Permit Application Status

B1000039


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B1000039
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
NEW SHELL BUILDING
NEW TWO STORY BUILDING Mike Weisenborn 09/20/2012 8:34 AM - THE FOLLOWING WORK HAS BEEN MOVED FROM THIS PERMIT TO PRCOM20121010. COMPLETION OF VESTIBULE 1F008. COMPLETION OF ENTRANCE 1F007B. COMPLETION OF SITE WORK NORTH OF BUILDING AS SHOWN ON SHEET C2.0 AND C3.0
01/19/2010
03/09/2010
04/25/2011
09/24/2012
Locations
Contacts
ACI BOLAND, Address:11229 NALL SUITE 140  
J E DUNN CONSTRUCTION, Address:929 HOLMES  
P1 GROUP INC, Address:16210 WEST 108TH ST  
P1 GROUP INC, Address:16210 WEST 108TH ST  
STRUCTURAL ENGINEERING ASSOCIATES INC, Address:1000 WALNUT SUITE 1570  
SHAW ELECTRIC COMPANY, Address:3600 FULLER AVE  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 09/01/2010 10/29/2010
Correction

Fire Department- 2006 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenat commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).
Correction

Fire Department- 2006 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official.
Correction

Fire Department- 2006 IFC 510.1- Identification. Fire protection equipment shall be identified in an approved manner. Rooms containing controls for air-conditioning systems, sprinkler risers and valves, or other fire detection, suppression or control elements shall be identified for the use of the fire department. Approved signs required to identify fire protection equipment and equipment location, shall be constructed of durable materials, permanently installed and readily visible.
Correction

Fire Department- 2006 IFC 703.1- Maintenance. The required fire-resistance rating of fire-resistance-rated construction (including walls, firestops, shaft enclosures, partitions, smoke barriers, floors, fire-resistive coatings and sprayed fire-resistant materials applied to structural members and fire-resistant joint systems) shall be maintained. Such elements shall be properly repaired, restored or replaced when damaged, altered, breached or penetrated. Openings made therein for the passage of pipes, electrical conduit, wires, ducts, air transfer openings and holes made for any reason shall be protected with approved methods capable of resisting the passage of smoke and fire. Openings through fire-resistance-rated assemblies shall be protected by self- or automatic-closing doors of approved construction meeting the fire protection requirements for the assembly.
Correction

Fire Department- 2006 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
Correction

Fire Department- 2006 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
Correction

Fire Department- 2006 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Correction

Fire Department: Medical gas systems including, but not limited to, distribution piping, supply manifolds, connections, pressure regulators, and relief devices and valves, shall comply with NFPA 99 and the general provisions of this chapter. Documentation shall be provided of the pressure test of at least 150 psi for a minimum of 24 hours on installers letterhead.
Correction

Codes Administration - 2006 IBC 1704.1.1 - Statement of special inspections. The permit applicant shall submit a statement of special inspections prepared by the registered design professional in responsible charge in accordance with 106.1 as a condition for permit issuance. This statement shall be in accordance with Section 1705. Exceptions: 1. A statement of special inspections is not required for structures designed and constructed in accordance with the conventional construction provisions of Section 2308. 2. The statement of special inspections is permitted to be prepared by a qualified person approved by the building official for construction not designed by a registered design professional.
Correction

Codes Administration - 2006 IBC 1704.1.2 - Report Requirement. Special inspectors shall keep records of inspections. The special inspector shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was done in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If the discrepancies are not corrected, the discrepancies shall be brought to the attention of the building official and to the registered design professional in responsible charge prior to the completion of that phase of the work. A final report documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted at a point in time agreed upon by the permit applicant and the building official prior to the start of work.
Correction

Codes Administration - 2006 IBC 3006.4 - Machine rooms and machinery spaces. Elevator machine rooms and machinery spaces shall be enclosed with fire barriers with a fire-resistance rating not less than the required rating of the hoistway enclosure served by the machinery. Openings shall be protected with assemblies having a fire-protection rating not less than that required for the hoistway enclosure doors.
Correction

Codes Administration - The egress information provided on Sheet A0.5 does not reflect exiting from the existing hospital building.
Correction

Fire Department- What is the proposed use of the space? Door widths for a Group I2 occupancy shall have a minimum width of 41.5 inches.
Correction

Fire Department- Unable to locate information on the exterior door hardware on door 1F013D. The door shall be openable from the exterior with a key.
Correction

Fire Department- For IT room additions. Adjust sprinkler coverage per NFPA 13.
Correction

