Permit Application Status

PRCOM20132633


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20132633
Building Permit - Commercial
Final Completion
DRIENIK INVESTMENTS LLC
ALTERATION COMMERCIAL
SOLAR PANELS - 24.71 KW
12/10/2013
12/16/2013
01/31/2014
Locations
Contacts
FACILITY SOLUTIONS GROUP INC, Address:17880 W 99TH ST, Phone:(913) 422-8400  
DRIENIK INVESTMENTS LLC, Address:1009 SE BROWNING ST  
BRIGHTERGY LLC, Address:1712 MAIN STREEET 6TH FLOOR, Phone:(816) 866-0555  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved with Conditions 12/20/2013 12/11/2013
Jim Eden
Misc
Corrective Action Required
12/11/2013

Fire Department- 102.7 Subjects not regulated by this code. Where no applicable standards or requirements are set forth in this code, or are contained within other laws, codes, regulations, ordinances or bylaws adopted by the jurisdiction, compliance with applicable standards of the National Fire Protection Association or other nationally recognized fire safety standards, as approved, shall be deemed as prima facie evidence of compliance with the intent of this code. Nothing herein shall derogate from the authority of the fire code official to determine compliance with codes or standards for those activities or installations within the fire code official’s jurisdiction or responsibility. 102.8 Matters not provided for. Requirements that are essential for the public safety of an existing or proposed activity, building or structure, or for the safety of the occupants thereof, which are not specifically provided for by this code shall be determined by the fire code official. Whereas the 2006 IFC does not address PV systems, this document was reviewd under the 2012 IFC, adopted by the City of Lee's Summit effective Jan. 1, 2014.
Misc
Corrective Action Required
12/11/2013

All markings are subject to site inspection.
Building Plan Review Approved with Conditions 12/20/2013 12/11/2013
Mike Weisenborn
Misc
Corrective Action Required
12/11/2013

Lee's Summit Unified Development Ordinance - Section 8.150.B. Roof-mounted solar collectors located on front or side building roofs, which are visible from the public right-of-way, shall not extend above the peak of the roof plane on which they are mounted, and no portion of the solar collector shall extend more than twenty four (24) inches perpendicular to the point of the roof where it is mounted. Action required - This comment is for information purposes and compliance will be verified on inspection.
Misc
Corrective Action Required
12/11/2013

Lee's Summit Unified Development Ordinance - Section 8.150.A Roof-mounted solar components servicing the collector panel shall be concealed and all exposed metal shall be finished with similar colors to the structure on which it is mounted. Action required - Action required - This comment is for information purposes and compliance will be verified on inspection.
Licensed Contractors Approved 12/20/2013 12/11/2013
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for Alteration to Commercial $45.53 $45.53 Paid 12/16/2013
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Final Electrical Inspection - Commercial Failed 12/31/2013 12/31/2013 at 12:00 AM 12/31/2013
Misc
Corrective Action Required
12/31/2013
-INSTALL DIRECTORY/PLAQUE PER NOTE 4 -REMOVE ENAMEL AT BONDING CONNECTION INSIDE SOLAR AC DISCONNECT
Final Electrical Inspection - Commercial Partial 1/3/2014 1/3/2014 at 12:00 AM 01/03/2014
Misc
Corrective Action Required
12/31/2013
-INSTALL DIRECTORY LABEL REQUIRED PER NEC 705.12(D)(4) AND 705.10 PER NOTE 4. 2 LABELS REQUIRED -THE CONNECTION OF THE PV POWER AND GROUNDING CIRCUIT ON THE SUPPLY SIDE OF THE SERVICE DISCONNECT IS NOT COMPLETED AT THIS POINT, UNTIL AFTER THE METER IS DE-ENERGIZED AND REMOVED
Final Electrical Inspection - Commercial Passed 1/31/2014 at 12:00 AM 01/31/2014
Misc
Resolved
01/31/2014
-INSTALL DIRECTORY LABEL REQUIRED PER NEC 705.12(D)(4) AND 705.10 PER NOTE 4. 2 LABELS REQUIRED -THE CONNECTION OF THE PV POWER AND GROUNDING CIRCUIT ON THE SUPPLY SIDE OF THE SERVICE DISCONNECT IS NOT COMPLETED AT THIS POINT, UNTIL AFTER THE METER IS DE-ENERGIZED AND REMOVED
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home

*PLEASE NOTE - You must be logged in with your registered user account to view any documents related to your permit