Permit Application Status

PRCOM20143056


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20143056
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
ALTERATION COMMERCIAL
ALTERATIONS TO MEDICAL OFFICE - RELOCATING LOUNGE, ADDING ULTRASOUND ROOM, EXPANDING WAITING ROOM
10/29/2014
07/02/2015
10/07/2015
Locations
Contacts
GUY GRONBERG ARCHITECTS, Address:113 SE 3RD ST, Phone:(816) 524-0878  
P1 CONSTRUCTION LLC, Address:13605 W 96TH TERR, Phone:(913) 529-5000  
HEARTLAND ELECTRIC CORPORATION, Address:947 LOCUST HILL CIR, Phone:(816) 318-8500  
P1 CONSTRUCTION LLC, Address:13605 W 96TH TERR, Phone:(913) 529-5000  
SAINT LUKES EAST HOSPITAL, Address:901 E 104TH ST MAILSTOP 900N  
DAVID E ROSS CONSTRUCTION CO, Address:10201 E 75TH ST, Phone:(816) 737-2953  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 07/27/2015 07/27/2015
Joe Dir
Misc
Corrective Action Required
07/27/2015

No FD Comments
Licensed Contractors Approved 11/10/2014 07/02/2015
Codes Admin
LC - General Contractor
Resolved
07/02/2015

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
LC - MEP Subs
Resolved
07/02/2015

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Excerpt from Sec. 7-130, Lees Summit Code of Ordinances. Action required: MEP subcontractors are required to be listed on permit. Provide company names of MEP contractors.
Building Plan Review Approved with Conditions 11/10/2014 11/10/2014
Mike Weisenborn
Fire Plan Review Approved with Conditions 11/10/2014 11/10/2014
Mike Weisenborn
Misc
Corrective Action Required
10/30/2014