Fire Department- Elevator Addition. Revise shell building fire sprinkler plans.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $27,163.14 $27,163.14 Paid 03/09/2010
84 Water Meters $1,291.95 $1,291.95 Paid 03/09/2010
85 Water Taps $62,016.00 $62,016.00 Paid 03/09/2010
9123001-Escrow Deposit $10,878.99 $10,878.99 Paid 07/06/2011
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Commercial Partial 11/30/2010 at 12:00 AM 03/25/2010
Correction
Partial Correction
03/25/2010
SHEET S1.0 - WALL INSPECTION - ADDED FREIGHT ELEVATOR PR12 - INSPECTION COMPLETED BY 3rd PARTY INSPECTOR
Miscellaneous Inspection Partial 03/30/2010
Correction
Partial Correction
03/30/2010
ON-GOING COORDINATION
Footing Inspection - Commercial Passed 04/14/2010
Correction
Resolved
04/14/2010
PREPARATION TO POUR ELEVATOR PIT BASE SLAB OK TO POUR WHEN READY
Concrete Walls and Columns Inspection Partial 04/19/2010
Correction
Partial Correction
04/19/2010
PREPARATION TO POUR ELEVATOR PIT WALLS OK TO POUR WHEN READY FOOTING TO GRADE
Footing Inspection - Commercial Partial 04/22/2010
Correction
Partial Correction
04/22/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS ON 12 FROM CC.5 TO EE; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 04/28/2010
Correction
Partial Correction
04/28/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS ON 12 FROM CC.5 TO EE; 12/EE.3 TO EE/12 TO EE/10 TO L.2/6.5; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underground Plumbing Inspection - Commercial Partial 04/30/2010
Correction
Partial Correction
04/30/2010
UNDERGROUND SANITARY PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
04/30/2010
UNDERGROUND ROOF DRAIN STORM PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2 (APPROVED CONTINGENT ON A/E VERIFICATION OF SIZE REDUCTION FROM 10" TO 6"); OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 4/30/2010 4/30/2010 04/30/2010
Footing Inspection - Commercial Partial 05/04/2010
Correction
Partial Correction
05/04/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS 12/CC.5 TO 12/EE; 12/EE.3 TO EE/12 TO EE/10 TO L.2/6.5; J.3/6 TO J.3/5.6; 6.2/H.2 TO 6.2/J.8 TO 6.4/L; J.5/6 TO J.5/6.3; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Concrete Walls and Columns Inspection Partial 05/05/2010
Correction
Resolved
05/05/2010
PREPARATION TO POUR ELEVATOR PIT WALLS FOOTING TO GRADE
Correction
Partial Correction
05/05/2010
PERPARATION TO POUR ELEVATOR SHAFT WALLS 1ST LEVEL; OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Underground Electrical Inspection - Commercial Partial 05/05/2010
Correction
Partial Correction
05/05/2010
INSTALLATION OF SECONDARY ELECTRICAL SERVICE CONDUIT BELOW GRADE BEAM AT E/2.3; FOUR 4" PVC + TWO 4" PVC DATACOM
Underground Plumbing Inspection - Commercial Partial 05/05/2010
Correction
Partial Correction
05/05/2010
UNDERGROUND SANITARY PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2; 4" C.I. FROM H.6/6 TO H.6/4.9 TO F.2/4.9; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Foundation Inspection - Commercial Partial 05/06/2010
Correction
Partial Correction
05/06/2010
PREPARATION TO POUR PERIMETER FOUNDATION WALL EE/10.4 TO EE/12 TO 12/CC.6; OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Footing Inspection - Commercial Partial 05/06/2010
Correction
Partial Correction
05/06/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS 12/CC.5 TO 12/EE; 12/EE.3 TO EE/12 TO EE/10 TO L.2/6.5; J.3/6 TO J.3/5.6; 6.2/H.2 TO 6.2/J.8 TO 6.4/L; J.5/6 TO J.5/6.3; 7/M.7 TO 7/D TO BB/14; 7/D TO AA/13 TO D/6 TO D/7; 9/M.2 TO 9/12; F/6 TO F/8; 11/EE TO 9/L; 12/DD TO 9/L; H/6.2 TO H/10; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Concrete Walls and Columns Inspection Partial 05/07/2010
Correction
Partial Correction
05/07/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS D/7; F/7; H/7; L/7; L/9; BB/14; CC/14; F/8; AA/13; DD/12; EE/12; EE/11; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Footing Inspection - Commercial Partial 05/07/2010
Correction
Resolved
05/07/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS 12/CC.5 TO 12/EE; 12/EE.3 TO EE/12 TO EE/10 TO L.2/6.5; J.3/6 TO J.3/5.6; 6.2/H.2 TO 6.2/J.8 TO 6.4/L; J.5/6 TO J.5/6.3; 7/M.7 TO 7/D TO BB/14; 7/D TO AA/13 TO D/6 TO D/7; 9/M.2 TO 9/12; F/6 TO F/8; 11/EE TO 9/L; 12/DD TO 9/L; H/6.2 TO H/10; CONT'D. OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Correction
Partial Correction
05/07/2010
PREP TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D D/6 TO F.3/6; D/6 TO D/6.3; D/6 TO AA/12; D/6 TO B.7/6; D/6 TO D/5.4; F/6.3 TO F/5.5; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underground Plumbing Inspection - Commercial Partial 05/11/2010
Correction
Partial Correction
05/11/2010
UNDERGROUND SANITARY PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2; 4" C.I. FROM H.6/6 TO H.6/4.9 TO F.2/4.9; H.8/6.3 TO H.8/7.2; H.8/6.9 TO F/6.9; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
05/11/2010
UNDERGROUND ROOF DRAIN STORM PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2 (APPROVED CONTINGENT ON A/E VERIFICATION OF SIZE REDUCTION FROM 10" TO 6"); H.8/6.3 TO H.8/7.2; H.8/6.9 TO F/6.9; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Concrete Walls and Columns Inspection Partial 05/12/2010
Correction
Partial Correction
05/12/2010
PERPARATION TO POUR ELEVATOR SHAFT WALLS 1ST LEVEL; OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
05/12/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS D/7; F/7; H/7; L/7; L/9; BB/14; CC/14; F/8; AA/13; DD/12; EE/12; EE/11; H/9; EE/12; J.5/6; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Correction
Partial Correction
05/12/2010
PREPARATION TO POUR STAIRWELL WALLS 1ST LEVEL W & E WALLS; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underground Plumbing Inspection - Commercial Partial 05/12/2010
Correction
Partial Correction
05/12/2010
UNDERGROUND SANITARY PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2; 4" C.I. FROM H.6/6 TO H.6/4.9 TO F.2/4.9; H.8/6.3 TO H.8/7.2; H.8/6.9 TO F/6.9 TO D.2/6.9 TO D.2/6; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
05/12/2010
UNDERGROUND ROOF DRAIN STORM PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2 (APPROVED CONTINGENT ON A/E VERIFICATION OF SIZE REDUCTION FROM 10" TO 6"); H.8/6.9 TO F/6.9 TO D.2/6.9 TO D.2/6; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/11/2010 5/12/2010 05/12/2010
Concrete Walls and Columns Inspection Partial 05/13/2010
Correction
Partial Correction
05/13/2010
PREPARATION TO POUR STAIRWELL WALLS 1ST LEVEL W & E WALLS; 1ST LEVEL N WALL; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underground Plumbing Inspection - Commercial Not Ready 05/13/2010
Correction
Corrective Action Required
05/13/2010
READINESS FOR INSPECTION WORK REQUESTED FOR INSP NOT COMPLETED
Underground Plumbing Inspection - Commercial Request Complete 5/12/2010 5/13/2010 05/13/2010
Concrete Walls and Columns Inspection Partial 05/14/2010
Correction
Partial Correction
05/14/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS D/7; F/7; H/7; L/7; L/9; BB/14; CC/14; F/8; AA/13; DD/12; EE/12; EE/11; H/9; EE/12; J.5/6; D/6; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Underground Plumbing Inspection - Commercial Partial 05/14/2010
Correction
Partial Correction
05/14/2010
UNDERGROUND SANITARY PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2; 4" C.I. FROM H.6/6 TO H.6/4.9 TO F.2/4.9; H.8/6.3 TO H.8/7.2; H.8/6.9 TO F/6.9 TO D.2/6.9 TO D.2/6; H.8/6.9 TO H.8/7.8 TO 7.8/L.2; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
05/14/2010
UNDERGROUND ROOF DRAIN STORM PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2 (APPROVED CONTINGENT ON A/E VERIFICATION OF SIZE REDUCTION FROM 10" TO 6"); H.8/6.9 TO F/6.9 TO D.2/6.9 TO D.2/6; H.8/6.9 TO H.8/7.8 TO 7.8/L.2; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Resolved
05/14/2010
READINESS FOR INSPECTION
Underground Plumbing Inspection - Commercial Request Complete 5/13/2010 5/14/2010 05/14/2010
Footing Inspection - Commercial Partial 05/18/2010
