Summary
PRCOM20254119
Building Permit - Commercial
In Plan Review
RED SUMMIT FAIR LLC
CHANGE OF TENANT
LASERAWAY LEE'S SUMMIT - CHANGE OF TENANT / RETAIL AND LASER HAIR REMOVAL - NO ARCHITECTURAL CHANGES - MEP ONLY
09/25/2025
04/05/2026
Locations
Contacts
RED SUMMIT FAIR LLC, Address:ONE E WASHINGTON ST STE 300  
  
EXPANSION@LASERAWAY.NET  
  
  
  
Shremshock Architects, Address:7775 Walton Parkway Suite 2540, Phone:(614) 455-0 Ext:150  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved 10/24/2025 10/23/2025
Craig Hill
Fire Plan Review Approved 10/07/2025 10/07/2025
Craig Hill
Building Plan Review Rejected 10/07/2025 10/06/2025
Joe Frogge
Gen - Plan submittal documents
Corrective Action Required
10/06/2025

Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted in two (2) or more sets with each application for a permit. A registered design professionaLee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted digitally with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri.l licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri. Action required: Submit plans with engineer's seal/signature.
IBC 1606.2 Design dead load - structural
Corrective Action Required
10/06/2025

2018 IBC 1606.2 Design dead load. For purposes of design, the actual weights of materials of construction and fixed service equipment shall be used. In the absence of definite information, values used shall be subject to the approval of the building official. Action required: Provide engineer’s report to verify that existing roof structure will support additional load.
Licensed Contractors Rejected 10/07/2025 10/06/2025
Joe Frogge
LC - General Contractor
Corrective Action Required
10/06/2025

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
10/06/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Alarm Plan Review Pending
Craig Hill
Sprinkler Plan Review Pending
Craig Hill
Building Plan Review Pending 10/24/2025
Joe Frogge
Gen - Plan submittal documents
Corrective Action Required
10/17/2025

Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted in two (2) or more sets with each application for a permit. A registered design professionaLee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted digitally with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri.l licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri. Action required: Submit plans with engineer's seal/signature.
IBC 1606.2 Design dead load - structural
Corrective Action Required
10/17/2025

2018 IBC 1606.2 Design dead load. For purposes of design, the actual weights of materials of construction and fixed service equipment shall be used. In the absence of definite information, values used shall be subject to the approval of the building official. Action required: Provide engineer’s report to verify that existing roof structure will support additional load.
Licensed Contractors Pending 10/24/2025
Joe Frogge
LC - General Contractor
Corrective Action Required
10/17/2025

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
10/17/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fees
Paid Fees Amount Paid Owing Date Paid
None $0.00 $0.00 $0.00
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
09/25/2025 Application Form APPLICATION
09/30/2025 Plans LA Lees Summit_ MO Elec-Mech Set
09/30/2025 Letter License Tax Bill
10/07/2025 Letter DS P/R Corrections Document
10/17/2025 Plans 250422 - Laseraway Lees Summit, MO - MEP S&S_ Rv1
10/17/2025 Letter Laseraway Lee's Summit, MO SMBH CU Letter SS
10/17/2025 Letter LSA Lee's Summit_revision letter
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home