PRCOM20170399


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20170399
Building Permit - Commercial
Certificate of Occupancy
M150 ECHELON LAND DEV LLC
NEW MULTI-FAMILY
NEW 3 STORY APARTMENT BUILDING FDTN PERMIT - PRCOM20181561 *NOT TO BE ISSUED UNTIL FIRE DEPARTMENT RELEASES PERMIT
02/16/2017
08/07/2018
04/21/2020
Locations
Contacts
LUKE DRAILY CONSTRUCTION INC, Address:75 NW BUSINESS PARK LANE, Phone:(816) 459-8531  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
ELECTRICAL ENTERPRISES INC, Address:PO BOX 127, Phone:(785) 242-7971  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
NSPJ ARCHITECTS, Address:3515 W 75TH ST, SUITE 201, Phone:(913) 831-1415 Ext:278  
KANSAS CITY TESTING & ENGINEERING, Address:1308 ADAMS STREET, Phone:(913) 321-8100  
M150 ECHELON LAND DEV LLC, Address:120 SE 30TH ST  
GRIFFIN RILEY PROPERTY GROUP, Address:21 SE 29TH TER, Phone:(816) 366-7900  
CITY OF LEE'S SUMMIT MISSOURI, Address:220 SE GREEN ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved 03/06/2017 04/12/2018
Joe Frogge
Building Plan Review Approved 06/14/2018 04/12/2018
Joe Frogge
Licensed Contractors Approved 05/17/2019 04/12/2018
Joe Frogge
Special Inspections Review Approved 02/05/2018
Joe Frogge
Final Development Plan Review Approved 03/06/2017 12/15/2017
Joe Frogge
Alarm Plan Review Released for Construction 05/24/2017
Joe Dir
Sprinkler Plan Review Released for Construction 05/24/2017
Joe Dir
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Multi-Family $12,578.78 $12,578.78 Paid 12/20/2017
8331507-Sewer Connection Fee $3,000.00 $3,000.00 Paid 12/20/2017
Not Ready Inspection Fee $50.00 $50.00 Paid Not payable online 11/25/2019
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $50.00 $0.00 $50.00 Not Paid


$50.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 9/27/2018 (3:00) 9/27/2018 09/27/2018
Misc
Partial Correction
09/27/2018
perimeter footing approved
Electrical Service Inspection Partial 5/6/2019 5/6/2019 05/06/2019
Misc
Partial Correction
05/06/2019
TEMP POWER APPROVED
All Rough Inspection - Commercial Failed 9/20/2019 9/20/2019 09/20/2019
Misc
Corrective Action Required
09/20/2019
Building number 2 3rd floor Unit 310 -fire blocking needed above electrical panel in wall -missing stud in coat closet in right side -fasteners missing trusses in main room -sprinkler head missing in bathroom -gaps in rated assembly in SE corner of main room need to be filled Unit 311 -stud shoe needed in bathroom Unit 309 -cut roof trusses in bedroom, need engineers approval Unit 307 -missing draft stop in bay in bedroom, SE corner - cut roof trusses in front hall way, need engineers approval Unit 306 -draft stopping in sprinkler stud bay, left of front door -cut trusses in front hall way, need engineers approval -protect piping on north side of wall at top and bottom plate in bedroom closet -repair draft stopping for 4 inch pipe in main room, SE corner - putty pads needed for boxes in double wall, north side of main room Unit 305 -cut trusses in front hall way, need engineers approval Unit 304 -cut trusses in front hall way, need engineers approval Unit 303 -cut trusses in bedroom. Need engineer approval Unit 301 -stud shoe needed in exterior wall in bathroom where piping is going through - cut trusses above refrigerator area, in hall way, need engineers approval Unit 300 -cut trusses in kitchen, and in entrance hall way, needs engineers approval -hurricane straps needed trusses, east side of main room -draft stopping in bay of electrical panel 2nd floor Unit 200 -missing stud in closet, north side -need UL listing for duct work (through out floor) does not look to be UL listed - fire caulk needs to be added to floor penetrations on north side bedroom, north wall -damages truss top plate, north bedroom left side -damages 2x6 on exterior wall, north side bedroom -cut 2x6 exterior stud, north side bedroom Unit 201 -sheer wall boot needs to be tightened down in north side bedroom -secure electrical wiring for box on right side of closet entrance north side Unit 203 -protect waterlines in bathroom Unit 202 -protect plumbing at bottom plate, south side wall in main room Unit 204 -protect clothes washer water lines at top plate -putty pads needed for junction boxes in double wall, separating washer/dryer rooms Unit 205 -protect fire line at bottom plate, left side of entrance Unit 206 -Protect waterlines at top plate, north side -protect plumbing at top plate in closet, north side Unit 207 -protect fire line at bottom plate, ride side of entry door -protect water lines at bottom plate in washer/dryer closet -putty pads needed on boxes separating units 207 and 206, in washer/dryer closets -protect sprinkler line at bottom plate, north side main room Unit 208 -fire stop at top plate, dead space separating bedroom and closet, south side of unit Unit 211 -protect sprinkler line, left side of entrance at bottom plate
