Permit Application Status

B0900223


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0900223
Building Permit - Commercial
Final Completion
RED SUMMIT FAIR LLC
NEW OTHER
THIS PERMIT COVERS THE WORK AROUND THE BUILDINGS INCLUDING BUT NOT LIMITED TO THE ELECTRICAL, PLUMBING, STORM WATER, STAIRS, RAMPS AND HANDRAILS.
03/27/2009
04/03/2009
03/10/2010
09/21/2009
Locations
Contacts
SALADINO PLUMBING AND HEATING CO., Address:2210 TELEVISION PLACE  
OCHSNER HARE & HARE, Address:KOREY SCHULZ  
ARGO PLUMBING, Address:3671 STATE HIGHWAY P  
VCC, Address:216 LOUISIANA ST  
WESTHUES ELECTRIC INC., Address:4813 RAYTOWN RD  
RED SUMMIT FAIR LLC, Address:1 E WASHINGTON ST STE 300  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 09/23/2009 10/29/2010
Correction

Codes Administrations - 2006 IBC 1009.3 - Stair treads and risers. Stair riser heights shall be 7 inches maximum and 4 inches minimum. Stair tread depths shall be 11 inches minimum. The riser height shall be measured vertically between the leading edges of adjacent treads. The tread depth shall be measured horizontally between the vertical planes of the foremost projection of adjacent treads and at a right angle to the tread's leading edge. Winder treads shall have a minimum tread depth of 11 inches measured at a right angle to the tread's leading edge at a point 12 inches from the side where the treads are narrower and a minimum tread depth of 10 inches.
Correction

Codes Administration - 2006 IBC 1012.2 - Height. Handrail height, measured above the stair tread nosing, or finish surface of ramp slope shall be uniform, not less than 34 inches and not more than 38 inces.
Correction

Codes Administration - 2006 IBC 1012.5 - Handrail Extensions. Handrails shall return to a wall, guard or the walking surface or shall be continuous to the handrail of an adjacent stair flight or ramp run. At stairways where handrails are not continuous between flights, the handrails shall extend horizontally at least 12 inches beyond the top riser and continue to slope for the depth of one tread beyond the bottom riser. At ramps where handrails are not continuous between runs, the handrail shall extend horizontally above the landing 12 inches minimum beyond the top and bottom ramps.
Correction

Codes Administration - 2003 ICC/ANSI A117.1 405.2 - Slope. Ramp runs shall have a running slope not steeper than 1:12.
Correction

Codes Administration - 2003 ICC/ANSI A117.1 405.6 - Rise. The rise for any ramp run shall be 30 inches maximum.
Correction

Codes Administration - I don't believe that the water service shown on Sheet C1-021 has been purchased.
Correction

Codes Administration - Sheet C1-021 does not indicate a backflow device on the water service for the fountain and the fountain details indicate that the backflow is located prior to the vault.
Correction

Codes Administration - I am unable to locate the water service for the irrigation system.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $1,163.88 $1,163.88 Paid 04/03/2009
84 Water Meters $218.27 $218.27 Paid 05/05/2009
85 Water Taps $2,907.00 $2,907.00 Paid 05/05/2009
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underground Plumbing Inspection - Commercial Partial 04/07/2009
Correction
Partial Correction
04/07/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Underground Electrical Inspection - Commercial Not Ready 04/07/2009
Correction
Corrective Action Required
04/07/2009
READINESS FOR INSPECTION WORK REQUESTED FOR INSP NOT COMPLETED
Underground Electrical Inspection - Commercial Request Complete 4/6/2009 4/7/2009 04/07/2009
Underground Plumbing Inspection - Commercial Partial 04/14/2009
Correction
Partial Correction
04/14/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Underground Plumbing Inspection - Commercial Request Complete 4/13/2009 4/14/2009 04/14/2009
Underground Plumbing Inspection - Commercial Not Ready 04/15/2009
Correction
Corrective Action Required
04/15/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underground Plumbing Inspection - Commercial Partial 04/16/2009
Correction
Partial Correction
04/16/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Correction
Resolved
04/16/2009
READINESS FOR INSPECTION
Underground Plumbing Inspection - Commercial Request Complete 4/15/2009 4/16/2009 04/16/2009
Underground Electrical Inspection - Commercial Request Complete 4/15/2009 4/16/2009 04/16/2009
Underground Plumbing Inspection - Commercial Not Ready 04/20/2009
Correction
Corrective Action Required
04/20/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underground Plumbing Inspection - Commercial Partial 04/21/2009
Correction
Partial Correction
04/21/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; 8"RD-41-12"S> 6"RD>8"RD; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Correction
Partial Correction
04/21/2009
READINESS FOR INSPECTION
Underground Plumbing Inspection - Commercial Request Complete 4/20/2009 4/21/2009 04/21/2009
Underground Electrical Inspection - Commercial Not Ready 04/22/2009
Correction
Corrective Action Required
04/22/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underground Electrical Inspection - Commercial Partial 04/22/2009
Correction
Partial Correction
04/22/2009
READINESS FOR INSPECTION
Correction
Partial Correction
04/22/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Partial 04/22/2009
Correction
Partial Correction
04/22/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; 8"RD-41-12"S> 6"RD>8"RD; 65-64-63; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Correction
Resolved
04/22/2009
READINESS FOR INSPECTION
