Permit Application Status

PRCOM20253769


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20253769
Building Permit - Commercial
Issued
CWW ENTERPRISES LLC
NEW OTHER (COMMERCIAL)
CHARLIE'S CAR WASH - NEW VACUUMS AND EQUIPMENT BUILDING SERVING EXISTING CAR WASH
09/05/2025
10/21/2025
Locations
Contacts
James Ray - XLNT Contracting, Phone:(903) 335-8897  
XLNT Contracting LLC, Address:903 Interstate Highway 30 E  
AFC HEATING AND COOLING, Address:824 NW MAIN ST , Phone:(816) 347-8388  
ROZIER ELECTRIC, Address:1608 SW JEFFERSON ST, Phone:(816) 246-9000  
WHATEVER IT TAKES ELECTRICAL CONTRACTORS LLC (WITEC), Address:9709 E 56TH STREET, Phone:(816) 743-0770  
OLSSON , Address:7301 W 133RD ST STE 200, Phone:(913) 381-1170  
CWW ENTERPRISES LLC, Address:500 GRAVES BLVD  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 09/19/2025 10/21/2025
Joe Frogge
LC - General Contractor
Resolved
10/17/2025

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
LC - MEP Subs
Resolved
10/21/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Approved 09/19/2025 09/22/2025
Craig Hill
Building Plan Review Approved 09/19/2025 09/19/2025
Joe Frogge
Final Development Plan Review Approved 09/19/2025 09/19/2025
Daniel Fernandez
Fire Plan Review Approved 09/19/2025 09/18/2025
Craig Hill
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Other $900.00 $900.00 Paid 09/22/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Final Inspection - Commercial Pending
Underground Plumbing Inspection - Commercial Pending
Misc
Informational
11/18/2025
10-31-25 PS Partial inspection of 3/4" pex water line and 2" sanitary forced line at trench crossing parking lot east west at express bays. -Vac lines and irrigation west across drive -Vac lines from building to north stations 11/18/25 Tuesday JMJ Contractor installed 3/4" blue poly-waterline 35'.
Occupancy Inspection - Codes Commercial Pending
Occupancy Inspection - Planning Pending
Underground Plumbing Inspection - Commercial Partial 10/31/2025 10/31/2025 10/31/2025
Misc
Informational
10/31/2025
10-31-25 PS Partial inspection of 3/4" pex water line and 2" sanitary forced line at trench crossing parking lot east west at express bays.
Underground Electrical Inspection - Commercial Partial 11/4/2025 11/4/2025 11/04/2025
Misc
Informational
11/04/2025
From building across main drive to curb line
Miscellaneous Inspection Partial 11/7/2025 11/7/2025 11/07/2025
Misc
Informational
11/07/2025
11/07/25 Friday JMJ Contractor continued to excavating site to construct new building and utilities.
Underground Electrical Inspection - Commercial Partial 11/12/2025 11/12/2025 11/12/2025
Misc
Informational
11/04/2025
From building across main drive to curb line -Conduit for (18) vac stations
Underground Plumbing Inspection - Commercial Partial 11/13/2025 11/13/2025 11/13/2025
Misc
Informational
10/31/2025
10-31-25 PS Partial inspection of 3/4" pex water line and 2" sanitary forced line at trench crossing parking lot east west at express bays. -Vac lines and irrigation across drive
Underground Plumbing Inspection - Commercial Partial 11/14/2025 11/14/2025 11/14/2025
Misc
Informational
11/13/2025
10-31-25 PS Partial inspection of 3/4" pex water line and 2" sanitary forced line at trench crossing parking lot east west at express bays. -Vac lines and irrigation west across drive -Vac lines from building to north stations
Underground Electrical Inspection - Commercial Partial 11/14/2025 11/14/2025 11/14/2025
Misc
Informational
11/12/2025
From building across main drive to curb line -Conduit for (18) vac stations -Conduit from building to north vac stations
Water Line - Construction Inspection Partial 11/18/2025 11/18/2025 11/18/2025
Misc
Informational
11/18/2025
11/18/25 Tuesday JMJ (XLNT Contractor) Contractor installed approximately 35' of 3/4" PVC waterline along the NW corner of the building.
Underground Plumbing Inspection - Commercial Partial 11/18/2025 11/18/2025
Misc
Informational
11/14/2025
10-31-25 PS Partial inspection of 3/4" pex water line and 2" sanitary forced line at trench crossing parking lot east west at express bays. -Vac lines and irrigation west across drive -Vac lines from building to north stations 11/18/25 Tuesday JMJ Contractor installed 3/4" blue poly-waterline 35'.
Footing Inspection - Commercial Passed 11/19/2025 11/19/2025 11/19/2025
Misc
Informational
11/19/2025
Footing for vacuum structure Copper UFER
Underground Electrical Inspection - Commercial Partial 11/19/2025 11/19/2025 11/19/2025
Misc
Informational
11/14/2025
From building across main drive to curb line -Conduit for (18) vac stations -Conduit from building to north vac stations -Conduit 20' next to building to junction then tied into conduit across drive.
Piers/Caissons Inspection - Commercial Failed 12/8/2025 12/8/2025 12/08/2025
Misc
Corrective Action Required
12/08/2025
-Remove loose soil and water from piers. -Provide min 3” clearance to earth at rebar
Piers/Caissons Inspection - Commercial Passed 12/9/2025 12/9/2025 12/09/2025
Misc
Resolved
12/09/2025
-Remove loose soil and water from piers. -Provide min 3” clearance to earth at rebar
Pavement-Surface Partial 12/9/2025 12/9/2025 12/09/2025
Miscellaneous Correction
Informational
12/09/2025
