Summary
PRCOM20172507
Building Permit - Commercial
Certificate of Occupancy
PARROT PROPERTIES INC
NEW MULTI-FAMILY
BUILDING #3 NEW APARTMENT WITH PARKING GARAGE BENEATH FOUNDATION PERMIT - PRCOM20180699
07/24/2017
01/07/2019
01/28/2020
Locations
Contacts
CITYSCAPE CONSTRUCTION VIEW HIGH LLC, Address:10 W CARMEL DR STE 200, Phone:(317) 574-1600 Ext:100  
STANDARD HEATING & COOLING TOO LLC, Address:2006 E PRAIRIE CIRCLE , Phone:(913) 782-5409  
STANDARD ELECTRIC TOO LLC, Address:2006 E PRAIRIE CIRCLE, Phone:(913) 782-5409  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
SGN+A ARCHITECTS, Address:315 W PONCE DE LEON AVE #755, Phone:(404) 373-7370  
LATIMER SOMMERS & ASSOCIATES PA, Address:3639 SW SUMMERFIELD DR STE A, Phone:(785) 233-3232  
PARROT PROPERTIES INC, Address:11303 VIEW HIGH DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 07/25/2018 11/08/2018
Dawn Bell
Final Development Plan Review Approved 08/07/2018 02/16/2018
Joe Frogge
Building Plan Review Approved 08/07/2018 02/16/2018
Joe Frogge
Special Inspections Review Approved 08/24/2017
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Multi-Family $5,943.05 $5,943.05 Paid 01/07/2019
8331507-Sewer Connection Fee $3,000.00 $3,000.00 Paid 01/07/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Commercial Failed 2/4/2019 02/04/2019
Misc
Corrective Action Required
02/04/2019
no address, permits or building numbers posted
Sewer Service Inspection Passed 2/5/2019 2/5/2019 02/05/2019
Foundation Inspection - Commercial Passed 4/12/2019 (9:45) 4/12/2019 04/12/2019
Underslab Plumbing Inspection - Commercial Passed 4/22/2019 4/22/2019 04/22/2019
All Rough Inspection - Commercial Failed 7/16/2019 7/16/2019 07/16/2019
Misc
Corrective Action Required
07/16/2019
108 - studs at laundry, pre rock caulk pvc, Dwv. Turn out clean outs. 106- tun out clean outs clean outs . Tie top plates bedroom north wall. Broken outlet box seats wall bedroom. 208,206-stud under sprinkler pipe north wall. 207- prerock.ok 205- joist hanger joist into lvl’s. 306- strap top plates north wall at header for porch, stud under header also. 308, 307.,305ok. North section-301,302- 303- support SE cable in attic. 304- stud under header for stair wall. Stud for sprinkler pipe south wall kit. 201-caulk water line north wall. Complete sprinkler pipe through top plate and wall.203 fix elect to switch box west exterior door. 202-electrical rear east door. 204-strap top plates bedroom south exterior wall. 101-104 strap top plates porch wall.
Electrical Service Inspection Failed 7/16/2019 7/16/2019 07/16/2019
Misc
Corrective Action Required
07/16/2019
connect ufer ground to south meter bank
Rated Assembly Inspection Failed 7/16/2019 7/16/2019 07/16/2019
Misc
Corrective Action Required
07/16/2019
incomplete- caulk all pre-rock penetrations
All Rough Inspection - Commercial Failed 7/19/2019 7/19/2019 07/19/2019
Misc
Resolved
09/06/2019
108 - studs at laundry,Dwv. Turn out clean outs. 106- tun out clean outs clean outs . 208,206-stud under sprinkler pipe north wall. 207- prerock.ok 205- joist hanger joist into lvl’s. 306-308, 307.,305ok. North section-304- stud under header for stair wall. Stud for sprinkler pipe south wall kit. 201-caulk water line north wall. Complete sprinkler pipe through top plate and wall.
Rated Assembly Inspection Partial 8/2/2019 8/2/2019 07/19/2019
Misc
Corrective Action Required
07/19/2019
Pre-rock 3 floors ok Dryer boxes 3 floors ok. Fire collars ok Ready for units pending rough approval
Rated Assembly Inspection Partial 7/31/2019 08/09/2019
Misc
Corrective Action Required
07/19/2019
Pre-rock 3 floors ok Dryer boxes 3 floors ok. Fire collars ok Ready for units pending rough approval
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/09/2019
RC CHANNEL ALL ROOMS EXCEPT FOYER AND STAIR TOWERS
Rated Assembly Inspection Failed 8/14/2019 8/14/2019 08/14/2019
Misc
Corrective Action Required
08/09/2019
Pre-rock 3 floors ok Dryer boxes 3 floors ok. Fire collars ok Ready for units pending rough approval
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/09/2019
RC CHANNEL ALL ROOMS EXCEPT FOYER AND STAIR TOWERS
Sprinkler - Hydrostatic Test Passed 8/16/2019 08/16/2019
Rated Assembly Inspection Partial 8/19/2019 08/19/2019
Misc
Corrective Action Required
08/14/2019
Pre-rock 3 floors ok Dryer boxes 3 floors ok. Fire collars ok Ready for units pending rough approval
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/14/2019
RC CHANNEL ALL ROOMS EXCEPT FOYER AND STAIR TOWERS UNITS - ok
Rated Assembly Inspection Passed 9/6/2019 9/6/2019 09/06/2019
Misc
Resolved
09/06/2019
Pre-rock 3 floors ok Dryer boxes 3 floors ok. Fire collars ok Ready for units pending rough approval
THE FOLLOWING AREAS ARE APPROVED
Resolved
09/06/2019
units and rooms complete.
