Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Underslab Plumbing Inspection - Commercial
|
Failed
|
|
|
05/10/2007
|
|
Correction
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
|
|
05/11/2007
|
|
Correction
|
|
Correction
|
Rough Framing Inspection - Commercial
|
Failed
|
|
|
05/23/2007
|
|
Correction
|
Rough Plumbing Inspection - Commercial
|
Partial
|
|
|
05/23/2007
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
5/22/2007
|
5/23/2007
|
05/23/2007
|
Miscellaneous Inspection
|
Partial
|
|
|
05/25/2007
|
|
Correction
|
|
Correction
|
Miscellaneous Inspection
|
Passed
|
|
|
06/05/2007
|
|
Correction
|
|
Correction
|
Rough Electrical Inspection - Commercial
|
Partial
|
|
|
06/05/2007
|
|
Correction
|
Above Ceiling Inspection
|
Failed
|
|
|
07/12/2007
|
|
Correction
Corrective Action Required
|
Rough Electrical Inspection - Commercial
|
Partial
|
|
|
07/12/2007
|
|
Correction
|
Rough Plumbing Inspection - Commercial
|
Partial
|
|
|
07/12/2007
|
|
Correction
|
Rough Framing Inspection - Commercial
|
Failed
|
|
|
07/12/2007
|
|
Correction
|
Above Ceiling Inspection
|
Failed
|
|
|
07/16/2007
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
Above Ceiling Inspection
|
Failed
|
|
|
07/20/2007
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
|
|
Correction
|
Rough Electrical Inspection - Commercial
|
Partial
|
|
|
07/20/2007
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
Rough Framing Inspection - Commercial
|
Failed
|
|
|
07/20/2007
|
|
Correction
|
Rough Electrical Inspection - Commercial
|
Passed
|
|
|
07/26/2007
|
|
Correction
|
|
Correction
|
|
Correction
|
Above Ceiling Inspection
|
Passed
|
|
|
07/26/2007
|
|
Correction
|
|
Correction
|
|
Correction
|
|
Correction
|
All Rough Inspection - Commercial
|
Failed
|
|
|
07/26/2007
|
|
Correction
Corrective Action Required
|
Rough Plumbing Inspection - Commercial
|
Passed
|
|
|
07/26/2007
|
|
Correction
|
Rough Framing Inspection - Commercial
|
Passed
|
|
|
07/26/2007
|
|
Correction
|
All Rough Inspection - Commercial
|
Passed
|
|
|
07/27/2007
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
07/27/2007
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
08/02/2007
|
|
Correction
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
08/15/2007
|
|
Correction
|
|
Correction
|
Electrical Service Inspection
|
Passed
|
|
|
08/23/2007
|
|
Correction
|
Electrical Service Inspection
|
Passed
|
|
|
09/19/2007
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Passed
|
|
|
09/27/2007
|
|
Correction
|