Summary
B0602669
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
ADDITION COMMERCIAL
SECOND FLOOR ADDITION
09/22/2006
11/09/2006
05/08/2007
07/13/2007
Locations
Contacts
ACI BOLAND, Address:11229 NALL SUITE 140  
A D JACOBSON CO INC, Address:16210 W 108TH ST  
A D JACOBSON CO INC, Address:16210 W 108TH ST  
A D JACOBSON CO INC, Address:16210 W 108TH ST  
A D JACOBSON CO INC, Address:16210 W 108TH ST  
JE DUNN, Address:929 HOLMES  
SHAW ELECTRIC COMPANY, Address:3600 FULLER AVE  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 05/08/2007 10/29/2010
Correction

Fire Department; The required fire-resistance rating of fire-resistance-rated construction (including walls, fire stops, shaft enclosures, partitions and floors) shall be maintained. Such elements shall be properly repaired, restored or replaced when damaged, altered, breached or penetrated. Openings made therein for the passage of pipes, electrical conduit, wires, ducts, air transfer openings, and holes made for any reason shall be protected with approved methods capable of resisting the passage of smoke and fire. Openings through fire-resistance rated assemblies shall be protected by self-closing or automatic- closing doors of approved construction meeting the fire protection requirements for the assembly.
Correction

Fire Department: Fire protection systems shall be maintained in accordance with the original installation standards for that system. Required fire protection systems shall be extended, altered, or augmented as necessary to maintain and continue pro-tection whenever the building is altered, remodeled or added to.
Correction

Codes Administration - 2003 IBC 1704.1.1 - Building permit requirements. The permit applicant shall submit a statement of special inspections prepared by the registered design professional in responsible charge in accordance with Section 106.1 as a condition for permit issuance. This statement shall include a complete list of materials and work requiring special inspections by this section, the inspections to be performed and a list of the individuals, approved agencies or firms intended to be retained for conducting such inspections.
Correction

Codes Administration - 2003 IBC 1704.1.2 - Report Requirement. Special inspectors shall keep records of inspections. The special inspector shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was done in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If the discrepancies are not corrected, the discrepancies shall be brought to the attention of the building official and to the registered design professional in responsible charge prior to the completion of that phase of the work. A final report documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted at a point in time agreed upon by the permit applicant and the building official prior to the start of work.
Correction

Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-1300.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

Fire Department; Required means of egress components shall be maintained during construction and demolition.
Correction

