Permit Application Status

B0700523


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0700523
Building Permit - Commercial
Certificate of Occupancy
CITY OF LEES SUMMIT
ADDITION COMMERCIAL
ADDITION TO THE COMMUNITY CENTER
03/20/2007
08/31/2007
02/27/2008
10/20/2008
Locations
Contacts
JAKES REFRIGERATION HTG/COOLING, Address:1101 SW 1ST ST  
BALES ELECTRIC, Address:17505 E 163RD ST  
SCHICK PLUMBING & HEATING COMPANY, Address:11200 BILYOU RD  
KRAUS-ANDERSON CONSTRUCTION CO, Address:15612 COLLEGE BLVD  
CITY OF LEES SUMMIT, Address:PO BOX 1600  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 02/27/2008 10/29/2010
Correction

Codes Administration - 2003 IBC 1004.1 - Design occupant load. In determining means of egress requirements, the number of occupants for whom meansof egress facilities shall be provided shall be established by the largest number computed in accordance with Sections 1004.1.1 through 1004.1.3.
Correction

Codes Administration - 2003 IBC 1109.2.1 - Unisex toilet and bathing rooms. In assembly and mercantile occupancies, an accessible unisex toilet room shall be provided where an aggregate of six or more male and female water closets is required. In buildings of mixed occupancy, only those water closets required for the assembly or mercantile occupancy shall be used to determine the unisex toilet room requirement. In recreational facilities where separate-sex bathing rooms are provided, an accessible unisex toilet and bathing rooms shall be included in determining the number of fixtures provided in an occupancy.
Correction

Codes Administration - I am unable to locate information on the wall types.
Correction

Codes Administration - The code compliance plan indicates that there are one-hour fire-resistive assemblies in two locations in the buildings. The plans do not provide a listing for the walls and I am unsure as to why the walls are being provided as one is a small mechanical room and the other is an S-1 occupancy in a non-separated use building.
Correction

Codes Analysis - The code analysis indicates that one of the occupancy types is an E but I am unsure if this is accurate.
Correction

Codes Administration - I am unable to locate the testing and listing information for the cementious shake shingles.
Correction

Codes Administration - The project cost provided was for the entire project but the project is being broken into two permits.
Correction

Codes Administration - Section 803.4 of ANSI A117.1-1998 requires a bench be installed per Section 903 be installed in locker rooms.
Correction

Codes Administration - ANSI A117.1-1998 404.2.6 - Two doors in Series. Distance between two hinged or pivoted doors in series shall be 48 inches minimum plus the width of any door swinging into the space. Doors in series shall swing either in the same direction or away from space between doors.
Correction

Fire Department- Unable to locate exit or emergency lighting on the plans.
Correction

Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-1300.
Correction

Fire Department- Unable to locate the fire department connection (FDC).
Correction

Fire Department- 905.1 General. Standpipe systems shall be provided in new buildings and structures in accordance with this section and as required by the Code Offical. Fire hose threads used in connection with standpipe systems shall comply with NFPA 1963 or as otherwise approved and shall be compatible with fire department hose threads. The location of fire department hose connections shall be approved. In build-ings used for high-piled combustible storage, fire protection shall be in accordance with Chapter 23.
Correction

Fire Department- 1004.3 Posting of occupant load. Every room or space that isan assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exitor exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent.
Correction

Codes Administration - The clear floor space on the exterior of the showers as required by ANSI A117.1 is not provided.
Correction

Codes Administration - The revisions to Sheet LS101 provides exit width factors of .3 for stairs and .2 for other egress components. As the building is fully sprinkled the exit width factors are .2 for stairs ands .15 for other egress components.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

Fire Department; Fire apparatus access roads shall have an unobstructed width of not less than 20 feet except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches.
Correction

Fire Department; New and existing buildings shall have approved address numbers, building numbers, placed in a position to be plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background.
Correction

Fire Department: Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the code official is authorized to require a key box to be installed in an accessible location. The key box shall be of an approved type and shall contain keys to gain access as required by the code official.
Correction

Fire Department. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. The plans and specifications shall bear a State of Missouri licensed engineers seal. This includes fire sprinkler systems, grease hood and duct suppression systems as well as other fire suppression system.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department; Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Documents shall bear a State of Missouri architect/engineers seal..Construction documents shall include, but not be limited to, all of the following: 1. A floor plan. 2. Locations of alarm-initiating and notification appli- ances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing informa- tion for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Correction

