Footing Inspection - Commercial
|
Partial
|
11/9/2021 (1:00)
|
11/9/2021
|
11/09/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/10/2021 (11:00)
|
11/10/2021
|
11/10/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
11/11/2021
|
11/11/2021
|
11/11/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
|
11/12/2021
|
11/12/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/12/2021
|
11/12/2021
|
11/12/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/15/2021 (1:00)
|
11/15/2021
|
11/15/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/16/2021 (11:00)
|
11/16/2021
|
11/16/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/17/2021 (1:00)
|
11/17/2021
|
11/17/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/18/2021 (1:00)
|
11/18/2021
|
11/18/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/19/2021 (1:00)
|
11/19/2021
|
11/19/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
11/22/2021
|
11/22/2021
|
11/22/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/22/2021
|
11/22/2021
|
11/22/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/24/2021 (8:00)
|
11/24/2021
|
11/24/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Foundation Inspection - Commercial
|
Partial
|
|
11/29/2021
|
11/29/2021
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/29/2021 (11:15)
|
11/29/2021
|
11/29/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/30/2021 (11:00)
|
11/30/2021
|
11/30/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
12/1/2021
|
12/1/2021
|
12/01/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/1/2021 (11:00)
|
12/1/2021
|
12/01/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
12/2/2021
|
12/2/2021
|
12/02/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/3/2021 (11:00)
|
12/3/2021
|
12/03/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/6/2021 (11:00)
|
12/6/2021
|
12/06/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/7/2021 (11:00)
|
12/7/2021
|
12/07/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/8/2021 (11:15)
|
12/8/2021
|
12/08/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/9/2021 (11:00)
|
12/9/2021
|
12/09/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
|
12/10/2021
|
12/10/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/10/2021 (11:15)
|
12/10/2021
|
12/10/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Partial
|
12/13/2021
|
12/13/2021
|
12/13/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
|
12/13/2021
|
12/13/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
|
12/15/2021
|
12/15/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
12/21/2021
|
12/21/2021
|
12/21/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
|
12/21/2021
|
12/21/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Partial
|
12/21/2021
|
12/21/2021
|
12/21/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Partial
|
12/27/2021
|
12/27/2021
|
12/27/2021
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|