Summary
B0801641
Building Permit - Commercial
Final Completion
RED SUMMIT FAIR LLC
PARTIAL COMMERCIAL
FOUNDATION AND UNDERSLAB
11/21/2008
12/04/2008
06/02/2009
02/05/2009
Locations
Contacts
WESTHUES ELECTRIC INC., Address:4813 RAYTOWN RD  
ARGO PLUMBING, Address:3671 STATE HIGHWAY P  
GEOTECHNOLOGY INC, Address:9136 CODY  
THE PRESTON PARTNERSHIP, LLC, Address:100 ABERNATHY ROAD NE, SUITE 600  
VCC, Address:216 LOUISIANA ST  
RED SUMMIT FAIR LLC, Address:1 E WASHINGTON ST STE 300  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 05/23/2009 10/29/2010
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $341.97 $341.97 Paid 12/04/2008
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 01/16/2009
Correction
Partial Correction
01/16/2009
PREP TO POUR EXTERIOR GRADE BEAM + INTEGRAL COLUMN FOOTINGS N2.8/NK TO N2.8/NC.2 TO NC.2/N1; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Rough Electrical Inspection - Commercial Passed 01/20/2009
Correction
Resolved
01/20/2009
INSTALLATION OF FOOTING GROUND ELECTRODE RE-BAR DRIVEN INTO TRENCH ABOVE FTG POUR AT NC.2/N1
Footing Inspection - Commercial Partial 01/20/2009
Correction
Partial Correction
01/20/2009
PREP TO POUR EXTERIOR GRADE BEAM + INTEGRAL COLUMN FOOTINGS N2.8/NK TO N2.8/NC.2 TO NC.2/N1; NC.2/N1 TO NA/N1 TO NA/N5.2 TO N5/NC; N5/NC TO N5/NH.1; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Correction
Partial Correction
01/20/2009
PREPARATION TO POUR ISOLATED COLUMN FOOTINGS N4/NG; N4/NF; N4/NE; N4/ND; NH/N3; ND/N3; NC/N4; NC/N3; NC/N2; NB/N3.5; NB/N2; OK TO POUR WHEN READY LOCATIONS DESCRIBED BELOW
Correction
Partial Correction
01/20/2009
PREP TO POUR MOMENT FRAME FOOTING ON N1 FROM NB TO NC; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Passed 01/21/2009
Correction
Resolved
01/21/2009
PREP TO POUR EXTERIOR GRADE BEAM + INTEGRAL COLUMN FOOTINGS N2.8/NK TO N2.8/NC.2 TO NC.2/N1; NC.2/N1 TO NA/N1 TO NA/N5.2 TO N5/NC; N5/NC TO N5/NH.1; NY/N11 TO NZ/N11 TO NK/N2.8 OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Correction
Resolved
01/21/2009
PREPARATION TO POUR ISOLATED COLUMN FOOTINGS N4/NG; N4/NF; N4/NE; N4/ND; NH/N3; ND/N3; NC/N4; NC/N3; NC/N2; NB/N3.5; NB/N2 OK TO POUR WHEN READY LOCATIONS DESCRIBED BELOW
Correction
Resolved
01/21/2009
PREP TO POUR MOMENT FRAME FOOTING ON N1 FROM NB TO NC; ON N3 FROM NE TO NG; ON NK FROM N3.7 TO N3 OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underslab Electrical Inspection - Commercial Partial 01/26/2009
Correction
Partial Correction
01/26/2009
UNDER-SLAB ELECTRICAL CONDUIT OK TO COVER WHEN READY MATERIAL & WORKMANSHIP FLOOR AREA BEYOND ELEC RM
Underslab Electrical Inspection - Commercial Partial 01/27/2009
Correction
Corrective Action Required
01/27/2009
READINESS FOR INSPECTION REQUEST CANCELED BY P.H.
Underslab Electrical Inspection - Commercial Partial 01/28/2009
Correction
Resolved
01/28/2009
UNDER-SLAB ELECTRICAL CONDUIT MATERIAL & WORKMANSHIP FLOOR AREA BEYOND ELEC RM
Correction
Resolved
01/28/2009
READINESS FOR INSPECTION
Correction
Partial Correction
01/28/2009
UNDER-SLAB ELECTRICAL CONDUIT AT ELECTRICAL ROOM LOWER LIFT CONDUIT; MATERIAL & WORKMANSHIP OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Passed 02/02/2009
Correction
Resolved
02/02/2009
UNDER-SLAB WASTE, SOIL, VENT PIPING
Correction
Resolved
02/02/2009
UNDER-SLAB STORM DRAIN PIPING
Underslab Electrical Inspection - Commercial Passed 02/02/2009
Correction
Resolved
02/02/2009
UNDER-SLAB ELECTRICAL CONDUIT AT ELECTRICAL ROOM LOWER LIFT CONDUIT; UPPER LIFT CONDUIT MATERIAL & WORKMANSHIP OK TO COVER WHEN READY
Underground Electrical Inspection - Commercial Request Complete 1/29/2009 2/2/2009 02/02/2009
Underground Plumbing Inspection - Commercial Request Complete 1/30/2009 2/2/2009 02/02/2009
Final Inspection - Commercial Passed 02/04/2009
Correction
Resolved
02/04/2009
FOUNDATION AND UNDERSLAB SYSTEMS CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home