| Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
|
Erosion Control Inspection
|
Partial
|
|
|
08/20/2025
|
|
|
Misc
|
|
Storm Sewer Construction Inspection
|
Partial
|
|
8/22/2025
|
08/22/2025
|
|
|
Misc
|
|
Erosion Control Inspection
|
Partial
|
|
8/26/2025
|
08/26/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
8/26/2025
|
08/26/2025
|
|
|
Misc
|
|
Storm Sewer Construction Inspection
|
Partial
|
|
8/26/2025
|
08/26/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
8/28/2025
|
8/28/2025
|
08/28/2025
|
|
|
Misc
|
|
Sanitary Sewer Construction Inspection
|
Partial
|
8/28/2025
|
8/28/2025
|
08/28/2025
|
|
|
Misc
|
|
Storm Sewer Construction Inspection
|
Partial
|
8/28/2025
|
8/28/2025
|
08/28/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
9/8/2025
|
09/08/2025
|
|
|
Misc
|
|
Underground Electrical Inspection - Commercial
|
Partial
|
9/10/2025
|
9/10/2025
|
09/10/2025
|
|
|
Misc
|
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
9/11/2025
|
09/11/2025
|
|
|
Misc
|
|
Erosion Control Inspection
|
Partial
|
9/15/2025
|
9/15/2025
|
09/15/2025
|
|
|
Misc
|
|
Water Line - Construction Inspection
|
Partial
|
9/15/2025
|
9/15/2025
|
09/15/2025
|
|
|
Misc
|
|
Pavement-Aggregate Base
|
Partial
|
9/15/2025
|
9/15/2025
|
09/15/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
9/23/2025
|
09/23/2025
|
|
|
Misc
|
|
Water Line - Construction Inspection
|
Partial
|
9/22/2025
|
9/22/2025
|
09/23/2025
|
|
|
Misc
|
|
Erosion Control Inspection
|
Partial
|
9/22/2025
|
9/22/2025
|
09/23/2025
|
|
|
Misc
|
|
Footing Inspection - Commercial
|
Failed
|
10/1/2025
|
10/1/2025
|
10/01/2025
|
|
|
Misc
Corrective Action Required
|
|
Site Visit
|
Partial
|
10/1/2025
|
10/1/2025
|
10/01/2025
|
|
|
Misc
|
|
Footing Inspection - Commercial
|
Passed
|
|
10/1/2025
|
10/01/2025
|
|
|
Misc
|
|
Piers/Caissons Inspection - Commercial
|
Partial
|
10/2/2025
|
10/2/2025
|
10/02/2025
|
|
|
Misc
|
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
10/9/2025
|
10/9/2025
|
10/09/2025
|
|
|
Misc
|
|
Erosion Control Inspection
|
Failed
|
|
10/9/2025
|
10/09/2025
|
|
|
Misc
|
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
10/10/2025
|
10/10/2025
|
10/10/2025
|
|
|
Misc
|
|
Erosion Control Inspection
|
Partial
|
10/13/2025
|
10/13/2025
|
10/13/2025
|
|
|
Misc
|
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
10/13/2025
|
10/13/2025
|
10/13/2025
|
|
|
Misc
|
|
Erosion Control Inspection
|
Failed
|
|
10/14/2025
|
10/14/2025
|
|
|
Misc
|
|
Underslab Electrical Inspection - Commercial
|
Passed
|
10/16/2025
|
10/16/2025
|
10/16/2025
|
|
Underground Electrical Inspection - Commercial
|
Partial
|
10/29/2025
|
10/29/2025
|
10/29/2025
|
|
|
Misc
|
|
Water Line - Construction Inspection
|
Partial
|
|
10/30/2025
|
10/30/2025
|
|
|
Misc
|
|
Underground Electrical Inspection - Commercial
|
Partial
|
10/30/2025
|
10/30/2025
|
10/30/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
11/6/2025
|
11/06/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
11/7/2025
|
11/07/2025
|
|
|
Misc
|
|
Rough Electrical Inspection - Commercial
|
Partial
|
11/10/2025
|
11/10/2025
|
11/10/2025
|
|
|
Misc
|
|
All Rough Inspection - Commercial
|
Partial
|
11/10/2025
|
11/10/2025
|
11/10/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
11/12/2025
|
