Permit Application Status

B0601542


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0601542
Building Permit - Commercial
Final Completion
NEW COMMERCIAL
PICNIC AREA RESTROOM AND SITE ELECTRICAL
07/24/2006
08/01/2006
01/28/2007
08/16/2007
Locations
Contacts
AL J MUELLER CONSTRUCTION, Address:3920 PETTIS ROAD  
BOWMAN BOWMAN NOVICK INC, Address:411 NICHOLS RD SUITE 246  
UNIVERSAL ELECTRIC, Address:PO BOX 3628  
HYTEC PLUMBING, INC., Address:PO BOX 331  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 01/27/2007 10/29/2010
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $162.45 $162.45 Paid 08/01/2006
89 Sewer Tap Fees $150.00 $150.00 Paid 08/01/2006
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sewer Service Inspection Failed 08/10/2006
Correction
Corrective Action Required
08/10/2006
COMMENTS 1- APPROVED PLANS MUST BE ON SITE FOR INSPECTIONS. 2- CLEANOUTS TO BE 100' MAX. SPACING.
Correction
Partial Correction
08/10/2006
None APPROVED TO COVER INITIAL 160' OF PIPE CONTINGENT UPON LEAVING NEW CLEANOUT (AT 100' MARK) AND TAP AT MANHOLE EXPOSED. PUBLIC WORKS MUST APPROVE TAP AT MANHOLE.
Sewer Service Inspection - Commercial Request Complete 8/10/2006 8/10/2006 08/10/2006
Sewer Service Inspection Failed 08/11/2006
Correction
Corrective Action Required
08/11/2006
See Comment UNABLE TO LOCATE ANYONE ON SITE. UNABLE TO LOCATE OPEN SEWER TRENCH
Sewer Service Inspection - Commercial Request Complete 8/11/2006 8/11/2006 08/11/2006
Sewer Service Inspection Failed 08/14/2006
Correction
Partial Correction
08/14/2006
None APPROVED TO COVER INITIAL 160' OF PIPE CONTINGENT UPON LEAVING NEW CLEANOUT (AT 100' MARK) AND TAP AT MANHOLE EXPOSED. PUBLIC WORKS MUST APPROVE TAP AT MANHOLE.
Correction
Corrective Action Required
08/14/2006
See Comment AS INSTALLED DO NOT MATCH APPROVED PLANS. SUBMIT CHANGES TO CITY PLANS EXAMINER.
Sewer Service Inspection - Commercial Request Complete 8/14/2006 8/14/2006 08/14/2006
Sewer Service Inspection Failed 08/17/2006
Correction
Corrective Action Required
08/17/2006
See Comment UNCOVER LINE BETWEEN 1st & 2nd CLEANOUT (CLOSEST TO MANHOLE) FO INSPECTION
Correction
Resolved
08/17/2006
See Comment AS INSTALLED DO NOT MATCH APPROVED PLANS. SUBMIT CHANGES TO CITY PLANS EXAMINER.
Correction
Resolved
08/17/2006
See Comment UNABLE TO LOCATE ANYONE ON SITE. UNABLE TO LOCATE OPEN SEWER TRENCH
Correction
Resolved
08/17/2006
COMMENTS 1- APPROVED PLANS MUST BE ON SITE FOR INSPECTIONS. 2- CLEANOUTS TO BE 100' MAX. SPACING.
Sewer Service Inspection - Commercial Request Complete 8/17/2006 8/17/2006 08/17/2006
Footing Inspection - Commercial Passed 08/18/2006
Correction
Resolved
08/18/2006
See Comment approved as per plans
Sewer Service Inspection Passed 08/18/2006
Correction
Resolved
08/18/2006
See Comment see B0601541
Correction
Resolved
08/18/2006
None see B0601541
Correction
Resolved
08/18/2006
See Comment see B0601541
Correction
Resolved
08/18/2006
See Comment see B0601541
Correction
Resolved
08/18/2006
None see B0601541
Correction
Resolved
08/18/2006
COMMENTS see B0601541
Sewer Service Inspection - Commercial Request Complete 8/18/2006 8/18/2006 08/18/2006
Underslab Plumbing Inspection - Commercial Passed 08/22/2006
Correction
Resolved
08/22/2006
None AS PER PLANS.
