Permit Application Status

PRCOM20172541


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20172541
Building Permit - Commercial
Certificate of Occupancy
PARROT PROPERTIES INC
NEW COMMERCIAL
MAINTENANCE BUILDING FOUNDATION PERMIT - PRCOM20181920
07/24/2017
02/25/2020
01/31/2018
09/25/2020
Locations
Contacts
CITYSCAPE CONSTRUCTION VIEW HIGH LLC, Address:10 W CARMEL DR STE 200, Phone:(317) 574-1600 Ext:100  
STANDARD HEATING & COOLING TOO LLC, Address:2006 E PRAIRIE CIRCLE , Phone:(913) 782-5409  
STANDARD ELECTRIC COMPANY INC, Address:2006 E PRAIRIE CIRCLE, Phone:(913) 782-5409  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
SGN+A ARCHITECTS, Address:315 W PONCE DE LEON AVE #755, Phone:(404) 373-7370  
PARROT PROPERTIES INC, Address:11303 VIEW HIGH DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/22/2017 06/19/2018
Joe Frogge
LC - General Contractor
Corrective Action Required
08/22/2017

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor. 8/24/17 - Acknowledged.
LC - MEP Subs
Corrective Action Required
08/22/2017

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 8/24/17 - Acknowledged.
Licensed Contractors Approved 07/25/2017 06/19/2018
Joe Frogge
LC - General Contractor
Corrective Action Required
08/04/2017

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
LC - MEP Subs
Corrective Action Required
08/04/2017

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Building Plan Review Approved with Conditions 08/29/2017 02/16/2018
Joe Frogge
Misc
Corrective Action Required
08/22/2017

For clarity, this report covers all accessory structures including Maintenance Building, Garages, Trash Enclosure, etc. Action required: Comment is for informational purposes. 8/24/17 - Acknowledged.
Final Development Plan
Resolved
02/16/2018

The building permit for this project can not be issued until the Codes Administration Department has received the approved Final Development Plan from the Planning and Development Department. Action required: Comment is for informational purposes. 8/24/17 - Acknowledged.
Project cost
Resolved
02/16/2018

The project cost, which is used to establish the permit fee, has not been provided. Action required: Comment is for informational purposes. We need a breakdown per structure. 8/24/17 - Acknowledged.
Engineered truss package
Corrective Action Required
08/22/2017

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide roof truss packages or request deferral. 8/24/17 - deferred per request
Bldg - Toilet room wall finish 1210.2.2
Resolved
08/24/2017

2012 IBC 1210.2.2 – Walls and partitions. Walls and partitions with 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant materials at Maintenance Building restroom and mop sink.
Misc
Corrective Action Required
08/22/2017

2012 IPC 502.1 General. Water heaters shall be installed in accordance with the manufacturer’s installation instructions. Oil-fired water heaters shall conform to the requirements of this code and the International Mechanical Code. Electric water heaters shall conform to the requirements of this code and provisions of NFPA 70. Gas-fired water heaters shall conform to the requirements of the International Fuel Gas Code. Action required: Provide expansion tanks at water heaters or provide verification that water heaters installed will not require expansion tanks in the manufacturer's written instructions. 8/24/17 - Approved contingent upon approval by manufacturer. Field Verify
Screening - Ground mounted equipment
Resolved
08/24/2017

Unified Development Ordinance Article 7, Section 7.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened per referenced UDO section.
Final Development Plan Review Approved 08/07/2018 02/16/2018
Joe Frogge
Fire Plan Review Approved with Conditions 08/29/2017 08/23/2017
Joe Dir
Building Plan Review Rejected 08/07/2017 08/04/2017
Joe Frogge
Misc
Corrective Action Required
08/04/2017

For clarity, this report covers all accessory structures including Maintenance Building, Garages, Trash Enclosure, etc. Action required: Comment is for informational purposes.
Final Development Plan
Corrective Action Required
08/04/2017

The building permit for this project can not be issued until the Codes Administration Department has received the approved Final Development Plan from the Planning and Development Department. Action required: Comment is for informational purposes.
Project cost
Corrective Action Required
08/04/2017

The project cost, which is used to establish the permit fee, has not been provided. Action required: Comment is for informational purposes. We need a breakdown per structure.
Engineered truss package
Corrective Action Required
08/04/2017

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide roof truss packages or request deferral.
Bldg - Toilet room wall finish 1210.2.2
Corrective Action Required
08/04/2017

2012 IBC 1210.2.2 – Walls and partitions. Walls and partitions with 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant materials at Maintenance Building restroom and mop sink.
Misc
Corrective Action Required
08/04/2017

2012 IPC 502.1 General. Water heaters shall be installed in accordance with the manufacturer’s installation instructions. Oil-fired water heaters shall conform to the requirements of this code and the International Mechanical Code. Electric water heaters shall conform to the requirements of this code and provisions of NFPA 70. Gas-fired water heaters shall conform to the requirements of the International Fuel Gas Code. Action required: Provide expansion tanks at water heaters or provide verification that water heaters installed will not require expansion tanks in the manufacturer's written instructions.
Screening - Ground mounted equipment
Corrective Action Required
08/04/2017

Unified Development Ordinance Article 7, Section 7.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened per referenced UDO section.
Fire Plan Review Approved with Conditions 08/07/2017 08/04/2017
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Commercial $159.35 $159.35 Paid 03/25/2019
8331507-Sewer Connection Fee $90.00 $90.00 Paid 03/25/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Commercial Failed 2/26/2020 2/26/2020 02/26/2020
Misc
Corrective Action Required
02/26/2020
Provide city stamped truss package- Install windows check flashing on wood sills- Provide anchor bolts perimeter of maintenance building & within 12” of plate breaks
All Rough Inspection - Commercial Passed 3/3/2020 3/3/2020 03/03/2020
Misc
Resolved
03/03/2020
Provide city stamped truss package- Install windows check flashing on wood sills- Provide anchor bolts perimeter of maintenance building & within 12” of plate breaks
Electrical Service Inspection Passed 4/2/2020 4/2/2020 04/02/2020
Verify Final Inspection (Final) Complete 9/21/2020 09/21/2020
Final Inspection - Commercial Passed 9/25/2020 9/25/2020 09/25/2020
Occupancy Inspection - Fire Passed 09/25/2020
Occupancy Inspection - Planning Passed 09/25/2020
Occupancy Inspection - Water Utilities Passed 09/25/2020
Occupancy Inspection - Codes Commercial Full C of O 09/25/2020
Documents & Images
Date Uploaded File Type Document Name
08/04/2017 Letter Codes P/R Corrections Document
10/16/2017 Meridian Site Map
03/25/2019 Receipt Receipt for transaction: 2019-001048
02/26/2020 Letter INSPECTION SUMMARY
03/03/2020 Letter INSPECTION SUMMARY
04/02/2020 Letter INSPECTION SUMMARY
09/25/2020 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home