Fire Department. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. The plans and specifications shall bear a State of Missouri licensed engineers seal. This includes fire sprinkler systems, grease hood and duct suppression systems as well as other fire suppression system.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department- 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection. Exceptions: 1. The supervisory signal at a constantly attended location is not required where duct smoke detectors activate the building’s alarm notification appliances. 2. In occupancies not required to be equipped with a fire alarm system, actuation of a smoke detector shall activate a visible and an audible signal in an approved location. 3. Smoke detector trouble conditions shall activate a visible or audible signal in an approved location and shall be identified as air duct detector trouble.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

Lee's Summit Code of Ordinance - Sec.17-309 - Smoking. A. "No Smoking" signs or the international "No Smoking" symbol (consisting of a pictorial representation of a burning cigarette enclosed in a red circle with a red bar across it) shall be clearly and conspicicuously posted at every public place and place of emplyment where smoking is prohibited by this Article, by the owner, operator, manager, or other person in control of that place. B. Every public place and place of employment where smoking is prohibited by this Article shall have posted at every entrance a conspicuous sign clearly stating that smoking is prohibited.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Fees
Paid Fees Amount Paid Owing Date Paid
Road and Bridge Escrow $5,527.22 $5,527.22 Paid 10/30/2006
0120 Building Permit Fee $12,942.60 $12,942.60 Paid 11/09/2006
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 11/17/2006
Correction
Partial Correction
11/17/2006
PREP FOR GRADE BEAM POUR AT STAIR TOWERS STAIR #2; OK TO POUR WHEN READY PORTIONS LISTED BELOW:
Rough Framing Inspection - Commercial Partial 11/17/2006
Correction
Partial Correction
11/17/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3; D/3; B.6/4; C.6/4; E/4; F/4; OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Rough Framing Inspection - Commercial Partial 11/20/2006
Correction
Partial Correction
11/20/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3; D/3; B.6/4; C.6/4; E/4; F/4; D/4; E/3; E/5; F/5; G/4; OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Rough Framing Inspection - Commercial Request Complete 11/20/2006 11/20/2006 11/20/2006
Rough Framing Inspection - Commercial Partial 11/21/2006
Correction
Partial Correction
11/21/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3; D/3; B.6/4; C.6/4; E/4; F/4; D/4; E/3; E/5; F/5; G/4; C/2; D/2; E/2; OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Footing Inspection - Commercial Partial 11/21/2006
Correction
Resolved
11/21/2006
SPREAD FOOTINGS AT STAIR TOWER #1 TWO TYPE F1 OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 11/22/2006
Correction
Partial Correction
11/22/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3; D/3; B.6/4; C.6/4; E/4; F/4; D/4; E/3; E/5; F/5; G/4; C/2; D/2; E/2; F/3; G/3; G/5; H/5; E/6; H/3; H/4; F/6; G/6; H/6; G/7; H/7; OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Rough Framing Inspection - Commercial Partial 11/27/2006
