B0800057
Building Permit - Commercial
Certificate of Occupancy
EMERGENT CARE ASSET HOLDINGS LLC
NEW COMMERCIAL
EMERGENT CARE PLUS OF LEES SUMMIT
01/24/2008
03/27/2008
04/08/2009
10/14/2008
Locations
Contacts
L B A AIR CONDITIONING, HEATING AND PLUMBING INC, Address:6226 MERRIAM DR  
L B A AIR CONDITIONING, HEATING AND PLUMBING INC, Address:6226 MERRIAM DR  
ACI BOLAND - KANSAS CITY, Address:1421 E 104TH STREET  
T D ELECTRIC, LLC, Address:2704 W 43RD AVE  
L B A AIR CONDITIONING, HEATING AND PLUMBING INC, Address:6226 MERRIAM DR  
L B A AIR CONDITIONING, HEATING AND PLUMBING INC, Address:6226 MERRIAM DR  
MILLER STAUCH CONSTRUCTION, Address:10600 LACKMAN RD  
EMERGENT CARE ASSET HOLDINGS LLC, Address:3074 SW GRANDSTAND CIR  
EMERGENT CARE ASSET HOLDINGS LLC, Address:2741 NE MCBAINE DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 09/22/2008 10/29/2010
Correction

Fire Department- 2006 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
Correction

Fire Department- 2006 IFC 906.2 - General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department- 2006 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Correction

Codes Administration - ICC/ANSI A117.1 2003 604.3.1 - Size. A clearance around a water closet 60 inches minimum, measured perpendicular from the sidewall, and 56 inches minimum, measured perpendicular from the rear wall, shall be provided.
Correction

Codes Administration - ICC/ANSI A117.1 2003 604.3.2 - Overlap. The required clearance around the water closet shall be permitted to overlap the water closet, associated grab bars, paper dispensers, sanitary napkin receptacles, coat hooks, shelves, accessible routes, clear floor space at other fixtures and the turning space. No other fixtures or obstructions shall be within the required water closet clearance.
Correction

Codes Administration - 2005 NEC 517.13 - Grounding of receptacles and fixed electric equipment in patient care areas. Wiring in patient care areas shall comply with 517.13(A) and 517.13(B).
Correction

Codes Administration - 2006 IBC 1210.1 - Floors. In other than dwelling units, toilet and bathing room floors shall have a smooth, hard, nonabsorbant surface that extends upward onto the walls at least 6 inches.
Correction

Codes Administration - 2006 IMC 403.2 - Outdoor air required. The minimum ventilation of outdoor air shall be determined in accordance with Section 403.3. Exception: Where the registered design professional demonstrates that an engineered ventilation system design will prevent the maximum concentration of contaminants from exceeding the obtainable by the rate of outdoor air ventilation determined in accordance with Section 403.3, the minimum required rate of outdoor air shall be reduced in accordance with such engineered system design.
Correction

Codes Administration - 2006 IMC 602.2.2.1 - Materials exposed within plenums. Except as required by Sections 602.2.1.1 through 602.2.1.5, materials within plenums shall be noncombustible or shall have a flame spread index of not more than 25 and a smoke-developed index of not more than 50 when tested in accordance with ASTM E 84.
Correction

Codes Administration - 2006 IPC 403.2 - Separate facilities. Where plumbing fixtures are required, separate facilities shall be provided for each sex. (See code for possible exceptions.)
Correction

Codes Administration - 2006IPC 708.3.2 - Building sewers. Building sewers shall be provided with cleanouts located not more than 100 feet apart measured from the upstream entrance of the cleanout. For building sewers 8 inches and larger, manholes shall be provided and located not more than 200 from the junction of the building drain and building sewer, at each change in direction and at intervals of not more than 400 feet apart. Manholes and manhole covers shall be of an approved type.
Correction

Fire Department- Remove the exterior horn/strobe.
Correction

Fire Department- What, and how will medical gases be stored at the site?
Correction

Fire Department- 2006 IFC 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection.
Correction

Codes Administration - No certificate of occupancy shall be granted until the offsite easement documents are recorded with Jackson County for the 55' utiltiy easement on the south side of NE Independence Avenue.
Correction

Codes Administration - The finish schedule is incomplete.
Correction

Codes Administration - The structural plans reference the 2003 IBC as the design standard.
Correction