Fire Department- 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection. Exceptions: 1. The supervisory signal at a constantly attended location is not required where duct smoke detectors activate the building’s alarm notification appliances. 2. In occupancies not required to be equipped with a fire alarm system, actuation of a smoke detector shall activate a visible and an audible signal in an approved location. 3. Smoke detector trouble conditions shall activate a visible or audible signal in an approved location and shall be identified as air duct detector trouble.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

Codes Administration - 2003 IPC 403.1 - Minimum number of fixtures. Plumbing fixtures shall be provided for the type of occupancy and in the minimum number shown in Table 403.1. Types of occupancies not shown in Tale 403.1 shall be considered individually by the code official. The number of occupants shall be deetermined by the International Building Code. Occupancy classification shall be determined in accordance with the International Building Code.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

Lee's Summit Code of Ordinance - Sec.17-309 - Smoking. A. "No Smoking" signs or the international "No Smoking" symbol (consisting of a pictorial representation of a burning cigarette enclosed in a red circle with a red bar across it) shall be clearly and conspicicuously posted at every public place and place of emplyment where smoking is prohibited by this Article, by the owner, operator, manager, or other person in control of that place. B. Every public place and place of employment where smoking is prohibited by this Article shall have posted at every entrance a conspicuous sign clearly stating that smoking is prohibited.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $5,596.80 $5,596.80 Paid 08/31/2007
89 Sewer Tap Fees $300.00 $300.00 Paid 08/31/2007
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 09/19/2007
Correction
Partial Correction
09/19/2007
GRADE BEAM + INTEGRAL COLUMN FOOTINGS @ REC CENTER C.8/7 TO C.3/7; C.3/8.2 TO C.3/8.4 TO B.3/8.4; A/4.8 TO A/3.3 TO AA/3.3 TO AA/7.4; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 09/20/2007
Correction
Partial Correction
09/20/2007
GRADE BEAM + INTEGRAL COLUMN FOOTINGS @ REC CENTER C.8/7 TO C.3/7; C.3/8.2 TO C.3/8.4 TO B.3/8.4; A/4.8 TO A/3.3 TO AA/3.3 TO AA/7.4; C.3/7 TO C.3/8; A/4.8 TO AA/4.8; AA/7.5 TO A/7.5 TO A/8.3; OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 09/21/2007
Correction
Partial Correction
09/21/2007
GRADE BEAM + INTEGRAL COLUMN FOOTINGS @ REC CENTER C.8/7 TO C.3/7; C.3/8.2 TO C.3/8.4 TO B.3/8.4; A/4.8 TO A/3.3 TO AA/3.3 TO AA/7.4; C.3/7 TO C.3/8; A/4.8 TO AA/4.8; AA/7.5 TO A/7.5 TO A/8.3; A/8 TO A/8.4 TO B.3/8.4 OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Sewer Service Inspection Partial 09/28/2007
Correction
Partial Correction
09/28/2007
None -AA LINE FROM 5.0 TO CLEANOUT NEAR 7.1
Underslab Plumbing Inspection - Commercial Partial 10/01/2007
Correction
Partial Correction
10/01/2007
UNDER-SLAB DWV PIPING BLDG DRAIN ON (7.2) FROM (A) TO (C.2); BRANCH PIPING @ A106 + SINK @ A105 SE; OK TO COVER WHEN READY PORTIONS DESCRIBED BELOW:
Correction
Partial Correction
10/01/2007
STORM DRAIN PIPING ON (A.5) FROM (7) 45' WEST TO CONNECTION TO EXSTG SEWER LINE OK TO COVER WHEN READY PORTIONS DESCRIBED BELOW:
