Permit Application Status

PRCOM20236273


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20236273
Building Permit - Commercial
Final Completion
NEW OTHER (COMMERCIAL)
installing four power pedestals and 10 dedicated circuits for pop up tents west of field five
11/29/2023
11/29/2023
04/18/2024
Locations
Contacts
WESTHUES ELECTRIC INC, Address:PO BOX 18220, Phone:(816) 356-5223  
KEVIN@WESTHUES.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/29/2023 11/29/2023
Brandon Kalwei
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Other $50.00 $50.00 Paid 11/29/2023
9110078-Additional Permit Fee $50.00 $50.00 Paid 11/29/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Rough Electrical Inspection - Commercial Passed 11/30/2023
Final Electrical Inspection - Commercial Passed 11/30/2023
Misc
Informational
11/30/2023
-Circuits16-22, 26-32, 36,38. in panel P1 for pop up tent receptacles west of field 5
Final Inspection - Commercial Passed 11/30/2023 11/30/2023 11/30/2023
Misc
Informational
11/30/2023
-Circuits16-22, 26-32, 36,38. in panel P1 for pop up tent receptacles west of field 5
Documents & Images
Date Uploaded File Type Document Name
11/29/2023 Application Form APPLICATION
11/29/2023 Receipt Receipt for transaction:2023-008769
11/29/2023 Letter DS Building Permit
11/30/2023 Letter INSPECTION SUMMARY
11/30/2023 Letter INSPECTION SUMMARY
11/30/2023 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home