Underground Plumbing Inspection - Commercial Request Complete 4/22/2009 4/22/2009 04/22/2009
Underground Plumbing Inspection - Commercial Partial 04/23/2009
Correction
Partial Correction
04/23/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; 8"RD-41-12"S> 6"RD>8"RD; 65-64-63; CB131-132-142-144-145;129-130;84-85-86; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Underground Plumbing Inspection - Commercial Request Complete 4/22/2009 4/23/2009 04/23/2009
Underground Plumbing Inspection - Commercial Partial 04/24/2009
Correction
Partial Correction
04/24/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; 8"RD-41-12"S> 6"RD>8"RD; 65-64-63; CB131-132-142-144-145;129-130;84-85-86;CB 146,147,148;C82,83,48; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Underground Plumbing Inspection - Commercial Request Complete 4/24/2009 4/24/2009 04/24/2009
Underground Electrical Inspection - Commercial Request Complete 4/24/2009 4/24/2009 04/24/2009
Underground Plumbing Inspection - Commercial Partial 04/28/2009
Correction
Partial Correction
04/28/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; 8"RD-41-12"S> 6"RD>8"RD; 65-64-63;CB131-132-142-144-145; 129-130;84-85-86; CB146-147-148; C82-83-48; 50-49-CB82D; 149>CI022-CI022; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Underground Plumbing Inspection - Commercial Request Complete 4/27/2009 4/28/2009 04/28/2009
Underground Plumbing Inspection - Commercial Request Complete 4/28/2009 4/28/2009 04/28/2009
Underground Plumbing Inspection - Commercial Partial 04/29/2009
Correction
Resolved
04/29/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; 8"RD-41-12"S> 6"RD>8"RD; 65-64-63;CB131-132-142-144-145; 129-130;84-85-86; CB146-147-148; C82-83-48; 50-49-CB82D; 149>CI022-CI022; 8" DRAIN SE TO 35H; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Correction
Partial Correction
04/29/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55C>56C>66C>59C>58C>57C>62C; OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Underground Plumbing Inspection - Commercial Request Complete 4/29/2009 4/29/2009 04/29/2009
Underground Plumbing Inspection - Commercial Not Ready 04/30/2009
Correction
Corrective Action Required
04/30/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underground Plumbing Inspection - Commercial Partial 05/01/2009
Correction
Partial Correction
05/01/2009
READINESS FOR INSPECTION
Correction
Partial Correction
05/01/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55C>56C>66C>59C>58C>57C>62C; 90>89>88>61>38A; 63>40'S; OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Underground Plumbing Inspection - Commercial Request Complete 4/30/2009 5/1/2009 05/01/2009
Underground Plumbing Inspection - Commercial Partial 05/04/2009
Correction
Partial Correction
05/04/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55-56-66-59-58-57-62; 90-89-88-61-ST38A; CB46C-CB67C-8"LAT@18' -CB67AC; CB46-CB47-CB48; CB63-ST38A; OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Underground Plumbing Inspection - Commercial Request Complete 5/1/2009 5/4/2009 05/04/2009
Underground Electrical Inspection - Commercial Partial 05/05/2009
Correction
Partial Correction
05/05/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-25; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Electrical Inspection - Commercial Partial 05/05/2009
Correction
Partial Correction
05/05/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Partial 05/05/2009
Correction
Partial Correction
05/05/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55-56-66-59-58-57-62; 90-89-88-61-ST38A; CB46C-CB67C-8" LAT > TWO 8" TD'S-CB67AC; CB46-CB47-CB48; CB63-ST38A; OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Underground Plumbing Inspection - Commercial Partial 05/05/2009
Correction
Partial Correction
05/05/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55-56-66-59-58-57-62; 90-89-88-61-ST38A; CB46C-CB67C-8" LAT > TWO 8" TD'S-CB67AC; CB46-CB47-CB48; CB63-ST38A; OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Underground Plumbing Inspection - Commercial Request Complete 5/4/2009 5/5/2009 05/05/2009
Underground Plumbing Inspection - Commercial Request Complete 5/4/2009 5/5/2009 05/05/2009
Underground Electrical Inspection - Commercial Request Complete 5/4/2009 5/5/2009 05/05/2009
Underground Electrical Inspection - Commercial Partial 05/07/2009
Correction
Resolved
05/07/2009
READINESS FOR INSPECTION
Correction
Partial Correction
05/07/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Footing Inspection - Commercial Passed 05/07/2009
Correction
Resolved
05/07/2009
FOOTINGS FOR FOUNTAINS, SEAT WALLS, PLANTER WALLS **NOTE: INSPECTIONS OF ELECTRICAL AND PLUMBING WORK ARE NOT WAIVED PREP TO POUR CONCRETE CODES INSPECTION WAIVED
Underground Plumbing Inspection - Commercial Partial 05/07/2009
Correction
Resolved
05/07/2009
READINESS FOR INSPECTION
Correction
Partial Correction
05/07/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55-56-66-59-58-57-62; 90-89-88-61-ST38A; CB46C-CB67C-8" LAT > TWO 8" TD'S-CB67AC; CB46-CB47-CB48; CB63-ST38A; 140-141-10x6T; 8x4T-163-ST5C; 152-153^ST5D^154; OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Underground Plumbing Inspection - Commercial Request Complete 5/7/2009 5/7/2009 05/07/2009
Underground Plumbing Inspection - Commercial Request Complete 5/7/2009 5/7/2009 05/07/2009
Underground Plumbing Inspection - Commercial Partial 05/08/2009
Correction
Resolved
05/08/2009