12/09/25 Jamie S, Contractor is using existing AB3 and has installed wire mesh with hats. Approved to pour.
Pavement-Surface Partial 12/16/2025 12/16/2025 12/11/2025
Miscellaneous Correction
Informational
12/09/2025
12/09/25 Jamie S, Contractor is using existing AB3 and has installed wire mesh with hats. Approved to pour. 12/11/25 Thursday JMJ Contractor will pour 2' X 60' pad area behind curbs on the north side to encase junction boxes. Contractor will pour pier area on the West and East side of entrance to the detail garages 1 thru 4. Contractor plans to pour concrete 5' X 80' strip of concrete to fill excavation for newly installed utilities. Inspector informed contractor that white cure and blankets are required due to winter condition.
Underground Electrical Inspection - Commercial Passed 1/26/2026 1/26/2026 12/12/2025
Misc
Resolved
12/12/2025
From building across main drive to curb line -Conduit for (18) vac stations -Conduit from building to north vac stations -Conduit 20' next to building to junction then tied into conduit across drive.
Underslab Plumbing Inspection - Commercial Partial 12/12/2025
Misc
Corrective Action Required
12/12/2025
Sleeves and water line into building below grade
Water Line - Construction Inspection Partial 12/12/2025 12/12/2025 12/12/2025
Misc
Informational
11/18/2025
11/18/25 Tuesday JMJ (XLNT Contractor) Contractor installed approximately 35' of 3/4" PVC waterline along the NW corner of the building. 12/12/25 Friday JMJ (XLNT Contractor) Contractor install underground utilities and plumbing and backfill construction work for small building as-per project plans.
Concrete Walls and Columns Inspection Passed 12/19/2025 12/19/2025
Misc
Corrective Action Required
12/19/2025
INSPECTION OF CMU BUILDING STEEL APPROVED
All Rough Inspection - Commercial Passed 12/24/2025 12/23/2025 12/23/2025
Site Visit Partial 12/31/2025 12/31/2025 12/31/2025
Misc
Corrective Action Required
12/31/2025
12/31/25 PS No activity on site at inspection
Site Visit Partial 1/13/2026 1/13/2026 01/13/2026
Misc
Corrective Action Required
12/31/2025
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI
Site Visit Partial 1/16/2026 1/16/2026 01/16/2026
Misc
Corrective Action Required
01/13/2026
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI 1/16/25 PS Made site visit, no inspections for FEI today
Underslab Plumbing Inspection - Commercial Passed 1/28/2026 1/28/2026 01/28/2026
Misc
Resolved
01/28/2026
Sleeves and water line into building below grade
Underslab Electrical Inspection - Commercial Passed 1/28/2026 1/28/2026 01/28/2026
Site Visit Partial 1/28/2026 1/28/2026 01/28/2026
Misc
Corrective Action Required
01/16/2026
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI 1/16/25 PS Made site visit, no inspections for FEI today 1-28-26 PS Made site visit, no inspections for FEI today
Site Visit Partial 1/30/2026 1/30/2026 01/30/2026
Misc
Corrective Action Required
01/28/2026
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI 1/16/25 PS Made site visit, no inspections for FEI today 1-28-26 PS Made site visit, no inspections for FEI today 1/30/26 PS Made site visit, no inspections for FEI today
Site Visit Partial 1/30/2026 1/30/2026 01/30/2026
Misc
Corrective Action Required
01/30/2026
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI 1/16/25 PS Made site visit, no inspections for FEI today 1-28-26 PS Made site visit, no inspections for FEI today 1/30/26 PS Made site visit, no inspections for FEI today
Site Visit Partial 2/3/2026 2/3/2026 02/03/2026
Misc
Corrective Action Required
01/30/2026
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI 1/16/25 PS Made site visit, no inspections for FEI today 1-28-26 PS Made site visit, no inspections for FEI today 1/30/26 PS Made site visit, no inspections for FEI today 2/3/26 PS Made site visit, no inspections for FEI today
Site Visit Partial 2/24/2026 2/24/2026 02/24/2026
Misc
Corrective Action Required
02/03/2026
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI 1/16/25 PS Made site visit, no inspections for FEI today 1-28-26 PS Made site visit, no inspections for FEI today 1/30/26 PS Made site visit, no inspections for FEI today 2/3/26 PS Made site visit, no inspections for FEI today 2/24/26 PS Made site visit, no inspections for FEI today
Site Visit Partial 2/25/2026 2/25/2026 02/25/2026
Misc
Corrective Action Required
02/24/2026
12/31/25 PS No activity on site at inspection 1/13/25 PS Made site visit, contractors working on building construction, no inspections for FEI 1/16/25 PS Made site visit, no inspections for FEI today 1-28-26 PS Made site visit, no inspections for FEI today 1/30/26 PS Made site visit, no inspections for FEI today 2/3/26 PS Made site visit, no inspections for FEI today 2/24/26 PS Made site visit, no inspections for FEI today 2/25/26 PS Made site visit, no inspections for FEI
Occupancy Inspection - Engineering Passed 03/24/2026
Misc
Informational
03/24/2026
03/24/26 Tuesday JMJ All completed construct work inspected appears to meet specification for occupancy.
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home

*PLEASE NOTE - You must be logged in with your registered user account to view any documents related to your permit