Correction
Partial Correction
11/27/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3; D/3; B.6/4; C.6/4; E/4; F/4; D/4; E/3; E/5; F/5; G/4; C/2; D/2; E/2; F/3; G/3; G/5; H/5; E/6; H/3; H/4; F/6; G/6; H/6; G/7; H/7; G/2.7; H/2.7; E/1; F/1; F/2; OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Rough Framing Inspection - Commercial Partial 11/28/2006
Correction
Partial Correction
11/28/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3; D/3; B.6/4; C.6/4; E/4; F/4; D/4; E/3; E/5; F/5; G/4; C/2; D/2; E/2; F/3; G/3; G/5; H/5; E/6; H/3; H/4; F/6; G/6; H/6; G/7; H/7; G/2.7; H/2.7; E/1; F/1; F/2; B/1; C/1; D/1; B/2; B/3; B/4; OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Rough Framing Inspection - Commercial Request Complete 11/28/2006 11/28/2006 11/28/2006
Rough Framing Inspection - Commercial Partial 12/04/2006
Correction
Partial Correction
12/04/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3; D/3; B.6/4; C.6/4; E/4; F/4; D/4; E/3; E/5; F/5; G/4; C/2; D/2; E/2; F/3; G/3; G/5; H/5; E/6; H/3; H/4; F/6; G/6; H/6; G/7; H/7; G/2.7; H/2.7; E/1; F/1; F/2; B/1; C/1; D/1; B/2; B/3; B/4; A/3; A/4; B/5; C/5; D/5; OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Rough Framing Inspection - Commercial Partial 12/06/2006
Correction
Partial Correction
12/06/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3;D/3;B.6/4;C.6/4;E/4;F/4;D/4;E/3;E/5;F/5;G/4;C/2;D/2;E/2;F/3;G/3;G/5; H/5;E/6;H/3;H/4;F/6;G/6;H/6;G/7;H/7;G/2.7;H/2.7;E/1;F/1;F/2;B/1;C/1;D/1; B/2;B/3;B/4;A/3;A/4;B/5;C/5;D/5;B/6;C/6;D/6;A/5; TO ELEV 981'-8": D.6/7.6; D.6/8; D.6/7; D.9/8 OK TO POUR WHEN READY COLUMNS LISTED BELOW:
Rough Framing Inspection - Commercial Request Complete 12/5/2006 12/6/2006 12/06/2006
Rough Framing Inspection - Commercial Passed 12/07/2006
Correction
Resolved
12/07/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS C/3;D/3;B.6/4;C.6/4;E/4;F/4;D/4;E/3;E/5;F/5;G/4;C/2;D/2;E/2;F/3;G/3;G/5; H/5;E/6;H/3;H/4;F/6;G/6;H/6;G/7;H/7;G/2.7;H/2.7;E/1;F/1;F/2;B/1;C/1;D/1; B/2;B/3;B/4;A/3;A/4;B/5;C/5;D/5;B/6;C/6;D/6;A/5; D.6/7; D.9/7; D.9/8; E.3/8; F/7.6; F/7 OK TO POUR WHEN READY COLUMNS AT ROOF:
Correction
Resolved
12/07/2006
PREP FOR POUR OF C.I.P. CONCRETE COLUMNS D.6/7.6; D.6/8; D.6/7; D.9/8 FOOTING TO ELEV 981'-8"
Rough Framing Inspection - Commercial Request Complete 12/7/2006 12/7/2006 12/07/2006
Footing Inspection - Commercial Partial 12/15/2006
Correction
Partial Correction
12/15/2006
PREP FOR GRADE BEAM POUR AT STAIR TOWERS STAIR #2; STAIR #1 AT LINES 8 & D.6; OK TO POUR WHEN READY PORTIONS LISTED BELOW:
Footing Inspection - Commercial Passed 12/18/2006
Correction
Resolved
12/18/2006
PREP FOR GRADE BEAM POUR AT STAIR TOWERS STAIR #2; STAIR #1 AT LINES 8 & D.6; AT LINE D.9 PER SECT 10 & 11 ON SHEET 2.0 OK TO POUR WHEN READY PORTIONS LISTED BELOW:
Rough Plumbing Inspection - Commercial Failed 04/10/2007
Correction
Corrective Action Required
04/10/2007
ADDITIONS/MODIFICATIONS TO ROOF DRAIN SYSTEM FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Correction
Corrective Action Required
04/10/2007
ADDITIONS/MODIFICATIONS TO DWV SYSTEM FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Rough Plumbing Inspection - Commercial Partial 04/17/2007
Correction
Corrective Action Required