INSTALLATION OF AREA DRAIN PIPING & RISERS CB42-12J-43-40A; 22-21-20-12H-19-18; 192-191-190-193-17- 8' SHORT OF 12G; 23-24-25+26-27-28-TEE TO 40A; 8"RD-41-12"S> 6"RD>8"RD; 65-64-63;CB131-132-142-144-145; 129-130;84-85-86; CB146-147-148; C82-83-48; 50-49-CB82D; 149>CI022-CI022; 8" DRAIN SE TO 35H; OK TO COVER WHEN READY BETWEEN FOLLOWING POINTS:
Correction
Partial Correction
05/08/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55-56-66-59-58-57-62; 90-89-88-61-ST38A; CB46C-CB67C-8" LAT > TWO 8" TD'S-CB67AC; CB46-CB47-CB48; CB63-ST38A; 140-141-10x6T; 8x4T-163-ST5C; 152-153^ST5D^154; 9B-137-^138^-10x6T-141-8x8T-140; -155-156/121; 124+120>ST12Q; 118+119>ST13B; 117>ST13A; OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Underground Plumbing Inspection - Commercial Request Complete 5/7/2009 5/8/2009 05/08/2009
Underground Plumbing Inspection - Commercial Request Complete 5/7/2009 5/8/2009 05/08/2009
Underground Electrical Inspection - Commercial Partial 05/11/2009
Correction
Partial Correction
05/11/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
05/11/2009
PREPARATION TO POUR LIGHT POLE BASES 1; 2; 3; 4; 5; 24; 25; 26; 27;}} IF POUR , AT RISK** **VERIFICATION REQUIRED RE DIAMETER & LENGTH OF ANCHOR BOLTS OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Underground Plumbing Inspection - Commercial Partial 05/11/2009
Correction
Partial Correction
05/11/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55-56-66-59-58-57-62; 90-89-88-61-ST38A; CB46C-CB67C-8" LAT > TWO 8" TD'S-CB67AC; CB46-CB47-CB48; CB63-ST38A; 140-141-10x6T; 8x4T-163-ST5C; 152-153^ST5D^154; 9B-137-^138^-10x6T-141-8x8T-140; -155-156/121; 124+120>ST12Q; 118+119>ST13B; 117>ST13A; 14>15>16 OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Correction
Partial Correction
05/11/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/11/2009 5/11/2009 05/11/2009
Underground Plumbing Inspection - Commercial Request Complete 5/11/2009 5/11/2009 05/11/2009
Underground Plumbing Inspection - Commercial Partial 05/12/2009
Correction
Resolved
05/12/2009
UNDERGROUND STORM DRAIN PIPING & RISERS 55-56-66-59-58-57-62; 90-89-88-61-ST38A; CB46C-CB67C-8" LAT > TWO 8" TD'S-CB67AC; CB46-CB47-CB48; CB63-ST38A; 140-141-10x6T; 8x4T-163-ST5C; 152-153^ST5D^154; 9B-137-^138^-10x6T-141-8x8T-140; -155-156/121; 124+120>ST12Q; 118+119>ST13B; 117>ST13A; 14>15>16 OK TO COVER WHEN READY SEGMENTS/RISERS @ POINTS:
Correction
Partial Correction
05/12/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/12/2009 5/12/2009 05/12/2009
Underground Plumbing Inspection - Commercial Request Complete 5/12/2009 5/12/2009 05/12/2009
Underground Plumbing Inspection - Commercial Not Ready 05/13/2009
Correction
Corrective Action Required
05/13/2009
READINESS FOR INSPECTION READINESS FOR INSPECTION NOT COMPLETED
Underground Plumbing Inspection - Commercial Request Complete 5/13/2009 5/13/2009 05/13/2009
Rough Electrical Inspection - Commercial Partial 05/14/2009
Correction
Partial Correction
05/14/2009
CONDUIT & BOXES TO BE CAST-IN AT CONCRETE LANDSCAPE STRUCTURES SEAT WALLS AT RAMP WEST OF CLOCK TOWER; OK TO COVER WHEN READY AT FOLLOWING LOCATIONS:
Underground Plumbing Inspection - Commercial Partial 05/14/2009
Correction
Partial Correction
05/14/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; 100>116; 101>102>105; 103>104>105; 107>106>ST15A; 126>125>106; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/14/2009 5/14/2009 05/14/2009
Underground Electrical Inspection - Commercial Partial 05/15/2009
Correction
Corrective Action Required
05/15/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underground Plumbing Inspection - Commercial Partial 05/15/2009
Correction
Partial Correction
05/15/2009
READINESS FOR INSPECTION
Correction
Partial Correction
05/15/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; 100>116; 101>102>105; 103>104>105; 107>106>ST15A; 126>125>106; 116>^116A> 110^>112; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/14/2009 5/15/2009 05/15/2009
Underground Plumbing Inspection - Commercial Request Complete 5/14/2009 5/15/2009 05/15/2009
Underground Electrical Inspection - Commercial Partial 05/18/2009
Correction
Resolved
05/18/2009
READINESS FOR INSPECTION
Correction
Partial Correction
05/18/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
05/18/2009
PREPARATION TO POUR LIGHT POLE BASES 1; 2; 3; 4; 5; 24; 25; 26; 27; OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Underground Plumbing Inspection - Commercial Not Ready 05/18/2009
Correction
Corrective Action Required
05/18/2009
READINESS FOR INSPECTION UPDATED DRAWINGS NOT READY FOR USE
Correction
Partial Correction
05/18/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; 100>116; 101>102>105; 103>104>105; 107>106>ST15A; 126>125>106; 116>^116A> 110^>112; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/15/2009 5/18/2009 05/18/2009
Underground Electrical Inspection - Commercial Partial 05/19/2009
Correction
Partial Correction
05/19/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; 10-9 +60' E; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
05/19/2009
PREPARATION TO POUR LIGHT POLE BASES 1; 2; 3; 4; 5; 24; 25; 26; 27; 28; 29; 30; 31; 32; 10; 9; OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Underground Plumbing Inspection - Commercial Partial 05/19/2009
Correction
Partial Correction
05/19/2009
READINESS FOR INSPECTION
Correction
Partial Correction
05/19/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; 100>116; 101>102>105; 103>104>105; 107>106>ST15A; 126>125>106; 116>^116A> 110^>112; 66>179*>59>58; *NEW(REPLACEMENT) OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
05/19/2009
INSTALLATION OF GREASE TRAP ENGINEER CLARIFICATION REQUIRED REGARDING VENTING -- NOT SHOWN ON DRAWINGS. EAST OF 860 -- BLDG D OK TO COVER EXCEPT:
