Summary
B0801415
Building Permit - Commercial
Final Completion
MACY'S RETAIL HOLDINGS INC
PARTIAL COMMERCIAL
FOUNDATION AND UNDERSLAB WORK ONLY
09/30/2008
10/02/2008
03/31/2009
02/11/2009
Locations
Contacts
GEOTECHNOLOGY INC, Address:9136 CODY  
A.B. MAY, Address:2017 WEST 104TH  
S M WILSON AND CO, Address:13316 W 98TH ST  
DURRANT GROUP, INC., Address:1066 EXECUTIVE PARKWAY, SUITE 100  
UNIVERSAL ELECTRIC, Address:PO BOX 3628  
MACY'S RETAIL HOLDINGS INC, Address:7 W 7TH ST  
WIN LLC, Address:1901 SW WANAMAKER RD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 03/30/2009 10/29/2010
Correction

Codes Administration - 2006 IBC 1704.1.1 - Statement of special inspections. The permit applicant shall submit a statement of special inspections prepared by the registered design professional in responsible charge in accordance with 106.1 as a condition for permit issuance. This statement shall be in accordance with Section 1705. Exceptions: 1. A statement of special inspections is not required for structures designed and constructed in accordance with the conventional construction provisions of Section 2308. 2. The statement of special inspections is permitted to be prepared by a qualified person approved by the building official for construction not designed by a registered design professional.
Correction

Codes Administration - 2006 IBC 1704.1.2 - Report Requirement. Special inspectors shall keep records of inspections. The special inspector shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was done in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If the discrepancies are not corrected, the discrepancies shall be brought to the attention of the building official and to the registered design professional in responsible charge prior to the completion of that phase of the work. A final report documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted at a point in time agreed upon by the permit applicant and the building official prior to the start of work.
Correction

