfilled the hole in the street with 3/4 " rock and then had 8" of KCCMB mix with 2" left for surface after they finish the rest.Steve Robbins 11/17/2016 4:21 PM
PW-Misc
Informational
11/17/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/17/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
PW-Misc
Informational
11/17/2016
Today they finished stacking the MH and wrapping it, and continued to backfill the hole in the street.Steve Robbins 11/15/2016 4:23 PM
PW-Misc
Informational
11/23/2016
On friday 11/18 MH 1-2 was installed and all pipe up to it.Steve Robbins 11/23/2016 9:13 AM
Sanitary Sewer - Air Test Partial 11/21/2016 11/23/2016
PW-Misc
Informational
11/23/2016
On 11/21 we did a air test from MH 1-1 to MH 1-2, it passed.Steve Robbins 11/23/2016 9:18 AM
Sanitary Sewer Construction Inspection Partial 11/23/2016 11/23/2016
PW-Misc
Informational
11/23/2016
Today they continued on with the sanitary pipe, they went around several utilitiy lines and then at the end of the day they hit rock. They backfilled the hole in the street with 3/4 " rock and then had 8" of KCCMB mix with 2" left for surface after they finish the rest.Steve Robbins 11/17/2016 4:21 PM
PW-Misc
Informational
11/23/2016
Today they installed 8" sanitary pipe up to MH 1-3 and they also installed the MH, they do not have the cone on yet. Yesterday they also installed 8" of concrete on ashurst covering up base rock and dirt, they left it 2" low so they can put an asphalt cap on it.They also opened the road up for through traffic and gave the 2 houses on the corner access to their driveway for the holidays.Steve Robbins 11/23/2016 1:57 PM
PW-Misc
Informational
11/23/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/23/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
PW-Misc
Informational
11/23/2016
Today they finished stacking the MH and wrapping it, and continued to backfill the hole in the street.Steve Robbins 11/15/2016 4:23 PM
PW-Misc
Informational
11/23/2016
On friday 11/18 MH 1-2 was installed and all pipe up to it.Steve Robbins 11/23/2016 9:13 AM
Sanitary Sewer Construction Inspection Partial 11/28/2016 11/28/2016
PW-Misc
Informational
11/23/2016
Today they installed 8" sanitary pipe up to MH 1-3 and they also installed the MH, they do not have the cone on yet. Yesterday they also installed 8" of concrete on ashurst covering up base rock and dirt, they left it 2" low so they can put an asphalt cap on it.They also opened the road up for through traffic and gave the 2 houses on the corner access to their driveway for the holidays.Steve Robbins 11/23/2016 1:57 PM
PW-Misc
Informational
11/23/2016
Today they continued on with the sanitary pipe, they went around several utilitiy lines and then at the end of the day they hit rock. They backfilled the hole in the street with 3/4 " rock and then had 8" of KCCMB mix with 2" left for surface after they finish the rest.Steve Robbins 11/17/2016 4:21 PM
PW-Misc
Informational
11/23/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/23/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
PW-Misc
Informational
11/23/2016
Today they finished stacking the MH and wrapping it, and continued to backfill the hole in the street.Steve Robbins 11/15/2016 4:23 PM
PW-Misc
Informational
