Permit Application Status

PRCOM20251178


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20251178
Building Permit - Commercial
Issued
DOUGLAS STATION PARTNERS LLC
NEW MULTI-FAMILY
SLOAN APARTMENTS - NEW APARTMENT BUIDING
03/31/2025
10/15/2025
04/06/2025
Locations
Contacts
DOUGLAS STATION PARTNERS LLC, Address:8305 NE 89TH ST  
LEVEL BUILDERS LLC, Address:P O BOX 29145, Phone:(816) 541-4204  
Shane Turnbow - Level Builders, Address:3170 NE Carnegie, Suite 400, Phone:(816) 721-2747  
Polar Aire Heating & Cooling Service, Address:400 S. Kansas Ave, Phone:(913) 782-8238  
M & S ELECTRIC, Address:PO BOX 1147, Phone:(816) 427-5913  
PINNACLE PLUMBING COMPANY LLC, Address:P O BOX 2407, Phone:(913) 375-3783  
NSPJ ARCHITECTS, Address:3515 W 75TH ST, SUITE 201, Phone:(913) 831-1415 Ext:278  
KANSAS CITY TESTING & ENGINEERING, Address:1308 ADAMS STREET, Phone:(913) 321-8100  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved with Conditions 10/29/2024 04/16/2025
Mike Weisenborn
Miscellaneous Correction
Corrective Action Required
04/16/2025

This review includes all structures on site. Separate permits will be created for each structure at a later date. Action required: Comment is informational. 10/3/2024 - Acknowledged in letter.
Final Development Plan
Resolved
03/31/2025

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational. 10/3/2024 - Acknowledged in letter.
IBC 1704.2 Special Inspections
Resolved
11/05/2024

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections. 10/3/2024 - Acknowledged in letter.
Engineered truss package
Corrective Action Required
04/16/2025

Copies of the engineered truss package were not provided at the time of permit application. Action required: Comment is informational. Truss packages deferred per request. 10/3/2024 - Acknowledged in letter.
Health Dept Review (aquatic)
Resolved
03/31/2025

For the Health Department review of public pools contact Casey Elledge with the Jackson County Public Works Department, Environmental Services Division, at (816) 223-9769. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is informational. 10/3/2024 - Acknowledged in letter.
Health Dept Inspection (aquatic)
Resolved
03/31/2025

For the Health Department inspection of public pools contact Casey Elledge with the Jackson County Public Works Department, Environmental Health Division at (816) 223-9769. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is informational. 10/3/2024 - Acknowledged in letter.
Miscellaneous Correction
Corrective Action Required
04/02/2025

Vertical construction will not be permitted until released by the Fire Department. Paved access and live hydrants must be present adjacent to the structure.
Final Development Plan Review Approved 04/14/2025 04/08/2025
Mike Weisenborn
Fire Plan Review Approved 04/14/2025 04/01/2025
Joe Frogge
Fire Plan Review Approved 10/29/2024 10/29/2024
Craig Hill
Miscellaneous Correction
Corrective Action Required
03/24/2025

