Summary
PRCOM20215245
Building Permit - Commercial
Closed
PARTIAL COMMERCIAL
FOUNDATION AND UNDERSLAB FOR APARTMENT BUILDING **THIS PERMIT INCLUDES 1 STORY FRAMING BUT NO INSPECTIONS UNTIL WATER INFRASTRUCTURE IS FULLY TESTED AND APPROVED. ****INSPECTIONS COMPLETED UNDER PERMIT PRCOM20213548
10/07/2021
11/03/2021
12/15/2023
Locations
Contacts
BRINKMANN CONSTRUCTORS, Address:16650 CHESTERFIELD GROVE RD, Phone:(636) 537-9700  
nwintjen@brinkmannconstructors.com, Address:nwintjen@brinkmannconstructors.com  
LYNN ELECTRIC & COMMUNICATIONS INC, Address:725 N 2ND ST STE K, Phone:(785) 843-5709  
MILLER PLUMBING CO, Address:PO BOX 393 , Phone:(913) 851-1333  
CFS ENGINEERS, Address:1421 EAST 104TH STREET STE 100, Phone:(816) 333-4477  
TRI Architects, Address:9812 Manchester rd, Phone:(314) 395-9750  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 10/07/2021 10/07/2021
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Partial Commercial $2,018.50 $2,018.50 Paid 10/13/2021
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Commercial Not Ready 11/9/2021 11/9/2021 11/09/2021
Misc
Corrective Action Required
11/09/2021
NO UNDERSLAB PLUMBING READY FOR INSPECTION Michael Harkins 11/09/2021 9:22 AM
Underslab Plumbing Inspection - Commercial Partial 11/16/2021 11/16/2021 11/16/2021
Misc
Informational
11/16/2021
- 6" MAIN TRUNK RUNNING WEST TO EAST TO MAIN CAP -
Underslab Plumbing Inspection - Commercial Partial 11/23/2021 11/23/2021 11/23/2021
Misc
Informational
11/16/2021
- 6" MAIN TRUNK RUNNING WEST TO EAST TO MAIN CAP SOUTH WING - - 6" MAIN TRUNK SOUTH TO NORTH IN WEST WING -
Footing Inspection - Commercial Partial 12/16/2021 12/16/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/16/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT -
Footing Inspection - Commercial Partial 12/20/2021 (1:00) 12/20/2021 12/20/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/16/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA C 50' FOOTING NORTH EXTERIOR WALL -
Footing Inspection - Commercial Partial 12/21/2021 12/21/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/20/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA C 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA C 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL -
Footing Inspection - Commercial Partial 12/22/2021 (1:00) 12/22/2021 12/22/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/21/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA C 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA C 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA B, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL -
Footing Inspection - Commercial Partial 12/27/2021 12/27/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/22/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM -
Footing Inspection - Commercial Partial 12/29/2021 12/29/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/27/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST -
Foundation Inspection - Commercial Partial 12/30/2021 12/30/2021
Misc
Informational
12/30/2021
- 12/30/21 FOUNDATION WALL @ ELEVATOR PIT PER PLAN -
Footing Inspection - Commercial Partial 12/30/2021 (9:30) 12/30/2021 12/30/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/29/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST - - 12/30/21 BLDG 1 AREA B 65' SOUTH FOOTING, AREA C EAST FOOTING 75' -
Footing Inspection - Commercial Partial 1/4/2022 01/04/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/30/2021