11/23/2016
On friday 11/18 MH 1-2 was installed and all pipe up to it.Steve Robbins 11/23/2016 9:13 AM
PW-Misc
Informational
11/28/2016
Today they are continuing putting the 8" sanitary pipe coming from MH 1-3 to MH 1-4. MH 1-4 and MH 1-5 were installed while I was gone out of town. Steve Robbins 11/28/2016 9:20 AM
Sanitary Sewer Construction Inspection Partial 11/29/2016 11/29/2016
PW-Misc
Informational
11/28/2016
Today they installed 8" sanitary pipe up to MH 1-3 and they also installed the MH, they do not have the cone on yet. Yesterday they also installed 8" of concrete on ashurst covering up base rock and dirt, they left it 2" low so they can put an asphalt cap on it.They also opened the road up for through traffic and gave the 2 houses on the corner access to their driveway for the holidays.Steve Robbins 11/23/2016 1:57 PM
PW-Misc
Informational
11/28/2016
Today they continued on with the sanitary pipe, they went around several utilitiy lines and then at the end of the day they hit rock. They backfilled the hole in the street with 3/4 " rock and then had 8" of KCCMB mix with 2" left for surface after they finish the rest.Steve Robbins 11/17/2016 4:21 PM
PW-Misc
Informational
11/28/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/28/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
PW-Misc
Informational
11/28/2016
Today they finished stacking the MH and wrapping it, and continued to backfill the hole in the street.Steve Robbins 11/15/2016 4:23 PM
PW-Misc
Informational
11/28/2016
On friday 11/18 MH 1-2 was installed and all pipe up to it.Steve Robbins 11/23/2016 9:13 AM
PW-Misc
Informational
11/28/2016
Today they are continuing putting the 8" sanitary pipe coming from MH 1-3 to MH 1-4. MH 1-4 and MH 1-5 were installed while I was gone out of town. Steve Robbins 11/28/2016 9:20 AM
PW-Misc
Informational
11/29/2016
Today the 8" sanitary pipe has been installed from MH 1-3 to 1-4. All of the MH 's have been installed and all pipe. Steve Robbins 11/29/2016 2:49 PM
Sanitary Sewer - Vacuum Partial 11/29/2016 11/29/2016
PW-Misc
Informational
11/16/2016
MH 1-1 has been installed and we did a vaccum test so they can get this backfilled and tested and get the road back open. It passed the test 2.5 minutes. We will continue with the others after they are installed.Steve Robbins 11/16/2016 2:14 PM
PW-Misc
Informational
11/29/2016
Steve Robbins 11/29/2016 4:36 PMToday MH 1-2 , 1-3 and 1-5 passed the vaccum test. 1-4 failed.
Sanitary Sewer - Air Test Passed 11/29/2016 11/29/2016
PW-Misc
Informational
11/23/2016
On 11/21 we did a air test from MH 1-1 to MH 1-2, it passed.Steve Robbins 11/23/2016 9:18 AM
PW-Misc
Informational
11/29/2016
We did all the compression tests between all the MH's and they all passed 8" pipe .Steve Robbins 11/29/2016 4:42 PM
Sanitary Sewer - Vacuum Passed 11/30/2016 12/08/2016
PW-Misc
Informational
11/29/2016
MH 1-1 has been installed and we did a vaccum test so they can get this backfilled and tested and get the road back open. It passed the test 2.5 minutes. We will continue with the others after they are installed.Steve Robbins 11/16/2016 2:14 PM
PW-Misc
Informational
11/29/2016
Steve Robbins 11/29/2016 4:36 PMToday MH 1-2 , 1-3 and 1-5 passed the vaccum test. 1-4 failed.