All Rough Inspection - Commercial Partial 9/26/2019 9/26/2019 09/26/2019
Misc
Corrective Action Required
09/20/2019
Building number 2 2nd floor Unit 200 -missing stud in closet, north side -need UL listing for duct work (through out floor) does not look to be UL listed - fire caulk needs to be added to floor penetrations on north side bedroom, north wall -damages truss top plate, north bedroom left side -damages 2x6 on exterior wall, north side bedroom -cut 2x6 exterior stud, north side bedroom Unit 201 -sheer wall boot needs to be tightened down in north side bedroom -secure electrical wiring for box on right side of closet entrance north side Unit 203 -protect waterlines in bathroom Unit 202 -protect plumbing at bottom plate, south side wall in main room Unit 204 -protect clothes washer water lines at top plate -putty pads needed for junction boxes in double wall, separating washer/dryer rooms Unit 205 -protect fire line at bottom plate, left side of entrance Unit 206 -Protect waterlines at top plate, north side -protect plumbing at top plate in closet, north side Unit 207 -protect fire line at bottom plate, ride side of entry door -protect water lines at bottom plate in washer/dryer closet -putty pads needed on boxes separating units 207 and 206, in washer/dryer closets -protect sprinkler line at bottom plate, north side main room Unit 208 -fire stop at top plate, dead space separating bedroom and closet, south side of unit Unit 211 -protect sprinkler line, left side of entrance at bottom plate
THIRD FLOOR
Corrective Action Required
09/26/2019
Building number 2 3rd floor Unit 311 -stud shoe needed in bathroom Unit 301 -stud shoe needed in exterior wall in bathroom where piping is going through *these items were supposed to be fixed after we left, will verify on next inspection
Above Ceiling Inspection Partial 9/26/2019 9/26/2019 09/26/2019
Misc
Corrective Action Required
09/26/2019
Above ceiling is approved for building #2
All Rough Inspection - Commercial Partial 10/1/2019 10/1/2019 10/01/2019
Misc
Resolved
10/01/2019
decond floor ok to insulate and rock
THIRD FLOOR
Resolved
10/01/2019
third floor ok to insulate and rock
All Rough Inspection - Commercial Failed 10/2/2019 10/2/2019 10/02/2019
Misc
Corrective Action Required
10/02/2019
1st floor Need to verify low voltage wires being secured *** Unit 101 -protect piping in north side bedroom closet, north wall Unit 109 -on west side of bathroom, address cut 2x6 studs where piping is coming through, stud shoe needed -west side bedroom wall, protect vent stack above sink, on hall way side -west side bathroom wall, protect plumbing at bottom plate Unit 111 - protect plumbing in north side bedroom at bottom plate -protect water line, south side bathroom at SW corner towards bottom plate Far south garage, plumbing incomplete coming down from second floor and also in hall way outside of that garage Far north side garage, electrical needs to be boxed up, in separating wall between garage and utility room Second storage unit from far north end, top plates need to be strapped and plumbing needs to be protected Storage room just north of south side stair tower, light fixture wiring needs to be secured
Sprinkler - Hydrostatic Test Passed 10/4/2019 10/04/2019
All Rough Inspection - Commercial Failed 10/8/2019 10/8/2019 10/08/2019
Misc
Corrective Action Required
10/02/2019
1st floor Need to verify low voltage wires being secured *** needs to be secured within 12” of box Stud wall across from room 203, need to be fixed with piping going through. Notched more than 40% Room 103 bathroom needs draft stopping at top plate Joist hangers needed in east side stair tower underneath landing Far north side garage, electrical needs to be boxed up, in separating wall between garage and utility room Storage room just north of south side stair tower, light fixture wiring needs to be secured