Correction
Partial Correction
05/18/2010
PREP TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D D/6 TO F.3/6; D/6 TO D/6.3; D/6 TO AA/12; D/6 TO B.7/6; D/6 TO D/5.4; F/6.3 TO F/5.5; COMPLETION OF TIE BEAMS ON (7) & (9) INTO NORTH FOUNDATION WALL; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underground Electrical Inspection - Commercial Partial 05/18/2010
Correction
Partial Correction
05/18/2010
INSTALLATION OF SECONDARY ELECTRICAL SERVICE CONDUIT FOUR 4" PVC BELOW GRADE BEAM AT E/2.3; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
05/18/2010
INSTALLATION OF UNDERGROUND DATACOMM CONDUIT TWO 4" PVC BELOW GRADE BEAM AT E/2.3; TWO 4" PVC FROM E/2.3 TO PHONE ROOM 002; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Foundation Inspection - Commercial Partial 05/18/2010
Correction
Partial Correction
05/18/2010
PREPARATION TO POUR PERIMETER FOUNDATION WALL EE/10.4 TO EE/12 TO 12/CC.6; EE/10.4 TO L.3/6.5 (RE-BAR DOWLING APPROVED BY SEA); OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Footing Inspection - Commercial Partial 05/19/2010
Correction
Partial Correction
05/19/2010
PREP TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D D/6 TO F.3/6; D/6 TO D/6.3; D/6 TO AA/12; D/6 TO B.7/6; D/6 TO D/5.4; F/6.3 TO F/5.5; COMPLETION OF TIE BEAMS ON (7) & (9) INTO N FOUNDATION WALL; 7/M.8 TO 7/P TO 6/N TO 5/M; 6/N TO 6/M.4; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underground Plumbing Inspection - Commercial Partial 05/19/2010
Correction
Partial Correction
05/19/2010
UNDERGROUND ROOF DRAIN STORM PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2 (APPROVED CONTINGENT ON A/E VERIFICATION OF SIZE REDUCTION FROM 10" TO 6"); H.8/6.9 TO F/6.9 TO D.2/6.9 TO D.2/6; H.8/6.9 TO H.8/7.8 TO 7.8/L.2; 8.5/L.1 TO 8.5/M.2 TO CONN TO CORRUGATED @ EE/10.2; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/18/2010 5/19/2010 05/19/2010
Concrete Walls and Columns Inspection Partial 05/20/2010
Correction
Partial Correction
05/20/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS D/7; F/7; H/7; L/7; L/9; BB/14; CC/14; F/8; AA/13; DD/12; EE/12; EE/11; H/9; EE/12; J.5/6; D/6; P/7; N/6; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Footing Inspection - Commercial Partial 05/21/2010
Correction
Partial Correction
05/21/2010
PREP TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D D/6 TO F.3/6; D/6 TO D/6.3; D/6 TO AA/12; D/6 TO B.7/6; D/6 TO D/5.4; F/6.3 TO F/5.5; COMPLETION OF TIE BEAMS ON (7) & (9) INTO N FOUNDATION WALL; 7/M.8 TO 7/P TO 6/N TO 5/M; 6/N TO 6/M.4; M/5 TO J/5 TO H.3/4.2; K/3 TO F.7/4 TO F.3/2; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 05/24/2010
Correction
Resolved
05/24/2010
PREP TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D D/6 TO F.3/6; D/6 TO D/6.3; D/6 TO AA/12; D/6 TO B.7/6; D/6 TO D/5.4; F/6.3 TO F/5.5; COMPLETION OF TIE BEAMS ON (7) & (9) INTO N FOUNDATION WALL; 7/M.8 TO 7/P TO 6/N TO 5/M; 6/N TO 6/M.4; M/5 TO J/5 TO H.3/4.2; K/3 TO F.7/4 TO F.3/2; CONT'D OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Correction
Partial Correction
05/24/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS M/5 TO K/3; H/5 TO B.5/3; C/1 TO D/4 TO D.5.7; E/2 TO F/4 TO F/5.7; D/4 TO F/4; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Concrete Walls and Columns Inspection Partial 05/25/2010
Correction
Partial Correction
05/25/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS D/7; F/7; H/7; L/7; L/9; BB/14; CC/14; F/8; AA/13; DD/12; EE/12; EE/11; H/9; EE/12; J.5/6; D/6; P/7; N/6; D/5; F/5; H/5; J/5; M/5; D/4; F/4; G/3; K/3; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Suspended Slab Inspection Passed 05/25/2010
Correction
Resolved
05/25/2010
INSPECTION OF PAN-FORMED SUSPENDED SLABS DEFERRED TO INSPECTION BY STRUCTURAL ENGINEER 2ND FLOOR & ROOF CITY INSPECTION WAIVED
Footing Inspection - Commercial Partial 06/15/2010
Correction
Partial Correction
06/15/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS M/5 TO K/3; H/5 TO B.5/3; C/1 TO D/4 TO D.5.7; E/2 TO F/4 TO F/5.7; D/4 TO F/4; 6/B.8 TO 6/B TO 5/B TO 1/A TO 1/C TO 1/E TO E/2 TO E/2.3; E/2 TO F/4; C/1 TO D/4; 5/B.3 TO 5/B; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Concrete Walls and Columns Inspection Partial 06/16/2010
Correction
Partial Correction
06/16/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS COLUMNS @ LOCATIONS: D/7; F/7; H/7; L/7; L/9; BB/14; CC/14; F/8; AA/13; DD/12; EE/12; EE/11; H/9; EE/12; J.5/6; D/6; P/7; N/6; D/5; F/5; H/5; J/5; M/5; D/4; F/4; G/3; K/3; B/6; B/5; 1/A; 1/C; 1/E; E/2; 1ST LEVEL OK TO POUR WHEN READY
Correction
Partial Correction
06/16/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS -- 2ND LEVEL F/7; D/7; BB/14; CC/14; F/8; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Concrete Walls and Columns Inspection Partial 06/25/2010
Correction
Resolved
06/25/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS COLUMNS @ LOCATIONS: D/7; F/7; H/7; L/7; L/9; BB/14; CC/14; F/8; AA/13; DD/12; EE/12; EE/11; H/9; EE/12; J.5/6; D/6; P/7; N/6; D/5; F/5; H/5; J/5; M/5; D/4; F/4; G/3; K/3; B/6; B/5; 1/A; 1/C; 1/E; E/2; 1ST LEVEL OK TO POUR WHEN READY
Correction
Partial Correction
06/25/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS -- 2ND LEVEL F/7; D/7; BB/14; CC/14; F/8; N/6; J/5; H/5*; P/7; O/9; EE/11; EE/12; DD/12; H/9; H/7; L/7; L/9; *INSTALLATION OF TIES IN PROGRESS OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Concrete Walls and Columns Inspection Partial 07/01/2010
Correction
Partial Correction
07/01/2010
PERPARATION TO POUR ELEVATOR SHAFT WALLS 1ST LEVEL; 2ND LEVEL EAST WALL, SOUTH WALL, & S 12' OF WEST WALL; OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
07/01/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS -- 2ND LEVEL F/7; D/7; BB/14; CC/14; F/8; N/6; J/5; H/5*; P/7; O/9; EE/11; EE/12; DD/12; H/9; H/7; L/7; L/9; G/3; K/3; M/5; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Concrete Walls and Columns Inspection Partial 07/02/2010
Correction
Partial Correction
07/02/2010
PERPARATION TO POUR ELEVATOR SHAFT WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
07/02/2010
PREPARATION TO POUR STAIRWELL WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Concrete Walls and Columns Inspection Partial 07/21/2010
Correction
Resolved
07/21/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS -- 2ND LEVEL F/7; D/7; BB/14; CC/14; F/8; N/6; J/5; H/5*; P/7; O/9; EE/11; EE/12; DD/12; H/9; H/7; L/7; L/9; G/3; K/3; M/5; AA/13; B/6; B/5; A/1; C/1; E/1; D/4; D/5; D/6; F/4; F/5; E/2 OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Concrete Walls and Columns Inspection Partial 08/03/2010
Correction
Partial Correction
08/03/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS - ROOF LEVEL PERIMETER STUB COLUMNS AT G/3 & H/9 AND N/NW THEREOF; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Concrete Walls and Columns Inspection Partial 08/09/2010
Correction
Partial Correction
08/09/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS - ROOF LEVEL ALL STUB COLUMNS (EXCLUDES SHAFT COLUMNS AND MEZZANINE COLUMNS); ENSURE CONNECTOR TOPS ARE SEALED AGAINST CONCRETE ENTRY. MINIMIZE AMOUNT OF ENCRUSTED CONCRETE ON RE-BAR AND REMOVE LOOSE MATERIAL PRIOR TO POUR. OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Concrete Walls and Columns Inspection Partial 08/11/2010
Correction
Partial Correction
08/11/2010
PERPARATION TO POUR ELEVATOR SHAFT WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; ROOF LEVEL SOUTH & WEST WALLS; OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
08/11/2010
PREPARATION TO POUR STAIRWELL WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; ROOF LEVEL WEST WALL; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Correction
Partial Correction
08/11/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS - ROOF LEVEL ALL STUB COLUMNS; MEZZANINE COLUMNS 5/D, 5/F, 5/H, 5/J, 6/D; (SHAFT COLUMNS NOT INCLUDED) OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Concrete Walls and Columns Inspection Partial 08/12/2010