PW-Misc
Informational
12/08/2016
MH 1-4 has passed the vaccum test . Steve Robbins 12/08/2016 8:33 AM
Pavement-Surface Passed 12/08/2016
PW-Misc
Informational
12/08/2016
The road on Ashurst where they installed MH 1-1 it has been filled back in with rock and dirt, it has 10 inches of concrete in the entire road where they dug up for the sanitary pipe. 4 ft wide on each side of the pipe.. They left 2 inches for surface asphalt, it has been cold so it may be a while before they finish, while they are waiting for the weather the road is open so they can get to thier driveway.Steve Robbins 12/08/2016 8:44 AM
Street - Concrete Partial 12/12/2016 12/12/2016
PW-Misc
Informational
12/12/2016
8" inches of concrete has already been installed on ashurst and edgewood. Today they milled 2" of asphalt in the area they worked on in the street. The street is now ready for 2" of surface.Steve Robbins 12/12/2016 3:45 PM
Street - Concrete Passed 12/13/2016 12/13/2016
PW-Misc
Informational
12/12/2016
8" inches of concrete has already been installed on ashurst and edgewood. Today they milled 2" of asphalt in the area they worked on in the street. The street is now ready for 2" of surface.Steve Robbins 12/12/2016 3:45 PM
Street - Surface Course Partial 12/13/2016 12/13/2016
PW-Misc
Informational
12/13/2016
Talked to Mark from A.L.Huber today and let him know that the temp has to be 40 and rising for the asphalt surface to be able to go in on ashurst.Steve Robbins 12/13/2016 2:24 PM
Erosion Control Inspection Passed 12/19/2016 12/19/2016
Sanitary Sewer Construction Inspection Passed 12/19/2016 12/19/2016
PW-Misc
Informational
11/29/2016
Today they installed 8" sanitary pipe up to MH 1-3 and they also installed the MH, they do not have the cone on yet. Yesterday they also installed 8" of concrete on ashurst covering up base rock and dirt, they left it 2" low so they can put an asphalt cap on it.They also opened the road up for through traffic and gave the 2 houses on the corner access to their driveway for the holidays.Steve Robbins 11/23/2016 1:57 PM
PW-Misc
Informational
11/29/2016
Today they continued on with the sanitary pipe, they went around several utilitiy lines and then at the end of the day they hit rock. They backfilled the hole in the street with 3/4 " rock and then had 8" of KCCMB mix with 2" left for surface after they finish the rest.Steve Robbins 11/17/2016 4:21 PM
PW-Misc
Informational
11/29/2016
MH 1-1 has been installed, but not yet has been stacked, today they continued to dig around the utilities . Monday they are going to put the encasement around the drop.Steve Robbins 11/11/2016 2:37 PM
PW-Misc
Informational
11/29/2016
Today they are working on the encasement for MH drop. They built the cage with rebar and concrete is coming at 11;30.Steve Robbins 11/14/2016 10:30 AM
PW-Misc
Informational
11/29/2016
Today they finished stacking the MH and wrapping it, and continued to backfill the hole in the street.Steve Robbins 11/15/2016 4:23 PM
PW-Misc
Informational
11/29/2016
On friday 11/18 MH 1-2 was installed and all pipe up to it.Steve Robbins 11/23/2016 9:13 AM
PW-Misc
Informational
11/29/2016
Today they are continuing putting the 8" sanitary pipe coming from MH 1-3 to MH 1-4. MH 1-4 and MH 1-5 were installed while I was gone out of town. Steve Robbins 11/28/2016 9:20 AM
PW-Misc
Informational
11/29/2016
Today the 8" sanitary pipe has been installed from MH 1-3 to 1-4. All of the MH 's have been installed and all pipe. Steve Robbins 11/29/2016 2:49 PM
PW-Misc
Informational
12/19/2016
All sanitary sewer has been installed , all that needs to be done is the mandrel testing.Steve Robbins 12/19/2016 3:30 PM
Street - Surface Course Partial 12/19/2016 12/19/2016
PW-Misc
Informational
12/13/2016
Talked to Mark from A.L.Huber today and let him know that the temp has to be 40 and rising for the asphalt surface to be able to go in on ashurst.Steve Robbins 12/13/2016 2:24 PM
PW-Misc
Informational
12/19/2016
I talked with Mark from A.L. Huber today, if they can get asphalt later in the week they may try and surface on ashurst if the temerature is high enough. I also got a complaint from a citizen in the neighborhood, service request 117890 , I talked with Tom Turner and he is not happy that the surface is not in yet and it is causing problems. I explained the situation about our temperature standards for ashpalt and he said he understood. Steve Robbins 12/19/2016 3:39 PM
