Summary
PRCOM20122279
Building Permit - Commercial
Final Completion
STANLEY EVENT SPACE LLC, THE
PARTIAL COMMERCIAL
FOUNDATION ONLY, UNDERSLAB AND SUPER STRUCTURE FULL BUILDING PERMIT - PRCOM20122702
10/15/2012
11/09/2012
04/30/2013
06/10/2013
Locations
Contacts
TXR ARCHITECTS & CONSTRUCTORS, Address:101 CROSSING WEST DR, STE 200, Phone:(573) 552-8145  
STANLEY EVENT SPACE LLC, THE, Address:308 SE DOUGLAS ST  
KANSAS CITY PLUMBING COMPANY LLC, Address:107 W 63RD ST, STE 285, Phone:(816) 591-4433  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved with Conditions 10/31/2012 11/08/2012
Jim Eden
Misc
Corrective Action Required
10/30/2012

Approval is for foundation only. All other comments are preliminary. See attached letter for revisions to the original location of the fire main and riser.
Construction documents for fire alarm systems
Corrective Action Required
10/30/2012

2006 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action required: Provided alarm shop drawings for review and approval.
Misc
Carried Forward
10/30/2012

102.7 Subjects not regulated by this code. Where no applicable standards or requirements are set forth in this code, or are contained within other laws, codes, regulations, ordinances or bylaws adopted by the jurisdiction, compliance with applicable standards of the National Fire Protection Association or other nationally recognized fire safety standards, as approved, shall be deemed as prima facie evidence of compliance with the intent of this code. Nothing herein shall derogate from the authority of the fire code official to determine compliance with codes or standards for those activities or installations within the fire code official’s jurisdiction or responsibility. 102.8 Matters not provided for. Requirements that are essential for the public safety of an existing or proposed activity, building or structure, or for the safety of the occupants thereof, which are not specifically provided for by this code shall be determined by the fire code official. Whereas the 2006 IFC is adopted by the City of Lee's Summit but does not address roof top occupancies, and the 2012 IFC is currently under review for adoption does. The 2012 IFC will be the referenced review document for the roof top portion of this project.
Misc
Corrective Action Required
10/30/2012

Amended IFC 905.3.1 Building height. Class I standpipe systems shall be installed throughout buildings where the floor level of the highest story is located more than two stories above the lowest level of the fire department vehicle access, or where the floor level of the lowest story is located more than two stories below the highest level of fire department vehicle access. Action required: 2 1/2 inch hose valves (standpipe) shall be provided in the main interior stairway with access to the roof.
Address numbers required
Corrective Action Required
10/30/2012

2006 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). Action required: Post the address and suite designations.
Fire protection equipment identification
Corrective Action Required
10/31/2012

2006 IFC 510.1- Identification. Fire protection equipment shall be identified in an approved manner. Rooms containing controls for air-conditioning systems, sprinkler risers and valves, or other fire detection, suppression or control elements shall be identified for the use of the fire department. Approved signs required to identify fire protection equipment and equipment location, shall be constructed of durable materials, permanently installed and readily visible. Action required: The room/space shall be posted.
Misc
Corrective Action Required
10/31/2012

Provide a detail for the space under Stair 1 and how it is to be used for the riser. The size of the space may not be adequate.
Portable fire extinguishers - general
Corrective Action Required
10/31/2012

2006 IFC 906.2 - General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Action required: Show the locations of fire extinguishers throughout the building.
Posting of occupant load
Corrective Action Required
10/31/2012

2006 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. Action required: The occupant load shall be posted in each assembly area, including the roof. Verified at inspection.
Misc
Corrective Action Required
10/31/2012

1006.3 Illumination emergency power. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. In the event of power supply failure, an emergency electrical system shall automatically illuminate the following areas: 1. Aisles and unenclosed egress stairways in rooms and spaces that require two or more means of egress. 2. Corridors, exit enclosures and exit passageways in buildings required to have two or more exits. 3. Exterior egress components at other than the level of exit discharge until exit discharge is accomplished for buildings required to have two or more exits. 4. Interior exit discharge elements, as permitted in Section 1024.1, in buildings required to have two or more exits. 5. Exterior landings, as required by Section 1008.1.5, for exit discharge doorways in buildings required to have two or more exits. The emergency power system shall provide power for a duration of not less than 90 minutes and shall consist of storage batteries, unit equipment or an on-site generator. The installation of the emergency power system shall be in accordance with Section 2702 of the International Building Code. Action required: Provide and show the location of interior and exterior emergency lighting.
Knox box required
Corrective Action Required
10/31/2012

2006 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action required: A Knox box shall be located 6' AFF, over the FDC. An application for a Knox lock may be obtained from the fire department.
Misc
Corrective Action Required
10/31/2012

