Permit Application Status

PRCOM20192060


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20192060
Building Permit - Commercial
Voided
LEES SUMMIT 29197 L L C
NEW COMMERCIAL
NEW FAST FOOD RESTAURANT WITH DRIVE-THRU
07/31/2019
09/04/2019
Locations
Contacts
LEES SUMMIT 29197 L L C, Address:605 W 47TH ST 100  
LINEAR ARCHITECTURE - MARK GRIFFIN, Address:8951 CYPRESS WATERS BLVD, STE 130, Phone:(469) 299-7056  
  
  
  
  
MGRIFFIN@LINEAR-ARCHITECTURE.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved with Conditions 08/10/2019
Michael Weissenbach
Posting of occupant load
Corrective Action Required
08/10/2019

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. (Verified At Inspection) Post occupant load at 61
Address numbers required
Corrective Action Required
08/10/2019

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Type I hood - Where required
Corrective Action Required
08/10/2019

2018 IFC 609.2- Where required. A Type I hood shall be installed at or above all commercial cooking appliances and domestic cooking appliances used for commercial purposes that produce grease vapors. (Verified At Inspection) Label the hood systems at the pull stations and on the hoods to clearly identify each one.
Installation acceptance testing
Corrective Action Required
08/10/2019

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to test the hood systems and the duct detection.
Portable fire extinguishers for commercial cooking equipment.
Corrective Action Required
08/10/2019

2018 IFC 904.11.5- Portable fire extinguishers for commercial cooking equipment. Portable fire extinguishers shall be provided within a 30-foot (9144 mm) travel distance of commercial-type cooking equipment. Cooking equipment involving vegetable or animal oils and fats shall be protected by a Class K rated portable extinguisher. (Verified At Inspection)
Portable fire extinguishers - conspicuous locations
Corrective Action Required
08/10/2019

2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel. Verified At Inspection)
Duct smoke detectors
Corrective Action Required
08/10/2019

2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection. (Action Required) Duct detection to have audible/visual notification in the building.
Panic and fire exit hardware
Corrective Action Required
08/10/2019

2018 IFC 1010.1.10 Panic and fire exit hardware. Doors serving a Group H occupancy and doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock unless it is a panic hardware or fire exit hardware. (Verified At Inspection)
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
08/10/2019 Letter Fire Building Plan Review
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home