Permit Application Status

B0600026


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0600026
Building Permit - Commercial
Final Completion
RAINTREE VILLAGE SHOPPING CENTER LLC
NEW SHELL BUILDING
SHELL BUILDING
01/06/2006
03/14/2006
09/10/2006
12/04/2006
Locations
Contacts
ARCHER ENGINEERS, Address:3731 NE TROON DR  
CAPITAL CONSTRUCTION SERVICES, Address:839 NE WOODS CHAPEL RD  
DAVIDSON DESIGN GROUP, Address:11301STRANG LINE ROAD  
RAINTREE VILLAGE SHOPPING CENTER LLC, Address:3215 NE CARNEGIE DR STE 400  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 07/29/2006 10/29/2010
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - Tenant finish plans shall be submitted to the Codes Administration Department prior to any interior alteration or improvments. Permits shall be obtained prior to any performing any work which requires permits.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department- 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection. Exceptions: 1. The supervisory signal at a constantly attended location is not required where duct smoke detectors activate the building’s alarm notification appliances. 2. In occupancies not required to be equipped with a fire alarm system, actuation of a smoke detector shall activate a visible and an audible signal in an approved location. 3. Smoke detector trouble conditions shall activate a visible or audible signal in an approved location and shall be identified as air duct detector trouble.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

Fire Department; The required fire-resistance rating of fire-resistance-rated construction (including walls, fire stops, shaft enclosures, partitions and floors) shall be maintained. Such elements shall be properly repaired, restored or replaced when damaged, altered, breached or penetrated. Openings made therein for the passage of pipes, electrical conduit, wires, ducts, air transfer openings, and holes made for any reason shall be protected with approved methods capable of resisting the passage of smoke and fire. Openings through fire-resistance rated assemblies shall be protected by self-closing or automatic- closing doors of approved construction meeting the fire protection requirements for the assembly.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

Codes Administration - 2003 IBC 903.2.1.2 - Group A-2. An automatic sprinkler system shall be provided for Group A-2 occupancies where on of the following conditions exists: 1. The fire area exceeds 5,000 square feet. 2. The fire area has an occupant load of 300 or more. 3. The fire area is located on a floor other than the level of exit discharge.
Correction

Codes Administration - Possible tenant address area 817, 821, 825, 829 and 833.
Correction

Fire Department- The size of the building does not allow for use as an A2 without fire area separation or an automatic sprinkler system.
Correction

Codes Administration - 2003 IBC 1008.1.5 - Landings at doors. Landings shall have a width not less than the width of the stairway or the door, whichever is the greater. Doors in the fully open position shall not reduce a required dimension by more than 7 inches (178 mm). When the landing serves an occupant load of 50 or more, doors in any position shall not reduce the landings to less than one-half its required width. Landings shall have a length measured in the direction of travel of not less than 44 inches (1118 mm).
Correction

