Permit Application Status

B1000794


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B1000794
Building Permit - Commercial
Certificate of Occupancy
SAINT LUKES EAST HOSPITAL
ALTERATION COMMERCIAL
RELOCATE EXISTING MRI TO NEW LOCATION IN DIAGNOSTIC BUILDING. THE EXISTING MRI ROOM WILL THEN BE REMODELED FOR A NEW CT MACHINE. Per John Borns MRI only is approved to occupy until March 3, 2011.
07/14/2010
08/25/2010
04/16/2011
04/15/2011
Locations
Contacts
ACI BOLAND - KANSAS CITY, Address:1421 E 104TH STREET  
J E DUNN CONSTRUCTION, Address:1001 LOCUST  
P1 GROUP INC, Address:16210 WEST 108TH ST  
P1 GROUP INC, Address:16210 WEST 108TH ST  
SHAW ELECTRIC COMPANY, Address:3600 FULLER AVE  
P1 GROUP INC, Address:16210 WEST 108TH ST  
P1 GROUP INC, Address:16210 WEST 108TH ST  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 02/19/2011 10/29/2010
Correction

Fire Department- 2006 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
Correction

Fire Department- 2006 IFC 906.2 - General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department- 2006 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Correction

Fire Department: Medical gas systems including, but not limited to, distribution piping, supply manifolds, connections, pressure regulators, and relief devices and valves, shall comply with NFPA 99 and the general provisions of this chapter. Documentation shall be provided of the pressure test of at least 150 psi for a minimum of 24 hours on installers letterhead.
Correction

Codes Administration - ICC/ANSI A117 2003 803.4 - Benches. A bench complying with Section 903 shall be provided within the room.
Correction

Fire Department- 2006 IFC 901.4 Installation. Fire protection systems shall be maintained in accordance with the original installation standards for that system. Required systems shall be extended, altered, or augmented as necessary to maintain and continue protection whenever the building is altered, remodeled or added to. Alterations to fire protection systems shall be done in accordance with applicable standards.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $2,067.99 $2,067.99 Paid 08/25/2010
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Rough Framing Inspection - Commercial Failed 09/22/2010
Correction
Partial Correction
09/22/2010
MRI IC145 PARENT WALL 1C145- OK TO TOP OUT BOTH SIDES OF WALL. LINE F8-G TO-2.5 -3
Rough Framing Inspection - Commercial Request Complete 9/21/2010 9/22/2010 09/22/2010
All Rough Inspection - Commercial Partial 10/07/2010
Correction
Partial Correction
10/07/2010
OK TO COVER WHEN READY WALLS @SPACES LISTED: WALL FRAMING + IN-WALL SYSTEMS PARENT WALL 1C145 - OK TO TOP OUT BOTH SIDES OF WALL + OK TO 1-SIDE INSIDE FACE;
Rough Framing Inspection - Commercial Request Complete 10/6/2010 10/7/2010 10/07/2010
All Rough Inspection - Commercial Partial 10/12/2010 at 12:00 AM 10/12/2010
Correction
Partial Correction
10/12/2010
WALL FRAMING + IN-WALL SYSTEMS ALL NEW & RENOVATED WALLS @ MRI; OK TO COVER WHEN READY FOLLOWING WALLS:
Rated Assembly Inspection Partial 10/13/2010
Correction
Partial Correction
10/13/2010
1-HR RATED 5/8" TYPE X GWB WALL ASSEMBLY 149 NW WALL; OK TO TAPE/MUD/FIRE-SEAL FOLLOWING LOCATIONS:
Rated Assembly Inspection Partial 10/15/2010
Correction
Partial Correction
10/15/2010
1-HR RATED 5/8" TYPE X GWB WALL ASSEMBLY RATED WALL @ 145 SW CORNER (145 FACE) OK FOR SHIELDING INSTALLATION AFTER P1 LOW VOLTAGE WIRE PENETRATIONS ARE FIRE-SEALED; OK TO TAPE/MUD/FIRE-SEAL FOLLOWING LOCATIONS:
Rated Assembly Inspection Partial 10/18/2010
Correction
Partial Correction
10/18/2010
1-HR RATED 5/8" TYPE X GWB WALL ASSEMBLY RATED WALL @ 145 SW CORNER (145 FACE) OK FOR SHIELDING INSTALLATION AFTER P1 LOW VOLTAGE WIRE PENETRATIONS ARE FIRE-SEALED; OK TO TAPE/MUD/FIRE-SEAL FOLLOWING LOCATIONS:
Rated Assembly Inspection Partial 10/19/2010
Correction
Partial Correction
10/19/2010
1-HR RATED 5/8" TYPE X GWB WALL ASSEMBLY RATED WALL @ 145 SW CORNER (145 FACE) OK FOR SHIELDING INSTALLATION; OK TO TAPE/MUD/FIRE-SEAL FOLLOWING LOCATIONS:
In-wall Inspection Partial 11/8/2010 at 12:00 AM 11/08/2010
Misc
Partial Correction
11/08/2010
OK TO COVER WHEN READY: WOOD FRAMING & IN-WALL SYSTEMS AT INNER WALL OF SPACE 1C145;
Above Ceiling Inspection Passed 3/8/2011 at 12:00 AM 12/13/2010
Alarm Test Passed 12/21/2010 at 12:00 AM 12/21/2010
Corrective Action Required
12/21/2010
All new and relocated alarm notification devices operated during the test
Occupancy Inspection - Fire Temporary C of O 01/03/2011
In-wall Inspection Partial 01/03/2011
Misc
Partial Correction
11/08/2010
OK TO COVER WHEN READY: WOOD FRAMING & IN-WALL SYSTEMS AT INNER WALL OF SPACE 1C145;
Occupancy Inspection - Codes Commercial Not Ready 1/3/2011 at 12:00 AM 01/03/2011
Misc
Corrective Action Required
01/03/2011
TESTING OF ELECTRICAL RECEPTACLES NOT READY FOR INSPECTION DUE TO INTENTIONAL DELAY IN COMPLETING TERMINATIONS AT GROUNDING BUS BAR;
Misc
Corrective Action Required
01/03/2011
SMOKE GASKET TO BE INSTALLED AT DOOR IC147
In-wall Inspection Passed 2/14/2011 at 12:00 AM 02/14/2011
Misc
Resolved
02/14/2011
OK TO COVER WHEN READY: WOOD FRAMING & IN-WALL SYSTEMS AT INNER WALL OF SPACE 1C145;
Occupancy Inspection - Codes Commercial Partial 2/14/2011 at 12:00 AM 02/14/2011
Misc
Resolved
02/14/2011
TESTING OF ELECTRICAL RECEPTACLES NOT READY FOR INSPECTION DUE TO INTENTIONAL DELAY IN COMPLETING TERMINATIONS AT GROUNDING BUS BAR;
Misc
Resolved
02/14/2011
SMOKE GASKET TO BE INSTALLED AT DOOR IC147
Misc
Corrective Action Required
02/14/2011
RESOLVE FIRE DEPARTMENT ISSUES
Occupancy Inspection - Fire Temporary C of O 2/14/2011 at 12:00 AM 02/14/2011
Corrective Action Required
02/14/2011
(1) PATIENT DRESSING ROOMS NEED MESHED TOP CURTAINS INSTALLED (2) DOCUMENTATION OF THE EMERGENCY SHUT DOWN SWICTH OPERATING AS DESIGNED. (3) LABEL THE SUITE DOORS OFF THE CORRIDOR WITH THE APPROPRIATE WARNING SIGNAGE.
Occupancy Inspection - Fire Temporary C of O 2/15/2011 at 12:00 AM 02/15/2011
In-wall Inspection Partial 2/15/2011 at 12:00 AM 02/15/2011
Misc
Corrective Action Required
02/15/2011
WALL FRAMING AND IN-WALL SYSTEMS OK TO COVER WHEN READY AFTER ONE LOOSE DOOR FRAME IS FULLY SECURED.
Occupancy Inspection - Codes Commercial Temporary C of O 2/15/2011 at 12:00 AM 02/15/2011
Misc
Resolved
02/15/2011
TESTING OF ELECTRICAL RECEPTACLES NOT READY FOR INSPECTION DUE TO INTENTIONAL DELAY IN COMPLETING TERMINATIONS AT GROUNDING BUS BAR;
Misc
Resolved
02/15/2011
SMOKE GASKET TO BE INSTALLED AT DOOR IC147
Misc
Corrective Action Required
02/15/2011
RESOLVE FIRE DEPARTMENT ISSUES.
Above Ceiling Inspection Failed 3/8/2011 3/8/2011 at 12:00 AM 03/08/2011
Misc
Corrective Action Required
03/08/2011
HVAC AIR DUCT INSULATION TO BE COMPLETED.
Misc
Corrective Action Required
03/08/2011
ONE ELECT BOX @ E WALL OPEN
Misc
Corrective Action Required
03/08/2011
SEAL SMOKE WALL @ CORRIDOR
Above Ceiling Inspection Passed 3/9/2011 at 12:00 AM 03/09/2011
Misc
Resolved
03/09/2011
HVAC AIR DUCT INSULATION TO BE COMPLETED.
Misc
Resolved
03/09/2011
ONE ELECT BOX @ E WALL OPEN
Misc
Resolved
03/09/2011
SEAL SMOKE WALL @ CORRIDOR
Occupancy Inspection - Codes Commercial Partial 3/30/2011 3/31/2011 at 12:00 AM 03/31/2011
Misc
Partial Correction
03/31/2011
CT AREA OK TO SET UP FOR BUSINESS.
Occupancy Inspection - Fire Temporary C of O 3/31/2011 at 12:00 AM 03/31/2011
Misc
Corrective Action Required
03/31/2011
OK FOR TCO OF CT ROOM TO SET UP EQUIPMENT WHEN APPROVED BY CODES ADMINISTRATION
In-wall Inspection Passed 4/7/2011 at 12:00 AM 04/07/2011
Misc
Resolved
04/07/2011
WALL FRAMING AND IN-WALL SYSTEMS OK TO COVER WHEN READY AFTER ONE LOOSE DOOR FRAME IS FULLY SECURED.
Occupancy Inspection - Codes Commercial Temporary C of O 4/7/2011 at 12:00 AM 04/07/2011
Misc
Partial Correction
03/31/2011
CT AREA OK TO SET UP FOR BUSINESS.
Final Inspection - Commercial Passed 4/15/2011 at 12:00 AM 04/15/2011
Occupancy Inspection - Fire Passed 4/15/2011 at 12:00 AM 04/15/2011
Misc
Corrective Action Required
04/15/2011
OK FOR TCO OF CT ROOM TO SET UP EQUIPMENT WHEN APPROVED BY CODES ADMINISTRATION
Occupancy Inspection - Codes Commercial Full C of O 4/15/2011 at 12:00 AM 05/05/2011
Misc
Partial Correction
05/05/2011
CT AREA OK TO SET UP FOR BUSINESS.
Rated Assembly Inspection Passed 5/17/2011 at 12:00 AM 05/17/2011
Correction
Resolved
05/17/2011
1-HR RATED 5/8" TYPE X GWB WALL ASSEMBLY RATED WALL @ 145 SW CORNER (145 FACE) OK FOR SHIELDING INSTALLATION; OK TO TAPE/MUD/FIRE-SEAL FOLLOWING LOCATIONS:
Documents & Images
Date Uploaded File Type Document Name
11/08/2010 Letter Inspection Summary
12/13/2010 Letter Inspection Summary
12/21/2010 Letter Fire Loss Reduction Form
01/03/2011 Letter Fire Loss Reduction Form
02/14/2011 Letter Inspection Summary
02/14/2011 Letter Fire Loss Reduction Form
02/15/2011 Letter Temporary Certificate of Occupancy
02/15/2011 Letter Inspection Summary
03/02/2011 Letter Temporary Certificate of Occupancy
03/08/2011 Letter Inspection Summary
03/09/2011 Letter Inspection Summary
03/31/2011 Letter Inspection Summary
03/31/2011 Letter Inspection Summary
04/07/2011 Letter Temporary Certificate of Occupancy
04/15/2011 Letter Final Certificate of Occupancy
04/15/2011 Letter Fire Loss Reduction Form
05/05/2011 Letter Field Certificate of Occupancy
05/17/2011 Letter Inspection Summary
05/18/2011 Letter Final Certificate of Occupancy
06/21/2013 Letter Fire Loss Reduction Form
08/27/2013 Letter Temporary Certificate of Occupancy
08/27/2013 Letter Temporary Certificate of Occupancy
08/28/2013 Letter Temporary Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home