PRCOM20160873
Building Permit - Commercial
Final Completion
THE UNITED METHODIST CHURCH OF LEES SUMM
PARTIAL COMMERCIAL
FOUNDATION AND UNDERSLAB FOR NEW CHURCH AND EDUCATION FACILITY BUILDING PERMIT: PRCOM20152438
04/15/2016
04/19/2016
09/01/2016
Locations
Contacts
A L HUBER INC, Address:10770 EL MONTE, Phone:(913) 341-4880  
CENTRAL PLUMBING HTG & A/C INC, Address:P O BOX 218, Phone:(816) 942-6355  
ELDECON INC, Address:120 SE 30TH ST, Phone:(660) 553-1121  
THE UNITED METHODIST CHURCH OF LEES SUMM, Address:114 SE DOUGLAS ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 06/23/2016
Joe Dir
Misc
Corrective Action Required
06/23/2016

FIRE DEPARTMENT CONNECTION SHALL BE LOCATED WITHIN 100' OF A FIRE HYDRANT. COORDINATE WITH THE PROJECT MANAGER TO CONFIRM LOCATION OF HYDRANTS TO BE INSTALLED.
Misc
Corrective Action Required
06/23/2016

PLANS SHOW AN ELECTRIC BELL ABOVE THE FDC. REPLACE THE ELECTRIC BELL WITH A OUTSIDE HORN/STOBE NOTIFICATION DEVICE TO ACTIVATE ON WATER FLOW ONLY. (VERIFIED AT INSPECTION)
Installation acceptance testing
Corrective Action Required
06/23/2016

2012 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. FIELD AND ACCEPTANCE TESTING WILL BE REQUIRED FOR THE SYSTEM PRIOR TO THE FINAL OCCUPANCY INSPECTION. TO SCHEDULE TESTING CONTACT THE FIRE DEPARTMENT AT 816-969-1300
Building Plan Review Approved 04/15/2016
Joe Frogge
Licensed Contractors Approved 04/15/2016 04/15/2016
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Partial Commercial $241.30 $241.30 Paid 04/18/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 5/2/2016 (1:00) 5/2/2016 05/02/2016
Misc
Partial Correction
05/02/2016
OK TO POUR WHEN READY ALL INTERIOR ISOLATED FOOTINGS.
Footing Inspection - Commercial Partial 5/3/2016 05/03/2016
Misc
Partial Correction
05/03/2016
OK TO POUR WHEN READY ALL INTERIOR ISOLATED FOOTINGS INCLUDING L/5.
Misc
Partial Correction
05/03/2016
OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS AT: D.1/2 TO D.1/2.8; C/2 TO N/2 TO N/10;
Footing Inspection - Commercial Partial 5/4/2016 5/4/2016 05/04/2016
Misc
Partial Correction
05/03/2016
OK TO POUR WHEN READY ALL INTERIOR ISOLATED FOOTINGS INCLUDING L/5.
Misc
Partial Correction
05/03/2016
OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS AT: D.1/2 TO D.1/2.8; C/2 TO N/2 TO N/10; N/10 TO D.1/10 TO D.1/2.8; D.1/9 TO A/9;
Footing Inspection - Commercial Partial 5/5/2016 (1:00) 5/5/2016 05/05/2016
Misc
Partial Correction
05/04/2016
OK TO POUR WHEN READY ALL INTERIOR ISOLATED FOOTINGS INCLUDING L/5.
Misc
Partial Correction
05/04/2016
OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS AT: D.1/2 TO D.1/2.8; C/2 TO N/2 TO N/10; N/10 TO D.1/10 TO D.1/2.8; D.1/9 TO A/9; A/9 TO A/2.6 TO B/2.6; B/9 TO B/1 TO C/1;
Footing Inspection - Commercial Partial 5/6/2016 (10:00) 5/6/2016 05/06/2016
Misc
Partial Correction
05/05/2016
OK TO POUR WHEN READY ALL INTERIOR ISOLATED FOOTINGS INCLUDING L/5.