Correction
Resolved
08/12/2010
PERPARATION TO POUR ELEVATOR SHAFT WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; ROOF LEVEL SOUTH & WEST WALLS; ROOF LEVEL EAST WALL + CROSS-WALL INCLUDING ELECT CONDUIT [ALL INCLUDING INTEGRAL COLUMNS] OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Correction
Resolved
08/12/2010
PREPARATION TO POUR STAIRWELL WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; ROOF LEVEL WEST WALL; ROOF LEVEL NORTH & EAST WALLS + CROSS-WALL INCLUDING ELECT CONDUIT [ALL INCLUDING INTEGRAL COLUMNS] OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Correction
Partial Correction
08/12/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS - ROOF LEVEL ALL STUB COLUMNS; MEZZANINE COLUMNS 5/D, 5/F, 5/H, 5/J, 6/D; OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Foundation Inspection - Commercial Passed 08/17/2010
Correction
Resolved
08/17/2010
PREPARATION TO POUR PERIMETER FOUNDATION WALL EE/10.4 TO EE/12 TO 12/CC.6; EE/10.4 TO L.3/6.5 (RE-BAR DOWLING APPROVED BY SEA); OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Underslab Electrical Inspection - Commercial Partial 08/17/2010
Correction
Partial Correction
08/17/2010
UNDER-SLAB CONDUIT AT NORMAL ELECT & EMERGENCY ELECT RMS MATERIAL & WORKMANSHIP OK TO COVER WHEN READY
Underground Plumbing Inspection - Commercial Passed 08/17/2010
Correction
Resolved
08/17/2010
UNDERGROUND SANITARY PIPING 20' OF 6" C.I. BELOW G.B. AT H.8/6.2; 4" C.I. FROM H.6/6 TO H.6/4.9 TO F.2/4.9; H.8/6.3 TO H.8/7.2; H.8/6.9 TO F/6.9 TO D.2/6.9 TO D.2/6; H.8/6.9 TO H.8/7.8 TO 7.8/L.2; 4" C.I. + TWO F.D. STUB-UPS @ "WATER" RM; 4" C.I. + STUB-UPS @ H/6 & L/6 PER PR-7 OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Resolved
08/17/2010
UNDERGROUND ROOF DRAIN STORM PIPING 20' OF 6" C.I. BELOW GRADE BEAM AT H.8/6.2 (APPROVED CONTINGENT ON A/E VERIFICATION OF SIZE REDUCTION FROM 10" TO 6"); H.8/6.9 TO F/6.9 TO D.2/6.9 TO D.2/6; H.8/6.9 TO H.8/7.8 TO 7.8/L.2; 8.5/L.1 TO 8.5/M.2 TO CONN TO CORRUGATED @ EE/10.2; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Footing Inspection - Commercial Passed 08/17/2010
Correction
Resolved
08/17/2010
PREPARATION TO POUR GRADE BEAM + INTEGRAL COLUMN FOOTINGS M/5 TO K/3; H/5 TO B.5/3; C/1 TO D/4 TO D.5.7; E/2 TO F/4 TO F/5.7; D/4 TO F/4; 6/B.8 TO 6/B TO 5/B TO 1/A TO 1/C TO 1/E TO E/2 TO E/2.3; E/2 TO F/4; C/1 TO D/4; 5/B.3 TO 5/B; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underslab Electrical Inspection - Commercial Partial 08/18/2010
Correction
Partial Correction
08/18/2010
UNDER-SLAB CONDUIT AT NORMAL ELECT & EMERGENCY ELECT RMS LOWER LIFT MAIN CIRCUIT CONDUITS; UPPER LIFT BELOW-SLAB CONDUITS; TWO #3/0 GROUNDING CONDUCTORS STUBBED ABOVE SLAB POUR MATERIAL & WORKMANSHIP OK TO COVER WHEN READY
Concrete Walls and Columns Inspection Partial 08/23/2010
Correction
Resolved
08/23/2010
PERPARATION TO POUR ELEVATOR SHAFT WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; ROOF LEVEL SOUTH & WEST WALLS; ROOF LEVEL EAST WALL + CROSS-WALL INCLUDING ELECT CONDUIT [ALL INCLUDING INTEGRAL COLUMNS]; TOP-OUT TO EL 1036' OK TO POUR WHEN READY FOLLOWING SEGMENTS:
Correction
Resolved
08/23/2010
PREPARATION TO POUR STAIRWELL WALLS 1ST LEVEL; 2ND LEVEL COMPLETE; ROOF LEVEL WEST WALL; ROOF LEVEL NORTH & EAST WALLS + CROSS-WALL INCLUDING ELECT CONDUIT [ALL INCLUDING INTEGRAL COLUMNS]; TOP-OUT TO EL 1036' OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Concrete Walls and Columns Inspection Passed 08/24/2010
Correction
Resolved
08/24/2010
PREPARATION TO POUR C.I.P. CONCRETE COLUMNS - ROOF LEVEL ALL STUB COLUMNS @ MAIN ROOF ELEVATION; MEZZANINE COLUMNS 5/D, 5/F, 5/H, 5/J, 6/D; STUB COLUMNS @ MEZZANINE ROOF ELEVATION OK TO POUR WHEN READY COLUMNS @LOCATIONS BELOW:
Rough Framing Inspection - Commercial Partial 08/30/2010
Correction
Partial Correction
08/30/2010
None -PARAPET ALONG THE BLD. OUTER EDGE FROM E/1 TO CC/14 APPROVED TO COVER BELOW
Rough Framing Inspection - Commercial Request Complete 8/27/2010 8/30/2010 08/30/2010
Rough Framing Inspection - Commercial Partial 09/02/2010
Correction
Resolved
09/02/2010
None SHEET A2.1 - - COLUMN LINE F8 TO EE12. - COLUMN LINE EE FROM 10 TO 11. - COLUMN LINE E1 TO H.5 X 4
Rough Framing Inspection - Commercial Request Complete 9/1/2010 9/2/2010 09/02/2010
Rough Framing Inspection - Commercial Partial 09/09/2010
Correction
Partial Correction
09/09/2010
None -PARAPET ALONG THE BLD. OUTER EDGE FROM E/1 TO CC/14 APPROVED TO COVER BELOW Sheet A2.2
Correction
Resolved
09/09/2010
None SHEET A2.1 - - COLUMN LINE F8 TO EE12. - COLUMN LINE EE FROM 10 TO 11. - COLUMN LINE E1 TO H.5 X 4 - COLUMN LINE 6.5 AT LINE L. - COLIUMN LINE EE FROM 10 TO 12.
Rough Framing Inspection - Commercial Request Complete 9/7/2010 9/9/2010 09/09/2010
Rough Framing Inspection - Commercial Partial 09/14/2010
Correction
Partial Correction
09/14/2010
None -PARAPET ALONG THE BLD. OUTER EDGE FROM E/1 TO CC/14 -PARAPET FROM E5 TO PLAN EAST OF GLASS LANE-OK TO COVER ONE SIDE. 2 HR EXPANSION JOINT WILL BE INSPECTED AT LATER TIME APPROVED TO COVER BELOW SHEETA2.3- ROOF
Correction
Resolved
09/14/2010
None - COLUMN LINE F8 TO EE12. - COLUMN LINE EE FROM 10 TO 11. - COLUMN LINE E1 TO H.5 X 4 - COLUMN LINE 6.5 AT LINE L. - COLIUMN LINE EE FROM 10 TO 12. OK TO COVER BELOW SHEET A2.1-1ST FL
Correction
Partial Correction
09/14/2010
None -CC14.5 TO H9 APPROVED TO COVER BELOW SHEET 2.2-2ND FL
Rough Framing Inspection - Commercial Request Complete 9/13/2010 9/14/2010 09/14/2010
Rated Assembly Inspection Partial 09/20/2010
Correction
Partial Correction
09/20/2010
None ROOF LEVEL - SEPARATION WALL BETWEEN NEW ADDITION ROCKHILL ORTHPEDICS PROVIDE SPECT SHEET ON MATERIAL. INSTALLED - BALCO MBF2H04 - UL FILE #R15951 COVER AT OWN RISK
Rough Framing Inspection - Commercial Partial 09/20/2010
Correction
Resolved
09/20/2010
None - PARAPET WALL ON ROOF - SHEET A2.3
Rough Framing Inspection - Commercial Request Complete 9/17/2010 9/20/2010 09/20/2010
Rough Framing Inspection - Commercial Partial 09/24/2010
Correction
Partial Correction
09/24/2010
LIGHT-GUAGE STEEL FRAMING HANGING BULKHEAD ALONG FIRST FLOOR ARC WALL FROM H.5/4 TO H.5/5.5 + PERIMETER OF VEST 008; EXTERIOR WALL AT PERIMETER OF PENTHOUSE & STAIR/ELEVATOR SHAFTS; OK TO COVER WHEN READY FOLLOWING AREAS:
Rough Framing Inspection - Commercial Request Complete 9/23/2010 9/24/2010 09/24/2010
Rough Framing Inspection - Commercial Partial 09/28/2010
Correction
Partial Correction
09/28/2010
LIGHT-GUAGE STEEL FRAMING HANGING BULKHEAD ALONG FIRST FLOOR ARC WALL FROM H.5/4 TO H.5/5.5 + PERIMETER OF VEST 008 + ARC WALL FROM L/6.3 TO O/10; EXTERIOR WALL AT PERIMETER OF PENTHOUSE & STAIR/ELEVATOR SHAFTS; OK TO COVER WHEN READY FOLLOWING AREAS:
Rough Framing Inspection - Commercial Request Complete 9/27/2010 9/28/2010 09/28/2010
Rough Framing Inspection - Commercial Partial 09/30/2010
Correction
Partial Correction
09/30/2010
LIGHT-GUAGE STEEL FRAMING HANGING BULKHEAD ALONG FIRST FLOOR ARC WALL FROM H.5/4 TO H.5/5.5 + PERIMETER OF VEST 008 + ARC WALL FROM L/6.3 TO O/10; EXTERIOR WALL AT PERIMETER OF PENTHOUSE & STAIR/ELEVATOR SHAFTS; OK TO COVER WHEN READY FOLLOWING AREAS:
Correction
Partial Correction
09/30/2010
LIGHT-GUAGE STEEL FRAMING @ ROOF PARAPET D.5/8.7 TO B.5/7.3 TO B.8/6.9 TO B.3/6.4; OK TO COVER WHEN READY FOLLOWING LOCATIONS:
Rated Assembly Inspection Partial 09/30/2010
Correction
Resolved
09/30/2010
None
Correction
Partial Correction
09/30/2010
FIRE-STOPPING @ INTERSECTION OF EXISTING ROOF WITH NEW ROOF BETWEEN BLDG L & BLDG F; D.5/8.7 TO B.5/7.3 TO B.8/6.9 TO B.3/6.4; BALCO MBF2H04 UL FILE #R15951
Rough Framing Inspection - Commercial Request Complete 9/29/2010 9/30/2010 09/30/2010
Rough Framing Inspection - Commercial Not Ready 10/07/2010
Correction
Partial Correction
10/07/2010
LIGHT-GUAGE STEEL FRAMING @ ROOF PARAPET D.5/8.7 TO B.5/7.3 TO B.8/6.9 TO B.3/6.4; OK TO COVER WHEN READY FOLLOWING LOCATIONS:
Rough Framing Inspection - Commercial Partial 10/07/2010
Correction