04/17/2007
ADDITIONS/MODIFICATIONS TO DWV SYSTEM NO INSPECTIONS TO DATE FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Correction
Partial Correction
04/17/2007
ADDITIONS/MODIFICATIONS TO ROOF DRAIN SYSTEM RELOCATION OF 5" D.S. ABOVE 1ST FLR CEILING AT B.7/2.8; FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Rough Plumbing Inspection - Commercial Partial 04/23/2007
Correction
Partial Correction
04/23/2007
ADDITIONS/MODIFICATIONS TO DWV SYSTEM ABOVE CEILING ALL AREAS EXCEPT 245; 254; 272; 274 FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Correction
Partial Correction
04/23/2007
ADDITIONS/MODIFICATIONS TO ROOF DRAIN SYSTEM ABOVE CEILING ALL AREAS EXCEPT 245; 254; 272; 274 FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
All Rough Inspection - Commercial Partial 04/23/2007
Correction
Partial Correction
04/23/2007
WALL FRAMING + IN-WALL SYSTEMS 202-204; WALLS (G) FROM (3) TO (5) + (5) FROM (G) TO (H); OK TO COVER WHEN READY WALLS@SPACES LISTED BELOW
Correction
Partial Correction
04/23/2007
PREPARATION TO INSTALL GWB AT STAIRWELLS STAIR #1; OK TO COVER WHEN READY COMPONENTS LISTED BELOW:
Rated Assembly Inspection Partial 04/23/2007
Correction
Partial Correction
04/23/2007
RATED WALLS WALLS IN ELEVATOR EQUIPMENT ROOM PRESENTED FOR INSPECTION OF LAMINATED LAYERS; 1ST LAYER WAS NOT REQUESTED FOR INSPECTION BEFORE BEING COVERED
Rough Plumbing Inspection - Commercial Partial 04/25/2007
Correction
Partial Correction
04/25/2007
ADDITIONS/MODIFICATIONS TO DWV SYSTEM ABOVE CEILING ALL AREAS EXCEPT 145; 146 FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Correction
Partial Correction
04/25/2007
ADDITIONS/MODIFICATIONS TO ROOF DRAIN SYSTEM ABOVE CEILING ALL AREAS EXCEPT 145; 146 FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Underground Electrical Inspection - Commercial Partial 04/25/2007
Correction
Corrective Action Required
04/25/2007
GROUNDING OF SITE LIGHT POLE OK TO COVER WHEN READY GROUNDING AT BASES LISTED
Correction
Corrective Action Required
04/25/2007
PREP TO POUR CONCRETE LIGHT POLE BASE OK TO POUR WHEN READY FOLLOWING L.P. BASE(S)
Correction
Partial Correction
04/25/2007
BURIED CONDUIT FOR SITE ELECTRICAL FEEDER FROM EXSTG L.P. TO L.P.#2; 1<>2<>3; 5<>6; OK TO COVER WHEN READY TRENCHED CONDUIT BETWEEN
Underground Electrical Inspection - Commercial Request Complete 4/24/2007 4/25/2007 04/25/2007
Underground Electrical Inspection - Commercial Partial 04/26/2007
Correction
Resolved
04/26/2007
BURIED CONDUIT FOR SITE ELECTRICAL FEEDER FROM EXSTG L.P. TO L.P.#2; 1<>2<>3; 5<>6; 3<>5 OK TO COVER WHEN READY TRENCHED CONDUIT BETWEEN
Underground Electrical Inspection - Commercial Request Complete 4/25/2007 4/26/2007 04/26/2007
Rough Plumbing Inspection - Commercial Passed 04/27/2007
Correction
Resolved
04/27/2007
ADDITIONS/MODIFICATIONS TO DWV SYSTEM WORK ABOVE 1ST FLOOR CEILINGS ALL AREAS LISTED BELOW FOLLOWING 2ND FLOOR SPACES ALL NOW COMPLETE INCLUDING TODAY 245; 272; 274; 297 FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Correction
Resolved
04/27/2007
ADDITIONS/MODIFICATIONS TO ROOF DRAIN SYSTEM WORK ABOVE 1ST FLOOR CEILINGS ALL AREAS LISTED BELOW FOLLOWING 2ND FLOOR SPACES ALL NOW COMPLETE INCLUDING TODAY 245; 272; 274; 297 FIRST FLOOR LEVEL PORTIONS BELOW APPROVED:
Rated Assembly Inspection Partial 04/27/2007
Correction
Partial Correction
04/27/2007
RATED WALLS 201-204; OK TO COVER WHEN READY GWB AT AREAS LISTED:
Rated Assembly Inspection Partial 05/04/2007
Correction
Partial Correction
05/04/2007
RATED WALLS 201-204; OUTER FACE OF EAST & SOUTH WALLS OF 201; BULKHEAD ABOVE DOOR 205 OK TO COVER WHEN READY GWB AT AREAS LISTED:
Rated Assembly Inspection Partial 05/10/2007
Correction
Partial Correction
05/10/2007
RATED WALLS 201-204; OUTER FACE OF EAST & SOUTH WALLS OF 201; BULKHEAD ABOVE DOOR 205; ELEVATOR SHAFT INSIDE FACE LINER BOARD; OK TO COVER WHEN READY GWB AT AREAS LISTED:
Rough Electrical Inspection - Commercial Partial 05/11/2007
Correction
Partial Correction
05/11/2007
INSTALLATION OF SERVICE EQUIPMENT PANELBOARDS E2-1-HN; E2-2-LN; E2-3-HLS; E2-4-LC; E2-6-LA DISTRIBUTION PANEL DP-E2-5-HA TRANSFORMER X-E2-6-LA INCLUDING WIRING RACEWAYS + GROUNDING / BONDING
Rated Assembly Inspection Partial 05/11/2007
Correction
Partial Correction
05/11/2007
RATED WALLS 201-204; OUTER FACE OF EAST & SOUTH WALLS OF 201; BULKHEAD ABOVE DOOR 205; ELEVATOR SHAFT INSIDE FACE LINER BOARD; ELEVATOR SHAFT NORTH WALL 1ST LAYER 5/8" TYPE X OK TO COVER WHEN READY GWB AT AREAS LISTED:
Rated Assembly Inspection Partial 05/17/2007
Correction
Partial Correction
05/17/2007
RATED WALLS 201-204 RATED WALLS, INCLUDING FIRE-CAULKING; OUTER FACE OF EAST & SOUTH WALLS OF 201; BULKHEAD ABOVE DOOR 205; ELEVATOR SHAFT INSIDE FACE LINER BOARD; ELEVATOR SHAFT NORTH WALL 1ST LAYER 5/8" TYPE X; OK TO COVER WHEN READY GWB AT AREAS LISTED:
Rated Assembly Inspection Partial 05/21/2007
Correction
Partial Correction
05/21/2007
RATED WALLS 201-204 RATED WALLS, INCLUDING FIRE-CAULKING; OUTER FACE OF EAST & SOUTH WALLS OF 201; BULKHEAD ABOVE DOOR 205; ELEVATOR SHAFT INSIDE FACE LINER BOARD; ELEVATOR SHAFT N,W,S WALLS 1ST LAYER 5/8" TYPE X; OK TO COVER WHEN READY GWB AT AREAS LISTED:
Correction
Resolved
05/21/2007
ELEVATOR DOOR OPENING AT 1ST FLOOR 1" LINER BOARD + TWO LAYERS 5/8" TYPE X CUT-OUT EXSTG PERIMETER TO BE RE-BUILT TO FRAME
Above Ceiling Inspection Passed 05/21/2007
Correction
Resolved
05/21/2007
GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS AFTER ALL FIRE-CAULKING IS COMPLETED -- POINTED-OUT OK TO COVER WHEN READY ROOMS 202-204
Above Ceiling Inspection Partial 05/23/2007
Correction
Partial Correction
05/23/2007
GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS ROOMS 202-204 OK AFTER SPRINKLER HEADS INSTALLED, TEMP ELECT REMOVED, AND FIRE-CAULKING COMPLETED OK TO COVER WHEN READY FRAMING, M/E/P +FIRECAULK
Rated Assembly Inspection Partial 05/23/2007
Correction
Partial Correction
05/23/2007
RATED WALLS 201-204 RATED WALLS, INCLUDING FIRE-CAULKING; OUTER FACE OF EAST & SOUTH WALLS OF 201; BULKHEAD ABOVE DOOR 205; ELEVATOR SHAFT INSIDE FACE LINER BOARD; ELEVATOR SHAFT 1ST LAYER 5/8" TYPE X + W & S WALLS 2ND LAYER OK TO COVER WHEN READY GWB AT AREAS LISTED:
Underground Electrical Inspection - Commercial Partial 05/23/2007
Correction
Partial Correction
05/23/2007
PREP TO POUR CONCRETE LIGHT POLE BASE NUMBERED WEST-TO-EAST -- #1-5 OK TO POUR + #6 IN PROGRESS; OK TO POUR WHEN READY FOLLOWING L.P. BASE(S)
Correction
Corrective Action Required
05/23/2007