Underground Electrical Inspection - Commercial Passed 10/02/2007
Correction
Resolved
10/02/2007
UNDERGROUND SECONDARY SERVICE CONDUIT @ REC CENTER TWO 4" SCH 40 PVC IN LIEU OF 3" SHOWN ON DRAWING SHEETS E101A-A.1 & E310 FROM BUILDING ENTRY TO CONNECTION TO EXISTING
Underslab Plumbing Inspection - Commercial Partial 10/02/2007
Correction
Partial Correction
10/02/2007
UNDER-SLAB DWV PIPING BLDG DRAIN ON (7.2) FROM (A) TO (C.2); BRANCH PIPING @ A106 + SINK @ A105 SE; RMS A115, A116; A117; OK TO COVER WHEN READY PORTIONS DESCRIBED BELOW:
Underground Electrical Inspection - Commercial Request Complete 10/1/2007 10/2/2007 10/02/2007
Underground Electrical Inspection - Commercial Partial 10/04/2007
Correction
Partial Correction
10/04/2007
BURIED DATA-COMM CONDUIT 2" PVC OK TO COVER WHEN READY FROM CONNECTION @ EXSTG TO BLDG ENTRY @ A107
Underslab Plumbing Inspection - Commercial Partial 10/10/2007
Correction
Partial Correction
10/10/2007
SANITARY LIFT PUMP BASIN INCLUDING PIPING OK TO COVER WHEN READY
Footing Inspection - Commercial Passed 10/12/2007
Correction
Resolved
10/12/2007
GRADE BEAM + INTEGRAL COLUMN FOOTINGS @ REC CENTER C.8/7 TO C.3/7; C.3/8.2 TO C.3/8.4 TO B.3/8.4; A/4.8 TO A/3.3 TO AA/3.3 TO AA/7.4; C.3/7 TO C.3/8; A/4.8 TO AA/4.8; AA/7.5 TO A/7.5 TO A/8.3; A/8 TO A/8.4 TO B.3/8.4; A.1/7 TO A.1/7.5 TO A/7.5 OK TO POUR WHEN READY SECTIONS DESCRIBED BELOW:
Water Service Inspection Passed 10/16/2007
Correction
Resolved
10/16/2007
WATER SERVICE LINE OK TO COVER WHEN READY FROM EXISTING LINE AT SW TO NEW SW BLDG CORNER
Water Service Inspection - Commercial Request Complete 10/16/2007 10/16/2007 10/16/2007
Sewer Service Inspection Passed 10/18/2007
Correction
Resolved
10/18/2007
None
Correction
Resolved
10/18/2007
SANITARY SEWER SERVICE INSTALLATION CONNECT TO EXISTING SERVICE LINE 70' TO SW. 4" FORCE SERVICE LINE FROM 5' O/S BLDG LINE TO
Sewer Service Inspection - Commercial Request Complete 10/18/2007 10/18/2007 10/18/2007
Footing Inspection - Commercial Passed 10/26/2007
Correction
Resolved
10/26/2007
PREPARATION TO POUR ISOLATED COLUMN FOOTINGS A.3/7.1; A.7/7.1; B.1/7.1; AA.9/4.9; AA.9/5.9 OK TO POUR WHEN READY LOCATIONS DESCRIBED BELOW
Underslab Electrical Inspection - Commercial Partial 11/02/2007
Correction
Partial Correction
11/02/2007
None UNDERSLAB ELECT. APPROVED. COMMUNITY CENTER ADDITION
Rough Plumbing Inspection - Commercial Partial 11/20/2007
Correction
Partial Correction
11/20/2007
TOP ROUGH PLUMBING @ MASONRY WALLS OK TO COVER WHEN READY SPACES 115; 117
Rough Plumbing Inspection - Commercial Partial 11/30/2007
Correction
Partial Correction
11/30/2007
TOP ROUGH PLUMBING @ MASONRY WALLS 11-30-07 TOP ROUGH WOMENS-A115, MENS A117- APPROVED OK TO COVER WHEN READY SPACES 115; 117
Electrical Service Inspection Partial 12/14/2007
Correction
Partial Correction
12/14/2007
TEMPORARY ELECTRICAL SERVICE INSTALLATION RELEASE TEMPORARY SERVICE
Piers/Caissons Inspection - Commercial Passed 03/06/2008
Correction
Resolved
03/06/2008
EXTERIOR AWNING NORHT COLUMNS 4.5-9 ( PIERS 5,6,7,8,9) WEST SIDE AA-E ( PIERS A,B,C,D,E,F) COLUMN LINE AA-E 4.5-9
Electrical Service Inspection Passed 03/14/2008
Correction
Resolved
03/14/2008
TEMPORARY ELECTRICAL SERVICE INSTALLATION
Correction
Resolved
03/14/2008