Street - Surface Course Passed 12/23/2016 12/27/2016
PW-Misc
Informational
12/19/2016
Talked to Mark from A.L.Huber today and let him know that the temp has to be 40 and rising for the asphalt surface to be able to go in on ashurst.Steve Robbins 12/13/2016 2:24 PM
PW-Misc
Informational
12/19/2016
I talked with Mark from A.L. Huber today, if they can get asphalt later in the week they may try and surface on ashurst if the temerature is high enough. I also got a complaint from a citizen in the neighborhood, service request 117890 , I talked with Tom Turner and he is not happy that the surface is not in yet and it is causing problems. I explained the situation about our temperature standards for ashpalt and he said he understood. Steve Robbins 12/19/2016 3:39 PM
PW-Misc
Informational
12/27/2016
On friday 12/23/16 the surface was laid at the intesection of ashurst and edgewood. I talked to Mark today about getting the signs picked up and getting a way to block peope from driving back on ashurst. He already had it blocked off from the site so no construction traffic could go through.Steve Robbins 12/27/2016 10:46 AM
ESC - (Vegetation/Ground Cover) Passed 12/29/2016
Sanitary Sewer - Invert Passed 12/29/2016 12/29/2016
PW-Misc
Informational
12/29/2016
All the inverts have been poured for MH 1-5Steve Robbins 12/29/2016 2:15 PM
Site Visit Complete 12/30/2016 12/30/2016
PW-Misc
Informational
12/30/2016
I drove by ashurst and edgewood today and all the signs have been picked up and they also built a dirt berm on ashurst so no one can drive in the churches propery. Some of the neighbors were complaining that people were driving up on the property.Steve Robbins 12/30/2016 11:29 AM
Sanitary Sewer - Mandrel Passed 2/21/2017 02/21/2017
PW-Misc
Informational
02/21/2017
The mandrel test passed, I have ordered the camera test, Steve Robbins 02/21/2017 3:41 PM
Sanitary Sewer Construction Inspection Partial 3/6/2017 03/06/2017
PW-Misc
Informational
03/06/2017
The 8" sewer line and all MH"s have there video completed. The water dept. found 2 deflections during the video. I let them know they can dig it up and fix the deflection and then they have to wait 30 days and do another mandrel test. If they do not cut into the line they do not have to do the other tests.Steve Robbins 03/06/2017 2:13 PM
Sanitary Sewer Construction Inspection Partial 3/14/2017 03/14/2017
PW-Misc
Informational
03/14/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
Grading/Excavation/Fill Inspection Passed 4/14/2017 04/14/2017
PW-Misc
Informational
04/14/2017
All the grading for this project around the sanitary has been completed. Any other grading or vegetation for this project I will tie in with 20161240.Steve Robbins 04/14/2017 1:35 PM
Sanitary Sewer Construction Inspection Partial 4/14/2017 04/14/2017
PW-Misc
Informational
03/14/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
04/14/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
Sanitary Sewer Construction Inspection Failed 4/17/2017 04/17/2017
PW-Main inspection
Informational
04/14/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Main inspection
Corrective Action Required
04/17/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Misc
Informational
04/14/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
Sanitary Sewer Construction Inspection Partial 4/19/2017 04/19/2017
PW-Main inspection
Corrective Action Required
04/17/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Main inspection
Informational
04/17/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Misc
Informational
04/17/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
04/19/2017
A main inspection has uncovered the following problems. I have talked with C.J. and Josh from water and the problem is from M.H. 1-4 to 15. The sag is 15 -25 ft. out from the stub of M.H. 1-4 going up-stream. They also found that the lateral coming out from the building is dropping straight down instead of a 45. I am meeting with the owner of Central plumbing today and Mark to discuss the problem.Steve Robbins 04/19/2017 7:38 AM
Sanitary Sewer Construction Inspection Partial 4/20/2017 04/20/2017
PW-Main inspection
Corrective Action Required