Partial Correction
10/07/2010
LIGHT-GUAGE STEEL FRAMING HANGING BULKHEAD ALONG FIRST FLOOR ARC WALL FROM H.5/4 TO H.5/5.5 + PERIMETER OF VEST 008 + ARC WALL FROM L/6.3 TO O/10; EXTERIOR WALL AT PERIMETER OF PENTHOUSE & STAIR/ELEVATOR SHAFTS; OK TO COVER WHEN READY FOLLOWING AREAS:
Correction
Partial Correction
10/07/2010
LIGHT-GUAGE STEEL FRAMING, CONT'D SOUTH WALL @ 2ND FLR/ROOF PER SECTION 1/A6.2 [TOP TRACK IS DESIGNATED AS SLIP TRACK PER APPROVED SHOP DRWGS; OK TO COVER WHEN READY FOLLOWING FRAME SEGMENTS:
Rough Framing Inspection - Commercial Request Complete 10/6/2010 10/7/2010 10/07/2010
Rough Plumbing Inspection - Commercial Partial 10/11/2010
Correction
Partial Correction
10/11/2010
ROUGH-IN OF ROOF DRAIN PIPING OK TO INSULATE WHEN READY
Correction
Partial Correction
10/11/2010
ROUGH-IN OF H&C WATER PIPING OK TO INSULATE WHEN READY
Rough Framing Inspection - Commercial Partial 10/12/2010
Correction
Resolved
10/12/2010
None -PARAPET ALONG THE BLD. OUTER EDGE FROM E/1 TO CC/14 -PARAPET FROM E5 TO PLAN EAST OF GLASS LANE APPROVED TO COVER BELOW SHEETA2.3- ROOF
Correction
Resolved
10/12/2010
None -CC14.5 TO H9 APPROVED TO COVER BELOW SHEET 2.2-2ND FL
Correction
Resolved
10/12/2010
LIGHT-GUAGE STEEL FRAMING HANGING BULKHEAD ALONG FIRST FLOOR ARC WALL FROM H.5/4 TO H.5/5.5 + PERIMETER OF VEST 008 + ARC WALL FROM L/6.3 TO O/10; EXTERIOR WALL AT PERIMETER OF PENTHOUSE & STAIR/ELEVATOR SHAFTS; OK TO COVER WHEN READY FOLLOWING AREAS:
Correction
Partial Correction
10/12/2010
LIGHT-GUAGE STEEL FRAMING @ ROOF PARAPET D.5/8.7 TO B.5/7.3 TO B.8/6.9 TO B.3/6.4; ABOVE "A" TO "L" PEDESTRIAN LINK NORTH & SOUTH BOUNDARIES PER SECTIONS 8/S3.4, 5/S3.5, AND 19/A6.2 OK TO COVER WHEN READY FOLLOWING LOCATIONS:
Rated Assembly Inspection Partial 10/12/2010
Correction
Partial Correction
10/12/2010
FIRE-STOPPING @ INTERSECTION OF EXISTING ROOF WITH NEW ROOF FIRE-RATED EXP JT BETWEEN BLDG L & BLDG F; D.5/8.7 TO B.5/7.3 TO B.8/6.9 TO B.3/6.4; FIRE-RATED EXP JT @ NE WALL OF BLDG "A" STAIR SHAFT PER SECT 1/A6.3; FIRE CAULK @ 1/2" GAP TO BLDG "A" PER SECT 16/A6.1; BALCO MBF2H04 UL FILE #R15951
Rated Assembly Inspection Partial 10/13/2010
Correction
Partial Correction
10/13/2010
FIRE-STOPPING @ INTERSECTION OF EXISTING ROOF WITH NEW ROOF FIRE-RATED EXP JT BETWEEN BLDG L & BLDG F INCLUDING @ "A" TO "L" LINK; D.5/8.7 TO B.5/7.3 TO B.8/6.9 TO B.3/6.4; FIRE-RATED EXP JT @ NE WALL OF BLDG "A" STAIR SHAFT PER SECT 1/A6.3; FIRE CAULK @ 1/2" GAP TO BLDG "A" PER SECT 16/A6.1 BALCO MBF2H04 UL FILE #R15951
Correction
Partial Correction
10/13/2010
RATED LID AT TOP OF ELEVATOR SHAFT LINER BOARD ON TOP SIDE OF FRAMING; OK TO COVER WHEN READY FOLLOWING ELEMENT(S):
Rough Framing Inspection - Commercial Partial 10/13/2010
Correction
Partial Correction
10/13/2010
LIGHT-GUAGE STEEL FRAMING @ ROOF PARAPET D.5/8.7 TO B.5/7.3 TO B.8/6.9 TO B.3/6.4; ABOVE "A" TO "L" PEDESTRIAN LINK NORTH & SOUTH BOUNDARIES PER SECTIONS 8/S3.4, 5/S3.5, AND 19/A6.2; ABOVE "A" TO "L" LINK @ BLDG "L" WEST WALL OK TO COVER WHEN READY FOLLOWING LOCATIONS:
Rated Assembly Inspection Partial 10/14/2010
Correction
Partial Correction
10/14/2010
RATED LID AT TOP OF ELEVATOR SHAFT LINER BOARD ON TOP SIDE OF FRAMING; 1ST LAYER 5/8" TYPE X GWB BOTTOM SIDE OF FRAMING; OK TO COVER WHEN READY FOLLOWING ELEMENT(S):
Rated Assembly Inspection Partial 10/15/2010
Correction
Partial Correction
10/15/2010
RATED LID AT TOP OF ELEVATOR SHAFT LINER BOARD ON TOP SIDE OF FRAMING; 1ST LAYER 5/8" TYPE X GWB BOTTOM SIDE OF FRAMING; 2ND LAYER 5/8" TYPE X GWB OK TO TAPE&MUD (PERIMETER FIRE CAULKING COMPLETED) OK TO COVER WHEN READY FOLLOWING ELEMENT(S):
Rated Assembly Inspection Partial 10/19/2010
Correction
Corrective Action Required
10/19/2010
RATED LID AT TOP OF ELEVATOR SHAFT LINER BOARD ON TOP SIDE OF FRAMING; 1ST LAYER 5/8" TYPE X GWB BOTTOM SIDE OF FRAMING; 2ND LAYER 5/8" TYPE X GWB; TAPE, MUD, FIRE CAULKING COMPLETED OK TO COVER WHEN READY FOLLOWING ELEMENT(S):
Rough Framing Inspection - Commercial Partial 10/25/2010
Correction
Resolved
10/25/2010
LIGHT-GUAGE STEEL FRAMING HANGING BULKHEAD ALONG FIRST FLOOR ARC WALL FROM H.5/4 TO H.5/5.5 + PERIMETER OF VEST 008 + ARC WALL FROM L/6.3 TO O/10; EXTERIOR WALL AT PERIMETER OF PENTHOUSE & STAIR/ELEVATOR SHAFTS;RM IF004,IF005 BOTHSIDES TO CORRIDOR WALL 003. OK TO COVER WHEN READY FOLLOWING AREAS:
Rough Framing Inspection - Commercial Request Complete 10/22/2010 10/25/2010 10/25/2010
Rated Assembly Inspection Failed 10/27/2010
Correction
Resolved
10/27/2010
RATED LID AT TOP OF ELEVATOR SHAFT LINER BOARD ON TOP SIDE OF FRAMING; 1ST LAYER 5/8" TYPE X GWB BOTTOM SIDE OF FRAMING; 2ND LAYER 5/8" TYPE X GWB; TAPE, MUD, FIRE CAULKING COMPLETED OK TO COVER WHEN READY FOLLOWING ELEMENT(S):
Correction
Corrective Action Required
10/27/2010
GWB AT UL RATED WALLS ELECT ROOM WALLS TO RECEIVE GEAR -- PROVIDE SCREW PATTERN PER UL465 INCLUDING AT BASE TRACK SPACES/WALLS LISTED BELOW
Rated Assembly Inspection Partial 10/28/2010
Correction
Partial Correction
10/28/2010
GWB AT UL RATED WALLS N-S WALLS @ ELECT ROOMS 004 & 005 TO RECEIVE ELECT GEAR; OK TO TAPE/MUD/FIRE-SEAL SPACES/WALLS LISTED BELOW
In-wall Inspection Partial 11/2/2010 at 12:00 AM 11/02/2010
B2308 CONVENTIONAL LIGHT-FRAME CONSTRUCTION
Partial Correction
11/02/2010
LIGHT-GUAGE STEEL FRAMING + IN-WALL SYSTEMS @ EXTERIOR WALLS OK TO COVER AT: J.1/6 TO J.1/J5.6; J.1/4.9 TO F/4.9; D/5 TO D/6;
B2308 CONVENTIONAL LIGHT-FRAME CONSTRUCTION
Partial Correction
11/02/2010
LIGHT-GUAGE STEEL FRAMING + IN-WALLS SYSTEMS OK TO COVER AT SPACES/WALLS: 012; 014;
In-wall Inspection Partial 11/02/2010
Misc
Partial Correction
11/02/2010
EXTERIOR WALL LIGHT-GUAGE STEEL FRAMING + ENCLOSED SYSTEMS: J.1/6 TO J.1/5.6 TO; J.1/4.9 TO F/4.9 TO D/5 TO D/6;
Misc
Partial Correction
11/02/2010
INTERIOR WALL FRAMING + ENCLOSED SYSTEMS @ SPACES/WALLS: 014; 012;
Underground Electrical Inspection - Commercial Partial 11/5/2010 at 12:00 AM 11/05/2010
Correction
Partial Correction
11/04/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY ELECTRICAL SERVICE CONDUIT FOUR 4" PVC BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N;
Correction
Partial Correction
11/04/2010
INSTALLATION OF UNDERGROUND DATACOMM CONDUIT TWO 4" PVC BELOW GRADE BEAM AT E/2.3; TWO 4" PVC FROM E/2.3 TO PHONE ROOM 002; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
In-wall Inspection Partial 11/8/2010 at 12:00 AM 11/08/2010
Misc
Partial Correction
11/02/2010
EXTERIOR WALL LIGHT-GUAGE STEEL FRAMING + ENCLOSED SYSTEMS: AT PENTHOUSE: J.1/6 TO J.1/5.6 TO; J.1/4.9 TO F/4.9 TO D/5 TO D/6;
Misc
Partial Correction
11/02/2010
INTERIOR WALL FRAMING + ENCLOSED SYSTEMS @ SPACES/WALLS: [OK FOR GWB, BUT NO WIRE PULLED -- SUBJECT TO APPROVAL BEFORE DEVICES ARE INSTALLED:: 1F012; 1F013 N, E, S WALLS; 1F014; 2F012; 2F014];
Rated Assembly Inspection Partial 11/9/2010 at 12:00 AM 11/09/2010
Correction
Resolved
11/09/2010
None ROOF LEVEL - SEPARATION WALL BETWEEN NEW ADDITION ROCKHILL ORTHPEDICS INSTALLED - BALCO MBF2H04 - UL FILE #R15951
Misc
Partial Correction
11/09/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS;
Misc
Partial Correction
11/09/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD;
Electrical Service Inspection Not Ready 11/9/2010 at 12:00 AM 11/09/2010
Rough Electrical Inspection - Commercial Partial 11/09/2010
Misc
Partial Correction
11/09/2010
IN-WALL CIRCUITS @ PENTHOUSE EXTERIOR WALLS: WIRE PULLED + GROUND PIGTAILS INSTALLED -- OK TO INSTALL DEVICES
Rated Assembly Inspection Partial 11/10/2010 at 12:00 AM 11/10/2010
Misc
Partial Correction
11/09/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; ONE LAYER 5/8" TYPE X GWB;
Misc
Partial Correction
11/09/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ONE LAYER 5/8" TYPE X GWB;
Underground Electrical Inspection - Commercial Partial 11/10/2010 at 12:00 AM 11/10/2010
Correction
Partial Correction
11/05/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION
Correction
Partial Correction
11/05/2010
