Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Footing Inspection - Commercial
|
Partial
|
11/5/2019
|
11/5/2019 at 12:55 PM
|
11/05/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/6/2019
|
11/6/2019 at 2:35 PM
|
11/06/2019
|
|
Misc
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
|
11/7/2019 at 1:10 PM
|
11/07/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/7/2019 (1:00)
|
11/7/2019 at 1:25 PM
|
11/07/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/8/2019 (1:00)
|
11/8/2019 at 1:00 PM
|
11/08/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/12/2019 (10:00)
|
11/13/2019 at 9:50 AM
|
11/13/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/15/2019 (9:00)
|
11/15/2019 at 9:00 AM
|
11/15/2019
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/19/2019 (1:30)
|
11/19/2019 at 1:30 PM
|
11/19/2019
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/20/2019 (11:00)
|
11/20/2019 at 10:45 AM
|
11/20/2019
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/22/2019
|
11/22/2019 at 10:15 AM
|
11/22/2019
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/26/2019
|
11/26/2019 at 1:05 PM
|
11/26/2019
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/27/2019
|
11/27/2019 at 8:55 AM
|
11/27/2019
|
|
Misc
|
|
Misc
|
Concrete Walls and Columns Inspection
|
Partial
|
|
12/5/2019 at 9:40 AM
|
12/05/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
12/5/2019 (11:00)
|
12/5/2019 at 11:25 AM
|
12/05/2019
|
|
Misc
|
|
Misc
|
Underslab Plumbing Inspection - Commercial
|
Failed
|
12/10/2019
|
12/10/2019 at 8:10 AM
|
12/10/2019
|
|
Misc
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
|
12/11/2019 at 8:55 AM
|
12/11/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
12/12/2019
|
12/12/2019 at 2:00 PM
|
12/12/2019
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
12/13/2019 (11:00)
|
12/13/2019 at 11:35 AM
|
12/13/2019
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
12/18/2019
|
12/18/2019 at 1:50 PM
|
12/18/2019
|
|
Misc
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
|
12/20/2019 at 9:15 AM
|
12/20/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
|
12/20/2019 at 1:55 PM
|
12/20/2019
|
|
Misc
|
|
Misc
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
12/23/2019
|
12/23/2019 at 8:45 AM
|
12/23/2019
|
|
Misc
|
Underslab Electrical Inspection - Commercial
|
Failed
|
12/31/2019
|
12/31/2019 at 7:20 AM
|
12/31/2019
|
Foundation Inspection - Commercial
|
Failed
|
|
12/31/2019 at 7:50 AM
|
12/31/2019
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
|
12/31/2019 at 1:15 PM
|
12/31/2019
|
|
Misc
|
Underslab Electrical Inspection - Commercial
|
Partial
|
|
12/31/2019 at 1:45 PM
|
12/31/2019
|
|
Misc
|
Underslab Electrical Inspection - Commercial
|
Partial
|
1/3/2020
|
1/3/2020 at 7:50 AM
|
01/03/2020
|
|
Misc
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
1/7/2020
|
1/7/2020 at 10:40 AM
|
01/07/2020
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
1/7/2020
|
1/7/2020 at 10:00 AM
|
01/07/2020
|
|
Misc
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
|
1/7/2020 at 11:00 AM
|
01/07/2020
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
1/9/2020
|
1/9/2020 at 11:00 AM
|
01/09/2020
|
|
Misc
|
|
Misc
|
Underslab Electrical Inspection - Commercial
|
Partial
|
|
1/9/2020 at 11:35 AM
|
01/09/2020
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
|
1/9/2020 at 2:55 PM
|
01/09/2020
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
1/13/2020 (9:15)
|
1/13/2020
|
01/13/2020
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
1/15/2020
|
1/15/2020
|
01/15/2020
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
|
1/16/2020
|
01/16/2020
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
1/23/2020 (9:30)
|
1/23/2020 at 9:50 AM
|
01/23/2020
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
1/24/2020
|
1/27/2020 at 10:50 AM
|
01/27/2020
|
|
Misc
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
|
1/27/2020 at 2:00 PM
|
01/27/2020
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
1/29/2020 (8:00)
|
1/29/2020 at 7:55 AM
|
01/29/2020
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
2/4/2020 (2:00)
|
2/4/2020 at 9:10 AM
|
02/04/2020
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
2/7/2020 (1:00)
|
2/7/2020 at 1:25 PM
|
02/07/2020
|
|
Misc
|
|
Misc
|
Piers/Caissons Inspection - Commercial
|
Partial
|
|
1/31/2020 at 2:30 PM
|
02/18/2020
|
|
Misc
|
Piers/Caissons Inspection - Commercial
|
Partial
|
|
2/18/2020 at 2:20 PM
|
02/18/2020
|
|
Misc
|
|
Misc
|
Concrete Walls and Columns Inspection
|
Partial
|
|
2/18/2020 at 2:35 PM
|
02/18/2020
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Partial
|
2/21/2020 (8:00)
|
2/21/2020 at 9:00 AM
|
02/21/2020
|
|
Misc
|
|
Misc
|
Underslab Electrical Inspection - Commercial
|
Partial
|
3/2/2020
|
2/28/2020 at 8:45 AM
|
02/28/2020
|
|
Misc
|
Underslab Electrical Inspection - Commercial
|
Partial
|
|
3/2/2020 at 8:05 AM
|
03/02/2020
|
|
Misc
|
Suspended Slab Inspection
|
Passed
|
3/5/2020 (11:15)
|
3/5/2020 at 1:50 PM
|
03/05/2020
|
Underslab Electrical Inspection - Commercial
|
Partial
|
3/11/2020
|
3/11/2020
|
03/11/2020
|
|
Misc
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
3/12/2020
|
3/12/2020
|
03/12/2020
|
|
Misc
|
|
Misc
|
Underslab Electrical Inspection - Commercial
|
Partial
|
3/12/2020
|
3/12/2020
|
03/12/2020
|
|
Misc
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Partial
|
3/16/2020
|
3/16/2020
|
03/16/2020
|
|
Misc
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Partial
|
4/8/2020
|
4/8/2020
|
04/08/2020
|
|
Misc
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Passed
|
4/30/2020
|
4/30/2020
|
04/30/2020
|
|
Misc
|
|
THE FOLLOWING AREAS ARE APPROVED
|
Final Inspection - Commercial
|
Passed
|
|
4/30/2020
|
04/30/2020
|