Underground Plumbing Inspection - Commercial Request Complete 5/18/2009 5/19/2009 05/19/2009
Underground Plumbing Inspection - Commercial Request Complete 5/18/2009 5/19/2009 05/19/2009
Underground Electrical Inspection - Commercial Request Complete 5/18/2009 5/19/2009 05/19/2009
Underground Electrical Inspection - Commercial Request Complete 5/18/2009 5/19/2009 05/19/2009
Underground Plumbing Inspection - Commercial Partial 05/20/2009
Correction
Partial Correction
05/20/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; 100>116; 101>102>105; 103>104>105; 107>106>ST15A; 126>125>106; 116>^116A> 110^>112; 66>179*>59>58; 134>136>ST37A; 133>135>ST37A; IJK RD CONNS @ J5/JH.3>J5/JK.5; *NEW(REPLACEMENT) OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Resolved
05/20/2009
INSTALLATION OF GREASE TRAP ENGINEER DETERMINATION THAT VENTING IS NOT REQUIRED EAST OF 860 -- BLDG D OK TO COVER CONTINGENT ON
Underground Plumbing Inspection - Commercial Request Complete 5/19/2009 5/20/2009 05/20/2009
Underground Electrical Inspection - Commercial Partial 05/21/2009
Correction
Partial Correction
05/21/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; 10-9 +60' E; ROUNDABOUT NE TO ^LP21^ TO C1/CH.3 @ "C"; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Partial 05/21/2009
Correction
Resolved
05/21/2009
READINESS FOR INSPECTION
Correction
Resolved
05/21/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; 100>116; 101>102>105; 103>104>105; 107>106>ST15A; 126>125>106; 116>^116A> 110^>112; 66>179*>59>58; 134>136>ST37A; 133>135>ST37A; IJK RD CONNS @ J5/JH.3>J5/JK.5>J5/JL.7>J5/JN>CB162; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
05/21/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D
Underground Plumbing Inspection - Commercial Request Complete 5/20/2009 5/21/2009 05/21/2009
Underground Plumbing Inspection - Commercial Request Complete 5/20/2009 5/21/2009 05/21/2009
Underground Plumbing Inspection - Commercial Partial 05/22/2009
Correction
Partial Correction
05/22/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D TD@N5/NC.7>ST17A; CB93>94>ST17B; 95>96>ST16A; 91>^92^>ST37A; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/22/2009 5/22/2009 05/22/2009
Underground Plumbing Inspection - Commercial Request Complete 5/22/2009 5/22/2009 05/22/2009
Underground Plumbing Inspection - Commercial Partial 05/27/2009
Correction
Resolved
05/27/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS 14>15>16+6'E; 128^127>ST14B; CB13>12; RD>CB10>11>12; 100>116; 101>102>105; 103>104>105; 107>106>ST15A; 126>125>106; 116>^116A> 110^>112; 66>179*>59>58; 134>136>ST37A; 133>135>ST37A; IJK RD CONNS @ J5/JH.3>J5/JK.5>J5/JL.7>J5/JN>CB162; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
05/27/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D TD@N5/NC.7>ST17A; CB93>94>ST17B; 95>96>ST16A; 91>^92^>ST37A; 36>37>38>39^ST18A^<40; 31>32>33>30>34; 29>30; ILD>34>6' SHORT OF ST12D; 12" TD LATERAL 10'W FROM TEE SE OF BLDG C; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/26/2009 5/27/2009 05/27/2009
Underground Plumbing Inspection - Commercial Request Complete 5/26/2009 5/27/2009 05/27/2009
Underground Plumbing Inspection - Commercial Partial 05/28/2009
Correction
Partial Correction
05/28/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D TD@N5/NC.7>ST17A; CB93>94>ST17B; 95>96>ST16A; 91>^92^>ST37A; 36>37>38>39^ST18A^<40; 31>32>33>30>34; 29>30; ILD>34>ST12D; 12" TD LATERAL 10'W FROM TEE SE OF BLDG C; 1>2>3>4; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 5/28/2009 5/28/2009 05/28/2009
Underground Plumbing Inspection - Commercial Request Complete 5/28/2009 5/28/2009 05/28/2009
Underground Plumbing Inspection - Commercial Partial 05/29/2009
Correction
Partial Correction
05/29/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D TD@N5/NC.7>ST17A; CB93>94>ST17B; 95>96>ST16A; 91>^92^>ST37A; 36>37>38>39^ST18A^<40; 31>32>33>30>34; 29>30; ILD>34>ST12D; 12" TD LATERAL 10'W FRM TEE SE OF BLDG C; 1>2>3>4; 9>8>7>5>ST39G; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Resolved
05/29/2009
PRESSURE TEST OF FOUNTAIN WATER PIPING SYSTEM VCC ADVISES DETAILED RECORD IS ON FILE AT THEIR PREMISES. WITNESSED @ => 30PSI PER VCC 5/28/09
Underground Plumbing Inspection - Commercial Request Complete 5/28/2009 5/29/2009 05/29/2009
Underground Plumbing Inspection - Commercial Request Complete 5/28/2009 5/29/2009 05/29/2009
Underground Electrical Inspection - Commercial Partial 06/01/2009
Correction
Partial Correction
06/01/2009
PREPARATION TO POUR LIGHT POLE BASES 1-5; 9; 10; 24-32; 6; 7; 8; 13*; 14*; 15*; *: GROUNDS NOT YET IN PLACE OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Underground Electrical Inspection - Commercial Request Complete 6/1/2009 6/1/2009 06/01/2009
Underground Plumbing Inspection - Commercial Partial 06/02/2009
Correction
Partial Correction
06/02/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D TD@N5/NC.7>ST17A; CB93>94>ST17B; 95>96>ST16A; 91>^92^>ST37A; 36>37>38>39^ST18A^<40; 31>32>33>30>34; 29>30; ILD>34>ST12D; 12" TD LATERAL 10'W FRM TEE SE OF BLDG C; 1>2>3>4; 9>8>7>5>ST39G; 108>109; 105>109; 109>111; 112>111; 111>113>114; 115>114>ST16A; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Plumbing Inspection - Commercial Request Complete 6/1/2009 6/2/2009 06/02/2009
Underground Electrical Inspection - Commercial Partial 06/03/2009
Correction
Partial Correction
06/03/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; 10-9 +60' E; ROUNDABOUT NE TO ^LP21^ TO C1/CH.3 @ "C"; 11-12; 12-13; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