Codes Administration - A separate permit will be required for the irrigation system.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

Lee's Summit Code of Ordinance - Sec.17-309 - Smoking. A. "No Smoking" signs or the international "No Smoking" symbol (consisting of a pictorial representation of a burning cigarette enclosed in a red circle with a red bar across it) shall be clearly and conspicicuously posted at every public place and place of emplyment where smoking is prohibited by this Article, by the owner, operator, manager, or other person in control of that place. B. Every public place and place of employment where smoking is prohibited by this Article shall have posted at every entrance a conspicuous sign clearly stating that smoking is prohibited.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $5,212.84 $5,212.84 Paid 03/27/2008
84 Water Meters $1,326.77 $1,326.77 Paid 03/27/2008
85 Water Taps $19,047.00 $19,047.00 Paid 03/27/2008
89 Sewer Tap Fees $750.00 $750.00 Paid 03/27/2008
91 EFHB Maybrook Water Shed $1,065.25 $1,065.25 Paid 03/27/2008
Right of Way Permit $35.00 $35.00 Paid 03/27/2008
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Failed 04/18/2008
Correction
Resolved
04/18/2008
Erosion Control
Correction
Corrective Action Required
04/18/2008
Tracking Mud, Debris STREET CLEANUP REQUIRED
Underslab Plumbing Inspection - Commercial Partial 04/18/2008
Correction
Partial Correction
04/18/2008
None STORM DRAINS APPROVED TO COVER. SAN. WASTE: APPROVED TO COVER WEST BRANCH TO MAIN ONLY.
Underslab Plumbing Inspection - Commercial Partial 04/22/2008
Correction
Partial Correction
04/22/2008
None STORM DRAINS APPROVED TO COVER. SAN. WASTE: APPROVED TO COVER ALL EXCEPT SE ROOM 122 & AS NOTED: NOTE: AT ABANDONED FLOOR SINK - DEAD END PIPING NOT PERMITTED. ROUTE PIPE UP FOR CLEAN OUT
Erosion Control Inspection Residential Failed 04/23/2008
Correction
Corrective Action Required
04/23/2008
Tracking Mud, Debris STREET CLEANUP REQUIRED 2ND NOTICE
Underslab Plumbing Inspection - Commercial Passed 04/23/2008
Correction
Resolved
04/23/2008
None
Underslab Electrical Inspection - Commercial Passed 04/30/2008
Erosion Control Inspection Residential Passed 04/30/2008
Correction
Resolved
04/30/2008
Tracking Mud, Debris
Underground Plumbing Inspection - Commercial Request Complete 5/6/2008 5/6/2008 05/06/2008
Sewer Service Inspection Passed 05/13/2008
Sewer Service Inspection - Commercial Request Complete 5/13/2008 5/13/2008 05/13/2008
Water Service Inspection Passed 05/15/2008
Water Service Inspection - Commercial Request Complete 5/15/2008 5/15/2008 05/15/2008
Water Service Inspection - Commercial Request Complete 5/15/2008 5/15/2008 05/15/2008
Underground Electrical Inspection - Commercial Partial 07/07/2008
Correction
Partial Correction
07/07/2008
POLE LIGHTS 5 NORTHERNMOST POLES OK TO POUR
Underground Electrical Inspection - Commercial Request Complete 7/3/2008 7/7/2008 07/07/2008
Underground Electrical Inspection - Commercial Request Complete 7/7/2008 7/8/2008 07/08/2008
Underground Electrical Inspection - Commercial Partial 07/09/2008
Correction
Partial Correction
07/09/2008
POLE LIGHTS ALL POLES OK TO POUR
Correction
Corrective Action Required
07/09/2008
POLE LIGHT CONDUITS NOT YET INSPECTED