All Rough Inspection - Commercial Partial 10/18/2019 10/18/2019 10/18/2019
Misc
Corrective Action Required
10/08/2019
1st floor Need to verify low voltage wires being secured *** needs to be secured within 12” of box Ok to insulate
Rated Assembly Inspection Partial 11/7/2019 11/7/2019 11/07/2019
Misc
Corrective Action Required
11/07/2019
first layer of sheet rock at stair tower lids and units on 3rd floor is approved and ok for second layer, leave sections out in each room to verify spacing of seams
Rated Assembly Inspection Not Ready 11/15/2019 11/15/2019 11/15/2019
Misc
Corrective Action Required
11/15/2019
For second and third floors sheet rock ** seams throughout 2nd and 3rd floor, screws are too close to the seams and Also screws are breaking paper making screw distances too far apart on walls and ceilings ** sheet rock seams are too close together throughout 3rd floor second layer, need to have proper seam spacing on walls and ceilings ** distance of screws to edges of the ceiling and wall connection are too far apart, need to be within code compliance ** damaged sheet rock throughout on 2nd and 3rd floors on walls and ceilings Go throughout both floors and correct all issues. Not ready fee is issued and will need to be paid before next inspection
Rated Assembly Inspection Failed 11/22/2019 11/22/2019 11/22/2019
Misc
Corrective Action Required
11/15/2019
For second and third floors sheet rock ** seams throughout 2nd and 3rd floor, screws are too close to the seams and Also screws are breaking paper making screw distances too far apart on walls and ceilings ** sheet rock seams are too close together throughout 3rd floor second layer, need to have proper seam spacing on walls and ceilings ** distance of screws to edges of the ceiling and wall connection are too far apart, need to be within code compliance ** damaged sheet rock throughout on 2nd and 3rd floors on walls and ceilings Go throughout both floors and correct all issues. Not ready fee is issued and will need to be paid before next inspection ***No inspection performed on 11/22/2019, not ready fee has not been paid from previous inspection. Fee must be paid before any further inspections ***
Rated Assembly Inspection Partial 11/26/2019 11/26/2019 11/26/2019
Misc
Informational
11/26/2019
3rd floor - third floor 2nd layer ceilings are ok - third floor first layer of walls are ok - stair tower 2nd layer is ok Ok to proceed
Misc
Informational
11/26/2019
2nd floor - first layer second floor ceilings and walls are good Walked with sheet rock crew and resolved all issues Ok to proceed
Rated Assembly Inspection Partial 12/13/2019 12/13/2019 12/13/2019
Misc
Informational
12/13/2019
2nd floor - first layer second floor ceilings and walls are good Walked with sheet rock crew and resolved all issues Ok to proceed
Misc
Informational
12/13/2019
3rd layer in stair towers are approved, ok for RC
Rated Assembly Inspection Partial 12/19/2019 12/19/2019 12/19/2019
Misc
Informational
12/13/2019
2nd floor - first layer second floor ceilings and walls are good Walked with sheet rock crew and resolved all issues Ok to proceed
Misc
Informational
12/13/2019
3rd layer in stair towers are approved, ok for RC
Misc
Informational
12/19/2019
RC channel for all four stair tower lids are approved and ok to cover
Rated Assembly Inspection Partial 12/26/2019 12/26/2019 12/26/2019
Misc
Resolved
12/26/2019
2nd floor - first layer second floor ceilings and walls are good Walked with sheet rock crew and resolved all issues Ok to proceed
Misc
Resolved
12/26/2019
3rd layer in stair towers are approved, ok for RC
Misc
Resolved
12/26/2019
RC channel for all four stair tower lids are approved and ok to cover
THE FOLLOWING AREAS ARE APPROVED
Informational
12/26/2019
RC APPROVED 2ND FLOOR ROCK APRROVED. 2ND FLOOR STAIR TOWERS 1ST OK;2ND;3RD; RC approved, 4th layer OK
FIRST FLOOR
Informational
12/26/2019
First layer sheet rock on 1st floor units, garages, storage rooms, mechanical rooms, IT rooms, are approved. Walked with sheetrockers and resolved all issues during inspection.