06/03/2009
BURIED CONDUIT AT FOUNTAIN EIGHT 1" + ONE 3/4" FROM FOUNTAIN NW TO PIT; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Plumbing Inspection - Commercial Partial 06/03/2009
Correction
Resolved
06/03/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D TD@N5/NC.7>ST17A; CB93>94>ST17B; 95>96>ST16A; 91>^92^>ST37A; 36>37>38>39^ST18A^<40; 31>32>33>30>34; 29>30; ILD>34>ST12D; 12" TD LAT 10'W FRM TEE SE OF BLDG C; 1>2>3>4; 9>8>7>5>ST39G; 108>109; 105>109; 109>111; 112>111; 111>113>114; 115>114>ST16A; CONT'D; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
06/03/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Electrical Inspection - Commercial Partial 06/04/2009
Correction
Partial Correction
06/04/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; 10-9 +60' E; ROUNDABOUT NE TO ^LP21^ TO C1/CH.3 @ "C"; 11-12; 12-13; 13-14; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Partial Correction
06/04/2009
PREPARATION TO POUR LIGHT POLE BASES 1-10; 11; 12; 13; 14*; 15*; 24-32; *: GROUNDS NOT YET IN PLACE OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Underground Plumbing Inspection - Commercial Request Complete 6/3/2009 6/4/2009 06/04/2009
Underground Plumbing Inspection - Commercial Request Complete 6/3/2009 6/4/2009 06/04/2009
Underground Electrical Inspection - Commercial Request Complete 6/3/2009 6/4/2009 06/04/2009
Underground Electrical Inspection - Commercial Partial 06/05/2009
Correction
Partial Correction
06/05/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; 10-9 +60' E; ROUNDABOUT NE TO ^LP21^ TO C1/CH.3 @ "C"; 11-12; 12-13; 13-14; 14-15-N>DIRECTORY; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Electrical Inspection - Commercial Request Complete 6/4/2009 6/5/2009 06/05/2009
Underground Electrical Inspection - Commercial Partial 06/09/2009
Correction
Partial Correction
06/09/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; 10-9 +60' E; ROUNDABOUT NE TO ^LP21^ TO C1/CH.3 @ "C"; 11-12; 12-13; 13-14; 14-15-N>DIRECTORY; ROUNDABOUT TO NW CRNR BLDG D; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Underground Electrical Inspection - Commercial Not Ready 06/10/2009
Correction
Corrective Action Required
06/10/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underground Electrical Inspection - Commercial Partial 06/11/2009
Underground Electrical Inspection - Commercial Request Complete 6/10/2009 6/11/2009 06/11/2009
Pool Steel/Bonding - Commercial Partial 06/15/2009
Correction
Partial Correction
06/15/2009
BONDING OF CONDUCTIVE ELEMENTS AT FOUNTAIN RE-BAR CAGES AT FOUNTAIN FOOTINGS -- CONTINGENT ON ELECT ENGINEER CONFIRMATION THAT IT IS SUFFICIENT TO CONNECT EACH CONTINUOUS CAGE AT JUST ONE LOCATION; OK TO COVER WHEN READY FOLLOWING ELEMENTS:
Underground Electrical Inspection - Commercial Partial 06/19/2009
Correction
Resolved
06/19/2009
READINESS FOR INSPECTION
Correction
Resolved
06/19/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS CONDUIT BETWEEN POINTS: LP1-2-3-4-5-STAIR LIGHT; 22-23-24-25; BLDG D N END TO CLOCK TOWER BASE; 24-25; 26-27; 28-29-30-31-32; 10-9 +60' E; ROUNDABOUT NE TO ^LP21^ TO C1/CH.3 @ "C"; 11-12; 12-13; 13-14; 14-15-N>DIRECTORY; OK TO COVER WHEN READY FOLLOWING COMPONENTS:
Correction
Resolved
06/19/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Plumbing Inspection - Commercial Partial 06/19/2009
Correction
Partial Correction
06/19/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 6/18/2009 6/19/2009 06/19/2009
Pool Steel/Bonding - Commercial Partial 06/22/2009
Correction
Partial Correction
06/22/2009
BONDING OF CONDUCTIVE ELEMENTS AT FOUNTAIN RE-BAR CAGES AT FOUNTAIN FOOTINGS, INCLUDING LOWER POUR 6/22/09 WITH CAGES BONDED TO GROUND RODS @ FOUR OUTER CORNERS; OK TO COVER WHEN READY FOLLOWING ELEMENTS:
Underground Electrical Inspection - Commercial Partial 06/22/2009
Correction
Partial Correction
06/22/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 6/19/2009 6/22/2009 06/22/2009
Underground Plumbing Inspection - Commercial Partial 06/23/2009
Correction
Partial Correction
06/23/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Partial 06/23/2009
Correction
Partial Correction
06/23/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; 168>167>ST8A; 150>151>ST8A; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 6/23/2009 6/23/2009 06/23/2009
Underground Plumbing Inspection - Commercial Request Complete 6/23/2009 6/23/2009 06/23/2009
Underground Plumbing Inspection - Commercial Partial 06/24/2009
Correction
Partial Correction
06/24/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; 168>167>ST8A; 150>151>ST8A; 158>159>157>CONN @ 8" MAIN; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 6/23/2009 6/24/2009 06/24/2009
Underground Plumbing Inspection - Commercial Request Complete 6/23/2009 6/24/2009 06/24/2009
Underground Electrical Inspection - Commercial Partial 06/25/2009
Correction
Partial Correction
06/25/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S EAST OF ROUNDABOUT; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Plumbing Inspection - Commercial Partial 06/25/2009
Correction
Partial Correction
06/25/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; 168>167>ST8A; 150>151>ST8A; 158>159>157>CONN @ 8" MAIN; 178>180>181>33' NORTH; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Electrical Inspection - Commercial Request Complete 6/24/2009 6/25/2009 06/25/2009
Underground Plumbing Inspection - Commercial Request Complete 6/24/2009 6/25/2009 06/25/2009
Underground Plumbing Inspection - Commercial Request Complete 6/24/2009 6/25/2009 06/25/2009