11/12/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
11/12/2025
|
11/12/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
11/13/2025
|
11/13/2025
|
|
|
Misc
|
|
Underground Electrical Inspection - Commercial
|
Partial
|
11/14/2025
|
11/14/2025
|
11/14/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
11/18/2025
|
11/18/2025
|
|
|
Misc
|
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
11/19/2025
|
11/19/2025
|
11/19/2025
|
|
|
Misc
Corrective Action Required
|
|
Site Visit
|
Partial
|
|
11/20/2025
|
11/20/2025
|
|
|
Misc
|
|
Pavement-Surface
|
Partial
|
|
11/26/2025
|
11/26/2025
|
|
|
Misc
|
|
All Rough Inspection - Commercial
|
Failed
|
12/2/2025
|
12/2/2025
|
12/02/2025
|
|
|
Misc
Corrective Action Required
|
|
Footing Inspection - Commercial
|
Partial
|
12/3/2025
|
12/3/2025
|
12/03/2025
|
|
|
Misc
|
|
Footing Inspection - Commercial
|
Partial
|
12/4/2025
|
12/4/2025
|
12/04/2025
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
12/4/2025
|
12/04/2025
|
|
|
Misc
|
|
Gas Service Inspection - Commercial
|
Passed
|
12/9/2025
|
12/9/2025
|
12/09/2025
|
|
In-wall Inspection
|
Passed
|
|
12/9/2025
|
12/09/2025
|
|
|
Misc
|
|
Erosion Control Inspection
|
Failed
|
|
12/10/2025
|
12/10/2025
|
|
|
Misc
|
|
Footing Inspection - Commercial
|
Partial
|
12/11/2025
|
12/11/2025
|
12/11/2025
|
|
|
Misc
|
|
Underground Electrical Inspection - Commercial
|
Partial
|
12/12/2025
|
12/12/2025
|
12/12/2025
|
|
|
Misc
|
|
Piers/Caissons Inspection - Commercial
|
Failed
|
12/12/2025
|
12/12/2025
|
12/12/2025
|
|
|
Miscellaneous Correction
Corrective Action Required
|
|
Sanitary Sewer Construction Inspection
|
Passed
|
|
12/16/2025
|
12/16/2025
|
|
|
Misc
|
|
Pavement-Aggregate Base
|
Partial
|
|
12/18/2025
|
12/18/2025
|
|
|
Misc
Corrective Action Required
|
|
Pavement-Aggregate Base
|
Passed
|
|
12/18/2025
|
12/18/2025
|
|
|
Misc
|
|
Pavement-Curb Construction
|
Partial
|
|
12/18/2025
|
12/18/2025
|
|
|
Misc
Corrective Action Required
|
|
Underground Plumbing Inspection - Commercial
|
Partial
|
|
12/23/2025
|
12/23/2025
|
|
|
Misc
|
|
Pavement-Stabilized Subgrade
|
Passed
|
|
12/27/2025
|
12/27/2025
|
|
Pavement-Stabilized Subgrade
|
Passed
|
|
12/27/2025
|
12/27/2025
|
|
Pavement-Surface
|
Partial
|
|
12/27/2025
|
12/27/2025
|
|
|
Misc
|
|
Pavement-Proof Roll
|
Passed
|
|
12/27/2025
|
12/27/2025
|
|
Pavement-Curb Construction
|
Partial
|
|
12/27/2025
|
12/27/2025
|
|
|
Misc
Corrective Action Required
|
|
Above Ceiling Inspection
|
Partial
|
12/31/2025
|
12/31/2025
|
12/31/2025
|
|
|
Misc
|
|
Hood/Duct Inspection
|
Partial
|
12/31/2025
|
12/31/2025
|
12/31/2025
|
|
|
Miscellaneous Correction
Corrective Action Required
|
|
Hood/Duct Inspection
|
Partial
|
1/5/2026
|
1/5/2026
|
01/05/2026
|
|
|
Miscellaneous Correction
Corrective Action Required
|
|
Sanitary Sewer Construction Inspection
|
Passed
|
|
1/8/2026
|
01/08/2026
|
|
|
Misc
|
|
Water Line - Construction Inspection
|
Partial
|
|
1/8/2026
|
01/08/2026
|
|
|
Misc
|
|
Pavement-Curb Construction
|
Partial
|
|
1/14/2026
|
01/14/2026
|
|
|
Misc
Corrective Action Required
|
|
Pavement-Surface
|
Partial
|
|
1/14/2026
|
01/14/2026
|
|
|
Misc
|
|
Above Ceiling Inspection
|
Passed
|
1/16/2026
|
1/16/2026
|
01/16/2026
|
|
|
Misc
|
|
Water Line - Hydrostatic Test
|
Passed
|
1/15/2026 (9:00)