Electrical Service Inspection Passed 1/16/2020 1/16/2020 01/16/2020
Sprinkler - Flow Test Not Ready 3/24/2020 03/24/2020
Alarm Test Not Ready 3/24/2020 03/24/2020
Sprinkler - Flow Test Passed 4/7/2020 04/07/2020
Alarm Test Failed 4/7/2020 04/07/2020
Occupancy Inspection - Planning Passed 04/09/2020
Occupancy Inspection - Engineering Passed 04/09/2020
Occupancy Inspection - Fire Failed 4/9/2020 04/09/2020
Alarm Test Failed 4/9/2020 04/09/2020
Occupancy Inspection - Codes Commercial Failed 4/9/2020 4/9/2020 04/09/2020
Misc
Corrective Action Required
04/09/2020
- 208 GFCI KITCHEN REFERGIRATOR & RANGE - - 300 DECK RAILING IN CORNER A 4" SPHERE SHALL NOT PASS THROUGH - - COMPLETE DOWNSPOUTS AT ENTRY DOORS - - PROVIDE SIDEWALKS AT REAR ENTRANCES -
Alarm Test Passed 4/16/2020 04/16/2020
Occupancy Inspection - Fire Passed 4/16/2020 04/16/2020
Rated Assembly Inspection Passed 4/20/2020 04/20/2020
THE FOLLOWING AREAS ARE APPROVED
Informational
12/26/2019
RC APPROVED 2ND FLOOR ROCK APRROVED. 2ND FLOOR STAIR TOWERS 1ST OK;2ND;3RD; RC approved, 4th layer OK
FIRST FLOOR
Informational
12/26/2019
First layer sheet rock on 1st floor units, garages, storage rooms, mechanical rooms, IT rooms, are approved. Walked with sheetrockers and resolved all issues during inspection.
Above Ceiling Inspection Passed 4/20/2020 04/20/2020
Misc
Corrective Action Required
09/26/2019
Above ceiling is approved for building #2
All Rough Inspection - Commercial Passed 4/20/2020 04/20/2020
Misc
Resolved
04/20/2020
Rough Mechanical Inspection - Commercial Passed 4/20/2020 04/20/2020
Rough Plumbing Inspection - Commercial Passed 4/20/2020 04/20/2020
Final Mechanical Inspection Passed 4/20/2020 04/20/2020
Rough Electrical Inspection - Commercial Passed 4/20/2020 04/20/2020
Water Service Inspection Passed 04/21/2020
Sewer Service Inspection Passed 04/21/2020
Final Electrical Inspection - Commercial Passed 4/20/2020 04/21/2020
Occupancy Inspection - Codes Commercial Full C of O 4/20/2020 4/20/2020 04/21/2020
Misc
Corrective Action Required
04/09/2020
-WATER & SEWER SERVICE PENDING ? - - FOOTING & FOUNDATION SPECIAL INSPECTIONS COMPLETE ? -
Footing Inspection - Commercial Passed 04/21/2020
Documents & Images
Date Uploaded File Type Document Name
05/22/2017 Permit Map
09/27/2017 spec insp
12/20/2017 Receipt Receipt for transaction: 2017-007716
08/07/2018 Letter Codes Building Permit
09/27/2018 Letter Inspection Summary
05/06/2019 Letter INSPECTION SUMMARY
09/20/2019 Letter INSPECTION SUMMARY
09/26/2019 Letter INSPECTION SUMMARY
09/26/2019 Letter INSPECTION SUMMARY
10/01/2019 Letter INSPECTION SUMMARY
10/02/2019 Letter INSPECTION SUMMARY
10/08/2019 Letter INSPECTION SUMMARY
10/18/2019 Letter INSPECTION SUMMARY
11/07/2019 Letter INSPECTION SUMMARY
11/15/2019 Letter INSPECTION SUMMARY
11/25/2019 Receipt Receipt for transaction: 2019-007468
11/26/2019 Letter INSPECTION SUMMARY
11/26/2019 Letter INSPECTION SUMMARY
12/13/2019 Letter INSPECTION SUMMARY
12/19/2019 Letter INSPECTION SUMMARY
12/26/2019 Letter INSPECTION SUMMARY
01/16/2020 Letter INSPECTION SUMMARY
04/09/2020 Letter INSPECTION SUMMARY
04/21/2020 Letter Field Certificate of Occupancy
04/21/2020 Letter Codes Final Certificate of Occupancy
08/03/2020 Letter DS Building Permit
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home