04/19/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Main inspection
Informational
04/19/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Misc
Informational
04/19/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
04/19/2017
A main inspection has uncovered the following problems. I have talked with C.J. and Josh from water and the problem is from M.H. 1-4 to 15. The sag is 15 -25 ft. out from the stub of M.H. 1-4 going up-stream. They also found that the lateral coming out from the building is dropping straight down instead of a 45. I am meeting with the owner of Central plumbing today and Mark to discuss the problem.Steve Robbins 04/19/2017 7:38 AM
PW-Main inspection
Informational
04/20/2017
On friday 4/21/17 I will be off, central plumbing is planning on coming out to correct the sag that is 15-25 ft. upstream from MH 1-4 and to start replacing the barrell on MH 1-5 that has a stub .Steve Robbins 04/20/2017 7:44 AM
Sanitary Sewer Construction Inspection Partial 4/24/2017 04/24/2017
PW-Main inspection
Corrective Action Required
04/20/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Main inspection
Informational
04/24/2017
Today central plumbing dug up 25ft from MH 1-4 to fix the sag that has been identified. They also fixed the lateral from the building, the wye was not at a45 degree angle, it is now in the correct position. We can now wait 30 days for a camera test.Steve Robbins 04/24/2017 2:39 PM
PW-Main inspection
Informational
04/20/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Misc
Informational
04/20/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
04/20/2017
A main inspection has uncovered the following problems. I have talked with C.J. and Josh from water and the problem is from M.H. 1-4 to 15. The sag is 15 -25 ft. out from the stub of M.H. 1-4 going up-stream. They also found that the lateral coming out from the building is dropping straight down instead of a 45. I am meeting with the owner of Central plumbing today and Mark to discuss the problem.Steve Robbins 04/19/2017 7:38 AM
PW-Main inspection
Informational
04/20/2017
On friday 4/21/17 I will be off, central plumbing is planning on coming out to correct the sag that is 15-25 ft. upstream from MH 1-4 and to start replacing the barrell on MH 1-5 that has a stub .Steve Robbins 04/20/2017 7:44 AM
Sanitary Sewer Construction Inspection Failed 5/24/2017 05/24/2017
PW-Main inspection
Informational
04/24/2017
Today central plumbing dug up 25ft from MH 1-4 to fix the sag that has been identified. They also fixed the lateral from the building, the wye was not at a45 degree angle, it is now in the correct position. We can now wait 30 days for a camera test.Steve Robbins 04/24/2017 2:39 PM
PW-Main inspection
Corrective Action Required
04/24/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Main inspection
Informational
04/24/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Misc
Informational
04/24/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
04/24/2017
A main inspection has uncovered the following problems. I have talked with C.J. and Josh from water and the problem is from M.H. 1-4 to 15. The sag is 15 -25 ft. out from the stub of M.H. 1-4 going up-stream. They also found that the lateral coming out from the building is dropping straight down instead of a 45. I am meeting with the owner of Central plumbing today and Mark to discuss the problem.Steve Robbins 04/19/2017 7:38 AM
PW-Main inspection
Informational
04/24/2017
On friday 4/21/17 I will be off, central plumbing is planning on coming out to correct the sag that is 15-25 ft. upstream from MH 1-4 and to start replacing the barrell on MH 1-5 that has a stub .Steve Robbins 04/20/2017 7:44 AM
Informational
05/24/2017
I talked with Kent yesterday about the stub coming out of the MH 1-5, the church is writing a letter to the water dept. We are going to wait till we get word of their decisicion before we camera the sag because the MH has not been dug up yet.Steve Robbins 05/24/2017 7:24 AM
Sanitary Sewer Construction Inspection Failed 7/6/2017 07/12/2017
PW-Main inspection
Informational
05/24/2017
Today central plumbing dug up 25ft from MH 1-4 to fix the sag that has been identified. They also fixed the lateral from the building, the wye was not at a45 degree angle, it is now in the correct position. We can now wait 30 days for a camera test.Steve Robbins 04/24/2017 2:39 PM