Water Utilities - Fire Protection System needs to be protected by a Double Check Detector Assembly. If chemicals will be introduced into the fire protection system, then a Reduced Pressure Backflow Detector Assembly is required.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $436.15 $436.15 Paid 10/02/2008
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Miscellaneous Inspection Failed 10/06/2008
Correction
Corrective Action Required
10/06/2008
PRE-CONSTRUCTION MEETING TO BE SCHEDULED TO DISCUSS PROCEDURES
Footing Inspection - Commercial Not Ready 10/15/2008
Correction
Corrective Action Required
10/15/2008
READINESS FOR INSPECTION WORK REQUESTED FOR INSP NOT COMPLETED
Footing Inspection - Commercial Partial 10/16/2008
Correction
Partial Correction
10/16/2008
PREPARATION TO POUR ISOLATED COLUMN FOOTINGS 2/B; 2/C; 2/D; 2/E; 2/F; 2/G; 3/B; 3/C; 3/D; 3/E; 3/F; 3/G; 4/E; 4/F; 4/G; OK TO POUR WHEN READY LOCATIONS DESCRIBED BELOW
Correction
Resolved
10/16/2008
READINESS FOR INSPECTION
Footing Inspection - Commercial Partial 10/17/2008
Correction
Partial Correction
10/17/2008
PREPARATION TO POUR ISOLATED COLUMN FOOTINGS 2/B; 2/C; 2/D; 2/E; 2/F; 2/G; 3/B; 3/C; 3/D; 3/E; 3/F; 3/G; 4/B; 4/C; 4/D; 4/E; 4/F; 4/G; 5/B; 5/C; 5/D; 5/E; 5/F; 5/G; 6/B; 6/C; 7/B; 7/C; 8/B; 8/C; 9/B; 9/C; 6/D; 6/E; 6/F; 6/G; 7/D; 7/E; 7/F; 7/G; 8/D; 8/E; OK TO POUR WHEN READY LOCATIONS DESCRIBED BELOW
Footing Inspection - Commercial Partial 10/20/2008
Correction
Partial Correction
10/20/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Correction
Resolved
10/20/2008
PREPARATION TO POUR ISOLATED COLUMN FOOTINGS ALL INTERIOR COLUMN FOOTINGS OK TO POUR WHEN READY LOCATIONS DESCRIBED BELOW
Footing Inspection - Commercial Partial 10/21/2008
Correction
Partial Correction
10/21/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); ON (1) FROM (A) TO (C.7); OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underslab Plumbing Inspection - Commercial Partial 10/21/2008
Correction
Partial Correction
10/21/2008
UNDER-SLAB WASTE, SOIL, VENT PIPING ALL WITHIN SECTOR (A) + 6" BLDG DRAIN ON (9.7) FROM (C.6) TO 80' WEST; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Underslab Plumbing Inspection - Commercial Not Ready 10/22/2008
Correction
Corrective Action Required
10/22/2008
READINESS FOR INSPECTION NO NEWWORK READY FOR INSP
Footing Inspection - Commercial Partial 10/24/2008
Correction
Partial Correction
10/24/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); ON (1) FROM (A) TO (H); ON (10) FROM (A) TO (D); OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 10/28/2008
Correction
Partial Correction
10/28/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); ON (1) FROM (A) TO (H); ON (10) FROM (A) TO (E.8); ON (H) FROM (1) TO (4.7); OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 10/29/2008
Correction
Partial Correction
10/29/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); ON (1) FROM (A) TO (H); ON (10) FROM (A) TO (E.8); ON (H) FROM (1) TO (6.5); OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 10/31/2008
Correction
Partial Correction
10/31/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); ON (1) FROM (A) TO (H); ON (10) FROM (A) TO (H.3); FROM H.3/10 TO H.3/9.3 TO I/9.3 TO I/8.2; ON (H) FROM (1) TO (6.5); OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underslab Electrical Inspection - Commercial Partial 10/31/2008
Correction
Partial Correction
10/31/2008
UNDER-FLOOR ELECTRICAL CONDUIT + BOXES SPOT CHECK CONDUCTED AS WORK PROGRESSES
Underslab Plumbing Inspection - Commercial Partial 10/31/2008
Correction
Resolved
10/31/2008
READINESS FOR INSPECTION
Correction
Partial Correction
10/31/2008
UNDER-SLAB WASTE, SOIL, VENT PIPING ALL WITHIN SECTOR (A) + 6" BLDG DRAIN ON (9.7) FROM (C.6) TO 80' W; HOUSEKEEPING 109 + 4" EAST/SOUTH TO BLDG EXIT; STARBUCKS 1570.5 + 6" BLDG DRAIN WEST TO G.6 INCL BRANCH TO STANDPIPE; OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Water Service Inspection Failed 11/03/2008
Correction
Corrective Action Required
11/03/2008
See Comment P1.3 LINE H X 10 - 4" IRON WATER LINE - STUBBED APPROX 4' OUTSIDE OF FOUNDATION & APPROX 2' INSIDE WITH RISER TO FLOOR LEVEL NO APPROVED PLANS - COVER AT OWN RISK
Water Service Inspection - Commercial Request Complete 11/3/2008 11/3/2008 11/03/2008
Underslab Plumbing Inspection - Commercial Partial 11/04/2008
Correction
Partial Correction
11/04/2008
UNDER-SLAB WASTE, SOIL, VENT PIPING ALL WITHIN SECTOR (A) + 6" BLDG DRAIN ON (9.7) FROM (C.6) TO 80' W; HOUSEKEEPING 109 + 4" EAST/SOUTH TO BLDG EXIT; STARBUCKS 1570.5 + 6" BLDG DRAIN WEST TO G.6 INCL BRANCH TO STANDPIPE; 3"/2" DVW WITHIN SECT. D OK TO COVER WHEN READY FOLLOWING SEGMENTS:
Footing Inspection - Commercial Partial 11/04/2008
Correction
Partial Correction
11/04/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); ON (1) FROM (A) TO (H); ON (10) FROM (A) TO (H.3); FROM H.3/10 TO H.3/9.3 TO I/9.3 TO I/8.2; ON (H) FROM (1) TO (6.5); FROM I/8.2 TO STEP FOOTING @ 1/7.5 OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underground Plumbing Inspection - Commercial Request Complete 11/4/2008 11/4/2008 11/04/2008
Footing Inspection - Commercial Passed 11/05/2008
Correction
Resolved
11/05/2008
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS ON (A): FROM (10) TO (6); FROM (6) TO (1); ON (1) FROM (A) TO (H); ON (10) FROM (A) TO (H.3); FROM H.3/10 TO H.3/9.3 TO I/9.3 TO I/8.2; ON (H) FROM (1) TO (6.5); FROM I/8.2 TO STEP FOOTING @ 1/7.5; REMAINDER OF FOOTINGS @ TRUCK WELL OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Underslab Plumbing Inspection - Commercial Passed 11/17/2008
Correction
Resolved
11/17/2008
UNDER-SLAB WASTE, SOIL, VENT PIPING
Underslab Electrical Inspection - Commercial Passed 11/17/2008
Correction
Resolved
11/17/2008
UNDER-FLOOR ELECTRICAL CONDUIT + BOXES
Miscellaneous Inspection Passed 11/17/2008
Correction
Resolved
11/17/2008
PRE-CONSTRUCTION MEETING
Final Inspection - Commercial Not Ready 11/18/2008
Correction
Corrective Action Required
11/18/2008
CLOSE PERMIT
Water Service Inspection Passed 11/18/2008
Correction
Resolved
11/18/2008
See Comment P1.3 LINE H X 10 - 4" IRON WATER LINE - STUBBED APPROX 4' OUTSIDE OF FOUNDATION & APPROX 2' INSIDE WITH RISER TO FLOOR LEVEL NO APPROVED PLANS - COVER AT OWN RISK
Underground Plumbing Inspection - Commercial Passed 11/24/2008
Correction
Resolved
11/24/2008
CONNECTION OF BUILDING ROOF DRAIN TO STORM SEWER STUB C.6/10; F.8/10 EXPOSED LOCATIONS ONLY OK TO COVER WHEN READY
Correction
Resolved
11/24/2008
CONNECTION OF BUILDING DRAIN TO BLDG SANITARY SEWER STUB C.6/10; E.4/1 OK TO COVER WHEN READY FOLLOWING LOCATIONS
Underground Plumbing Inspection - Commercial Request Complete 11/24/2008 11/24/2008 11/24/2008
Footing Inspection - Commercial Passed 12/31/2008
Correction
Resolved
12/31/2008
SCREEN WALLS SCREEN WALL FOR TRANSFORMER NORTHWEST CORNER NORTHWEST FOOTING
Footing Inspection - Commercial Partial 01/08/2009
Correction
Resolved
01/08/2009
READINESS FOR INSPECTION
Correction
Partial Correction
01/08/2009
PREPARATION TO POUR TRUCK WELL WALL FOOTING WEST WALL FOOTING; OK TO POUR WHEN READY PORTIONS DESCRIBED BELOW:
Final Inspection - Commercial Passed 02/10/2009
Correction
Resolved
02/10/2009
CLOSE PERMIT
Footing Inspection - Commercial Passed 02/10/2009
Correction
Resolved
02/10/2009
PREPARATION TO POUR ISOLATED COLUMN FOOTINGS
Correction
Resolved
02/10/2009
PREP TO POUR PERIMETER SPREAD FOOTING + INTEGRAL COLUMN FOOTINGS
Correction
Resolved
02/10/2009
PREPARATION TO POUR TRUCK WELL WALL FOOTING
Correction
Resolved
02/10/2009
SCREEN WALLS
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home