Permit Application Status

PRCOM20180598


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20180598
Building Permit - Commercial
Final Completion
NLV MANSION LLC
ALTERATION COMMERCIAL
INTERIOR ALTERATIONS **invite planner to final to verify screening of roof and ground mounted equipment
03/13/2018
04/25/2018
09/12/2018
08/29/2018
Locations
Contacts
NLV MANSION LLC, Address:1520 GRAND BLVD STE 2  
ROSEMANN & ASSOCIATES, Address:1526 GRAND BLVD, Phone:(816) 472-1448  
RAU CONSTRUCTION COMPANY, Address:1215 W 12TH STREET SUITE 200, Phone:(913) 642-6000  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
WESTHUES ELECTRIC INC, Address:PO BOX 18220, Phone:(816) 356-5223  
UNITED PLUMBING & SERVICE CO INC, Address:301 DUCK RD, Phone:(816) 761-5262  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved with Conditions 04/16/2018 04/11/2018
Joe Dir
Address numbers required
Corrective Action Required
04/09/2018

2012 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). ACTION REQUIRED:(verified at inspection) If not existing the numeric address needs to posted and readable from the roadway either on a monument or on the Mansion.
Misc
Corrective Action Required
04/09/2018

Exit/Emergency lights ACTION REQUIRED:(veriifed at inspection) All exit signage will need to illuminate on AC and DC current. All emergency lighting will need to illuminate on DC power.
Misc
Corrective Action Required
04/09/2018

fire extinguishers ACTION REQUIRED:(verified at inspection) All fire extinguishers need to be properly mounted and current with service inspections and maintenance. A current service tag shall be posted on a fire extinguishers.
Building Plan Review Approved with Conditions 04/16/2018 04/10/2018
Joe Frogge
License Tax Application
Corrective Action Required
04/09/2018

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes.
Health Dept Inspection
Corrective Action Required
04/09/2018

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes.
Code analysis required
Resolved
04/10/2018

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Provide detailed code analysis.
Bldg - Ramp handrails 1010.9
Resolved
04/10/2018

2012 IBC 1010.9 – Handrails. Ramps with a rise greater than 6 inches shall have handrails on both sides. Handrails shall comply with Section 1012. Action required: Handrails required on both sides of ramps.
Misc
Resolved
04/10/2018

2012 IMC 506.4.2 Type II terminations. Exhaust outlets serving Type II hoods shall terminate in accordance with the hood manufacturer's installation instructions and shall comply with all of the following: 1. Exhaust outlets shall terminate not less than 3 feet (914 mm) in any direction from openings into the building. 2. Outlets shall terminate not less than 10 feet (3048 mm) from property lines or buildings on the same lot. 3. Outlets shall terminate not less than 10 feet (3048 mm) above grade. 4. Outlets that terminate above a roof shall terminate not less than 30 inches (762 mm) above the roof surface. 5. Outlets shall terminate not less than 30 inches (762 mm) from exterior vertical walls 6. Outlets shall be protected against local weather conditions. 7. Outlets shall not be directed onto walkways. 8. Outlets shall meet the provisions for exterior wall opening protectives in accordance with the International Building Code. Action required: Modify design to show compliance at dishwasher hood exhaust termination.
IFGC - Air for combustion, ventilation and dilution of flue gases 304
Resolved
04/10/2018

2012 IFGC 304 General. Air for combustion, ventilation and dilution of flue gases for appliances installed in buildings shall be provided by application of one of the methods prescribed in Sections 304.5 through 304.9. Where the requirements of Section 304.5 are not met, outdoor air shall be introduced in accordance with one of the methods prescribed in Sections 304.6 through 304.9. Direct-vent appliances, gas appliances of other than natural draft design and vented gas appliances other than Category I shall be provided with combustion, ventilation and dilution air in accordance with the appliance manufacturer’s instructions. (see code for exception) 2012 IFGC 501.2 General. Every appliance shall discharge the products of combustion to the outdoors, except for appliances exempted by Section 501.8. Action required: Update design to show both combustion air locations/methods and exhaust locations/methods for all new or replaced furnaces and water heaters.
Misc
Resolved
04/10/2018

Plumbing design is not clear as to what fixtures are new versus existing. Action required: Clarify which plumbing fixtures are existing/new/replaced.
Misc
Resolved
04/10/2018

2012 IPC 605.4 Water distribution pipe. Water distribution pipe shall conform to NSF 61 and shall conform to one of the standards listed in Table 605.4. Hot water distribution pipe and tubing shall have a pressure rating of not less than 100 psi at 180degF. 2012 IPC 702.1 Above-ground sanitary drainage and vent pipe. Above-ground soil, waste and vent pipe shall conform to one of the standards listed in Table 702.1 2012 IPC 702.2 Underground building sanitary drainage and vent pipe. Underground building sanitary drainage and vent pipe shall conform to one of the standards listed in Table 702.2. Action required: Provide pipe material schedule to demonstrate compliance.
Misc
Resolved
04/10/2018

2011 NEC 210.8 (B) Other Than Dwelling Units. All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in 210.8(B)(1) through (8) shall have ground-fault circuit-interrupter protection for personnel. (1) Bathrooms (2) Kitchens (3) Rooftops (4) Outdoors (5) Sinks - where receptacles are installed within 6 feet of the outside edge of the sink. (6) Indoor wet locations (7) Locker rooms with associated showering facilities (8) Garages, service bays, and similar areas where electrical diagnostic equipment, electrical hand tools, or portable lighting equipment are to be used. (refer to code for exceptions) Action required: Modify drawings to show that all receptacles in kitchen will by GFCI protected.
Misc
Resolved
04/10/2018

Electrical design incomplete. Actions required: - Provide electrical specification to cover all materials and devices. - Provide details of the light poles and fixtures to be installed. Lighting must comply with the parking lot lighting requirements as outlined in Section 7.250 of the UDO.
Screening - Ground mounted equipment
Corrective Action Required
04/09/2018

Unified Development Ordinance Article 7, Section 7.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened per referenced UDO section. 4/10/18 - acknowledged. to be field verified
Screening - Rooftop equipment
Corrective Action Required
04/09/2018

Unified Development Ordinance Article 7, Section 7.180.E Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened per referenced UDO section. 4/10/18 - acknowledged. to be field verified
Licensed Contractors Approved 04/09/2018 04/10/2018
Joe Frogge
Health Department Review Approved 03/23/2018 03/16/2018
Joe Frogge
Fire Plan Review Approved with Conditions 03/23/2018 03/16/2018
Joe Dir
Address numbers required
Corrective Action Required
03/16/2018

2012 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). ACTION REQUIRED:(verified at inspection) If not existing the numeric address needs to posted and readable from the roadway either on a monument or on the Mansion.
Misc
Corrective Action Required
03/16/2018

Exit/Emergency lights ACTION REQUIRED:(veriifed at inspection) All exit signage will need to illuminate on AC and DC current. All emergency lighting will need to illuminate on DC power.
Misc
Corrective Action Required
03/16/2018

fire extinguishers ACTION REQUIRED:(verified at inspection) All fire extinguishers need to be properly mounted and current with service inspections and maintenance. A current service tag shall be posted on a fire extinguishers.
Building Plan Review Rejected 03/23/2018 03/14/2018
Joe Frogge
License Tax Application
Corrective Action Required
03/14/2018

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes.
Health Dept Inspection
Corrective Action Required
03/14/2018

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes.
Health Dept Review
Resolved
03/16/2018

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 847-7070. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is for informational purposes.
Code analysis required
Corrective Action Required
03/14/2018

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Provide detailed code analysis.
Bldg - Ramp handrails 1010.9
Corrective Action Required
03/14/2018

2012 IBC 1010.9 – Handrails. Ramps with a rise greater than 6 inches shall have handrails on both sides. Handrails shall comply with Section 1012. Action required: Handrails required on both sides of ramps.
Misc
Corrective Action Required
03/14/2018

2012 IMC 506.4.2 Type II terminations. Exhaust outlets serving Type II hoods shall terminate in accordance with the hood manufacturer's installation instructions and shall comply with all of the following: 1. Exhaust outlets shall terminate not less than 3 feet (914 mm) in any direction from openings into the building. 2. Outlets shall terminate not less than 10 feet (3048 mm) from property lines or buildings on the same lot. 3. Outlets shall terminate not less than 10 feet (3048 mm) above grade. 4. Outlets that terminate above a roof shall terminate not less than 30 inches (762 mm) above the roof surface. 5. Outlets shall terminate not less than 30 inches (762 mm) from exterior vertical walls 6. Outlets shall be protected against local weather conditions. 7. Outlets shall not be directed onto walkways. 8. Outlets shall meet the provisions for exterior wall opening protectives in accordance with the International Building Code. Action required: Modify design to show compliance at dishwasher hood exhaust termination.
IFGC - Air for combustion, ventilation and dilution of flue gases 304
Corrective Action Required
03/14/2018

2012 IFGC 304 General. Air for combustion, ventilation and dilution of flue gases for appliances installed in buildings shall be provided by application of one of the methods prescribed in Sections 304.5 through 304.9. Where the requirements of Section 304.5 are not met, outdoor air shall be introduced in accordance with one of the methods prescribed in Sections 304.6 through 304.9. Direct-vent appliances, gas appliances of other than natural draft design and vented gas appliances other than Category I shall be provided with combustion, ventilation and dilution air in accordance with the appliance manufacturer’s instructions. (see code for exception) 2012 IFGC 501.2 General. Every appliance shall discharge the products of combustion to the outdoors, except for appliances exempted by Section 501.8. Action required: Update design to show both combustion air locations/methods and exhaust locations/methods for all new or replaced furnaces and water heaters.
Misc
Corrective Action Required
03/14/2018

Plumbing design is not clear as to what fixtures are new versus existing. Action required: Clarify which plumbing fixtures are existing/new/replaced.
Misc
Corrective Action Required
03/14/2018