PW-Main inspection
Corrective Action Required
05/24/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Main inspection
Informational
05/24/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Misc
Informational
05/24/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
05/24/2017
A main inspection has uncovered the following problems. I have talked with C.J. and Josh from water and the problem is from M.H. 1-4 to 15. The sag is 15 -25 ft. out from the stub of M.H. 1-4 going up-stream. They also found that the lateral coming out from the building is dropping straight down instead of a 45. I am meeting with the owner of Central plumbing today and Mark to discuss the problem.Steve Robbins 04/19/2017 7:38 AM
PW-Main inspection
Informational
07/12/2017
A main inspection has uncovered the following problems. I was told by Dawn Bell and Kent Monter that the water dept. has decided that they will not accept the stub coming out of the MH . They will have to dig it up and replace it with no stub.Steve Robbins 07/12/2017 2:45 PM
Sanitary Sewer Construction Inspection Partial 9/19/2017 at 3:45 PM 09/19/2017
PW-Main inspection
Informational
07/12/2017
Today central plumbing dug up 25ft from MH 1-4 to fix the sag that has been identified. They also fixed the lateral from the building, the wye was not at a45 degree angle, it is now in the correct position. We can now wait 30 days for a camera test.Steve Robbins 04/24/2017 2:39 PM
PW-Main inspection
Corrective Action Required
07/12/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Main inspection
Informational
07/12/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Misc
Informational
07/12/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
07/12/2017
A main inspection has uncovered the following problems. I have talked with C.J. and Josh from water and the problem is from M.H. 1-4 to 15. The sag is 15 -25 ft. out from the stub of M.H. 1-4 going up-stream. They also found that the lateral coming out from the building is dropping straight down instead of a 45. I am meeting with the owner of Central plumbing today and Mark to discuss the problem.Steve Robbins 04/19/2017 7:38 AM
PW-Main inspection
Informational
07/12/2017
A main inspection has uncovered the following problems. I was told by Dawn Bell and Kent Monter that the water dept. has decided that they will not accept the stub coming out of the MH . They will have to dig it up and replace it with no stub.Steve Robbins 07/12/2017 2:45 PM
PW-Main inspection
Informational
09/19/2017
We are waiting on a decision to see if they are going to have to dig up the MH and replace the bottom barrell without a stub.Steve Robbins 09/19/2017 3:51 PM
Sanitary Sewer Construction Inspection Passed 9/26/2017 at 10:15 AM 09/26/2017
PW-Main inspection
Informational
09/19/2017
Today central plumbing dug up 25ft from MH 1-4 to fix the sag that has been identified. They also fixed the lateral from the building, the wye was not at a45 degree angle, it is now in the correct position. We can now wait 30 days for a camera test.Steve Robbins 04/24/2017 2:39 PM
PW-Main inspection
Corrective Action Required
09/19/2017
A main inspection has uncovered the following problems. There is still one deflection going up stream from MH 1-4 to 1-5. They also said MH 1-5 has to be taken out and replace the bottom barrell because it cannot be stubbed for a future sanitary line. They are going to be given a TCO so they can move their furniture in but not a substantial complettion until these items are resolved.Steve Robbins 04/17/2017 3:39 PM
PW-Main inspection
Informational
09/19/2017
I did not get the results from the camera test yet, but Josh Roach sent me an e-mail saying they have to replace the bottom barrel of the mh. The stub that is coming out for future extention is not allowed per the design and construction manual.Steve Robbins 04/14/2017 3:43 PM
PW-Misc
Informational
09/19/2017
Yesterday they dug up the sanitary line in the 2 areas that the deflections were in. They did not watch the video that the water dept. gave us, they needed a flashdrive, I offered to let them come to the office and watch it but they thought they get it figured out. They sought out the areas that were wrong and they believe they have them corrected. They burried the pipe on 3/13/17, they will have to wait 30 days till the water dept. will do another camera test.Steve Robbins 03/14/2017 3:11 PM