Provide a detail for the gates on the roof.
Misc
Corrective Action Required
10/31/2012

1008.1.9 Panic and fire exit hardware. Where panic and fire exit hardware is installed, it shall comply with the following: 1. The actuating portion of the releasing device shall extend at least one-half of the door leaf width. 2. The maximum unlatching force shall not exceed 15 pounds (67 N). Each door in a means of egress from a Group A or E occupancy having an occupant load of 50 or more and any Group H occupancy shall not be provided with a latch or lock unless it is panic hardware or fire exit hardware. Exception: A main exit of a Group A occupancy in compliance with Section 1008.1.8.3, Item 2. Electrical rooms with equipment rated 1,200 amperes or more and over 6 feet (1829 mm) wide that contain overcurrent devices, switching devices or control devices with exit access doors must be equipped with panic hardware and doors must swing in the direction of egress. If balanced doors are used and panic hardware is required, the panic hardware shall be the push-pad type and the pad shall not extend more then one-half the width of the door measured from the latch side. Action required: Indicate which doors will have panic hardware.
Misc
Resolved
11/08/2012

Installation of the the fire main and back flow shall be in accordance with LS Public Works Construction Manual and NFPA 24 Section 10.6. Action required: Make correction on the length of pipe under the building to comply with NFPA 24.
Misc
Corrective Action Required
11/08/2012

Permit approved for foundation only. Additional comments are preliminary
TRACY DEISTER 11/08/2012 12:02 PM JIM EDEN HAS APPROVED THE ISSUANCE OF A FOUNDATION ONLY PERMIT. THE CONTRACTOR IS GOING TO SUBMIT A DOCUMENT STATING WHAT WAS AGREED TO ON THE WATER SERVICE SIZE DOMESTIC/FIRE AND LOCATION.
Building Plan Review Approved 10/31/2012 11/08/2012
Tracy Deister
Business License
Corrective Action Required
10/31/2012

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawfull for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required - The general contractor is required to have a minimum of a Class B contractors license with the City of Lee's Summit. Provide the name of the licensed general contractor.
License contractors
Corrective Action Required
10/31/2012

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Expert from Sec. 7-130, Lees Summit Code of Ordinances. Action required - Provide the name of the licensed mechanical, electrical and plumbing contractors.
Bldg - Special inspections - Report requirement
Corrective Action Required
11/01/2012

2006 IBC 1704.1.2 - Report Requirement. Special inspectors shall keep records of inspections. The special inspector shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was done in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If the discrepancies are not corrected, the discrepancies shall be brought to the attention of the building official and to the registered design professional in responsible charge prior to the completion of that phase of the work. A final report documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted at a point in time agreed upon by the permit applicant and the building official prior to the start of work. Action required - This comment is for information purposes.
Bldg - Special inspections - Statement of special inspections
Corrective Action Required
11/01/2012

2006 IBC 1704.1.1 - Statement of special inspections. The permit applicant shall submit a statement of special inspections prepared by the registered design professional in responsible charge in accordance with 106.1 as a condition for permit issuance. This statement shall be in accordance with Section 1705. Exceptions: 1. A statement of special inspections is not required for structures designed and constructed in accordance with the conventional construction provisions of Section 2308. 2. The statement of special inspections is permitted to be prepared by a qualified person approved by the building official for construction not designed by a registered design professional. Action required - Provide a statment of spacial inspections from the company hired to perform them.
Final Development Plan
Corrective Action Required
11/01/2012

The building permit for this project can not be issued until the Codes Administration Department has received the approved Final Development Plan from the Planning and Development Department. Action required - The foundation only permit cannot be issued until the Public Works Department has approved the domestic and fire line locations.
Internal Plan Review (Res) Approved 10/31/2012 11/08/2012
Tracy Deister
True
Final Development Plan Review Approved 11/16/2012 11/07/2012
Tracy Deister
WAITING ON APPROVAL FROM PUBLIC WORKS ON THE DOMESTIC AND FIRE LINE. GENE WILLIAMS HAS APPROVED THE ISSUANCE OF AN AT RISK FOUNDATION UNDERSLAB UTILITIES. TRACY DEISTER 11/07/2012 4:31 PM
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Partial Commercial $559.30 $559.30 Paid 11/09/2012
$559.30
9110078-Additional Permit Fee $30.00 $30.00 Paid 01/02/2013
9110078-Valuation Fee for Partial Commercial $786.22 $786.22 Paid 02/05/2013
$1,345.52
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 11/21/2012 (2:30) 11/21/2012 at 12:00 AM 11/21/2012
Misc
Partial Correction
11/21/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT;
Misc
Partial Correction
11/21/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Footing Inspection - Commercial Partial 11/21/2012 at 12:00 AM 11/21/2012
Misc
Partial Correction
11/21/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT;
Misc
Partial Correction
11/21/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/21/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/26/2012 (3:00) 11/26/2012 at 12:00 AM 11/26/2012
Misc
Partial Correction
11/21/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW TO 9/A.3;
Misc
Partial Correction
11/21/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/21/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/26/2012 at 12:00 AM 11/26/2012
Misc
Partial Correction
11/26/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW TO COMPLETE @ EAST WALL;
Misc
Partial Correction
11/26/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/26/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/27/2012 (3:00) 11/27/2012 at 12:00 AM 11/27/2012
Misc
Partial Correction
11/26/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW TO COMPLETE @ EAST WALL;
Misc
Partial Correction
11/26/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/26/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Misc
Partial Correction
11/27/2012
OK TO POUR WHEN READY ISOLATED COLUMN FOOTINGS AT FOLLOWING LOCATIONS: 9/B; 9/D; 9/F;
Footing Inspection - Commercial Partial 11/28/2012 (1:00) 11/28/2012 at 12:00 AM 11/28/2012
Misc
Partial Correction
11/27/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW ON EAST WALL; ON (A) FROM (9) TO (13) TO COMPLETE EAST WALL
Misc
Partial Correction
11/27/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/27/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Misc
Partial Correction
11/27/2012
OK TO POUR WHEN READY ISOLATED COLUMN FOOTINGS AT FOLLOWING LOCATIONS: 9/B; 9/D; 9/F; 5/F; G/2; /2
Footing Inspection - Commercial Partial 11/28/2012 at 12:00 AM 11/28/2012
Misc
Partial Correction
11/28/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW ON EAST WALL; ON (A) FROM (9) TO (13) TO COMPLETE EAST WALL
Misc
Partial Correction
11/28/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/28/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Misc
Partial Correction
11/28/2012
OK TO POUR WHEN READY ISOLATED COLUMN FOOTINGS AT FOLLOWING LOCATIONS: 9/B; 9/D; 9/F; 5/F; 3/F; G/2; H/5;
Footing Inspection - Commercial Partial 11/30/2012 (10:00) 11/30/2012 at 12:00 AM 11/30/2012
Misc
Partial Correction
11/28/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW ON EAST WALL; ON (A) FROM (9) TO (13) TO COMPLETE EAST WALL
Misc
Partial Correction
11/28/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/28/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Misc
Partial Correction
11/28/2012
OK TO POUR WHEN READY ISOLATED COLUMN FOOTINGS AT FOLLOWING LOCATIONS: 9/B; 9/D; 9/F; 5/F; 3/F; G/2; H/5; B/4; D/4; F/6;
Concrete Walls and Columns Inspection Partial 12/7/2012 at 12:00 AM 12/07/2012
Misc
Partial Correction
12/07/2012
OK TO POUR WHEN READY C.I.P. CONCRETE WALLS & INTEGRAL PILASTERS AT FOLLOWING LOCATIONS: ON (13) FROM (B) TO (H); ON (J) FROM (1) TO (2.2); ON (1) FROM (A) TO (J):
Footing Inspection - Commercial Partial 12/7/2012 (1:00) 12/7/2012 at 12:00 AM 12/07/2012
Misc
