| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Licensed Contractors
|
Approved
|
03/07/2025
|
03/07/2025
|
|
|
Daniel Fernandez
|
|
|
|
|
ESC Application and Plan Review
|
Corrections
|
10/31/2024
|
10/29/2024
|
|
|
Daniel Fernandez
|
|
|
Miscellaneous Correction
Corrective Action Required
According to the plans, this should be titled as a Mass Grading and Erosion and Sediment Control Plan or equivalent language. Change title accordingly.
|
|
|
Miscellaneous Correction
Corrective Action Required
See comments in the Final Development Plan applicant letter related to the grading of the detention basin. There are several issues, including slopes that are too steep (i.e., greater than 3:1), and original submittal showed curvilinear grading within the detention basin, but most recent submittal (i.e., this submittal) shows rectilinear grading which does not appear practical. Corrections needed.
|
|
|
Miscellaneous Correction
Corrective Action Required
See comments in the Final Development Plan related to the detention basin and stormwater study. It is unclear whether this basin meets the requirements due to inconsistencies in the design of the outlet structure, questions on the outflow pipe size, and other issues related to the sanitary sewer and potential grading over the sanitary sewer to extend the fill to avoid conflict with the bridge. Corrections needed.
|
|
|
Miscellaneous Correction
Corrective Action Required
A SWPPP is required due to the disturbed area being greater than 1 acre. Correction required.
|
|
|
Miscellaneous Correction
Corrective Action Required
A cost estimate for all sitework is required since this is a mass grading and erosion and sediment control plan. Provide a signed and sealed cost estimate for the sitework shown on the mass grading and erosion and sediment control plan.
|
|
|
|
|
ESC Application and Plan Review
|
Corrections
|
09/27/2024
|
09/20/2024
|
|
|
Daniel Fernandez
|
|
|
Miscellaneous Correction
Corrective Action Required
According to the plans, this should be titled as a Mass Grading and Erosion and Sediment Control Plan or equivalent language. Change title accordingly.
|
|
|
Miscellaneous Correction
Corrective Action Required
See comments in the Final Development Plan applicant letter related to the grading of the detention basin. There are several issues, including slopes that are too steep (i.e., greater than 3:1), and original submittal showed curvilinear grading within the detention basin, but most recent submittal (i.e., this submittal) shows rectilinear grading which does not appear practical. Corrections needed.
|
|
|
Miscellaneous Correction
Corrective Action Required
See comments in the Final Development Plan related to the detention basin and stormwater study. It is unclear whether this basin meets the requirements due to inconsistencies in the design of the outlet structure, questions on the outflow pipe size, and other issues related to the sanitary sewer and potential grading over the sanitary sewer to extend the fill to avoid conflict with the bridge. Corrections needed.
|
|
|
Miscellaneous Correction
Corrective Action Required
A SWPPP is required due to the disturbed area being greater than 1 acre. Correction required.
|
|
|
Miscellaneous Correction
Corrective Action Required
A cost estimate for all sitework is required since this is a mass grading and erosion and sediment control plan. Provide a signed and sealed cost estimate for the sitework shown on the mass grading and erosion and sediment control plan.
|
|
|
|
|
ESC Application and Plan Review
|
Corrections
|
09/23/2024
|
09/20/2024
|
|
|
Gene Williams, P.E.
|
|
|
Miscellaneous Correction
Corrective Action Required
According to the plan, it would appear you are proposing more than clearing and grubbing. A land disturbance permit is appropriate if only clearing and grubbing are occurring. It does not cover mass grading of parking lot area, peripheral areas, embankment areas for bridge, or detention basins. Corrections required.
|
|
|
Miscellaneous Correction
Corrective Action Required
If performing activities beyond clearing and grubbing, see comments in the Final Development Plan applicant letter related to the grading of the detention basin, peripheral areas, embankment area for bridge, and the parking lot. There are several issues, including slopes that are too steep (i.e., greater than 3:1). In addition, original submittal showed curvilinear grading within the detention basin, but most recent submittal (i.e., this submittal) shows rectilinear grading which does not appear practical. Corrections needed if performing activities beyond clearing and grubbing.
|
|
|
Miscellaneous Correction
Corrective Action Required
If perfoming activities beyond clearing and grubbing, see comments in the Final Development Plan related to the detention basin and stormwater study. It is unclear whether this basin meets the requirements due to inconsistencies in the design of the outlet structure, questions on the outflow pipe size, and other issues related to the sanitary sewer and potential grading over the sanitary sewer to extend the fill to avoid conflict with the bridge. Corrections needed if performing activities beyond clearing and grubbing.
|
|
|
Miscellaneous Correction
Corrective Action Required
A SWPPP is required due to the disturbed area being greater than 1 acre. Correction required.
|
|
|
Miscellaneous Correction
Corrective Action Required
If you are needing a permit for land disturbance AND mass grading, a cost estimate for all sitework is required. The land disturbance permit fee is based on acreage, but is limited to clearing and grubbing. Mass grading is based on the cost estimate. Provide a signed and sealed cost estimate for the sitework shown on the Mass Grading/Erosion and Sediment Control Plan if applicable.
|
|
|
Miscellaneous Correction
Corrective Action Required
If your desire is to install storm lines and storm structures with a Mass Grading/Erosion and Sediment Control Plan, ensure there are plan and profile views of the storm lines and associated HGL for the design storm shown on the profile view, a revised detention basin detail sheet (see comments on Final Development Plan), along with a revised stormwater study which addresses the comments made on the Final Development Plan.
|
|
|
Miscellaneous Correction
Corrective Action Required
If the desire is to submit a land disturbance permit application for clearing and grubbing only, ensure there are no grading activities shown on the plan. If this is the desire, the cost estimate is not required since the land disturbance permit fee is based on acreage rather than cost estimate. A SWPPP, however, would still be required.
|
|
|
|