Hydrants and the base asphalt for the parking lots shall be in place before any vertical combustible construction.
Licensed Contractors Approved 10/29/2024 10/29/2024
Joe Frogge
Alarm Plan Review Pending
Craig Hill
Sprinkler Plan Review Pending
Craig Hill
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Multi-Family $14,953.81 $14,953.81 Paid 04/15/2025
Residential Excise Tax Fee $10,183.68 $10,183.68 Paid 04/15/2025
Water Tap Fee $27,200.00 $27,200.00 Paid 09/03/2025
Water Meter Fee $3,922.34 $3,922.34 Paid 09/03/2025
Sanitary Sewer Development Fee $15,995.00 $15,995.00 Paid 09/03/2025
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$75.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Piers/Caissons Inspection - Commercial Pending
Erosion Control Inspection Pending
Sewer Service Inspection Pending
Water Service Inspection Pending
Electrical Service Inspection Pending
Gas Piping Inspection - Commercial Pending
Gas Service Inspection - Commercial Pending
Above Ceiling Inspection Pending
All Rough Inspection - Commercial Pending
THIRD FLOOR
Corrective Action Required
03/25/2026
Approved
SECOND FLOOR
Corrective Action Required
03/25/2026
Approved
FIRST FLOOR
Corrective Action Required
03/25/2026
Units and corridor approved
Rated Assembly Inspection Pending
THIRD FLOOR
Corrective Action Required
04/02/2026
Complete
SECOND FLOOR
Corrective Action Required
04/02/2026
Complete
FIRST FLOOR
Corrective Action Required
04/02/2026
-Screw pattern and tape at pre rock ok -RC at units approved -Screw pattern at units approved
Underslab Electrical Inspection - Commercial Pending 7/15/2025
Footing Inspection - Commercial Passed 6/25/2025 6/25/2025 06/25/2025
Footing Inspection - Commercial Passed 7/9/2025 07/09/2025
Underslab Plumbing Inspection - Commercial Partial 7/22/2025 7/22/2025 07/22/2025
Misc
Corrective Action Required
07/22/2025
Subgrade main plumbing line OK to cover
Underslab Plumbing Inspection - Commercial Passed 7/24/2025 7/24/2025 07/24/2025
Misc
Resolved
07/24/2025
Subgrade main plumbing line OK to cover
All Rough Inspection - Commercial Partial 2/25/2026 2/25/2026 02/25/2026
THIRD FLOOR
Corrective Action Required
02/25/2026
Pre rock behind tubs ok to cover
SECOND FLOOR
Corrective Action Required
02/25/2026
Pre rock behind tubs ok to cover
FIRST FLOOR
Corrective Action Required
02/25/2026
Pre rock behind tubs ok to cover
Rated Assembly Inspection Partial 3/5/2026 3/5/2026 03/05/2026
Misc
Corrective Action Required
03/05/2026
- 302,303,306 Block out top plate of chase at separation wall. Inspected 3rd Floor Only all other units ready to tape.
Rated Assembly Inspection Partial 3/6/2026 3/6/2026 03/06/2026
Misc
Resolved
03/06/2026
- 302,303,306 Block out top plate of chase at separation wall. Inspected 3rd Floor Only all other units ready to tape.
THIRD FLOOR
Corrective Action Required
03/06/2026
-Screw pattern at pre rock ok
SECOND FLOOR
Corrective Action Required
03/06/2026
FIRST FLOOR
Corrective Action Required
03/06/2026
Rated Assembly Inspection Partial 3/9/2026 3/9/2026 03/09/2026
THIRD FLOOR
Corrective Action Required
03/06/2026
-Screw pattern and tape at pre rock ok
SECOND FLOOR
Corrective Action Required
03/06/2026
-Screw pattern at pre rock ok
FIRST FLOOR
Corrective Action Required
03/06/2026
Rated Assembly Inspection Partial 3/10/2026 3/10/2026 03/10/2026
THIRD FLOOR
Corrective Action Required
03/09/2026
-Screw pattern and tape at pre rock ok
SECOND FLOOR
Corrective Action Required
03/09/2026
-Screw pattern at pre rock ok
FIRST FLOOR
Corrective Action Required
03/09/2026
-Screw pattern at pre rock ok
All Rough Inspection - Commercial Not Ready 3/11/2026 3/11/2026 03/11/2026
THIRD FLOOR
Corrective Action Required
02/25/2026
10/11/26 NOT READY, FEE ASSESSED. INSPECTION INCOMPLETE -Install vertical fireblocking at max 10' intervals at all party walls 301-Seal penetration at dead space, support dryer duct 4' oc max 302-Support dryer duct 4' oc max, strap top plate at back wall 303-Support dryer duct 4' oc max, strap top plate at back wall
SECOND FLOOR
Corrective Action Required
02/25/2026
Pre rock behind tubs ok to cover
FIRST FLOOR
Corrective Action Required
02/25/2026
Pre rock behind tubs ok to cover
Rated Assembly Inspection Partial 3/11/2026 3/11/2026 03/11/2026
THIRD FLOOR
Corrective Action Required
03/10/2026
-Screw pattern and tape at pre rock ok
SECOND FLOOR
Corrective Action Required
03/10/2026
-Screw pattern and tape at pre rock ok
FIRST FLOOR
Corrective Action Required
03/10/2026
-Screw pattern at pre rock ok
All Rough Inspection - Commercial Partial 3/12/2026 3/12/2026 03/12/2026
THIRD FLOOR
Corrective Action Required
03/11/2026
Approved
SECOND FLOOR
Corrective Action Required
03/11/2026
Pre rock behind tubs ok to cover
FIRST FLOOR
Corrective Action Required
03/11/2026
Pre rock behind tubs ok to cover
Rated Assembly Inspection Partial 3/12/2026 3/12/2026 03/12/2026
THIRD FLOOR
Corrective Action Required