Partial Correction
11/30/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW ON EAST WALL; ON (A) FROM (9) TO (13) TO COMPLETE EAST WALL; AROUND ELEVATOR PIT, THEN TO NE CORNER
Misc
Partial Correction
11/30/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
11/30/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Misc
Partial Correction
11/30/2012
OK TO POUR WHEN READY ISOLATED COLUMN FOOTINGS AT FOLLOWING LOCATIONS: 9/B; 9/D; 9/F; 5/F; 3/F; G/2; H/5; B/4; D/4; F/6;
Concrete Walls and Columns Inspection Failed 12/10/2012 12/10/2012 at 12:00 AM 12/10/2012
Misc
Partial Correction
12/07/2012
OK TO POUR WHEN READY C.I.P. CONCRETE WALLS & INTEGRAL PILASTERS AT FOLLOWING LOCATIONS: ON (13) FROM (B) TO (H); ON (J) FROM (1) TO (2.2); ON (1) FROM (A) TO (J): REMAINING WALL @ NE CORNER POURED W/O APPROVAL
Underslab Plumbing Inspection - Commercial Partial 1/2/2013 at 12:00 AM 01/02/2013
Misc
Corrective Action Required
01/02/2013
UNDERSLAB PLUMBING OK BELOW: -1ST FL SANITARY DRAINAGE FROM FLOOR SINK, FLOOR DRAINS, AND BATHRROMS
Underslab Electrical Inspection - Commercial Passed 1/4/2013 at 12:00 AM 01/04/2013
Underslab Plumbing Inspection - Commercial Passed 1/4/2013 at 12:00 AM 01/04/2013
Misc
Resolved
01/04/2013
UNDERSLAB PLUMBING OK BELOW: -1ST FL SANITARY DRAINAGE FROM FLOOR SINK, FLOOR DRAINS, AND BATHRROMS
Sewer Service Inspection Passed 1/14/2013 (1:45) 1/14/2013 at 12:00 AM 01/14/2013
Footing Inspection - Commercial Not Ready 6/6/2013 (9:30) 6/6/2013 at 12:00 AM 06/06/2013
Misc
Partial Correction
12/07/2012
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW ON EAST WALL; ON (A) FROM (9) TO (13) TO COMPLETE EAST WALL; AROUND ELEVATOR PIT, THEN TO NE CORNER
Misc
Partial Correction
12/07/2012
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Partial Correction
12/07/2012
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Misc
Partial Correction
12/07/2012
OK TO POUR WHEN READY ISOLATED COLUMN FOOTINGS AT FOLLOWING LOCATIONS: 9/B; 9/D; 9/F; 5/F; 3/F; G/2; H/5; B/4; D/4; F/6;
Footing Inspection - Commercial Partial 6/6/2013 (2:00) 6/6/2013 at 12:00 AM 06/06/2013
Misc
Resolved
06/06/2013
AFTER FOOTING GROUND JUMPER IS CONNECTED OK TO POUR WHEN READY SECTIONS OF CONCRETE GRADE BEAM + INTEGRAL COLUMN FOOTINGS DESCRIBED BELOW: NORTH WALL; EAST WALL N 15'; S WALL EXCEPT E 10'; W WALL FROM SW CORNER TO ELEVATOR PIT; FROM S WALL ~1/B CCW ON EAST WALL; ON (A) FROM (9) TO (13) TO COMPLETE EAST WALL; AROUND ELEVATOR PIT, THEN TO NE CORNER
Misc
Resolved
06/06/2013
ENSURE FULL 3" RE-BAR COVERAGE AT BOTTOMS AND BANKS
Misc
Resolved
06/06/2013
ELEVATOR PIT SLAB OK TO POUR WHEN READY
Misc
Resolved
06/06/2013
OK TO POUR WHEN READY ISOLATED COLUMN FOOTINGS AT FOLLOWING LOCATIONS: 9/B; 9/D; 9/F; 5/F; 3/F; G/2; H/5; B/4; D/4; F/6;
Misc
Partial Correction
06/06/2013
TWO 24: PIERS FOR FIRE ESCAPE STAIRS + 10' FOOTING FOR FLUME WALL @ NW CORNER OK TO POUR WHEN READY.
Footing Inspection - Commercial Passed 6/7/2013 (8:00) 6/6/2013 at 12:00 AM 06/06/2013
Misc
Resolved
06/06/2013
TWO 24: PIERS FOR FIRE ESCAPE STAIRS + 10' FOOTING FOR FLUME WALL @ NW CORNER OK TO POUR WHEN READY.
Foundation Inspection - Commercial Passed 6/7/2013 at 12:00 AM 06/07/2013
Concrete Walls and Columns Inspection Passed 6/10/2013 at 12:00 AM 06/10/2013
Misc
Resolved
06/10/2013
OK TO POUR WHEN READY C.I.P. CONCRETE WALLS & INTEGRAL PILASTERS AT FOLLOWING LOCATIONS: ON (13) FROM (B) TO (H); ON (J) FROM (1) TO (2.2); ON (1) FROM (A) TO (J): REMAINING WALL @ NE CORNER POURED W/O APPROVAL
Final Inspection - Commercial Passed 6/10/2013 at 12:00 AM 06/10/2013
Documents & Images
Date Uploaded File Type Document Name
11/01/2012 Letter Plan Review Conditions
11/08/2012 Drawing Stanley Event Center Underground Sizing.pdf
11/08/2012 Letter Stanley Event Center Underground Sizing.pdf
11/09/2012 Letter Building Permit
11/21/2012 Letter Inspection Summary
11/26/2012 Letter Inspection Summary
11/27/2012 Letter Inspection Summary
11/28/2012 Letter Inspection Summary
11/30/2012 Letter Inspection Summary
12/07/2012 Letter Inspection Summary
12/07/2012 Letter Inspection Summary
01/02/2013 Letter Inspection Summary
01/04/2013 Letter Inspection Summary
01/14/2013 Letter Inspection Summary
02/07/2013 Activity Document DOC020713-003.pdf
06/07/2013 Letter Inspection Summary
06/10/2013 Letter Inspection Summary
06/25/2013 Letter Fire Building Plan Review
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.