PERMANENT ELECTRICAL SERVICE INSTALLATION RELEASE SERVICE
Footing Inspection - Commercial Passed 03/25/2008
Correction
Resolved
03/25/2008
FOOTING WIDENING TO BEAR CURTAIN WALL OK TO POUR WHEN READY PER SECTION S401 SW, SE, NE CORNERS
All Rough Inspection - Commercial Partial 04/28/2008
Correction
Partial Correction
04/28/2008
WALL FRAMING + IN-WALL SYSTEMS A100; 101; 102; 103; 104; 105; OK TO COVER WHEN READY WALLS@SPACES LISTED BELOW
Above Ceiling Inspection Partial 04/28/2008
Correction
Partial Correction
04/28/2008
GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS 101; 102; 105; OK TO COVER WHEN READY CEILINGS @ SPACES BELOW:
All Rough Inspection - Commercial Partial 05/01/2008
Correction
Partial Correction
05/01/2008
WALL FRAMING + IN-WALL SYSTEMS A100; 101; 102; 103; 104; 105; 109; 109A; 110; 111; 112; 113; 114; 115; 116; 117; 118; OK TO COVER WHEN READY WALLS@SPACES LISTED BELOW
Above Ceiling Inspection Partial 05/06/2008
Correction
Partial Correction
05/06/2008
GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS 101; 102; 105; VESTIBULES SOFFITS @ DOORS A109-1 & A113-1; 115; 116; 117; OK TO COVER WHEN READY CEILINGS @ SPACES BELOW:
Above Ceiling Inspection Partial 05/21/2008
Correction
Partial Correction
05/21/2008
ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS 103; 104; 105; 110; 111; 112; 114; OKTO DROP TILE WHEN READY CEILINGS @ SPACES BELOW:
Above Ceiling Inspection Passed 05/22/2008
Correction
Resolved
05/22/2008
GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS
Correction
Resolved
05/22/2008
ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS 103-105; 109; 110-112; 113; 114; CORRIDOR TO 115&117 OKTO DROP TILE WHEN READY CEILINGS @ SPACES BELOW:
Occupancy Inspection - Codes Commercial Not Ready 05/23/2008
Correction
Partial Correction
05/23/2008
USE / OCCUPANCY APPROVAL STATUS NO CUSTOMERS OR PUBLIC UNTIL APPROVED BY CODES ADMINISTRATION OK FOR STAFF ONLY FOR SETUP FOR BUSINESS
Occupancy Inspection - Codes Commercial Failed 05/27/2008
Correction
Partial Correction
05/27/2008
USE / OCCUPANCY APPROVAL STATUS SEE TEMPORARY OCCUPANCY
Correction
Corrective Action Required
05/27/2008
Receive Fire Department approval
Correction
Corrective Action Required
05/27/2008
Receive Planning & Development Approval COORDINATE WITH JENNIFER THOMPSON @ 816-969-1606 SEE REPORT PROVIDED DATED 5/23/08
Correction
Partial Correction
05/27/2008
Receive Public Works Approval PHONE 816-969-1830 NO ISSUES PRESENTED CONTACT JON HALEY
Correction
Corrective Action Required
05/27/2008
Receive Water Utilities Approval CONTACT BEN HASKAMP PHONE 816-969-1930
Correction
Corrective Action Required
05/27/2008
ROOFTOP INSPECTION REQUEST INSPECTION WHEN READY
Correction
Partial Correction
05/27/2008
CIRCUIT SCHEDULES AT PANELS TEMPORARY SCHEDULES OK FOR TEMPORARY OCCUPANCY AUTHORIZATION PERMANENT SCHEDULES TO BE PREPARED
Correction
Corrective Action Required
05/27/2008
PENETRATIONS/HOLES IN EXTERIOR WALL CHECK / SEAL HOLES AND ANNULAR SPACES
Correction
Corrective Action Required
05/27/2008
ELECTRICAL BOX @ EXTERIOR SE CORNER PLUG UNUSED OPENING + SCREW COVER TIGHT
Correction
Corrective Action Required
05/27/2008
INSTALLATION OF ROOF DRAINAGE DOWNSPOUTS TO BE COMPLETED
Correction
Corrective Action Required
05/27/2008
INSTALLATION OF TOILET PARTITIONS & URINAL SCREENS TO BE COMPLETED