PW-Main inspection
Informational
09/19/2017
A main inspection has uncovered the following problems. I have talked with C.J. and Josh from water and the problem is from M.H. 1-4 to 15. The sag is 15 -25 ft. out from the stub of M.H. 1-4 going up-stream. They also found that the lateral coming out from the building is dropping straight down instead of a 45. I am meeting with the owner of Central plumbing today and Mark to discuss the problem.Steve Robbins 04/19/2017 7:38 AM
PW-Main inspection
Informational
09/19/2017
A main inspection has uncovered the following problems. I was told by Dawn Bell and Kent Monter that the water dept. has decided that they will not accept the stub coming out of the MH . They will have to dig it up and replace it with no stub.Steve Robbins 07/12/2017 2:45 PM
PW-Main inspection
Informational
09/19/2017
We are waiting on a decision to see if they are going to have to dig up the MH and replace the bottom barrell without a stub.Steve Robbins 09/19/2017 3:51 PM
PW-Main inspection
Informational
09/26/2017
This morning Central Plumbing installed an 8" plastic plug with a rubber gasket. The 8" plastic plug was installed 12" in the pipe, non-shrink grout in the 12" behind the plug to the end of the pipe. This completes the inspections for the sanitary sewer. There also was some string from a mandrel test that they removed.Steve Robbins 09/26/2017 12:17 PM
Street - Surface Course Passed 09/27/2017
Corrective Action Required
03/06/2017
Sanitary Sewer Construction Inspection Passed 9/27/2017 at 2:20 PM 09/27/2017
PW-Main inspection
Informational
09/27/2017
The camera test has passed and the sag has been corrected. The mandrel passed and all tests have been completed. The sanitary has been completed.Steve Robbins 09/27/2017 2:23 PM
Documents & Images
Date Uploaded File Type Document Name
07/07/2016 Receipt Receipt for transaction: 2016-004642
07/08/2016 Letter PW-Permit
08/30/2016 Letter PW-Daily Inspection Summary
11/10/2016 Letter PW-Daily Inspection Summary
11/11/2016 Letter PW-Daily Inspection Summary
11/14/2016 Letter PW-Daily Inspection Summary
11/15/2016 Letter PW-Daily Inspection Summary
11/16/2016 Letter PW-Daily Inspection Summary
11/17/2016 Letter PW-Daily Inspection Summary
11/23/2016 Letter PW-Daily Inspection Summary
11/23/2016 Letter PW-Daily Inspection Summary
11/23/2016 Letter PW-Daily Inspection Summary
11/28/2016 Letter PW-Daily Inspection Summary
11/29/2016 Letter PW-Daily Inspection Summary
11/29/2016 Letter PW-Daily Inspection Summary
11/29/2016 Letter PW-Daily Inspection Summary
12/08/2016 Letter PW-Daily Inspection Summary
12/08/2016 Letter PW-Daily Inspection Summary
12/12/2016 Letter PW-Daily Inspection Summary
12/13/2016 Letter PW-Daily Inspection Summary
12/19/2016 Letter PW-Daily Inspection Summary
12/19/2016 Letter PW-Daily Inspection Summary
12/27/2016 Letter PW-Daily Inspection Summary
12/29/2016 Letter PW-Daily Inspection Summary
12/30/2016 Letter PW-Daily Inspection Summary
02/21/2017 Letter PW-Daily Inspection Summary
03/06/2017 Letter PW-Daily Inspection Summary
03/14/2017 Letter PW-Daily Inspection Summary
04/14/2017 Letter PW-Daily Inspection Summary
04/14/2017 Letter PW-Daily Inspection Summary
04/17/2017 Letter PW-Daily Inspection Summary
04/17/2017 Letter PW-Daily Inspection Summary
04/19/2017 Letter PW-Daily Inspection Summary
04/20/2017 Letter PW-Daily Inspection Summary
04/24/2017 Letter PW-Daily Inspection Summary
04/25/2017 Letter PW-Project Inspection Summary
05/09/2017 Letter PW-Certificate of Substantial Completion Single Lot
05/09/2017 Letter PW-Punch List
05/09/2017 Letter PW-Certificate of Substantial Completion Single Lot
05/09/2017 Letter PW-Punch List
05/24/2017 Letter PW-Daily Inspection Summary
07/12/2017 Letter PW-Daily Inspection Summary
09/12/2017 DOC091217-09122017130228
09/19/2017 Letter DE-Daily Inspection Summary
09/26/2017 Letter DE-Daily Inspection Summary
09/27/2017 Letter DE-Daily Inspection Summary
10/11/2017 Letter DE-Certificate of Final Acceptance (Commercial)
10/11/2017 DOC101117-10112017090420
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents