Summary
B0603608
Building Permit - Commercial
Final Completion
LEES SUMMIT SCHOOL DIST R 7
PARTIAL COMMERCIAL
FOUNDATION AND UNDERSLAB
12/14/2006
12/15/2006
06/13/2007
07/27/2007
Locations
Contacts
MEYER BROTHERS BLDG CO, Address:200 NE MISSOURI RD. STE 100  
LEES SUMMIT SCHOOL DIST R 7, Address:600 MILLER  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 06/12/2007 10/29/2010
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $266.63 $266.63 Paid 12/15/2006
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 01/11/2007
Correction
Partial Correction
01/11/2007
EXTERIOR WALL FOOTING A/6 TO A/9 TO E.2/9; OK TO POUR WHEN READY SECTIONS LISTED BELOW:
Correction
Resolved
01/11/2007
ISOLATED FOOTINGS C/6.1; C/7.1 OK TO POUR WHEN READY AT LOCATIONS BELOW
Foundation Inspection - Commercial Partial 01/23/2007
Correction
Partial Correction
01/23/2007
C.I.P. CONCRETE WALL ON (A) COMPLETE; ON (9) FROM (A) TO (B.8); OK TO POUR WHEN READY PORTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Partial 01/25/2007
Correction
Partial Correction
01/25/2007
EXTERIOR WALL FOOTING A/6 TO A/9 TO E.2/9; E.2/9 TO F/9 TO F/8.1 TO E/8.1 TO E/6.3; OK TO POUR WHEN READY SECTIONS LISTED BELOW:
Underslab Plumbing Inspection - Commercial Passed 02/02/2007
Correction
Resolved
02/02/2007
UNDER-SLAB DWV PIPING RESTROOM @ BSMT S WALL OK TO COVER WHEN READY
Footing Inspection - Commercial Passed 02/06/2007
Correction
Resolved
02/06/2007
EXTERIOR WALL FOOTING A/6 TO A/9 TO E.2/9; E.2/9 TO F/9 TO F/8.1 TO E/8.1 TO E/6.3; COMPLETED TO E/6 OK TO POUR WHEN READY SECTIONS LISTED BELOW:
Correction
Resolved
02/06/2007
ISOLATED FOOTINGS
Foundation Inspection - Commercial Partial 02/27/2007
Correction
Partial Correction
02/27/2007
C.I.P. CONCRETE WALL ON (A) COMPLETE; ON (9) FROM (A) TO (B.8); FROM B.8/9 TO F/9 TO F/8.5; OK TO POUR WHEN READY PORTIONS DESCRIBED BELOW:
Foundation Inspection - Commercial Passed 03/02/2007
Correction
Resolved
03/02/2007
C.I.P. CONCRETE WALL ON (A) COMPLETE; ON (9) FROM (A) TO (B.8); FROM B.8/9 TO F/9 TO F/8.5; F/8.5 TO E/6 TO COMPLETE PERIMETER WALL OK TO POUR WHEN READY PORTIONS DESCRIBED BELOW:
Footing Inspection - Commercial Passed 03/06/2007
Correction
Resolved
03/06/2007
PREP TO POUR TRUCK WELL WALL FOOTINGS OK TO POUR WHEN READY
Foundation Inspection - Commercial Passed 03/08/2007
Correction
Resolved
03/08/2007
PREP TO POUR TRUCK WELL WALLS OK TO POUR WHEN READY
Underground Plumbing Inspection - Commercial Partial 03/08/2007
Correction
Partial Correction
03/08/2007
12" PVC STORM SEWER LINE OK TO COVER WHEN READY FROM J.B. @ TRUCK WELL NW 62' NW @ 1% TO C.B.
Footing Inspection - Commercial Partial 03/14/2007
Correction
Resolved
03/14/2007
PREP TO POUR FOOTING FOR RETAINING WALL "A" OK TO POUR WHEN READY
Correction
Partial Correction
03/14/2007
PREP TO POUR TRUCK WELL WALL FOOTINGS NORTH TRUCK WELL OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 03/15/2007
Correction
Partial Correction
03/15/2007
PREP TO POUR RETAINING WALL "A" OK TO POUR WHEN READY
Correction
Partial Correction
03/15/2007
PREP TO POUR TRUCK WELL WALLS NW TRUCK WELL COMPLETE; OK TO POUR WHEN READY FOLLOWING PORTIONS:
Correction
Resolved
03/15/2007
C.I.P. CONCRETE WALL PERIMETER FOUNDATION WALL COMPLETE
Miscellaneous Inspection Passed 03/28/2007
Foundation Inspection - Commercial Passed 06/07/2007
Correction
Resolved
06/07/2007
PREP TO POUR RETAINING WALL "A"
Correction
Resolved
06/07/2007
PREP TO POUR TRUCK WELL WALLS
Final Inspection - Commercial Failed 06/07/2007
Correction
Corrective Action Required
06/07/2007
SPECIAL INSPECTION REPORTS
Footing Inspection - Commercial Passed 06/07/2007
Correction
Resolved
06/07/2007
EXTERIOR WALL FOOTING
Correction
Resolved
06/07/2007
ISOLATED FOOTINGS
Correction
Resolved
06/07/2007
PREP TO POUR FOOTING FOR RETAINING WALL "A"
Correction
Resolved
06/07/2007
PREP TO POUR TRUCK WELL WALL FOOTINGS
Underground Plumbing Inspection - Commercial Passed 06/07/2007
Correction
Resolved
06/07/2007
12" PVC STORM SEWER LINE
Foundation Inspection - Commercial Passed 06/08/2007
Final Inspection - Commercial Passed 07/25/2007
Correction
Resolved
07/25/2007
SPECIAL INSPECTION REPORTS
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home