Underground Electrical Inspection - Commercial Request Complete 7/9/2008 7/9/2008 07/09/2008
Rough Electrical Inspection - Commercial Failed 07/18/2008
Correction
Corrective Action Required
07/18/2008
BRANCH CIRCUITS SERVING PATIENT CARE AREAS NEC 517.13-ALL BRANCH CIRCUITS SERVING PATIENT CARE AREAS SHALL COMPLY WITH THIS SECTION
Correction
Corrective Action Required
07/18/2008
None ELECTRICAL ROUGHIN INSPECTION TERMINATED. RESOLVE ALLOWABLE WIRING METHODS TO PATIENT CARE AREAS AND CALL FOR INSPECTION AGAIN WHEN READY.
Underground Electrical Inspection - Commercial Partial 07/18/2008
Correction
Partial Correction
07/18/2008
POLE LIGHTS ALL POLES OK TO POUR
Correction
Partial Correction
07/18/2008
POLE LIGHT CONDUITS -CONDUITS BETWEEN 4 STREET-FRONT LIGHT POLES, EXCEPT SOUTHERN-MOST POLE
Correction
Corrective Action Required
07/18/2008
GROUNDING OF LIGHT POLES NOT INSPECTED
Rough Electrical Inspection - Commercial Failed 07/18/2008
Correction
Corrective Action Required
07/18/2008
BRANCH CIRCUITS SERVING PATIENT CARE AREAS NEC 517.13-ALL BRANCH CIRCUITS SERVING PATIENT CARE AREAS SHALL COMPLY WITH THIS SECTION
Correction
Corrective Action Required
07/18/2008
None -ELECTRICAL ROUGHIN INSPECTION TERMINATED. RESOLVE ALLOWABLE WIRING METHODS TO PATIENT CARE AREAS AND CALL FOR INSPECTION AGAIN WHEN READY. **I TALKED WITH MIKE W. ABOUT THIS. PER SPEC LETTER, THE DESIGNER WANTS EMT INSTALLED**
Underground Electrical Inspection - Commercial Passed 07/23/2008
Correction
Resolved
07/23/2008
POLE LIGHTS ALL POLES OK TO POUR
Correction
Resolved
07/23/2008
POLE LIGHT CONDUITS UNDERGROUND CONDUITS TO LIGHT POLES, SIGNS, AND HOME RUN OK
Correction
Resolved
07/23/2008
GROUNDING OF LIGHT POLES
Rough Electrical Inspection - Commercial Failed 07/24/2008
Correction
Resolved
07/24/2008
None MC CABLE PERMITTED IN LIEU OF EMT PER ENGINEER'S LETTER DATED 7/23/08 (IN FILE)
Rough Plumbing Inspection - Commercial Failed 07/24/2008
Correction
Corrective Action Required
07/24/2008
Water/DWV Preotection Against Physical Damage (IRC) PIPING THRU BOTTOM PLATES WHERE WITHIN 1.5" OF NAILING SURFACE IS REQUIRED TO HAVE BOCA TYPE NAIL PROTECTION THROUGHOUT
Gas Piping Inspection - Commercial Passed 07/24/2008
Gas Service Inspection - Commercial Failed 07/24/2008
Correction
Corrective Action Required
07/24/2008
Gas Test Pressure (IRC) SYSTEM LOST PRESSURE DURING TEST
Rough Electrical Inspection - Commercial Failed 07/25/2008
Correction
Corrective Action Required
07/25/2008
BRANCH CIRCUITS SERVING PATIENT CARE AREAS NEC 517.13-ALL BRANCH CIRCUITS SERVING PATIENT CARE AREAS SHALL COMPLY WITH THIS SECTION **NOTE ALL BRANCH CIRCUITS, NOT JUST ONES POWERING THE RECEPTACLES
Correction
Corrective Action Required
07/25/2008
None EXCEPT FOR PATIENT CARE AREAS AND INCOMPLETED ROOMS (RM 110-112, 114, 116), OK TO ROCK ONLY AREAS WHERE NEC 517.13 DOES NOT APPLY OK TO ROCK @ FOLLOWING LC
Rough Plumbing Inspection - Commercial Passed 07/25/2008
Correction
Resolved
07/25/2008
Water/DWV Preotection Against Physical Damage (IRC)
Gas Service Inspection - Commercial Passed 07/25/2008
Correction
Resolved
07/25/2008
Gas Test Pressure (IRC) GAS PRESSURE TEST OK. APPROVED FOR RELEASE OF GAS SERVICE
Rough Electrical Inspection - Commercial Partial 07/28/2008
Correction
Partial Correction
07/28/2008