Misc
Partial Correction
05/05/2016
OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS AT: D.1/2 TO D.1/2.8; C/2 TO N/2 TO N/10; N/10 TO D.1/10 TO D.1/2.8; D.1/9 TO A/9; A/9 TO A/2.6 TO B/2.6; B/9 TO B/1 TO C/1; C/1 TO D.1/2 TO COMPLETE PERIMETER
Underslab Plumbing Inspection - Commercial Partial 5/6/2016 5/6/2016 05/06/2016
Misc
Partial Correction
05/06/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Underslab Plumbing Inspection - Commercial Partial 5/19/2016 5/19/2016 05/19/2016
Misc
Partial Correction
05/06/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; MAIN BLDG DRAIN EXTENDED SOUTH TO UNDER GRADE BEAM @ N/8.2; NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Underslab Plumbing Inspection - Commercial Partial 5/20/2016 5/20/2016 05/20/2016
Misc
Partial Correction
05/19/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; MAIN BLDG DRAIN EXTENDED SOUTH TO UNDER GRADE BEAM @ N/8.2; 4" BRANCH ON B.9 FROM MAIN BLDG DRAIN EAST TO 1.6; NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Underslab Electrical Inspection - Commercial Partial 5/19/2016 5/20/2016 05/20/2016
Misc
Partial Correction
05/20/2016
OK TO COVER WHEN READY UNDERSLAB CONDUIT FOR SECONDARY AND DATACOMM IN 2 TRENCHES FROM EAST B/L TO SPACE (115) -- 30' IN N TRENCH & 45' IN S TRENCH;
Underslab Plumbing Inspection - Commercial Partial 5/23/2016 5/23/2016 05/23/2016
Misc
Partial Correction
05/20/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; MAIN BLDG DRAIN EXTENDED SOUTH TO UNDER GRADE BEAM @ N/8.2; 4" BRANCH ON B.9 FROM MAIN BLDG DRAIN EAST TO 1.6; LATERALS TO AND PIPING AT 103, 104, 127, 152, 153; NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Underslab Electrical Inspection - Commercial Partial 5/23/2016 5/23/2016 05/23/2016
Misc
Partial Correction
05/20/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D);
Underslab Plumbing Inspection - Commercial Partial 5/24/2016 5/24/2016 05/24/2016
Misc
Partial Correction
05/23/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; MAIN BLDG DRAIN EXTENDED SOUTH TO UNDER GRADE BEAM @ N/8.2; 4" BRANCH ON B.9 FROM MAIN BLDG DRAIN EAST TO 1.6; LATERALS TO AND PIPING AT 103, 104, 127, 152, 153; LATERAL TO AND PIPING AT RR 132; NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Underslab Electrical Inspection - Commercial Partial 5/24/2016 5/24/2016 05/24/2016
Misc
Partial Correction
05/23/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153;
Underslab Electrical Inspection - Commercial Partial 5/25/2016 5/25/2016 05/25/2016
Misc
Partial Correction
05/24/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED CONDUIT SOUTH OF (E);
Underslab Plumbing Inspection - Commercial Partial 5/25/2016 5/25/2016 05/25/2016
Misc
Partial Correction
05/24/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; MAIN BLDG DRAIN EXTENDED SOUTH TO UNDER GRADE BEAM @ N/8.2; 4" BRANCH ON B.9 FROM MAIN BLDG DRAIN EAST TO 1.6; LATERALS TO AND PIPING AT 103, 104, 127, 152, 153; LATERAL TO AND PIPING AT RR 132; LATERAL TO AND PIPING AT 139 AND 154, 155, 156; NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Misc
Partial Correction
05/25/2016
OK TO COVER WHEN READY ROOF DRAIN PIPING: TO BELOW GRADE AND UNDER GRADE BEAM AT [105];