Underground Electrical Inspection - Commercial Request Complete 6/25/2009 6/25/2009 06/25/2009
Underground Electrical Inspection - Commercial Partial 06/26/2009
Correction
Partial Correction
06/26/2009
PREPARATION TO POUR LIGHT POLE BASES 1-10; 11; 12; 13; 14*; 15*; 24-32; 16*; 17*; 18*; 19*; 20*; 21*; *: GROUNDS NOT YET APPROVED OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Pool Steel/Bonding - Commercial Partial 06/26/2009
Correction
Partial Correction
06/26/2009
BONDING OF CONDUCTIVE ELEMENTS AT FOUNTAIN RE-BAR CAGES AT FOUNTAIN FOOTINGS, INCLUDING LOWER POUR 6/22/09 WITH CAGES BONDED TO GROUND RODS @ FOUR OUTER CORNERS; METALLIC CIRCULATION SYSTEM DEVICES AT FOUNTAIN POOL OK TO COVER WHEN READY FOLLOWING ELEMENTS:
Underground Plumbing Inspection - Commercial Partial 06/26/2009
Correction
Partial Correction
06/26/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; 168>167>ST8A; 150>151>ST8A; 158>159>157>CONN @ 8" MAIN; 178>180>181>33' NORTH; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 6/25/2009 6/26/2009 06/26/2009
Underground Electrical Inspection - Commercial Request Complete 6/26/2009 6/26/2009 06/26/2009
Underground Electrical Inspection - Commercial Partial 06/30/2009
Correction
Partial Correction
06/30/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S EAST OF ROUNDABOUT; 182>182A>183>ST3A; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Plumbing Inspection - Commercial Request Complete 6/29/2009 6/30/2009 06/30/2009
Pool Steel/Bonding - Commercial Partial 07/01/2009
Correction
Partial Correction
07/01/2009
BONDING OF CONDUCTIVE ELEMENTS AT FOUNTAIN RE-BAR CAGES AT FOUNTAIN FOOTINGS, INCLUDING LOWER POUR 6/22/09 WITH CAGES BONDED TO GROUND RODS @ FOUR OUTER CORNERS; METALLIC CIRCULATION SYSTEM DEVICES AT FOUNTAIN POOL BOTTOM; FOUR FILTER RETURN CAST-IN's @ FOUNTAIN WALLS; OK TO COVER WHEN READY FOLLOWING ELEMENTS:
Underground Electrical Inspection - Commercial Partial 07/01/2009
Correction
Partial Correction
07/01/2009
PREPARATION TO POUR LIGHT POLE BASES 1-10; 11; 12; 13; 14*; 15*; 24-32; 16*; 17*; 18*; 19*; 20*; 21*; 33; 34; 35; 40; 41; 42; 43; 44; *: GROUNDS NOT YET APPROVED OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Correction
Partial Correction
07/01/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S E OF ROUNDABOUT; POLE BASES, BOXES, STAIR LIGHTS ALONG 33-34-35-40-41-42-43-44; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Plumbing Inspection - Commercial Partial 07/01/2009
Correction
Resolved
07/01/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; 168>167>ST8A; 150>151>ST8A; 158>159>157> CONN @ 8" MAIN; 178>180>181>33' NORTH; 182>182A>183>ST3A; 186>184>ST3A; 164 REVISED TO TIE INTO ROOF DRAIN LINE; CONT'D OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
07/01/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 6/30/2009 7/1/2009 07/01/2009
Underground Electrical Inspection - Commercial Partial 07/02/2009
Correction
Partial Correction
07/02/2009
PREPARATION TO POUR LIGHT POLE BASES 1-10; 11; 12; 13; 14; 15*; 24-32; 16; 17; 18; 19; 20*; 21; 33; 34; 35; 40; 41; 42; 43; 44; *: GROUNDS COVERED WITHOUT APPROVAL OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Correction
Partial Correction
07/02/2009
BURIED CONDUIT AT FOUNTAIN EIGHT 1" + ONE 3/4" FROM FOUNTAIN NW TO FOUNTAIN EQPT VAULT; REMAINDER OF PVC CONDUIT TO VAULT @ LOWER LIFT; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Water Service Inspection Partial 07/02/2009
Correction
Partial Correction
07/02/2009
WATER SERVICE LINE TO FOUNTAIN EQUIPMENT VAULT 3/4" COPPER TO METER WELL TO BACKFLOW PREVENTION DEVICE WELL; 1-1/2" HDPE TO 5' NW; OK TO COVER WHEN READY FROM CITY TAP @ MAIN
Underground Plumbing Inspection - Commercial Partial 07/02/2009
Correction
Resolved
07/02/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; 168>167>ST8A; 150>151>ST8A; 158>159>157> CONN @ 8" MAIN; 178>180>181>W/I 12' OF ST4A; 182>182A>183>ST3A; 186>184>ST3A; 164 REV TO TIE INTO ROOF DRAIN LINE; CONT'D OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Water Service Inspection Passed 07/03/2009
Correction
Resolved
07/03/2009
WATER SERVICE LINE TO FOUNTAIN EQUIPMENT VAULT 3/4" COPPER TO METER WELL TO BACKFLOW PREVENTION DEVICE WELL; 1-1/2" HDPE TO FOUNTAIN EQUIPMENT VAULT OK TO COVER WHEN READY FROM CITY TAP @ MAIN
Underground Plumbing Inspection - Commercial Partial 07/06/2009
Correction
Partial Correction
07/06/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 174 TO 178 OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 7/2/2009 7/6/2009 07/06/2009
Underground Plumbing Inspection - Commercial Request Complete 7/2/2009 7/6/2009 07/06/2009
Underground Electrical Inspection - Commercial Partial 07/07/2009
Correction
Partial Correction
07/07/2009
BURIED CONDUIT AT FOUNTAIN EIGHT 1" + ONE 3/4" FROM FOUNTAIN NW TO FOUNTAIN EQPT VAULT; REMAINDER OF PVC CONDUIT TO VAULT @ LOWER LIFT; CONDUIT BETWEEN FOUNTAINS- TO VAULT;POWER TO VAULT; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Plumbing Inspection - Commercial Partial 07/07/2009
Correction
Partial Correction
07/07/2009
FOUNTAIN AREA PVC PIPING CONNECTING FOUNTAIN TO MAIN DRAIN;
Underground Electrical Inspection - Commercial Request Complete 7/6/2009 7/7/2009 07/07/2009
Underground Plumbing Inspection - Commercial Request Complete 7/6/2009 7/7/2009 07/07/2009
Underground Plumbing Inspection - Commercial Partial 07/08/2009
Correction
Resolved
07/08/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 164>160>161; 185>ST5K; 188>187>186>ST5K; 189>ST6B; 171>172>ST6B; 170>173>ST7A; 169>ST7A; 168>167>ST8A; 150>151>ST8A; 158>159>157> CONN @ 8" MAIN; 178>180>181>W/I 12' OF ST4A; 182>182A>183>ST3A; 186>184>ST3A; 164 REV TO TIE INTO ROOF DRAIN LINE; CONT'D OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Partial Correction