Occupancy Inspection - Codes Commercial Failed 05/30/2008
Underground Electrical Inspection - Commercial Passed 05/30/2008
Correction
Resolved
05/30/2008
UNDERGROUND SECONDARY SERVICE CONDUIT @ REC CENTER
Correction
Resolved
05/30/2008
BURIED DATA-COMM CONDUIT
All Rough Inspection - Commercial Passed 05/30/2008
Correction
Resolved
05/30/2008
WALL FRAMING + IN-WALL SYSTEMS
Underslab Plumbing Inspection - Commercial Passed 05/30/2008
Correction
Resolved
05/30/2008
UNDER-SLAB DWV PIPING
Correction
Resolved
05/30/2008
STORM DRAIN PIPING
Correction
Resolved
05/30/2008
SANITARY LIFT PUMP BASIN
Underslab Electrical Inspection - Commercial Passed 05/30/2008
Correction
Resolved
05/30/2008
None
Rough Plumbing Inspection - Commercial Passed 05/30/2008
Correction
Resolved
05/30/2008
TOP ROUGH PLUMBING @ MASONRY WALLS
Occupancy Inspection - Codes Commercial Failed 06/06/2008
Correction
Partial Correction
06/06/2008
Receive Fire Department approval AWAITING FD CONFIRMATION
Correction
Resolved
06/06/2008
Receive Public Works Approval NO ISSUES KNOWN REMAINING
Correction
Resolved
06/06/2008
Receive Water Utilities Approval PER BEN HASKAMP 6/6/08
Correction
Resolved
06/06/2008
ROOFTOP INSPECTION
Correction
Partial Correction
06/06/2008
CIRCUIT SCHEDULES AT PANELS 1) LABEL ALL SWITCHES AT MDP 2) PLACE COPY OF SCHEDULE IN BOTH DOOR POCKETS @ PANEL LP1 AND LABELING OF SWITCHES TO BE COMPLETED
Correction
Corrective Action Required
06/06/2008
PENETRATIONS/HOLES IN EXTERIOR WALL SEE ELECTRICAL SERVICE ENTRY POINTS CHECK / SEAL HOLES AND ANNULAR SPACES
Correction
Corrective Action Required
06/06/2008
ELECTRICAL BOX @ EXTERIOR SE CORNER PLUG UNUSED OPENING + SCREW COVER TIGHT
Correction
Resolved
06/06/2008
INSTALLATION OF ROOF DRAINAGE DOWNSPOUTS COMPLETED
Correction
Resolved
06/06/2008
INSTALLATION OF TOILET PARTITIONS & URINAL SCREENS
Correction
Corrective Action Required
06/06/2008
LIGHT SWITCH IN ELECT 107 SETBACK > 1/4" MAXIMUM + GAP ABOVE COVER PLATE
Correction
Corrective Action Required
06/06/2008
BACKFLOW PREVENTION FOR ICE MAKER @ 106 DEVICE NOT INSTALLED PER IPC 608
Correction
Corrective Action Required
06/06/2008
ELECTRICAL RECEPTACLE @ RTU-2 WET LOCATION NO PROTECTED-TYPE COVER
Occupancy Inspection - Codes Commercial Failed 06/25/2008
Correction
Resolved
06/25/2008
Receive Fire Department approval PER JOE DIR
Correction
Resolved
06/25/2008
PENETRATIONS/HOLES IN EXTERIOR WALL
Correction
Resolved
06/25/2008
ELECTRICAL BOX @ EXTERIOR SE CORNER
Occupancy Inspection - Codes Commercial Failed 06/27/2008
Correction
Resolved
06/27/2008
CIRCUIT SCHEDULES AT PANELS
Correction
Resolved
06/27/2008
LIGHT SWITCH IN ELECT 107
Correction
Resolved
06/27/2008
BACKFLOW PREVENTION FOR ICE MAKER @ 106
Correction
Resolved
06/27/2008
ELECTRICAL RECEPTACLE @ RTU-2
Occupancy Inspection - Codes Commercial Failed 07/21/2008
Correction
Corrective Action Required
07/21/2008
Receive Planning & Development Approval COORDINATE WITH JENNIFER THOMPSON @ 816-969-1606 SEE REPORT PROVIDED DATED 5/23/08
Occupancy Inspection - Codes Commercial Passed 10/17/2008
Correction
Resolved
10/17/2008
USE / OCCUPANCY APPROVAL STATUS
Correction
Resolved
10/17/2008
Receive Planning & Development Approval PER JENNIFER THOMPSON REPORT DATED 10/14/08
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home