2012 IPC 605.4 Water distribution pipe. Water distribution pipe shall conform to NSF 61 and shall conform to one of the standards listed in Table 605.4. Hot water distribution pipe and tubing shall have a pressure rating of not less than 100 psi at 180degF. 2012 IPC 702.1 Above-ground sanitary drainage and vent pipe. Above-ground soil, waste and vent pipe shall conform to one of the standards listed in Table 702.1 2012 IPC 702.2 Underground building sanitary drainage and vent pipe. Underground building sanitary drainage and vent pipe shall conform to one of the standards listed in Table 702.2. Action required: Provide pipe material schedule to demonstrate compliance.
Misc
Corrective Action Required
03/14/2018

2011 NEC 210.8 (B) Other Than Dwelling Units. All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in 210.8(B)(1) through (8) shall have ground-fault circuit-interrupter protection for personnel. (1) Bathrooms (2) Kitchens (3) Rooftops (4) Outdoors (5) Sinks - where receptacles are installed within 6 feet of the outside edge of the sink. (6) Indoor wet locations (7) Locker rooms with associated showering facilities (8) Garages, service bays, and similar areas where electrical diagnostic equipment, electrical hand tools, or portable lighting equipment are to be used. (refer to code for exceptions) Action required: Modify drawings to show that all receptacles in kitchen will by GFCI protected.
Misc
Corrective Action Required
03/14/2018

Electrical design incomplete. Actions required: - Provide electrical specification to cover all materials and devices. - Provide details of the light poles and fixtures to be installed. Lighting must comply with the parking lot lighting requirements as outlined in Section 7.250 of the UDO.
Screening - Ground mounted equipment
Corrective Action Required
03/14/2018

Unified Development Ordinance Article 7, Section 7.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened per referenced UDO section.
Screening - Rooftop equipment
Corrective Action Required
03/14/2018

Unified Development Ordinance Article 7, Section 7.180.E Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened per referenced UDO section.
Licensed Contractors Approved 04/13/2018 03/14/2018
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Alteration to Commercial $3,958.80 $3,958.80 Paid 04/25/2018
8331507-Sewer Connection Fee $30.00 $30.00 Paid 04/25/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underground Electrical Inspection - Commercial Partial 5/17/2018 5/17/2018 05/17/2018
Underground Electrical Inspection - Commercial Partial 5/18/2018 5/18/2018 at 1:00 PM 05/18/2018
Misc
Corrective Action Required
05/18/2018
4 pole base and conduit on west drive north up to entrance and sign.
Underground Electrical Inspection - Commercial Partial 5/21/2018 at 1:50 PM 05/21/2018
Misc
Corrective Action Required
05/18/2018
4 pole base and conduit on west drive north up to entrance and sign.
All Rough Inspection - Commercial Partial 5/31/2018 5/31/2018 at 10:00 AM 05/31/2018
Misc
Corrective Action Required
05/31/2018
Partial - partial plumbing inspection on venting and kitchen area. ok to proceed.
All Rough Inspection - Commercial Partial 6/11/2018 6/11/2018 06/11/2018
Misc
Corrective Action Required
05/31/2018
Partial - partial plumbing inspection on venting and kitchen area. ok to proceed.
Misc
Corrective Action Required
06/11/2018
Elevator wall /floor and framing-1st and 2nd floor only ok to cover pending installation of electrcial.
All Rough Inspection - Commercial Partial 6/29/2018 6/29/2018 06/29/2018
Misc
Corrective Action Required
06/11/2018
Partial - partial plumbing inspection on venting and kitchen area. ok to proceed.
Misc
Corrective Action Required
06/11/2018
Elevator wall /floor and framing-1st and 2nd floor only ok to cover pending installation of electrcial.
Final Inspection - Commercial Failed 9/4/2018 at 10:50 AM 09/04/2018
Misc
Corrective Action Required
09/04/2018
obtain health department approval
Occupancy Inspection - Fire Failed 9/4/2018 09/04/2018
Alternate Protection Systems Inspection Passed 9/6/2018 09/06/2018
Occupancy Inspection - Fire Passed 9/6/2018 09/06/2018
Final Inspection - Commercial Passed 9/6/2018 09/06/2018
Misc
Resolved
09/06/2018
obtain health department approval
Documents & Images
Date Uploaded File Type Document Name
03/16/2018 Letter Fire Building Plan Review
03/16/2018 Letter Codes P/R Corrections Document
03/16/2018 Change of Ownership Plan Review - Approved FTG 0001817
04/11/2018 Letter Fire Building Plan Review
04/12/2018 Letter Codes Plan Review Conditions
04/25/2018 Receipt Receipt for transaction: 2018-001576
04/25/2018 Letter Codes Building Permit
05/17/2018 Letter Inspection Summary
05/18/2018 Letter Inspection Summary
05/21/2018 Letter Inspection Summary
05/31/2018 Letter Inspection Summary
06/11/2018 Letter Inspection Summary
09/04/2018 Letter Inspection Summary
09/04/2018 Letter Inspection Summary
09/06/2018 Letter Inspection Summary
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home