INSTALLATION OF UNDERGROUND DATACOMM CONDUIT TWO 4" PVC BELOW GRADE BEAM AT E/2.3; TWO 4" PVC FROM E/2.3 TO PHONE ROOM 002; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
In-wall Inspection Partial 11/12/2010
Misc
Partial Correction
11/12/2010
OK TO COVER WHNE READY WALL FRAMING + IN-WALL SYSTEMS AT FOLLOWING SPACES: 1F001 PLAN SOUTH WALL; 1F002; 1F003;
Rated Assembly Inspection Partial 11/12/2010 at 12:00 AM 11/12/2010
Misc
Partial Correction
11/10/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/10/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/12/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: SHAFT LINER @ 2F012 S WALL N 6'; 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Rated Assembly Inspection Partial 11/17/2010 at 12:00 AM 11/17/2010
Misc
Partial Correction
11/12/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/12/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/12/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
11/17/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; ONE LAYER 5/8" TYPE X GWB @ MECH SHAFT ADJACENT TO 3F006; ONE LAYER 5/8" TYPE X GWB @ MECH SHAFT ADJACENT TO 2F012;
In-wall Inspection Partial 11/17/2010 at 12:00 AM 11/17/2010
Misc
Partial Correction
11/08/2010
EXTERIOR WALL LIGHT-GUAGE STEEL FRAMING + ENCLOSED SYSTEMS: AT PENTHOUSE: J.1/6 TO J.1/5.6 TO; J.1/4.9 TO F/4.9 TO D/5 TO D/6;
Misc
Partial Correction
11/08/2010
INTERIOR WALL FRAMING + ENCLOSED SYSTEMS @ SPACES/WALLS: [OK FOR GWB, BUT NO WIRE PULLED -- SUBJECT TO APPROVAL BEFORE DEVICES ARE INSTALLED:: 1F012; 1F013 N, E, S WALLS; 1F014; 2F012; 2F014]; 3F006 E & N WALLS BOTH FACES;
Underground Electrical Inspection - Commercial Partial 11/19/2010 at 12:00 AM 11/19/2010
Misc
Partial Correction
11/10/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP;
Misc
Partial Correction
11/10/2010
INSTALLATION OF UNDERGROUND DATACOMM CONDUIT TWO 4" PVC BELOW GRADE BEAM AT E/2.3; TWO 4" PVC FROM E/2.3 TO PHONE ROOM 002; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Rated Assembly Inspection Partial 11/22/2010 at 12:00 AM 11/22/2010
Misc
Partial Correction
11/17/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/17/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/17/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
11/17/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR -- OK TO TAPE, MUD, & FIRE-SEAL
Footing Inspection - Commercial Partial 11/29/2010 at 12:00 AM 11/29/2010
Misc
Partial Correction
11/29/2010
OK TO POUR WHEN READY BASE SLAB FOR FREIGHT ELEVATOR
Underground Electrical Inspection - Commercial Partial 11/29/2010 at 12:00 AM 11/29/2010
Misc
Partial Correction
11/29/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP; TWO 4" PVC DATACOMM FROM PULL BOX N/NE TO CONNECT TO TWO 4" PVC FROM EXISTING SERVICE; TWO 4" PVC DATACOMM FROM PULL BOX TO 50' W/NW;
Rated Assembly Inspection Partial 11/30/2010 at 12:00 AM 11/30/2010
Misc
Partial Correction
11/22/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/22/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/22/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
11/22/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR -- OK TO TAPE, MUD, & FIRE-SEAL
Misc
Partial Correction
11/30/2010
- SCREW PATTERN - IT ROOM AT STAIRWELL/ELEVATOR SHAFT -
Misc
Partial Correction
11/30/2010
-A2.1 - SCREW PATTERN AT CORRIDOR IF013, IF001, IF002, IF003,IF005, IF006
Underground Electrical Inspection - Commercial Partial 11/30/2010 at 12:00 AM 11/30/2010
Correction
Partial Correction
11/19/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP;
Correction
Partial Correction
11/19/2010
INSTALLATION OF UNDERGROUND DATACOMM CONDUIT TWO 4" PVC BELOW GRADE BEAM AT E/2.3; TWO 4" PVC FROM E/2.3 TO PHONE ROOM 002; OK TO COVER WHEN READY FOLLOWING SEGMENTS: FROM PREVIOUS LOCATION TO A POINT AT THE 4th EXTERIOR COLUMN
Underground Electrical Inspection - Commercial Partial 12/1/2010 at 12:00 AM 12/01/2010
Misc
Partial Correction
11/30/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP; TWO 4" PVC DATACOMM FROM PULL BOX N/NE TO CONNECT TO TWO 4" PVC FROM EXISTING SERVICE; TWO 4" PVC DATACOMM FROM PULL BOX W/NW TO CONNECT TO EXISTING CAMPUS PERIMETER DATACOMM CONDUIT RING
Rated Assembly Inspection Partial 11/2/2010 at 12:00 AM 12/02/2010
Correction
Partial Correction
12/02/2010
BALCO MBF2H04 (UL FILE #R15951) INSTALLED: ROOF LEVEL BETWEEN BLDG F & ROCKHILL ORTHOPEDICS; 2ND FLR LEVEL BETWEEN BLDG F & BLDG A;
Misc
Partial Correction
11/02/2010
RATED MECHANICAL SHAFT ENCLOSURE -- OK TO COVER WHEN READY: PENTHOUSE LEVEL SOUTH WALL LINER BOARD;
Underground Electrical Inspection - Commercial Partial 12/2/2010 at 12:00 AM 12/02/2010
Misc
Partial Correction
12/01/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP; TWO 4" PVC DATACOMM FROM PULL BOX N/NE TO CONNECT TO TWO 4" PVC FROM EXISTING SERVICE; TWO 4" PVC DATACOMM FROM PULL BOX W/NW TO CONNECT TO EXISTING CAMPUS PERIMETER DATACOMM CONDUIT RING
Misc
Partial Correction
12/02/2010
SERVICE GROUNDING AND LIGHTNING PROTECTION SYSTEM: CONDUCTOR FROM ROOFTOP LIGHTNING PROTECTION STUBBED OUT OF COLUMN P/7 AND CONNECTED TO MAIN GROUND RING; GROUND RING EXTENDED FROM NEAR P/7 W/SW TO EE/12;
Rated Assembly Inspection Partial 12/2/2010 at 12:00 AM 12/02/2010
Misc
Partial Correction
11/30/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/30/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
11/30/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
11/30/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR -- OK TO TAPE, MUD, & FIRE-SEAL
Misc
Partial Correction
11/30/2010
- SCREW PATTERN - IT ROOM AT STAIRWELL/ELEVATOR SHAFT -
Misc
Partial Correction
11/30/2010
-A2.1 - SCREW PATTERN AT CORRIDOR IF013, IF001, IF002, IF003,IF005, IF006
Misc
Partial Correction
12/02/2010
BALCO MBF2H04 (UL FILE #R15951) INSTALLED: ROOF LEVEL BETWEEN BLDG F & ROCKHILL ORTHOPEDICS; 2ND FLR LEVEL BETWEEN BLDG F & BLDG A FROM NEAR CC.2/14 TO NEAR AA/13.4;
Rated Assembly Inspection Partial 12/6/2010 at 12:00 AM 12/06/2010
Misc
Partial Correction
12/02/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
12/02/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
12/02/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
12/02/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR -- OK TO TAPE, MUD, & FIRE-SEAL
Misc
Partial Correction
12/02/2010
- SCREW PATTERN - IT ROOM AT STAIRWELL/ELEVATOR SHAFT -
Misc
Partial Correction
12/02/2010
-A2.1 - SCREW PATTERN AT CORRIDOR IF013(2ND LAYER ON "D"1ST ON "F"., IF001, IF002, IF003,IF005, IF006
Misc
Partial Correction
12/02/2010
BALCO MBF2H04 (UL FILE #R15951) INSTALLED: ROOF LEVEL BETWEEN BLDG F & ROCKHILL ORTHOPEDICS; 2ND FLR LEVEL BETWEEN BLDG F & BLDG A;
Underground Electrical Inspection - Commercial Partial 12/7/2010 at 12:00 AM 12/07/2010
Misc
Partial Correction
12/02/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP; TWO 4" PVC DATACOMM FROM PULL BOX N/NE TO CONNECT TO TWO 4" PVC FROM EXISTING SERVICE; TWO 4" PVC DATACOMM FROM PULL BOX W/NW TO CONNECT TO EXISTING CAMPUS PERIMETER DATACOMM CONDUIT RING
Misc
Partial Correction
12/02/2010
SERVICE GROUNDING AND LIGHTNING PROTECTION SYSTEM: CONDUCTOR FROM ROOFTOP LIGHTNING PROTECTION STUBBED OUT OF COLUMN P/7 AND CONNECTED TO MAIN GROUND RING; GROUND RING EXTENDED FROM NEAR P/7 W/SW TO EE/12;
Misc
Partial Correction
12/07/2010
SERVICE GROUNDING & LIGHTENING PROTECTION - FROM SW CORNER OF BUILDING TO TIE-IN WITH EXISTING GROUND ON NORTH SIDE OF BUILDING
Footing Inspection - Commercial Partial 11/30/2010 at 12:00 AM 12/09/2010
Misc
Partial Correction
11/29/2010
11-30-10 JB-OK TO POUR WHEN READY BASE SLAB FOR FREIGHT ELEVATOR
Misc
Partial Correction
12/09/2010
GRADE BEAM- AROUND FREIGHT ELEVATOR 12-9-10 MH
Underground Electrical Inspection - Commercial Partial 12/13/2010 at 12:00 AM 12/13/2010
Misc
Partial Correction
12/07/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP; TWO 4" PVC DATACOMM FROM PULL BOX N/NE TO CONNECT TO TWO 4" PVC FROM EXISTING SERVICE; TWO 4" PVC DATACOMM FROM PULL BOX W/NW TO CONNECT TO EXISTING CAMPUS PERIMETER DATACOMM CONDUIT RING; COMPLETION OF 4" PVC LOOP TO TRANSFORMER AT EXISTING DUCT BANK