Codes Administration - 2003 IBC 1008.1.4 - Floor elevation. There shall be a floor or landing on each side of a door. Such floor or landing shall be at the same elevation on each side of the door. Landings shall be level except for exterior landings, which are permitted to have a slope not to exceed 0.25 unit veritical in 12 units horizontal (2-percent slope).
Fees
Paid Fees Amount Paid Owing Date Paid
0120 Building Permit Fee $5,248.50 $5,248.50 Paid 03/14/2006
84 Water Meters $600.00 $600.00 Paid 03/14/2006
85 Water Taps $6,835.00 $6,835.00 Paid 03/14/2006
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sewer Service Inspection Failed 03/24/2006
Correction
Partial Correction
03/24/2006
None OK FROM STUB TO 10 FT OUTSIDE NORTH SIDE OF BUILDING 817
Sewer Service Inspection - Commercial Request Complete 3/23/2006 3/24/2006 03/24/2006
Footing Inspection - Commercial Failed 04/04/2006
Correction
Partial Correction
04/04/2006
PARTIAL APPROVED--1.5 EAST SIDE, SOUTH SIDE, WEST SIDE NORTH BACK TO 1.5. ---PIERS F56 F66 NEED TO BE INSPECTED ---NORTH SIDE NEEDS INSPECTION.
Electrical Service Inspection Failed 04/04/2006
Correction
Corrective Action Required
04/04/2006
FOOTING GROUND FOOTING GROUND APPROVED
Footing Inspection - Commercial Passed 04/05/2006
Correction
Resolved
04/05/2006
PARTIAL APPROVED--1.5 EAST SIDE, SOUTH SIDE, WEST SIDE NORTH BACK TO 1.5. ---PIERS F56 F66 NEED TO BE INSPECTED ---NORTH SIDE NEEDS INSPECTION.
Correction
Resolved
04/05/2006
NORTHSIDE NORTH , 2 PIERS INSIDE OK
Water Service Inspection Passed 04/06/2006
Correction
Resolved
04/06/2006
None
Water Service Inspection - Commercial Request Complete 4/6/2006 4/6/2006 04/06/2006
Underslab Plumbing Inspection - Commercial Passed 04/11/2006
Correction
Resolved
04/11/2006
None
Underslab Electrical Inspection - Commercial Passed 04/13/2006
Correction
Resolved
04/13/2006
None
Piers/Caissons Inspection - Commercial Passed 05/12/2006
Correction
Resolved
05/12/2006
None UNDER COLUMNS APPROVED GROUT INSPECTION
All Rough Inspection - Commercial Failed 07/07/2006
Correction
Corrective Action Required
07/07/2006
SHELL FRAMING 1. BOTTOM TRACK-- NAIL PATTERN TO SLAB. 2. SCREW OR WELD DBL STUD AT OPENIINGS.
All Rough Inspection - Commercial Failed 07/11/2006
Correction
Corrective Action Required
07/11/2006
SHELL FRAMING 2. SCREW OR WELD DBL STUD AT OPENIINGS. SOUTHEAST DOOR NOT COMPLETELY SCREWED. SCREW STUDS AND RECALL
Electrical Service Inspection Passed 07/27/2006
Correction
Resolved
07/27/2006
FOOTING GROUND FOOTING GROUND APPROVED
Correction
Resolved
07/27/2006
None HOUSE PANEL 100 AMP DOC. OFFICE 200 AMP
Sewer Service Inspection Passed 08/17/2006
Correction
Resolved
08/17/2006
None OK FROM STUB TO 10 FT OUTSIDE NORTH SIDE OF BUILDING 817 OK FROM MAIN TO BUILDING
All Rough Inspection - Commercial Passed 08/17/2006
Correction
Resolved
08/17/2006
SHELL FRAMING DBL STUD SCREW PATT. - APPROVED
Sewer Service Inspection - Commercial Request Complete 8/16/2006 8/17/2006 08/17/2006
Gas Service Inspection - Commercial Passed 08/29/2006
Correction
Resolved
08/29/2006
None
Gas Piping Inspection - Commercial Failed 08/29/2006
Correction
Corrective Action Required
08/29/2006
ROOF TOP PROVIDE ACCESS TO ROOF
Gas Piping Inspection - Commercial Passed 08/31/2006
Correction
Resolved
08/31/2006
ROOF TOP
Final Inspection - Commercial Failed 08/31/2006
Correction
Resolved
08/31/2006
Receive Fire Department approval OK PER CPT. DIR
Correction
Corrective Action Required
08/31/2006
Receive Planning & Development Approval
Correction
Corrective Action Required
08/31/2006
Receive Water Utilities Approval
Correction
Corrective Action Required
08/31/2006
Receive Public Works Approval
Correction
Corrective Action Required
08/31/2006
Grading (IRC) 1-EXTIOR ITEMS- GRADE-SOD-CANOPIES. 2-COMPLETE ELECTRICAL TO CANOPY LIGHTS.
Gas Service Inspection - Commercial Passed 11/17/2006
Correction
Resolved
11/17/2006
None ALL UNITS
Final Inspection - Commercial Failed 11/27/2006
Correction
Resolved
11/27/2006
Grading (IRC)
Final Inspection - Commercial Passed 12/01/2006
Correction
Resolved
12/01/2006
Receive Planning & Development Approval
Correction
Resolved
12/01/2006
Receive Water Utilities Approval
Correction
Resolved
12/01/2006
Receive Public Works Approval
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home