PRCOM20260499
Building Permit - Commercial
In Plan Review
MC PROPERTIES OF MO LLC
ALTERATION COMMERCIAL
FLORA FARMS - NEW ATS FEEDING THE EXISTING 225 AMP DISCONNECT / INSTALLING NEW 60KW GENERATOR
02/05/2026
08/17/2026
Locations
Contacts
MC PROPERTIES OF MO LLC, Address:704 NE LAKE POINTE DR  
REINHOLD ELECTRIC INC, Address:2511 LEMAY FERRY RD, Phone:(314) 631-1158  
REINHOLD ELECTRIC INC, Address:2511 LEMAY FERRY RD, Phone:(314) 631-1158  
  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Rejected 02/18/2026 02/18/2026
Joe Frogge
LC - MEP Subs
Corrective Action Required
02/18/2026

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (York Plumbing not licensed with us)
Fire Plan Review Rejected 02/18/2026 02/18/2026
Craig Hill
Misc
Corrective Action Required
02/18/2026

312.1 General. Vehicle impact protection required by this code shall be provided by posts that comply with Section 312.2 or by other approved physical barriers that comply with Section 312.3. Action Required: Provide impact protection for gas line and electric lines that run to the generator.
Building Plan Review Rejected 02/18/2026 02/12/2026
Joe Frogge
Misc
Corrective Action Required
02/12/2026

Generator must be installed per manufacturer's written instructions. Action required: Amend design to comply. See Note 4 on detail ADV-9760, sheet E-101.
Misc
Corrective Action Required
02/13/2026

Additional information required. Action required: Provide plot plat with dimensions to verify distances from building and property line. Generator, screening, and bollards to be shown fully dimensioned or to scale.
Zoning Review Rejected 02/18/2026 02/05/2026
Shannon McGuire
Miscellaneous Correction
Corrective Action Required
02/05/2026

All ground-mounted building equipment, including, but not limited to, HVAC and mechanical equipment, power transformers, back-up power generators, shall be fully screened from view from adjacent public streets and residential properties with landscaping, masonry screen walls, decorative fencing, or a combination thereof. Action required: Please provide a detailed description of how all ground-mounted equipment will be screened in accordance with Sec. 8.110. Include the type of screening (landscaping, masonry walls, decorative fencing, or combination), materials, height, and location. Screening must fully obstruct views from adjacent public streets and residential properties.
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
02/05/2026 Application Form APPLICATION
02/05/2026 Plans plans
02/05/2026 Photograph LOCATION
02/05/2026 Permit LOCATION
02/18/2026 Letter DS P/R Corrections Document
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home