All Rough Inspection - Commercial Passed 09/06/2019
Misc
Resolved
09/06/2019
108 - studs at laundry,Dwv. Turn out clean outs. 106- tun out clean outs clean outs . 208,206-stud under sprinkler pipe north wall. 207- prerock.ok 205- joist hanger joist into lvl’s. 306-308, 307.,305ok. North section-304- stud under header for stair wall. Stud for sprinkler pipe south wall kit. 201-caulk water line north wall. Complete sprinkler pipe through top plate and wall.
Electrical Service Inspection Passed 10/30/2019 10/30/2019 10/30/2019
Alarm Test Passed 1/13/2020 01/13/2020
Sprinkler - Flow Test Passed 1/13/2020 01/13/2020
Water Service Inspection Passed 1/14/2020 01/14/2020
Sewer Service Inspection Passed 1/14/2020 01/14/2020
Occupancy Inspection - Engineering Passed 1/14/2020 01/14/2020
Occupancy Inspection - Fire Failed 1/16/2020 01/16/2020
Occupancy Inspection - Codes Commercial Failed 1/16/2020 1/16/2020 01/16/2020
Misc
Corrective Action Required
01/16/2020
Water- failed see seperate report Fire failed see report Site inspecitons approved by steve robbins Planning OK for COFO Codes- >>Label main disconnect >>complete dryer vents on exterior. >>Complete addresses. >> install fan in sprinkler room in basement.
Occupancy Inspection - Codes Commercial Failed 1/16/2020 01/16/2020
Misc
Corrective Action Required
01/16/2020
Water- failed see seperate report Fire failed see report Site inspecitons approved by steve robbins Planning OK for COFO Codes- >>Label main disconnect >>complete dryer vents on exterior. >>Complete addresses. >> install fan in sprinkler room in basement. >>install required ADA fixtures in bathroom, under sink height is lower than 27", install required vertical grab bar and seat for shower.
Occupancy Inspection - Planning Passed 1/28/2020 01/28/2020
Occupancy Inspection - Fire Passed 1/28/2020 01/28/2020
Occupancy Inspection - Codes Commercial Full C of O 1/28/2020 1/28/2020 01/28/2020
Misc
Resolved
01/28/2020
Water- failed see seperate report Fire failed see report Site inspecitons approved by steve robbins Planning OK for COFO Codes- OK for COFO
Occupancy Inspection - Water Utilities Passed 1/16/2020 01/28/2020
Sewer Service Inspection Passed 2/3/2020 02/03/2020
Misc
Informational
02/03/2020
The sanitary service line has been connected with a fernco and has passed.
Piers/Caissons Inspection - Commercial Passed 4/17/2020 04/17/2020
Misc
Informational
04/17/2020
- LIGHT POLE BASE, DRIVEN GROUND ROD IN PLACE, NORTH END OF BLDG -
Documents & Images
Date Uploaded File Type Document Name
10/16/2017 Meridian Site Map
01/07/2019 Letter Codes Building Permit
01/07/2019 Receipt Receipt for transaction: 2019-000072
02/04/2019 Letter INSPECTION SUMMARY
02/05/2019 image
02/05/2019 image0
02/05/2019 Letter INSPECTION SUMMARY
04/22/2019 Letter INSPECTION SUMMARY
07/16/2019 Letter Codes Plan Review Conditions
07/16/2019 Letter INSPECTION SUMMARY
07/16/2019 Letter INSPECTION SUMMARY
07/16/2019 Letter INSPECTION SUMMARY
07/19/2019 Letter INSPECTION SUMMARY
07/19/2019 Letter INSPECTION SUMMARY
07/19/2019 Letter INSPECTION SUMMARY
07/19/2019 Letter INSPECTION SUMMARY
08/09/2019 Letter INSPECTION SUMMARY
08/14/2019 Letter INSPECTION SUMMARY
08/19/2019 Letter INSPECTION SUMMARY
10/30/2019 Letter INSPECTION SUMMARY
01/16/2020 Letter INSPECTION SUMMARY
01/16/2020 Letter INSPECTION SUMMARY
01/28/2020 Letter Codes Final Certificate of Occupancy
02/03/2020 Letter DE-Daily Inspection Summary
04/17/2020 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home