Misc
Partial Correction
12/07/2010
SERVICE GROUNDING AND LIGHTNING PROTECTION SYSTEM: CONDUCTOR FROM ROOFTOP LIGHTNING PROTECTION STUBBED OUT OF COLUMN P/7 AND CONNECTED TO MAIN GROUND RING; GROUND RING EXTENDED FROM NEAR P/7 W/SW TO EE/12;
Misc
Partial Correction
12/07/2010
SERVICE GROUNDING & LIGHTENING PROTECTION - FROM SW CORNER OF BUILDING TO TIE-IN WITH EXISTING GROUND ON NORTH SIDE OF BUILDING
Rated Assembly Inspection Partial 12/16/2010 at 12:00 AM 12/16/2010
Misc
Partial Correction
12/06/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
12/06/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
12/06/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
12/06/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR -- OK TO TAPE, MUD, & FIRE-SEAL
Misc
Partial Correction
12/06/2010
- SCREW PATTERN - IT ROOM AT STAIRWELL/ELEVATOR SHAFT -
Misc
Partial Correction
12/06/2010
-A2.1 - SCREW PATTERN AT CORRIDOR IF013(2ND LAYER ON "D"1ST ON "F"., IF001, IF002, IF003,IF005, IF006
Misc
Partial Correction
12/06/2010
BALCO MBF2H04 (UL FILE #R15951) INSTALLED: ROOF LEVEL BETWEEN BLDG F & ROCKHILL ORTHOPEDICS; 2ND FLR LEVEL BETWEEN BLDG F & BLDG A;
Misc
Partial Correction
12/16/2010
TYPE F WALL PER SECTION 6/A6.3: 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD; 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB;
Rated Assembly Inspection Partial 12/21/2010 at 12:00 AM 12/21/2010
Misc
Partial Correction
12/16/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
12/16/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
12/16/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
12/16/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR -- OK TO TAPE, MUD, & FIRE-SEAL
Misc
Partial Correction
12/16/2010
- SCREW PATTERN - IT ROOM AT STAIRWELL/ELEVATOR SHAFT -
Misc
Partial Correction
12/16/2010
-A2.1 - SCREW PATTERN AT CORRIDOR IF013(2ND LAYER ON "D"1ST ON "F"., IF001, IF002, IF003,IF005, IF006
Misc
Partial Correction
12/16/2010
BALCO MBF2H04 (UL FILE #R15951) INSTALLED: ROOF LEVEL BETWEEN BLDG F & ROCKHILL ORTHOPEDICS; 2ND FLR LEVEL BETWEEN BLDG F & BLDG A;
Misc
Partial Correction
12/16/2010
TYPE F WALL PER SECTION 6/A6.3: 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD + 1ST LAYER 5/8" TYPE X GWB; 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB;
Rated Assembly Inspection Partial 12/27/2010 at 12:00 AM 12/27/2010
Misc
Resolved
12/27/2010
RATED CLOSURES @ ELEVATOR DOOR OPENINGS: PENTHOUSE LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; 2ND FLOOR LEVEL -- FRAMING + 1" SHAFT LINER BOARD @ TWO OPENINGS; P.H. & 2ND FLR TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Resolved
12/27/2010
TEMPORARY SLAB CLOSURES @ FUTURE ELEVATOR SHAFT: ROOF SLAB -- FRAMING + 1" SHAFT LINER BOARD; 2ND FLOOR SLAB -- FRAMING + 1" SHAFT LINER BOARD; ROOF & 2ND FLOOR SLABS TWO LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
12/21/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
12/21/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR; SOUTH & EAST WALLS OF SHAFT @ 2ND FLR-- FRAMING + SHAFT LINER; EAST & NORTH WALLS OF SHAFT @ MEZZANINE -- FRAMING + SHAFT LINER;
Misc
Partial Correction
12/21/2010
- SCREW PATTERN - IT ROOM AT STAIRWELL/ELEVATOR SHAFT -
Misc
Partial Correction
12/21/2010
-A2.1 - SCREW PATTERN AT CORRIDOR IF013(2ND LAYER ON "D"1ST ON "F"., IF001, IF002, IF003,IF005, IF006
Misc
Resolved
12/27/2010
BALCO MBF2H04 (UL FILE #R15951) INSTALLED: ROOF LEVEL BETWEEN BLDG F & ROCKHILL ORTHOPEDICS; 2ND FLR LEVEL BETWEEN BLDG F & BLDG A;
Misc
Partial Correction
12/21/2010
TYPE F WALL PER SECTION 6/A6.3: 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD + 1ST LAYER 5/8" TYPE X GWB; 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB; 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A 2ND LAYER 5/8" TYPE X GWB
Rated Assembly Inspection Partial 12/29/2010 at 12:00 AM 12/29/2010
Misc
Resolved
12/29/2010
OK TO COVER WHEN READY RATED WALL SURFACES @ FOLLOWING LOCATIONS: 5/8" TYPE X GWB @ N&W WALLS 2F012; N,W,S WALLS 2F014; 1F012 N,W,S; 1F014 N,W,S;
Misc
Partial Correction
12/27/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR; SOUTH & EAST WALLS OF SHAFT @ 2ND FLR-- FRAMING + SHAFT LINER; EAST & NORTH WALLS OF SHAFT @ MEZZANINE -- FRAMING + SHAFT LINER; E, S, W SIDES OF SHAFT @ 2ND FLR & MEZZANINE 1ST LAYER OF 5/8" TYPE X GWB;
Misc
Resolved
12/29/2010
- SCREW PATTERN - IT ROOM AT STAIRWELL/ELEVATOR SHAFT -
Misc
Resolved
12/29/2010
-A2.1 - SCREW PATTERN AT CORRIDOR IF013(2ND LAYER ON "D"1ST ON "F"., IF001, IF002, IF003,IF005, IF006
Misc
Partial Correction
12/27/2010
TYPE F WALL PER SECTION 6/A6.3: 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD + 1ST LAYER 5/8" TYPE X GWB; 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB; 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" 2ND LAYER 5/8" TYPE X GWB
Rated Assembly Inspection Partial 1/4/2011 at 12:00 AM 01/04/2011
Misc
Partial Correction
12/29/2010
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR; SOUTH & EAST WALLS OF SHAFT @ 2ND FLR-- FRAMING + SHAFT LINER; EAST & NORTH WALLS OF SHAFT @ MEZZANINE -- FRAMING + SHAFT LINER; E, S, W SIDES OF SHAFT @ 2ND FLR & MEZZANINE TWO LAYERS OF 5/8" TYPE X GWB
Misc
Partial Correction
12/29/2010
TYPE F WALL PER SECTION 6/A6.3: 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD + 1ST LAYER 5/8" TYPE X GWB; 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB; 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" 2ND LAYER 5/8" TYPE X GWB
Electrical Service Inspection Passed 1/4/2011 at 12:00 AM 01/04/2011
Rough Electrical Inspection - Commercial Passed 1/24/2011 at 12:00 AM 01/24/2011
In-wall Inspection Passed 1/24/2011 at 12:00 AM 01/24/2011
Misc
Resolved
01/24/2011
OK TO COVER WHNE READY WALL FRAMING + IN-WALL SYSTEMS AT FOLLOWING SPACES: 1F001 PLAN SOUTH WALL; 1F002; 1F003;
Miscellaneous Inspection Passed 2/7/2011 at 12:00 AM 02/07/2011
Correction
Partial Correction
02/04/2011
ON-GOING COORDINATION
Rated Assembly Inspection Partial 2/10/2011 at 12:00 AM 02/10/2011
Misc
Partial Correction
01/04/2011
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR; SOUTH & EAST WALLS OF SHAFT @ 2ND FLR-- FRAMING + SHAFT LINER; EAST & NORTH WALLS OF SHAFT @ MEZZANINE -- FRAMING + SHAFT LINER; E, S, W SIDES OF SHAFT @ 2ND FLR & MEZZANINE TWO LAYERS OF 5/8" TYPE X GWB
Misc
Partial Correction
01/04/2011
TYPE F WALL PER SECTION 6/A6.3: 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD + 1ST LAYER 5/8" TYPE X GWB; 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB; 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" 2ND LAYER 5/8" TYPE X GWB
Misc
Partial Correction
02/10/2011
TEMPORARY CLOSURE OF ELEVATOR SHAFT OPENINGS @ 1ST FLOOR: FRAMING + SHAFT LINER;
Rated Assembly Inspection Partial 2/11/2011 at 12:00 AM 02/11/2011
Misc
Partial Correction
02/10/2011
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR; SOUTH & EAST WALLS OF SHAFT @ 2ND FLR-- FRAMING + SHAFT LINER; EAST & NORTH WALLS OF SHAFT @ MEZZANINE -- FRAMING + SHAFT LINER; E, S, W SIDES OF SHAFT @ 2ND FLR & MEZZANINE TWO LAYERS OF 5/8" TYPE X GWB
Misc
Partial Correction
02/10/2011
TYPE F WALL PER SECTION 6/A6.3: 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD + 1ST LAYER 5/8" TYPE X GWB; 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB; 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" 2ND LAYER 5/8" TYPE X GWB
Misc
Partial Correction
02/10/2011
TEMPORARY CLOSURE OF ELEVATOR SHAFT OPENINGS @ 1ST FLOOR: FRAMING + SHAFT LINER; 1ST LAYER 5/8" TYPE X GWB;
Rated Assembly Inspection Partial 2/15/2011 at 12:00 AM 02/15/2011
Misc
Resolved
02/15/2011