No FD comments
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Alteration to Commercial $98.97 $98.97 Paid 07/02/2015
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
In-wall Inspection Partial 7/10/2015 7/10/2015 at 12:00 AM 07/10/2015
Misc
Partial Correction
07/10/2015
OK TO COVER WHEN READY WALL CAVITY OPENED FOR INSTALLATION OF ELECTRICAL AND PLUMBING MODIFICATIONS AT LOCATIONS: 3D119;
Final Inspection - Commercial Partial 7/17/2015 at 12:00 AM 07/17/2015
Misc
Partial Correction
07/17/2015
FOLLOWING MODIFIED SPACE(S) OK FOR USE PER SCOPE OF PERMIT: 3D119; SUBJECT TO FIRE DEPARTMENT APPROVAL AT FIANL PHASE INSPECTION
Above Ceiling Inspection Partial 7/24/2015 at 12:00 AM 07/24/2015
Misc
Partial Correction
07/24/2015
NO ISSUES FOUND ON RELATED ABOVE-CEILING DRAIN AND VENT PLUMBING WORK ABOVE AND BELOW 3D119;
In-wall Inspection Partial 7/24/2015 7/24/2015 at 12:00 AM 07/24/2015
Misc
Partial Correction
07/10/2015
OK TO COVER WHEN READY WALL CAVITY OPENED FOR INSTALLATION OF ELECTRICAL AND PLUMBING MODIFICATIONS AT LOCATIONS: 3D119; AFTER MC ELECT CABLE IS SECURED WITHIN 12" OF ENTRY TO BOXES -- 3D127; 128; 129;
Above Ceiling Inspection Partial 8/5/2015 8/5/2015 at 12:00 AM 08/05/2015
Misc
Partial Correction
07/24/2015
NO ISSUES FOUND ON RELATED ABOVE-CEILING DRAIN AND VENT PLUMBING WORK ABOVE AND BELOW 3D119;
Misc
Partial Correction
08/05/2015
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING SPACES: 3D127; 128; 129;
Final Inspection - Commercial Partial 8/11/2015 at 12:00 AM 08/11/2015
Misc
Partial Correction
07/17/2015
FOLLOWING MODIFIED SPACE(S) OK FOR USE PER SCOPE OF PERMIT: 3D119; 127; 128; 129; SUBJECT TO FIRE DEPARTMENT APPROVAL AT FINAL PHASE INSPECTION
In-wall Inspection Partial 8/24/2015 8/24/2015 at 12:00 AM 08/24/2015
Misc
Partial Correction
07/24/2015
OK TO COVER WHEN READY WALL CAVITY OPENED FOR INSTALLATION OF ELECTRICAL AND PLUMBING MODIFICATIONS AT LOCATIONS: 3D119; AFTER MC ELECT CABLE IS SECURED WITHIN 12" OF ENTRY TO BOXES -- 3D127; 128; 129; NO ISSUES FOUND ON NEW CUT-IN ELECTRCIAL BOXES AT 3D126
Above Ceiling Inspection Partial 8/24/2015 at 12:00 AM 08/24/2015
Misc
Partial Correction
08/05/2015
NO ISSUES FOUND ON RELATED ABOVE-CEILING DRAIN AND VENT PLUMBING WORK ABOVE AND BELOW 3D119;
Misc
Partial Correction
08/05/2015
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING SPACES: 3D127; 128; 129; 3D126: REMOVE UNUSED BOX CONNECTOR @ EAST WALL & PLUG OPENING; SUPPORT MC CABLE FROM SLACK WIRES -- NOT FROM CEILING SUPPORT WIRES
Final Inspection - Commercial Partial 8/28/2015 8/28/2015 at 12:00 AM 08/28/2015
Misc
Partial Correction
08/11/2015
FOLLOWING MODIFIED SPACE(S) OK FOR USE PER SCOPE OF PERMIT: 3D119; 127; 128; 129; BREAK RM 3D126 OK FOR USE AFTER TWO ELECT RECEPTS WITHIN 6' OF EDGE OF SINK ARE GFCI-PROTECTED AND BOX AT MICROWAVE RECEPTACLE BOX IS EXTENDED FLUSH WITH COMBUSTIBLE SURFACE; ALSO, WATER SUPPLY TO SINK YET TO BE CONNECTED. SUBJECT TO FIRE DEPARTMENT APPROVAL AT FINAL PHASE INSPECTION
Final Inspection - Commercial Partial 8/31/2015 at 12:00 AM 08/31/2015
Misc
Partial Correction
08/28/2015
FOLLOWING MODIFIED SPACE(S) OK FOR USE PER SCOPE OF PERMIT: 3D119; 127; 128; 129; BREAK RM 3D126; SUBJECT TO FIRE DEPARTMENT APPROVAL AT FINAL PHASE INSPECTION
Miscellaneous Inspection Partial 9/3/2015 at 12:00 AM 09/03/2015
Above Ceiling Inspection Partial 9/12/2015 at 12:00 AM 09/12/2015
Misc
Partial Correction
08/24/2015
NO ISSUES FOUND ON RELATED ABOVE-CEILING DRAIN AND VENT PLUMBING WORK ABOVE AND BELOW 3D119;
Misc
Partial Correction
09/12/2015
PRELIMINARY ABOVE-CEILING INSPECTION IN WAITING ROOM BEING RENOVATED. TO BE RE-INSPECTED 9/14.
Above Ceiling Inspection Partial 9/14/2015 at 12:00 AM 09/14/2015
Misc
Partial Correction
09/12/2015
NO ISSUES FOUND ON CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: ABOVE AND BELOW 3D119; RECEPTION/WAITING ROOM;
Misc
Resolved
09/14/2015
PRELIMINARY ABOVE-CEILING INSPECTION IN WAITING ROOM BEING RENOVATED. TO BE RE-INSPECTED 9/14.
Final Inspection - Commercial Partial 9/14/2015 at 12:00 AM 09/14/2015
Misc
Partial Correction
08/31/2015
FOLLOWING MODIFIED SPACE(S) OK FOR USE PER SCOPE OF PERMIT: 3D119; 127; 128; 129; BREAK RM 3D126; RECEPTION/WAITING ROOM; SUBJECT TO FIRE DEPARTMENT APPROVAL AT FINAL PHASE INSPECTION
Final Inspection - Commercial Passed 10/7/2015 at 12:00 AM 10/07/2015
Misc
Resolved
10/07/2015
FOLLOWING MODIFIED SPACE(S) OK FOR USE PER SCOPE OF PERMIT: 3D119; 127; 128; 129; BREAK RM 3D126; RECEPTION/WAITING ROOM; SUBJECT TO FIRE DEPARTMENT APPROVAL AT FINAL PHASE INSPECTION
Above Ceiling Inspection Passed 10/7/2015 at 12:00 AM 10/07/2015
Misc
Resolved
10/07/2015
NO ISSUES FOUND ON CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: ABOVE AND BELOW 3D119; RECEPTION/WAITING ROOM;
In-wall Inspection Passed 8/24/2015 at 12:00 AM 10/07/2015
Misc
Partial Correction
10/07/2015
OK TO COVER WHEN READY WALL CAVITY OPENED FOR INSTALLATION OF ELECTRICAL AND PLUMBING MODIFICATIONS AT LOCATIONS: 3D119; AFTER MC ELECT CABLE IS SECURED WITHIN 12" OF ENTRY TO BOXES -- 3D127; 128; 129; NO ISSUES FOUND ON NEW CUT-IN ELECTRCIAL BOXES AT 3D126
Miscellaneous Inspection Passed 9/3/2015 at 12:00 AM 10/07/2015
Documents & Images
Date Uploaded File Type Document Name
10/30/2014 Letter Fire Building Plan Review
11/04/2014 Letter Codes P/R Corrections Document
07/02/2015 Letter Codes Building Permit
07/02/2015 Receipt Receipt for transaction: 2015-003771
07/10/2015 Letter Inspection Summary
07/17/2015 Letter Inspection Summary
07/24/2015 Letter Inspection Summary
07/27/2015 Letter Fire (Sprinkler) Plan Review
08/05/2015 Letter Inspection Summary
08/11/2015 Letter Inspection Summary
08/24/2015 Letter Inspection Summary
08/28/2015 Letter Inspection Summary
08/31/2015 Letter Inspection Summary
09/14/2015 Letter Inspection Summary
10/07/2015 Letter Inspection Summary
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home