Underslab Electrical Inspection - Commercial Partial 5/26/2016 05/26/2016
Misc
Partial Correction
05/25/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED PVC CONDUIT SOUTH OF (E);
Misc
Partial Correction
05/26/2016
OK TO COVER WHEN READY CURRENTLY-INSPECTED PORTIONS OF UNDER-SLAB STEEL AV CONDUIT
Underslab Plumbing Inspection - Commercial Partial 5/26/2016 05/26/2016
Misc
Partial Correction
05/25/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; MAIN BLDG DRAIN EXTENDED SOUTH TO UNDER GRADE BEAM @ N/8.2; 4" BRANCH ON B.9 FROM MAIN BLDG DRAIN EAST TO 1.6; LATERALS TO AND PIPING AT 103, 104, 127, 152, 153; LATERAL TO AND PIPING AT RR 132; LATERAL TO AND PIPING AT 139 AND 154, 155, 156; LATERAL TO AND PIPING AT 146, 148, 153 NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Misc
Partial Correction
05/25/2016
OK TO COVER WHEN READY ROOF DRAIN PIPING: TO BELOW GRADE AND UNDER GRADE BEAM AT [105]; [135]
Misc
Partial Correction
05/26/2016
2" COPPER DOMESTIC WATER SERVICE LINE AT [135] TO BELOW GRADE AND UNDER GRADE BEAM AND 5' OUTSIDE B/L
Underslab Electrical Inspection - Commercial Partial 5/27/2016 05/27/2016
Misc
Partial Correction
05/26/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED PVC CONDUIT SOUTH OF (E);
Misc
Partial Correction
05/26/2016
OK TO COVER WHEN READY CURRENTLY-INSPECTED PORTIONS OF UNDER-SLAB STEEL AV CONDUIT
Underslab Electrical Inspection - Commercial Partial 5/31/2016 05/31/2016
Misc
Partial Correction
05/27/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED PVC CONDUIT SOUTH OF (E);
Misc
Partial Correction
05/27/2016
OK TO COVER WHEN READY CURRENTLY-INSPECTED PORTIONS OF UNDER-SLAB STEEL AV CONDUIT
Underslab Electrical Inspection - Commercial Partial 6/1/2016 06/01/2016
Misc
Partial Correction
05/31/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED PVC CONDUIT SOUTH OF (E);
Misc
Partial Correction
05/31/2016
OK TO COVER WHEN READY CURRENTLY-INSPECTED PORTIONS OF UNDER-SLAB STEEL AV CONDUIT
Underslab Electrical Inspection - Commercial Partial 6/2/2016 06/02/2016
Misc
Partial Correction
06/01/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED PVC CONDUIT SOUTH OF (E);
Misc
Partial Correction
06/01/2016
OK TO COVER WHEN READY UNDER-SLAB RIGID STEEL AV CONDUIT THROUGHOUT EXCEPT APPROX 90LF OF THREE 2" PIPES PRESENTLY BEING TRENCHED NORTH OF (D);
Underground Electrical Inspection - Commercial Partial 6/2/2016 06/02/2016
Misc
Partial Correction
06/02/2016
FOUR 3" PVC CONDUITS FOR BUILDING SERVICE FROM TRANSFORMER LOCATION: TO APPROX 12' SOUTH;
Misc
Partial Correction
06/02/2016
FOUR 3" PVC CONDUITS FOR FUTURE AND ONE 2" FOR TEMPORARY POWER FROM TRANSFORMER LOCATION: TO APPROX 10' WEST;
Underground Electrical Inspection - Commercial Partial 6/3/2016 06/03/2016
Misc
Partial Correction
06/02/2016
FOUR 3" PVC CONDUITS FOR BUILDING SERVICE FROM TRANSFORMER LOCATION: TO APPROX 12' SOUTH; -SERVICE CONDUCTORS RACEWAYS FROM TRANSFORMER PAD TO KCPL CT CABINET
Misc
Partial Correction
06/02/2016
FOUR 3" PVC CONDUITS FOR FUTURE AND ONE 2" FOR TEMPORARY POWER FROM TRANSFORMER LOCATION: TO APPROX 10' WEST;
Underslab Electrical Inspection - Commercial Partial 6/3/2016 06/03/2016
Misc
Partial Correction
06/02/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED PVC CONDUIT SOUTH OF (E);