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST - - 12/30/21 BLDG 1 AREA B 65' SOUTH FOOTING, AREA C EAST FOOTING 75' - - 01/04/22 BLDG 1 AREA B 100' EAST EXTERIOR FOOTING -
Underslab Plumbing Inspection - Commercial Partial 1/4/2022 01/04/2022
Misc
Informational
11/23/2021
- 6" MAIN TRUNK RUNNING WEST TO EAST TO MAIN CAP SOUTH WING - - 6" MAIN TRUNK SOUTH TO NORTH IN WEST WING - - UNDERSLAB BLDG 1 AREA D -
Footing Inspection - Commercial Partial 1/10/2022 (11:00) 1/10/2022 01/10/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/04/2022
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST - - 12/30/21 BLDG 1 AREA B 65' SOUTH FOOTING, AREA C EAST FOOTING 75' - - 01/04/22 BLDG 1 AREA B 100' EAST EXTERIOR FOOTING - - 01/10/22 BLDG 1 AREA A NORTH FOOTING, 85' FOOTING WEST WALL, UFER LOCATED NW CORNER -
Footing Inspection - Commercial Partial 1/11/2022 (11:00) 1/11/2022 01/11/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/10/2022
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST - - 12/30/21 BLDG 1 AREA B 65' SOUTH FOOTING, AREA C EAST FOOTING 75' - - 01/04/22 BLDG 1 AREA B 100' EAST EXTERIOR FOOTING - - 01/10/22 BLDG 1 AREA A NORTH FOOTING, 85' FOOTING WEST WALL, UFER LOCATED NW CORNER - - 1/11/22 BLDG 1 AREA A 60' WEST FOOTING, AREA B 40' SOUTH FOOTING, 2 PADS AT ELEVATOR PIT, 9 PADS NORTH OF MAIN TRUNK -
Footing Inspection - Commercial Partial 1/12/2022 (11:15) 1/12/2022 01/12/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/11/2022
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST - - 12/30/21 BLDG 1 AREA B 65' SOUTH FOOTING, AREA C EAST FOOTING 75' - - 01/04/22 BLDG 1 AREA B 100' EAST EXTERIOR FOOTING - - 01/10/22 BLDG 1 AREA A NORTH FOOTING, 85' FOOTING WEST WALL, UFER LOCATED NW CORNER - - 1/11/22 BLDG 1 AREA A 60' WEST FOOTING, AREA B 40' SOUTH FOOTING, 2 PADS AT ELEVATOR PIT, 9 PADS NORTH OF MAIN TRUNK - - 1/12/22 BLDG 1 AREA B WEST FOOTING 55', AREA A & B 14 PADS AT MAIN TRUNK, GRADE BEAMS AREA D -
Underslab Electrical Inspection - Commercial Partial 1/12/2022 01/12/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/12/2022
- 1/12/22 BLDG 1 AREA D CONDUIT FOR KITCHEN ISLANDS IN 7 UNITS -
Footing Inspection - Commercial Partial 1/13/2022 (11:00) 1/13/2022 01/13/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/12/2022
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST - - 12/30/21 BLDG 1 AREA B 65' SOUTH FOOTING, AREA C EAST FOOTING 75' - - 01/04/22 BLDG 1 AREA B 100' EAST EXTERIOR FOOTING - - 01/10/22 BLDG 1 AREA A NORTH FOOTING, 85' FOOTING WEST WALL, UFER LOCATED NW CORNER - - 1/11/22 BLDG 1 AREA A 60' WEST FOOTING, AREA B 40' SOUTH FOOTING, 2 PADS AT ELEVATOR PIT, 9 PADS NORTH OF MAIN TRUNK - - 1/12/22 BLDG 1 AREA B WEST FOOTING 55', AREA A & B 14 PADS AT MAIN TRUNK, GRADE BEAMS AREA D - - 1/13/22 BLDG 1 AREA B 50' SOUTH FOOTING, 8 PADS WEST OF MAIN TRUNK -
Underslab Plumbing Inspection - Commercial Partial 1/14/2022 1/14/2022 01/14/2022
Misc
Informational
01/04/2022
- 6" MAIN TRUNK RUNNING WEST TO EAST TO MAIN CAP SOUTH WING - - 6" MAIN TRUNK SOUTH TO NORTH IN WEST WING - - UNDERSLAB BLDG 1 AREA D - - UNDERSLAB BLDG 1 AREA C, AREA D NORTH SIDE TO 1 PATIO EAST OF WEST WING, SOUTH SIDE 1 PATIO PAST ELEVATOR PIT -
Footing Inspection - Commercial Partial 1/18/2022 (8:00) 1/18/2022 01/18/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/13/2022