Water Service Inspection Failed 09/01/2006
Correction
Corrective Action Required
09/01/2006
Approved Plans NO APPROVED PLANS ON SITE. CALL FOR REINSPCTION
Underslab Electrical Inspection - Commercial Passed 09/06/2006
Correction
Resolved
09/06/2006
None
Water Service Inspection Passed 09/06/2006
Correction
Resolved
09/06/2006
Approved Plans NO APPROVED PLANS ON SITE. CALL FOR REINSPCTION
Correction
Resolved
09/06/2006
None SHEET CO2.02 CALLS FOR 2" PVC FROM METER TO VALVE PIT. ALREADY INSTALLED. SHEET P1 CALLS FOR 1 1/2" CW. 2" CW FROM VALVE PIT TO RESTROOM
Underground Electrical Inspection - Commercial Failed 10/05/2006
Correction
Corrective Action Required
10/05/2006
See Comment UNCOVER GROUND WIRE, TOP OF GROUND ROD & CLAMP FOR INSPECTION Parking Lot Lights
Piers/Caissons Inspection - Commercial Partial 10/05/2006
Correction
Partial Correction
10/05/2006
None APPROVED AS PER PLANS - EXCEPT PIER AT SE CORNER OF PARKING LOT & WEST SIDE, MIDDLE PIER. Parking Lot Lights
Piers/Caissons Inspection - Commercial Partial 11/09/2006
Correction
Partial Correction
11/09/2006
None APPROVED AS PER PLANS Parking Lot Lights
Correction
Partial Correction
11/09/2006
None 3 LIGHT POLES-APPROVED E Destination Play Ground
Underground Electrical Inspection - Commercial Request Complete 11/10/2006 11/10/2006 11/10/2006
Underground Electrical Inspection - Commercial Failed 03/15/2007
Correction
Corrective Action Required
03/15/2007
See Comment UNCOVER GROUND WIRE, TOP OF GROUND ROD & CLAMP FOR INSPECTION Parking Lot Lights
Final Inspection - Commercial Failed 03/15/2007
Correction
Corrective Action Required
03/15/2007
Drain Covers INSTALL ON SINK DRAIN LINES
Piers/Caissons Inspection - Commercial Passed 03/15/2007
Correction
Resolved
03/15/2007
None APPROVED AS PER PLANS Parking Lot Lights
Correction
Resolved
03/15/2007
None 3 LIGHT POLES-APPROVED E Destination Play Ground
Underground Electrical Inspection - Commercial Passed 03/26/2007
Correction
Resolved
03/26/2007
See Comment UNCOVER GROUND WIRE, TOP OF GROUND ROD & CLAMP FOR INSPECTION Parking Lot Lights
Final Inspection - Commercial Failed 05/01/2007
Correction
Corrective Action Required
05/01/2007
Receive Planning & Development Approval RECEIVE UNDER SEPARATE COVER
Correction
Corrective Action Required
05/01/2007
Receive Public Works Approval RECEIVE UNDER SEPARATE COVER
Final Inspection - Commercial Failed 08/07/2007
Correction
Resolved
08/07/2007
Receive Planning & Development Approval RECEIVE UNDER SEPARATE COVER see e-mail from Tom Scannell dated 6 Aug 07
Final Inspection - Commercial Failed 08/08/2007
Correction
Resolved
08/08/2007
Drain Covers
Final Inspection - Commercial Passed 08/15/2007
Correction
Resolved
08/15/2007
Receive Public Works Approval RECEIVE UNDER SEPARATE COVER see e-mail from Shawn Graff dated 7 Aug 07
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home