GROUNDING OF SITE LIGHT POLE NOT READY FOR INSPECTION SUBJECT TO APPROVAL
Rated Assembly Inspection Partial 05/24/2007
Rated Assembly Inspection Passed 05/29/2007
Correction
Resolved
05/29/2007
RATED WALLS 201-204 RATED WALLS, INCLUDING FIRE-CAULKING; OUTER FACE OF EAST & SOUTH WALLS OF 201; BULKHEAD ABOVE DOOR 205; ELEVATOR SHAFT INSIDE FACE LINER BOARD; ELEVATOR SHAFT 1ST LAYER 5/8" TYPE X + N,W & S WALLS 2ND LAYER OK TO COVER WHEN READY GWB AT AREAS LISTED:
Correction
Resolved
05/29/2007
ELEVATOR DOOR OPENING AT 1ST FLOOR
Underground Electrical Inspection - Commercial Passed 05/29/2007
Correction
Resolved
05/29/2007
BURIED CONDUIT FOR SITE ELECTRICAL
Correction
Resolved
05/29/2007
PREP TO POUR CONCRETE LIGHT POLE BASE
Correction
Resolved
05/29/2007
GROUNDING OF SITE LIGHT POLE OK TO COVER WHEN READY + CONDUIT CONNECTIONS @POLES 1 THRU 6 COMPLETE
Underground Electrical Inspection - Commercial Request Complete 5/25/2007 5/29/2007 05/29/2007
Underground Electrical Inspection - Commercial Passed 05/30/2007
Underground Electrical Inspection - Commercial Passed 05/31/2007
Underground Electrical Inspection - Commercial Passed 06/04/2007
Underground Electrical Inspection - Commercial Partial 06/05/2007
Correction
Resolved
06/05/2007
BURIED CONDUIT FOR SITE ELECTRICAL NORTH LOT COMPLETE
Correction
Resolved
06/05/2007
PREP TO POUR CONCRETE LIGHT POLE BASE NORTH LOT COMPLETE
Correction
Resolved
06/05/2007
GROUNDING OF SITE LIGHT POLE NORTH LOT COMPLETE
Correction
Partial Correction
06/05/2007
BURIED CONDUIT FOR SW LOT SITE ELECTRICAL FROM<>TO POLE #'S: 2<>3; 3<>4; 3<>6; 4<>7; OK TO COVER WHEN READY SEGMENTS DESCRIBED BELOW:
Correction
Partial Correction
06/05/2007
PREP TO POUR SW LOT LIGHT POLE BASES #1-4; 6; 7; OK TO POUR WHEN READY BASES NUMBERED AS FOLLOWS
Correction
Partial Correction
06/05/2007
GROUNDING OF SW LOT LIGHT POLES #1-4; 6; 7; OK TO COVER WHEN READY AT FOLLOWING POLE BASES:
Underground Electrical Inspection - Commercial Request Complete 6/4/2007 6/5/2007 06/05/2007
Underground Electrical Inspection - Commercial Passed 06/06/2007
Correction
Resolved
06/06/2007
BURIED CONDUIT FOR SW LOT SITE ELECTRICAL FROM<>TO POLE #'S: 2<>3; 3<>4; 3<>6; 4<>7; 7<>9; 5<>ORIGIN @ NORTH CURB OK TO COVER WHEN READY SEGMENTS DESCRIBED BELOW:
Correction
Resolved
06/06/2007
PREP TO POUR SW LOT LIGHT POLE BASES #1-4; 6; 7; 5; 8; 9(POURED PRIOR TO INSPECTION, BUT ASSUMED OK) OK TO POUR WHEN READY BASES NUMBERED AS FOLLOWS
Correction
Resolved
06/06/2007
GROUNDING OF SW LOT LIGHT POLES #1-4; 6; 7; 5; 8; 9 OK TO COVER WHEN READY AT FOLLOWING POLE BASES:
Underground Electrical Inspection - Commercial Request Complete 6/5/2007 6/6/2007 06/06/2007
Rough Electrical Inspection - Commercial Passed 07/12/2007
Correction
Resolved
07/12/2007
INSTALLATION OF SERVICE EQUIPMENT
Above Ceiling Inspection Passed 07/12/2007
Correction
Resolved
07/12/2007
GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS
All Rough Inspection - Commercial Passed 07/12/2007
Correction
Resolved
07/12/2007
PREPARATION TO INSTALL GWB AT STAIRWELLS
Correction
Resolved
07/12/2007
WALL FRAMING + IN-WALL SYSTEMS
Final Inspection - Commercial Passed 07/12/2007
Correction
Resolved
07/12/2007
CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home