- 12/16/21 BLDG 1 AREA C 80' FOOTING SE CORNER, 12 COLUMN PADS SOUTH OF MAIN TRUNK STARTING SE TO WEST, UFER LOCATED SE CORNER NEAR CLEAN OUT - - 12/20/21 BLDG 1 AREA D 50' FOOTING NORTH EXTERIOR WALL - - 12/21/21 BLDG 1 AREA D 9 PADS NORTH OF MAIN TRUNK, FOOTING POURING SOUTH ON EAST EXTERIOR WALL, FOOTING POURING WEST ON SOUTH EXTERIOR WALL - - 12/22/21 BLDG 1 AREA C, 11 PADS AT MAIN TRUNK, 50' FOOTING SOUTH EXTERIOR WALL - - 12/27/21 BLDG 1 AREA C ELEVATOR PIT, NORTH FOOTING 60' NEAR RISER ROOM - - 12/29/21 BLDG 1 AREA C 65' FOOTING NORTH EXTERIOR POURING WEST - - 12/30/21 BLDG 1 AREA B 65' SOUTH FOOTING, AREA C EAST FOOTING 75' - - 01/04/22 BLDG 1 AREA B 100' EAST EXTERIOR FOOTING - - 01/10/22 BLDG 1 AREA A NORTH FOOTING, 85' FOOTING WEST WALL, UFER LOCATED NW CORNER - - 1/11/22 BLDG 1 AREA A 60' WEST FOOTING, AREA B 40' SOUTH FOOTING, 2 PADS AT ELEVATOR PIT, 9 PADS NORTH OF MAIN TRUNK - - 1/12/22 BLDG 1 AREA B WEST FOOTING 55', AREA A & B 14 PADS AT MAIN TRUNK, GRADE BEAMS AREA D - - 1/13/22 BLDG 1 AREA B 50' SOUTH FOOTING, 3 PADS WEST OF MAIN TRUNK - - 1/18/22 BLDG 1 AREA B 12 PADS, 50' SOUTH FOOTING -
Underslab Electrical Inspection - Commercial Partial 1/24/2022 1/24/2022 01/24/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/12/2022
- 1/12/22 BLDG 1 AREA D CONDUIT FOR KITCHEN ISLANDS IN 7 UNITS - - 1/24/22 BLDG 1 AREA C & B, UNDERSLAB CONDUIT FOR KITCHEN ISLANDS & AT&T -
Underslab Plumbing Inspection - Commercial Partial 1/24/2022 1/24/2022 01/24/2022
Misc
Informational
01/14/2022
- 6" MAIN TRUNK RUNNING WEST TO EAST TO MAIN CAP SOUTH WING - - 6" MAIN TRUNK SOUTH TO NORTH IN WEST WING - - UNDERSLAB BLDG 1 AREA D - - UNDERSLAB BLDG 1 AREA C, AREA D NORTH SIDE TO 1 PATIO EAST OF WEST WING, SOUTH SIDE 1 PATIO PAST ELEVATOR PIT - - 1/24/22 UNDERSLAN PLUMBING BLDG 1 AREA C & D -
Underslab Plumbing Inspection - Commercial Passed 1/27/2022 1/27/2022 01/27/2022
Misc
Informational
01/24/2022
- 6" MAIN TRUNK RUNNING WEST TO EAST TO MAIN CAP SOUTH WING - - 6" MAIN TRUNK SOUTH TO NORTH IN WEST WING - - UNDERSLAB BLDG 1 AREA D - - UNDERSLAB BLDG 1 AREA C, AREA D NORTH SIDE TO 1 PATIO EAST OF WEST WING, SOUTH SIDE 1 PATIO PAST ELEVATOR PIT - - 1/24/22 UNDERSLAN PLUMBING BLDG 1 AREA C & D - 1-27-21-UNDERSLAB PLUMBING COMPLETE AT BUILDING 1
Underslab Electrical Inspection - Commercial Passed 1/31/2022 1/31/2022 01/31/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
01/24/2022
- 1/12/22 BLDG 1 AREA D CONDUIT FOR KITCHEN ISLANDS IN 7 UNITS - - 1/24/22 BLDG 1 AREA C & B, UNDERSLAB CONDUIT FOR KITCHEN ISLANDS & AT&T - - 1/31/22 BLDG 1 AREA A UNDERSLAB CONDUIT FOR KITCHEN ISLAND -
Documents & Images
Date Uploaded File Type Document Name
10/13/2021 Receipt Receipt for transaction:2021-007974
10/14/2021 Plans 20-001_The Signature at West Pryor_Foundation Permit_10_11_2021
10/18/2021 approved - The Signature at West Pryor_Foundation Permit_10_11_2022
11/03/2021 Letter DS Building Permit
11/09/2021 Letter INSPECTION SUMMARY
11/16/2021 Letter INSPECTION SUMMARY
11/23/2021 Letter INSPECTION SUMMARY
12/16/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/21/2021 Letter INSPECTION SUMMARY
12/22/2021 Letter INSPECTION SUMMARY
12/27/2021 Letter INSPECTION SUMMARY
12/29/2021 Letter INSPECTION SUMMARY
12/30/2021 Letter INSPECTION SUMMARY
12/30/2021 Letter INSPECTION SUMMARY
01/04/2022 Letter INSPECTION SUMMARY
01/04/2022 Letter INSPECTION SUMMARY
01/10/2022 Letter INSPECTION SUMMARY
01/11/2022 Letter INSPECTION SUMMARY
01/12/2022 Letter INSPECTION SUMMARY
01/12/2022 Letter INSPECTION SUMMARY
01/13/2022 Letter INSPECTION SUMMARY
01/14/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/24/2022 Letter INSPECTION SUMMARY
01/24/2022 Letter INSPECTION SUMMARY
01/27/2022 Letter INSPECTION SUMMARY
01/31/2022 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home