07/08/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 174 TO 178, 44>45>46 EAST OF ROUNDABOUT OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 7/7/2009 7/8/2009 07/08/2009
Underground Electrical Inspection - Commercial Partial 07/09/2009
Correction
Partial Correction
07/09/2009
BURIED CONDUIT AT FOUNTAIN EIGHT 1" + ONE 3/4" FROM FOUNTAIN NW TO FOUNTAIN EQPT VAULT; REMAINDER OF PVC CONDUIT TO VAULT @ LOWER LIFT; CONDUIT BETWEEN FOUNTAINS- TO VAULT;POWER TO VAULT;FOUNTAIN VAULT COMPLETE OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Plumbing Inspection - Commercial Partial 07/09/2009
Correction
Partial Correction
07/09/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 174 TO 178, 44>45>46 EAST OF ROUNDABOUT;41A AND CHANGE AT FOUNTAIN VAULT. OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 7/9/2009 7/9/2009 07/09/2009
Rough Electrical Inspection - Commercial Passed 07/16/2009
Correction
Resolved
07/16/2009
CONDUIT & BOXES TO BE CAST-IN AT CONCRETE LANDSCAPE STRUCTURES SEAT WALLS AT RAMP WEST OF CLOCK TOWER; OK TO COVER WHEN READY AT FOLLOWING LOCATIONS:
Correction
Resolved
07/16/2009
WIRING @ J-BOXES AT AMPITHEATER FOUNTAIN BASINS OK TO COVER AFTER TIGHTEN GROUND WIRE CONNECTIONS
Underground Plumbing Inspection - Commercial Request Complete 7/15/2009 7/16/2009 07/16/2009
Underground Plumbing Inspection - Commercial Partial 07/21/2009
Correction
Partial Correction
07/21/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 174 TO 178, 44>45>46 EAST OF ROUNDABOUT;41A AND CHANGE AT FOUNTAIN VAULT; TRENCH DRAIN PIPING ALONG S END OF BLDG C ~80 LF; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Correction
Resolved
07/21/2009
FOUNTAIN AREA PVC PIPING FROM FOUNTAIN TO MAIN DRAIN
Underground Plumbing Inspection - Commercial Request Complete 7/21/2009 7/21/2009 07/21/2009
Underground Plumbing Inspection - Commercial Request Complete 7/21/2009 7/21/2009 07/21/2009
Underground Electrical Inspection - Commercial Partial 07/23/2009
Correction
Partial Correction
07/23/2009
PREPARATION TO POUR LIGHT POLE BASES 1-10; 11; 12; 13; 14; 15*; 24-32; 16; 17; 18; 19; 20*; 21; 33; 34; 35; 40; 41; 42; 43; 44; EIGHT @ PERIMETER OF BLDG E LOT; *: GROUNDS COVERED WITHOUT APPROVAL OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Correction
Resolved
07/23/2009
BURIED CONDUIT AT FOUNTAIN EIGHT 1" + ONE 3/4" FROM FOUNTAIN NW TO FOUNTAIN EQPT VAULT; REMAINDER OF PVC CONDUIT TO VAULT @ LOWER LIFT; CONDUIT BETWEEN FOUNTAINS- TO VAULT;POWER TO VAULT;FOUNTAIN VAULT COMPLETE OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 7/22/2009 7/23/2009 07/23/2009
Underground Electrical Inspection - Commercial Partial 07/28/2009
Correction
Partial Correction
07/28/2009
PREPARATION TO POUR LIGHT POLE BASES 1-10; 11; 12; 13; 14; 15*; 24-32; 16; 17; 18; 19; 20*; 21; 33; 34; 35; 40; 41; 42; 43; 44; EIGHT @ PERIMETER OF BLDG E LOT; 51; 54; 55; 56; 57; 58; *: GROUNDS COVERED WITHOUT APPROVAL NOTE: 49; 50; 52; 53 NOT TO BE CONSTRUCTED AT THIS TIME OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Underground Plumbing Inspection - Commercial Not Ready 07/28/2009
Correction
Corrective Action Required
07/28/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underground Electrical Inspection - Commercial Request Complete 7/27/2009 7/28/2009 07/28/2009
Underground Plumbing Inspection - Commercial Partial 07/29/2009
Correction
Partial Correction
07/29/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 174 TO 178, 44>45>46 EAST OF ROUNDABOUT;41A AND CHANGE AT FOUNTAIN VAULT; TRENCH DRAIN PIPING ALONG S END OF BLDG C ~80 LF; 50 L.F. 15" PIPE ALONG E SIDE OF BLDG PER SHT C1-023; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Partial 07/30/2009
Correction
Partial Correction
07/30/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 174 TO 178, 44>45>46 EAST OF ROUNDABOUT;41A AND CHANGE AT FOUNTAIN VAULT; TRENCH DRAIN PIPING ALONG S END OF BLDG C ~80 LF; 133 L.F. 15" PIPE ALONG W SIDE OF BLDG TO ST4B PER SHT C1-023; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Plumbing Inspection - Commercial Request Complete 7/30/2009 7/30/2009 07/30/2009
Final Inspection - Commercial Not Ready 08/04/2009
Correction
Corrective Action Required
08/04/2009
UL LISTING OF LIGHTED DEVELOPMENT SIGNS PER NEC 600.3. IF INTERNALLY LIGHTED MUST BE UL SHOP-LABELED
Underground Electrical Inspection - Commercial Partial 08/05/2009
Correction
Partial Correction
08/05/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S E OF ROUNDABOUT; POLE BASES, BOXES, STAIR LIGHTS ALONG 33-34-35-40-41-42-43-44; 54-55-56; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 8/5/2009 8/5/2009 08/05/2009
Underground Electrical Inspection - Commercial Partial 08/07/2009
Correction
Partial Correction
08/07/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S E OF ROUNDABOUT; POLE BASES, BOXES, STAIR LIGHTS ALONG 33-34-35-40-41-42-43-44; 54-55-56; 36-37; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 8/7/2009 8/7/2009 08/07/2009
Miscellaneous Inspection Not Ready 08/11/2009
Correction
Corrective Action Required
08/11/2009
PRE-FINAL OBSERVATIONS
Underground Electrical Inspection - Commercial Partial 08/12/2009
Correction
Partial Correction
08/12/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S E OF ROUNDABOUT; POLE BASES, BOXES, STAIR LIGHTS ALONG 33-34-35-40-41-42-43-44; 54-55-56; 36-37; 56-57-58; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 8/12/2009 8/12/2009 08/12/2009