Misc
Partial Correction
06/02/2016
OK TO COVER WHEN READY UNDER-SLAB RIGID STEEL AV CONDUIT THROUGHOUT EXCEPT APPROX 90LF OF THREE 2" PIPES PRESENTLY BEING TRENCHED NORTH OF (D); -INSPECTED THE REMAINING AV RMC TO EQUIPMENT RM
Underslab Electrical Inspection - Commercial Passed 6/9/2016 6/9/2016 06/09/2016
Misc
Resolved
06/09/2016
OK TO COVER WHEN READY ALL LOWER-LEVEL UNDER-SLAB CONDUIT NORTH OF (D); EXTENSION OF 1-1/4" CONDUIT FROM (D) SW TO 152/153; REMAINDER OF DEEP-TRENCHED PVC CONDUIT SOUTH OF (E);
Misc
Resolved
06/09/2016
OK TO COVER WHEN READY UNDER-SLAB RIGID STEEL AV CONDUIT THROUGHOUT EXCEPT APPROX 90LF OF THREE 2" PIPES PRESENTLY BEING TRENCHED NORTH OF (D); -INSPECTED THE REMAINING AV RMC TO EQUIPMENT RM
Underground Electrical Inspection - Commercial Passed 6/7/2016 6/3/2016 08/19/2016
Misc
Resolved
08/19/2016
FOUR 3" PVC CONDUITS FOR BUILDING SERVICE FROM TRANSFORMER LOCATION: TO APPROX 12' SOUTH; -SERVICE CONDUCTORS RACEWAYS FROM TRANSFORMER PAD TO KCPL CT CABINET
Misc
Resolved
08/19/2016
FOUR 3" PVC CONDUITS FOR FUTURE AND ONE 2" FOR TEMPORARY POWER FROM TRANSFORMER LOCATION: TO APPROX 10' WEST;
Footing Inspection - Commercial Passed 8/30/2016 (1:00) 8/30/2016 08/30/2016
Misc
Resolved
08/30/2016
OK TO POUR WHEN READY ALL INTERIOR ISOLATED FOOTINGS INCLUDING L/5.
Misc
Resolved
08/30/2016
OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS AT: D.1/2 TO D.1/2.8; C/2 TO N/2 TO N/10; N/10 TO D.1/10 TO D.1/2.8; D.1/9 TO A/9; A/9 TO A/2.6 TO B/2.6; B/9 TO B/1 TO C/1; C/1 TO D.1/2 TO COMPLETE PERIMETER
Final Inspection - Commercial Passed 8/30/2016 08/30/2016
Underslab Plumbing Inspection - Commercial Passed 5/26/2016 09/01/2016
Misc
Resolved
09/01/2016
OK TO COVER WHEN READY UNDER-SLAB PVC SANITARY DRAIN, WASTE, & VENT PIPING: MAIN BUILDING DRAIN FROM A.9/6.5 TO D.2/6.5; BRANCH ON (C) TO C.O. OUTSIDE WEST B/L; MAIN BLDG DRAIN EXTENDED SOUTH TO UNDER GRADE BEAM @ N/8.2; 4" BRANCH ON B.9 FROM MAIN BLDG DRAIN EAST TO 1.6; LATERALS TO AND PIPING AT 103, 104, 127, 152, 153; LATERAL TO AND PIPING AT RR 132; LATERAL TO AND PIPING AT 139 AND 154, 155, 156; LATERAL TO AND PIPING AT 146, 148, 153 NOTE IPC 312 / IRC P2503.5.1 REQUIREMENT FOR PRESSURE-TESTING PIPING SYSTEM.
Misc
Resolved
09/01/2016
OK TO COVER WHEN READY ROOF DRAIN PIPING: TO BELOW GRADE AND UNDER GRADE BEAM AT [105]; [135]
Documents & Images
Date Uploaded File Type Document Name
04/18/2016 Letter Codes Building Permit
04/18/2016 Receipt Receipt for transaction: 2016-001199
05/02/2016 Letter Inspection Summary
05/03/2016 Letter Inspection Summary
05/04/2016 Letter Inspection Summary
05/05/2016 Letter Inspection Summary
05/06/2016 Letter Inspection Summary
05/06/2016 Letter Inspection Summary
05/19/2016 Letter Inspection Summary
05/20/2016 Letter Inspection Summary
05/23/2016 Letter Inspection Summary
05/24/2016 Letter Inspection Summary
05/25/2016 Letter Inspection Summary
05/26/2016 Letter Inspection Summary
06/02/2016 Letter Inspection Summary
06/03/2016 Letter Inspection Summary
06/09/2016 Letter Inspection Summary
06/24/2016 Letter Fire (Sprinkler) Plan Review
08/30/2016 Letter Inspection Summary
08/30/2016 Letter Inspection Summary
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home