BRANCH CIRCUITS SERVING PATIENT CARE AREAS NEC 517.13-ALL BRANCH CIRCUITS SERVING PATIENT CARE AREAS SHALL COMPLY WITH THIS SECTION **NOTE ALL BRANCH CIRCUITS, NOT JUST ONES POWERING THE RECEPTACLES
Correction
Partial Correction
07/28/2008
None OK TO ROCK ALL EXCEPT: ROOMS 111 & 112
Electrical Service Inspection Not Ready 08/06/2008
Correction
Corrective Action Required
08/06/2008
NOT READY FOR INSPECTION
Electrical Service Inspection Passed 08/07/2008
Correction
Resolved
08/07/2008
NOT READY FOR INSPECTION
Correction
Resolved
08/07/2008
None 400 AMP PANEL H-1 APPROVED PER PLANS. RELEASE ELECT.
Erosion Control Inspection Residential Passed 08/07/2008
Rough Electrical Inspection - Commercial Passed 08/08/2008
Correction
Resolved
08/08/2008
BRANCH CIRCUITS SERVING PATIENT CARE AREAS
Correction
Resolved
08/08/2008
None OK ROCK
Rough Framing Inspection - Commercial Passed 08/08/2008
Rated Assembly Inspection Partial 08/11/2008
Correction
Partial Correction
08/11/2008
None 1 HR WALL ASSY SCREW PATTERN OK
Driveway Inspection Passed 08/26/2008
Above Ceiling Inspection Failed 09/04/2008
Correction
Partial Correction
09/04/2008
None -ALL EXAM ROOMS, EXCEPT AT 109, 109A, 110, 111, 112, 121. -BATHS AND CORRIDORS WHERE OK DO NOT DROP CENTRAL AREAS/CORRIDORS, FRONT AREA, OR AREA WHERE INCOMPLETE, SOME OVERFILLED ELECTRICAL BOXES, OR COLEMAN CABLE NOT RATED FOR PLENUM USE ARE ROUTED OK TO DROP @ FOLLOWING LOCATIONS
Above Ceiling Inspection Partial 09/08/2008
Correction
Partial Correction
09/08/2008
None -ALL EXAM ROOMS, EXCEPT AT 121. -BATHS AND CORRIDORS WHERE OK DO NOT DROP FRONT CORRIDOR 115, WAITING AREA, X-RAY RM, PT RM, RM 121 OK TO DROP @ FOLLOWING LOCATIONS
Above Ceiling Inspection Passed 09/15/2008
Correction
Resolved
09/15/2008
None ABOVE CEILING APPROVED OK TO DROP @ FOLLOWING LOCATIONS
Sidewalk Inspection Passed 09/17/2008
Rated Assembly Inspection Passed 09/18/2008
Correction
Resolved
09/18/2008
None 1 HR WALL ASSY SCREW PATTERN OK
Occupancy Inspection - Codes Commercial Failed 09/23/2008
Correction
Corrective Action Required
09/23/2008
Receive Fire Department approval -DEFICIENCIES ON SEPARATE LIST. NOT OK FOR TCO
Correction
Corrective Action Required
09/23/2008
Receive Planning & Development Approval -LANDSCAPING -TEMPORARY CURBS ON NORTH/SOUTH SIDES
Correction
Corrective Action Required
09/23/2008
Receive Public Works Approval UTILITY EASEMENT RECORD ISSUE
Correction
Corrective Action Required
09/23/2008
MISC -COMPLETE OUTSIDE LIGHTING -HEATER IN VESTIBULE
Correction
Corrective Action Required
09/23/2008
PAINT EXTERIOR GAS LINES
Occupancy Inspection - Codes Commercial Failed 09/25/2008
Correction
Resolved
09/25/2008
Receive Fire Department approval
Correction
Corrective Action Required
09/25/2008
Receive Planning & Development Approval -LANDSCAPING -TEMPORARY CURBS ON NORTH/SOUTH SIDES
Correction
Resolved
09/25/2008
Receive Public Works Approval
Correction
Corrective Action Required
09/25/2008
MISC -COMPLETE OUTSIDE LIGHTING -HEATER IN VESTIBULE
Correction
Corrective Action Required
09/25/2008
PAINT EXTERIOR GAS LINES
Occupancy Inspection - Codes Commercial Passed 10/13/2008
Correction
Resolved
10/13/2008
Receive Planning & Development Approval
Correction
Resolved
10/13/2008
MISC
Correction
Resolved
10/13/2008
PAINT EXTERIOR GAS LINES
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home