03/11/2026
-Screw pattern and tape at pre rock ok -RC at units approved
SECOND FLOOR
Corrective Action Required
03/11/2026
-Screw pattern and tape at pre rock ok
FIRST FLOOR
Corrective Action Required
03/11/2026
-Screw pattern and tape at pre rock ok
All Rough Inspection - Commercial Partial 3/17/2026 3/17/2026 03/17/2026
THIRD FLOOR
Corrective Action Required
03/12/2026
Approved
SECOND FLOOR
Corrective Action Required
03/12/2026
Pre rock behind tubs ok to cover 208, 202, 206, 204- Nail T stud at overbored stud 12" oc min 203-Add stud 16" oc max at exterior wall/party wall
FIRST FLOOR
Corrective Action Required
03/12/2026
Pre rock behind tubs ok to cover
All Rough Inspection - Commercial Partial 3/20/2026 3/20/2026 03/20/2026
THIRD FLOOR
Corrective Action Required
03/17/2026
Approved
SECOND FLOOR
Corrective Action Required
03/17/2026
Approved
FIRST FLOOR
Corrective Action Required
03/17/2026
Pre rock behind tubs ok to cover
Rated Assembly Inspection Partial 3/20/2026 3/20/2026 03/20/2026
THIRD FLOOR
Corrective Action Required
03/12/2026
-Screw pattern and tape at pre rock ok -RC at units approved
SECOND FLOOR
Corrective Action Required
03/12/2026
-Screw pattern and tape at pre rock ok -RC at units approved
FIRST FLOOR
Corrective Action Required
03/12/2026
-Screw pattern and tape at pre rock ok
All Rough Inspection - Commercial Failed 3/23/2026 3/23/2026 03/23/2026
THIRD FLOOR
Corrective Action Required
03/20/2026
Approved
SECOND FLOOR
Corrective Action Required
03/20/2026
Approved
FIRST FLOOR
Corrective Action Required
03/20/2026
Pre rock behind tubs ok to cover 104-seal microduct 105-Seal microduct penetration, add stud at exterior wall/party wall, support dryer duct 48" oc 103-Seal microduct penetration, add stud at exterior wall/party wall, support dryer duct 48" oc 102-Seal microduct penetration 107-Seal microduct penetration 108-Seal microduct penetration 101-Seal microduct penetration, strap overbored top plate at micro duct, secure SER in joist space
Rated Assembly Inspection Partial 3/24/2026 3/24/2026 03/24/2026
THIRD FLOOR
Corrective Action Required
03/20/2026
-Screw pattern and tape at pre rock ok -RC at units approved -Screw pattern approved
SECOND FLOOR
Corrective Action Required
03/20/2026
-Screw pattern and tape at pre rock ok -RC at units approved
FIRST FLOOR
Corrective Action Required
03/20/2026
-Screw pattern and tape at pre rock ok
Rated Assembly Inspection Partial 3/25/2026 03/25/2026
THIRD FLOOR
Corrective Action Required
03/24/2026
-Screw pattern and tape at pre rock ok -RC at units approved -Screw pattern approved
SECOND FLOOR
Corrective Action Required
03/24/2026
-Screw pattern and tape at pre rock ok -RC at units approved
FIRST FLOOR
Corrective Action Required
03/24/2026
-Screw pattern and tape at pre rock ok -RC at units approved
All Rough Inspection - Commercial Partial 03/25/2026
THIRD FLOOR
Corrective Action Required
03/23/2026
Approved
SECOND FLOOR
Corrective Action Required
03/23/2026
Approved
FIRST FLOOR
Corrective Action Required
03/23/2026
Units and corridor approved
Rated Assembly Inspection Partial 3/26/2026 3/26/2026 03/26/2026
THIRD FLOOR
Corrective Action Required
03/25/2026
-Screw pattern and tape at pre rock ok -RC at units approved -Screw pattern approved
SECOND FLOOR
Corrective Action Required
03/25/2026
-Screw pattern and tape at pre rock ok -RC at units approved -Screw pattern approved
FIRST FLOOR
Corrective Action Required
03/25/2026
-Screw pattern and tape at pre rock ok -RC at units approved
Rated Assembly Inspection Partial 4/2/2026 4/2/2026 04/02/2026
THIRD FLOOR
Corrective Action Required
03/26/2026
Complete
SECOND FLOOR
Corrective Action Required
03/26/2026
Complete
FIRST FLOOR
Corrective Action Required
03/26/2026
-Screw pattern and tape at pre rock ok -RC at units approved -Screw pattern at units approved
Documents & Images
Date Uploaded File Type Document Name
04/15/2025 Receipt Receipt for transaction: 2025-002334
04/16/2025 Letter DS Building Permit
10/29/2024 Approved Plans Approved construction plans
06/25/2025 Letter INSPECTION SUMMARY
07/09/2025 Letter INSPECTION SUMMARY
07/24/2025 Letter INSPECTION SUMMARY
07/24/2025 Letter INSPECTION SUMMARY
09/03/2025 Receipt Receipt for transaction:2025-006857
02/25/2026 Letter INSPECTION SUMMARY
03/05/2026 Letter INSPECTION SUMMARY
03/06/2026 Letter INSPECTION SUMMARY
03/09/2026 Letter INSPECTION SUMMARY
03/10/2026 Letter INSPECTION SUMMARY
03/11/2026 Letter INSPECTION SUMMARY
03/11/2026 Letter INSPECTION SUMMARY
03/12/2026 Letter INSPECTION SUMMARY
03/12/2026 Letter INSPECTION SUMMARY
03/17/2026 Letter INSPECTION SUMMARY
03/20/2026 Letter INSPECTION SUMMARY
03/20/2026 Letter INSPECTION SUMMARY
03/23/2026 Letter INSPECTION SUMMARY
03/24/2026 Letter INSPECTION SUMMARY
03/25/2026 Letter INSPECTION SUMMARY
03/25/2026 Letter INSPECTION SUMMARY
03/26/2026 Letter INSPECTION SUMMARY
04/02/2026 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home