Underground Electrical Inspection - Commercial Partial 08/14/2009
Correction
Partial Correction
08/14/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S E OF ROUNDABOUT; POLE BASES, BOXES, STAIR LIGHTS ALONG 33-34-35-40-41-42-43-44; 54-55-56; 36-37; 56-57-58; 36-45; 10' S OF 45; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Correction
Partial Correction
08/14/2009
TRENCH _CONDUIT FOR SITE ELECTRICAL SYSTEMS 10' E.W. AT 46; SW TO ROAD AT 51; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 8/13/2009 8/14/2009 08/14/2009
Underground Electrical Inspection - Commercial Partial 08/18/2009
Correction
Resolved
08/18/2009
TRENCH & CONDUIT FOR SITE ELECTRICAL SYSTEMS ROUNDABOUT TO NW CRNR BLDG D; THREE 1-1/2" PVC CONDUITS FROM ROUNDABOUT TO SW CRNR BLDG C; NEAR LP21-16-17-18; TWO 1" PVC N-S E OF ROUNDABOUT; POLE BASES, BOXES, STAIR LITES @ 33-34-35-40-41-42-43-44; 54-55-56; 36-37; 56-57-58; 36-45; 10' S OF 45; CONT'D OK TO COVER WHEN READY FOLLOWING PORTIONS:
Correction
Partial Correction
08/18/2009
TRENCH _CONDUIT FOR SITE ELECTRICAL SYSTEMS 10' E.W. AT 46; SW TO ROAD AT 51; 45-46-47; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 8/18/2009 8/18/2009 08/18/2009
Pool Steel/Bonding - Commercial Passed 08/19/2009
Correction
Resolved
08/19/2009
BONDING OF CONDUCTIVE ELEMENTS AT FOUNTAIN RE-BAR CAGES AT FOUNTAIN FOOTINGS, INCLUDING LOWER POUR 6/22/09 WITH CAGES BONDED TO GROUND RODS @ FOUR OUTER CORNERS; METALLIC CIRCULATION SYSTEM DEVICES AT FOUNTAIN POOL BOTTOM; FOUR FILTER RETURN CAST-IN's @ FOUNTAIN WALLS; OK TO COVER WHEN READY FOLLOWING ELEMENTS:
Final Inspection - Commercial Not Ready 08/19/2009
Correction
Corrective Action Required
08/19/2009
UL LISTING OF LIGHTED DEVELOPMENT SIGNS PER NEC 600.3. SEE THREE FREE-STANDING INTERNALLY LIGHTED DIRECTORY CABINETS. IF INTERNALLY LIGHTED MUST BE UL SHOP-LABELED
Correction
Corrective Action Required
08/19/2009
FIRE PROTECTION HYDRANT WATER SHUT-OFF RISERS SET CASTINGS TO GRADE
Underground Electrical Inspection - Commercial Partial 08/25/2009
Correction
Partial Correction
08/25/2009
TRENCH _CONDUIT FOR SITE ELECTRICAL SYSTEMS 10' E.W. AT 46; SW TO ROAD AT 51; 45-46-47; 37-38-39; OK TO COVER WHEN READY FOLLOWING PORTIONS:
Underground Electrical Inspection - Commercial Request Complete 8/24/2009 8/25/2009 08/25/2009
Underground Electrical Inspection - Commercial Passed 08/26/2009
Correction
Resolved
08/26/2009
PREPARATION TO POUR LIGHT POLE BASES 1-10; 11; 12; 13; 14; 15*; 24-32; 16; 17; 18; 19; 20*; 21; 33; 34; 35; 40; 41; 42; 43; 44; EIGHT @ PERIMETER OF BLDG E LOT; 51; 54; 55; 56; 57; 58; *: GROUNDS COVERED WITHOUT APPROVAL NOTE: 49; 50; 52; 53 NOT TO BE CONSTRUCTED AT THIS TIME OK TO POUR WHEN READY BASES@FOLLOWING LOCATIONS
Correction
Resolved
08/26/2009
TRENCH _CONDUIT FOR SITE ELECTRICAL SYSTEMS 10' E.W. AT 46; SW TO ROAD AT 51; 45-46-47; 37-38-39; 47-48 OK TO COVER WHEN READY FOLLOWING PORTIONS:
Miscellaneous Inspection Passed 08/26/2009
Correction
Resolved
08/26/2009
PRE-FINAL OBSERVATIONS SEE FINAL BUILDING
Final Inspection - Commercial Failed 08/26/2009
Correction
Corrective Action Required
08/26/2009
UL LISTING OF LIGHTED DEVELOPMENT SIGNS PER NEC 600.3: SEE FOUR INTERNALLY-LIGHTED DIRECTORY CABINETS. IF INTERNALLY LIGHTED MUST BE UL SHOP-LABELED
Correction
Corrective Action Required
08/26/2009
Receive Planning & Development Approval
Correction
Corrective Action Required
08/26/2009
Receive Public Works Approval
Correction
Corrective Action Required
08/26/2009
Receive Water Utilities Approval
Correction
Corrective Action Required
08/26/2009
DEVELOPMENT AGREEMENT OFF-SITE IMPROVEMENTS SUBJECT TO PW APPROVAL CONTACT RED DEVELOPMENT
Underground Plumbing Inspection - Commercial Passed 08/26/2009
Correction
Resolved
08/26/2009
READINESS FOR INSPECTION
Correction
Resolved
08/26/2009
UNDERGROUND STORM DRAINAGE PIPING & RISERS, CONT'D 174 TO 178, 44>45>46 EAST OF ROUNDABOUT;41A AND CHANGE AT FOUNTAIN VAULT; TRENCH DRAIN PIPING ALONG S END OF BLDG C ~80 LF; 133 L.F. 15" PIPE ALONG W SIDE OF BLDG TO ST4B PER SHT C1-023 OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underground Electrical Inspection - Commercial Request Complete 8/26/2009 8/26/2009 08/26/2009
Final Inspection - Commercial Failed 09/08/2009
Correction
Resolved
09/08/2009
FIRE PROTECTION HYDRANT WATER SHUT-OFF RISERS CASTINGS SET TO GRADE
Final Inspection - Commercial Failed 09/09/2009
Final Inspection - Commercial Failed 09/10/2009
Final Inspection - Commercial Failed 09/11/2009
Final Inspection - Commercial Failed 09/14/2009
Final Inspection - Commercial Failed 09/15/2009
Final Inspection - Commercial Failed 09/16/2009
Final Inspection - Commercial Failed 09/17/2009
Correction
Resolved
09/17/2009
Receive Water Utilities Approval
Final Inspection - Commercial Passed 09/18/2009
Correction
Resolved
09/18/2009
UL LISTING OF LIGHTED DEVELOPMENT SIGNS E-MAIL STIPULATION TO JB DATED 9/18/09 TO BE RESOLVED PER RED DEVELOPMENT
Correction
Resolved
09/18/2009
Receive Planning & Development Approval E-MAIL STIPULATION TO JB DATED 9/18/09 REMAINING ISSUES TO BE RESOLVED PER RED DVLPT
Correction
Resolved
09/18/2009
Receive Public Works Approval E-MAIL STIPULATION TO JB DATED 9/18/09 REMAINING ISSUES TO BE RESOLVED PER RED DVLPT
Correction
Resolved
09/18/2009
DEVELOPMENT AGREEMENT OFF-SITE IMPROVEMENTS SEE BY RED DEVELOPMENT E-MAIL STIPULATION TO JB DATED 9/18/09 CORRECTIONS IN PROGRESS BY RED DEVELOPMENT
Documents & Images
Date Uploaded File Type Document Name
09/19/2017 B0900223summitfairhardscapecomments1
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home