OK TO COVER WHEN READY SHAFT WALLS @ FOLLOWING LOCATIONS: SHAFT LINER @ MECH SHAFT ADJACENT TO 2F012 S WALL N 6'; SHAFT LINER @ MECH SHAFT ADJACENT TO 3F006; TWO LAYERS 5/8" TYPE X GWB @ SOUTH WALL OF MECH SHAFT @ PENTHOUSE; TWO LAYERS 5/8" TYPE X GWB @ MECH SHAFT NW @ 2ND FLOOR; SOUTH & EAST WALLS OF SHAFT @ 2ND FLR-- FRAMING + SHAFT LINER; EAST & NORTH WALLS OF SHAFT @ MEZZANINE -- FRAMING + SHAFT LINER; E, S, W SIDES OF SHAFT @ 2ND FLR & MEZZANINE TWO LAYERS OF 5/8" TYPE X GWB
Misc
Resolved
02/15/2011
TYPE F WALL PER SECTION 6/A6.3: 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" FRAMING + 1" GWB LINER BOARD + 1ST LAYER 5/8" TYPE X GWB; 1ST FLR INTERFACE OF BLDG "F" WITH BLDG "A" NE FACE OF SW WALL OF CORR 1F013 2ND LAYER 5/8" TYPE X GWB; 2ND FLR INTERFACE OF BLDG "F" WITH BLDG "A" 2ND LAYER 5/8" TYPE X GWB
Misc
Partial Correction
02/11/2011
TEMPORARY CLOSURE OF ELEVATOR SHAFT OPENINGS @ 1ST FLOOR: FRAMING + SHAFT LINER; 1ST LAYER 5/8" TYPE X GWB; 2ND LAYER 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Above Ceiling Inspection Passed 10/19/2010 at 12:00 AM 03/01/2011
Rated Assembly Inspection Partial 3/22/2011 at 12:00 AM 03/22/2011
Misc
Resolved
03/22/2011
TEMPORARY CLOSURE OF ELEVATOR SHAFT OPENINGS @ 1ST FLOOR: FRAMING + SHAFT LINER; 1ST LAYER 5/8" TYPE X GWB; 2ND LAYER 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
Misc
Partial Correction
03/22/2011
RATED RECESS FOR CABINET HEATER AT COMMON WALL WITH EGRESS CORRIDOR @ 1ST FLOOR SOUTHWEST: FRAMING AND LINER BOARD OK TO COVER WHEN READY;
Sprinkler - Hydrostatic Test Passed 4/14/2011 at 12:00 AM 04/14/2011
Alarm Test Passed 5/5/2011 at 12:00 AM 05/05/2011
Sprinkler - Flow Test Failed 5/5/2011 at 12:00 AM 05/05/2011
Sprinkler - Flow Test Passed 05/12/2011
Rated Assembly Inspection Passed 5/13/2011 at 12:00 AM 05/13/2011
Misc
Resolved
05/13/2011
RATED RECESS FOR CABINET HEATER AT COMMON WALL WITH EGRESS CORRIDOR @ 1ST FLOOR SOUTHWEST: FRAMING AND LINER BOARD OK TO COVER WHEN READY;
Footing Inspection - Commercial Passed 11/30/2010 at 12:00 AM 05/24/2011
Misc
Partial Correction
12/09/2010
11-30-10 JB-OK TO POUR WHEN READY BASE SLAB FOR FREIGHT ELEVATOR
Misc
Partial Correction
12/09/2010
GRADE BEAM- AROUND FREIGHT ELEVATOR 12-9-10 MH
Underground Electrical Inspection - Commercial Passed 12/13/2010 at 12:00 AM 05/24/2011
Misc
Partial Correction
12/13/2010
OK TO COVER WHEN READY FOLLOWING SEGMENTS: INSTALLATION OF SECONDARY OK TO COVER WHEN READY: ELECTRICAL SERVICE CONDUIT FOUR 4" PVC CONDUITS BELOW GRADE BEAM AT E/2.3; 4" PVC CONDUITS(6 POWER + 2 DATACOM) PER NOTE 3 SHT EP2.1 FROM B/L TO 16' N; SIX POWER 4" PVC CONDUITS EXTENDED TO TRANSFORMER LOCATION; TWO 4" PVC DATACOM CONDUITS TO U.G. BOX LOCATION; TWO 4" PVC PRIMARY POWER CONDUITS FROM TRANSFORMER LOCATION TO 20' EAST TOWARD KCP&L SERVICE LOOP; TWO 4" PVC DATACOMM FROM PULL BOX N/NE TO CONNECT TO TWO 4" PVC FROM EXISTING SERVICE; TWO 4" PVC DATACOMM FROM PULL BOX W/NW TO CONNECT TO EXISTING CAMPUS PERIMETER DATACOMM CONDUIT RING; COMPLETION OF 4" PVC LOOP TO TRANSFORMER AT EXISTING DUCT BANK
Misc
Partial Correction
12/13/2010
SERVICE GROUNDING AND LIGHTNING PROTECTION SYSTEM: CONDUCTOR FROM ROOFTOP LIGHTNING PROTECTION STUBBED OUT OF COLUMN P/7 AND CONNECTED TO MAIN GROUND RING; GROUND RING EXTENDED FROM NEAR P/7 W/SW TO EE/12;
Misc
Partial Correction
12/13/2010
SERVICE GROUNDING & LIGHTENING PROTECTION - FROM SW CORNER OF BUILDING TO TIE-IN WITH EXISTING GROUND ON NORTH SIDE OF BUILDING
Miscellaneous Inspection Passed 5/25/2011 at 12:00 AM 05/25/2011
Final Inspection - Commercial Partial 5/26/2011 at 12:00 AM 05/26/2011
Misc
Corrective Action Required
05/26/2011
CURTAIN WALL @ 1ST FLOOR NORTH ELEVATION YET TO BE COMPLETED.
Misc
Corrective Action Required
05/26/2011
NORTH ENTRANCE CANOPY SOFFIT YET TO BE COMPLETED.
Misc
Corrective Action Required
05/26/2011
ENSURE ALL DEPARTMENT ISSUES ARE RESOLVED: FIRE DEPARTMENT WATER UTILITIED DEPARTMENT PUBLIC WORKS DEPARTMENT PLANNING & DEVELOPMENT DEPARTMENT
Occupancy Inspection - Fire Temporary C of O 05/26/2011
Final Inspection - Commercial Partial 6/6/2011 at 12:00 AM 06/06/2011
Misc
Corrective Action Required
05/26/2011
CURTAIN WALL @ 1ST FLOOR NORTH ELEVATION YET TO BE COMPLETED.
Misc
Corrective Action Required
05/26/2011
NORTH ENTRANCE CANOPY SOFFIT YET TO BE COMPLETED.
Misc
Corrective Action Required
05/26/2011
ENSURE ALL DEPARTMENT ISSUES ARE RESOLVED: FIRE DEPARTMENT WATER UTILITIED DEPARTMENT PUBLIC WORKS DEPARTMENT PLANNING & DEVELOPMENT DEPARTMENT
Final Inspection - Commercial Partial 6/16/2011 at 12:00 AM 06/16/2011
Misc
Corrective Action Required
06/06/2011
CURTAIN WALL @ 1ST FLOOR NORTH ELEVATION YET TO BE COMPLETED.
Misc
Corrective Action Required
06/06/2011
NORTH ENTRANCE CANOPY SOFFIT YET TO BE COMPLETED.
Misc
Corrective Action Required
06/06/2011
ENSURE ALL DEPARTMENT ISSUES ARE RESOLVED: FIRE DEPARTMENT WATER UTILITIED DEPARTMENT PUBLIC WORKS DEPARTMENT PLANNING & DEVELOPMENT DEPARTMENT
Rated Assembly Inspection Partial 8/18/2011 at 12:00 AM 08/18/2011
Misc
Partial Correction
08/18/2011
FREIGHT ELEVATOR TEMPORARY FLOOR CLOSURE @ 2ND FLOOR LEVEL -- TEMPORARY CONCRETE SLAB REMOVED PER SLHS DIRECTION TO JED, TO BE REPLACED WITH GWB SYSTEM: FRAMING + 1" SHAFT LINER BOARD COMPLETED;
Rated Assembly Inspection Passed 8/22/2011 8/22/2011 at 12:00 AM 08/22/2011
Misc
Resolved
08/22/2011
FREIGHT ELEVATOR TEMPORARY FLOOR CLOSURE @ 2ND FLOOR LEVEL -- TEMPORARY CONCRETE SLAB REMOVED PER SLHS DIRECTION TO JED, TO BE REPLACED WITH GWB SYSTEM: FRAMING + 1" SHAFT LINER BOARD COMPLETED;
Rated Assembly Inspection Passed 8/23/2011 at 12:00 AM 08/23/2011
Above Ceiling Inspection Passed 9/1/2011 at 12:00 AM 09/01/2011
Final Inspection - Commercial Passed 9/24/2012 at 12:00 AM 09/24/2012
Misc
Resolved
09/24/2012
CURTAIN WALL @ 1ST FLOOR NORTH ELEVATION YET TO BE COMPLETED. THIS WORK TRANSFERRED TO PERMIT PRCOM20121010.
Misc
Resolved
09/24/2012
NORTH ENTRANCE CANOPY SOFFIT YET TO BE COMPLETED.
Misc
Resolved
09/24/2012
FINISH SITEWORK NORTH OF BUILDING SUBJECT TO APPROVAL BY PLANNING & DEVELOPMENT DEPARTMENT. THIS WORK TRANSFERRED TO PERMIT PRCOM20121010.
Occupancy Inspection - Engineering Passed 5/27/2011 at 12:00 AM 04/12/2013
Documents & Images
Date Uploaded File Type Document Name
11/02/2010 Letter Inspection Summary
11/02/2010 Letter Inspection Summary
11/02/2010 Letter Inspection Summary
11/05/2010 Letter Inspection Summary
11/08/2010 Letter Inspection Summary
11/09/2010 Letter Inspection Summary
11/10/2010 Letter Inspection Summary
11/12/2010 Letter Inspection Summary
11/17/2010 Letter Inspection Summary
11/17/2010 Letter Inspection Summary
11/17/2010 Letter Inspection Summary
11/19/2010 Letter Inspection Summary
11/19/2010 Letter Inspection Summary
11/22/2010 Letter Inspection Summary
11/29/2010 Letter Inspection Summary
11/29/2010 Letter Inspection Summary
11/29/2010 Letter Inspection Summary
11/30/2010 Letter Inspection Summary
12/01/2010 Letter Inspection Summary
12/02/2010 Letter Inspection Summary
12/06/2010 Letter Inspection Summary
12/06/2010 Letter Inspection Summary
12/06/2010 Letter Inspection Summary
12/06/2010 Letter Inspection Summary
12/07/2010 Letter Inspection Summary
12/09/2010 Letter Inspection Summary
12/09/2010 Letter Inspection Summary
12/13/2010 Letter Inspection Summary
12/16/2010 Letter Inspection Summary
12/21/2010 Letter Inspection Summary
12/27/2010 Letter Inspection Summary
12/29/2010 Letter Inspection Summary
01/04/2011 Letter Inspection Summary
01/24/2011 Letter Inspection Summary
01/24/2011 Letter Inspection Summary
02/10/2011 Letter Inspection Summary
02/11/2011 Letter Inspection Summary
02/15/2011 Letter Inspection Summary
03/01/2011 Letter Inspection Summary
03/22/2011 Letter Inspection Summary
05/12/2011 Letter Fire Loss Reduction Form
05/13/2011 Letter Inspection Summary
05/26/2011 Letter Inspection Summary
05/26/2011 Letter Fire Loss Reduction Form
05/27/2011 Letter 20110527090213503.pdf
08/18/2011 Letter Inspection Summary
08/22/2011 Letter Inspection Summary
08/23/2011 Letter Inspection Summary
09/01/2011 Letter Inspection Summary
09/20/2012 Letter OCCUPANCY LETTER FROM JE DUNN
09/24/2012 Letter Inspection Summary
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home