|
1/15/2026
|
01/28/2026
|
|
|
Misc
Corrective Action Required
|
|
Electrical Service Inspection
|
Passed
|
1/29/2026
|
1/29/2026
|
01/29/2026
|
|
Site Visit
|
Partial
|
|
1/30/2026
|
01/30/2026
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
2/2/2026
|
02/02/2026
|
|
|
Misc
|
|
Storm Sewer Construction Inspection
|
Passed
|
|
2/2/2026
|
02/02/2026
|
|
|
Misc
|
|
Storm Sewer Construction Inspection
|
Passed
|
|
2/2/2026
|
02/02/2026
|
|
Water Line - Coliform Test 1
|
Passed
|
|
2/2/2026
|
02/02/2026
|
|
Water Line - Coliform Test 2
|
Passed
|
|
2/2/2026
|
02/02/2026
|
|
|
Misc
Corrective Action Required
|
|
Water Line - Hydrostatic Test
|
Passed
|
|
2/2/2026
|
02/02/2026
|
|
|
Misc
Corrective Action Required
|
|
Water Line - Coliform Test 1
|
Passed
|
|
2/2/2026
|
02/02/2026
|
|
Water Line - Coliform Test 2
|
Passed
|
|
2/2/2026
|
02/02/2026
|
|
Piers/Caissons Inspection - Commercial
|
Failed
|
|
2/3/2026
|
02/03/2026
|
|
|
Misc
|
|
|
Misc
Corrective Action Required
|
|
Piers/Caissons Inspection - Commercial
|
Passed
|
2/4/2026
|
2/4/2026
|
02/04/2026
|
|
|
Misc
|
|
|
Misc
|
|
Site Visit
|
Partial
|
|
2/6/2026
|
02/06/2026
|
|
|
Misc
|
|
Footing Inspection - Commercial
|
Passed
|
|
2/10/2026
|
02/10/2026
|
|
|
Misc
|
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
12/23/2025
|
12/23/2025
|
02/10/2026
|
|
|
Misc
Corrective Action Required
|
|
All Rough Inspection - Commercial
|
Passed
|
2/10/2026
|
2/10/2026
|
02/10/2026
|
|
|
Misc
Corrective Action Required
|
|
Hood/Duct Inspection
|
Passed
|
|
2/10/2026
|
02/10/2026
|
|
|
Miscellaneous Correction
|
|
Water Line - Construction Inspection
|
Passed
|
|
|
02/10/2026
|
|
|
Misc
|
|
Water Line - Hydrostatic Test
|
Passed
|
|
|
02/10/2026
|
|
|
Misc
|
|
Underground Electrical Inspection - Commercial
|
Passed
|
2/12/2026
|
2/12/2026
|
02/12/2026
|
|
|
Misc
|
|
Water Line - Coliform Test 1
|
Passed
|
|
|
02/17/2026
|
|
Water Line - Coliform Test 2
|
Passed
|
|
|
02/17/2026
|
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
|
2/17/2026
|
02/17/2026
|
|
|
Misc
Corrective Action Required
|
|
Occupancy Inspection - Planning
|
Temporary C of O
|
|
2/17/2026
|
02/17/2026
|
|
|
|
|
Occupancy Inspection - Water Utilities
|
Passed
|
|
2/17/2026
|
02/17/2026
|
|
Occupancy Inspection - Codes Commercial
|
Ready for Temp CO
|
|
2/17/2026
|
02/17/2026
|
|
|
Misc
Corrective Action Required
|
|
Grading/Excavation/Fill Inspection
|
Passed
|
|
|
02/19/2026
|
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
|
2/23/2026
|
02/19/2026
|
|
|
Misc
Corrective Action Required
|
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
|
|
02/20/2026
|
|
|
Misc
Corrective Action Required
|
|
Alarm Test
|
Passed
|
|
2/17/2026
|
02/23/2026
|
|
Alternate Protection Systems Inspection
|
Passed
|
|
2/17/2026
|
02/23/2026
|
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
2/5/2026
|
02/23/2026
|
|
Sprinkler - Flow Test
|
Passed
|
|
2/23/2026
|
02/23/2026
|
|
Occupancy Inspection - Fire
|
Passed
|
|
2/23/2026
|
02/23/2026
|
|
Occupancy Inspection - Engineering
|
Passed
|
|
|
02/23/2026
|
|
|
Misc
Corrective Action Required
|
|
Occupancy Inspection - Planning
|
Passed
|
|
2/23/2026
|
02/23/2026
|
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
|
2/23/2026
|
02/23/2026
|
|
|
Misc
|