Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Sewer Service Inspection
|
Failed
|
|
|
11/14/2005
|
|
Correction
Corrective Action Required
|
Sewer Service Inspection - Commercial Request
|
Complete
|
11/14/2005
|
11/14/2005
|
11/14/2005
|
Sewer Service Inspection
|
Passed
|
|
|
11/16/2005
|
|
Correction
|
Sewer Service Inspection - Commercial Request
|
Complete
|
11/16/2005
|
11/16/2005
|
11/16/2005
|
Water Service Inspection
|
Partial
|
|
|
11/17/2005
|
|
Correction
|
Water Service Inspection - Commercial Request
|
Complete
|
11/17/2005
|
11/17/2005
|
11/17/2005
|
Water Service Inspection
|
Partial
|
|
|
11/18/2005
|
|
Correction
|
Water Service Inspection - Commercial Request
|
Complete
|
11/18/2005
|
11/18/2005
|
11/18/2005
|
Footing Inspection - Commercial
|
Partial
|
|
|
11/23/2005
|
|
Correction
|
|
Correction
|
Water Service Inspection
|
Partial
|
|
|
12/02/2005
|
|
Correction
|
Water Service Inspection - Commercial Request
|
Complete
|
12/2/2005
|
12/2/2005
|
12/02/2005
|
Water Service Inspection
|
Partial
|
|
|
12/05/2005
|
|
Correction
|
Water Service Inspection - Commercial Request
|
Complete
|
12/2/2005
|
12/5/2005
|
12/05/2005
|
Underground Electrical Inspection - Commercial
|
Failed
|
|
|
12/28/2005
|
|
Correction
|
Underground Electrical Inspection - Commercial Request
|
Complete
|
12/27/2005
|
12/28/2005
|
12/28/2005
|
Underground Electrical Inspection - Commercial
|
Partial
|
|
|
12/30/2005
|
|
Correction
|
Underground Electrical Inspection - Commercial Request
|
Complete
|
12/29/2005
|
12/30/2005
|
12/30/2005
|
Underground Electrical Inspection - Commercial
|
Passed
|
|
|
01/24/2006
|
|
Correction
|
|
Correction
|
Underground Electrical Inspection - Commercial Request
|
Complete
|
1/24/2006
|
1/24/2006
|
01/24/2006
|
Rough Framing Inspection - Commercial
|
Partial
|
|
|
02/06/2006
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
2/3/2006
|
2/6/2006
|
02/06/2006
|
Rough Framing Inspection - Commercial
|
Partial
|
|
|
02/08/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
2/7/2006
|
2/8/2006
|
02/08/2006
|
Rough Framing Inspection - Commercial
|
Partial
|
|
|
02/16/2006
|
|
Correction
Corrective Action Required
|
Rough Framing Inspection - Commercial Request
|
Complete
|
2/15/2006
|
2/16/2006
|
02/16/2006
|
Rough Framing Inspection - Commercial
|
Partial
|
|
|
02/21/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
2/17/2006
|
2/21/2006
|
02/21/2006
|
Rough Framing Inspection - Commercial
|
Not Ready
|
|
|
02/24/2006
|
|
Correction
|
|
Correction
|
|
Correction
Corrective Action Required
|
Rough Framing Inspection - Commercial
|
Partial
|
|
|
02/27/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
2/24/2006
|
2/27/2006
|
02/27/2006
|
All Rough Inspection - Commercial
|
Partial
|
|
|
03/03/2006
|
|
Correction
|
All Rough Inspection - Commercial
|
Partial
|
|
|
03/15/2006
|
|
Correction
|
Rough Plumbing Inspection - Commercial
|
Passed
|
|
|
03/15/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Gas Piping Inspection - Commercial
|
Passed
|
|
|
03/15/2006
|
|
Correction
|
Gas Service Inspection - Commercial
|
Passed
|
|
|
03/15/2006
|
|
Correction
|
Water Service Inspection
|
Passed
|
|
|
03/22/2006
|
|
Correction
|
All Rough Inspection - Commercial
|
Partial
|
|
|
03/28/2006
|
|
Correction
|
Rated Assembly Inspection
|
Partial
|
|
|
03/28/2006
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
3/27/2006
|
3/28/2006
|
03/28/2006
|
Rough Framing Inspection - Commercial
|
Partial
|
|
|
03/31/2006
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
3/30/2006
|
3/31/2006
|
03/31/2006
|
Rough Framing Inspection - Commercial
|
Partial
|
|
|
04/05/2006
|
|
Correction
|
Rated Assembly Inspection
|
Partial
|
|
|
04/05/2006
|
|
Correction
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
4/4/2006
|
4/5/2006
|
04/05/2006
|
Rated Assembly Inspection
|
Partial
|
|
|
04/07/2006
|
|
Correction
|
Rough Electrical Inspection - Commercial
|
Partial
|
|
|
04/10/2006
|
|
Correction
|
Rough Framing Inspection - Commercial
|
Passed
|
|
|
04/10/2006
|
|
Correction
|
|
Correction
|
Rough Framing Inspection - Commercial Request
|
Complete
|
4/7/2006
|
4/10/2006
|
04/10/2006
|
All Rough Inspection - Commercial
|
Passed
|
|
|
04/18/2006
|
|
Correction
|
Above Ceiling Inspection
|
Partial
|
|
|
04/18/2006
|
|
Correction
|
Sidewalk Inspection
|
Passed
|
|
|
04/20/2006
|
Rated Assembly Inspection
|
Failed
|
|
|
05/12/2006
|
|
Correction
|
|
Correction
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
|
|
05/12/2006
|
|
Correction
|
|
Correction
|
Electrical Service Inspection
|
Passed
|
|
|
05/12/2006
|
|
Correction
|
Above Ceiling Inspection
|
Partial
|
|
|
05/15/2006
|
|
Correction
|
|
Correction
|
Above Ceiling Inspection
|
Partial
|
|
|
05/17/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Above Ceiling Inspection
|
Partial
|
|
|
05/19/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Above Ceiling Inspection
|
Passed
|
|
|
06/12/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Not Ready
|
|
|
06/12/2006
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Not Ready
|
|
|
06/22/2006
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
|
Rough Electrical Inspection - Commercial
|
Passed
|
|
|
06/22/2006
|
|
Correction
|
Rated Assembly Inspection
|
Passed
|
|
|
06/22/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Footing Inspection - Commercial
|
Passed
|
|
|
06/22/2006
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
06/26/2006
|
|
Correction
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
06/28/2006
|
|
Correction
|
|
Correction
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
07/07/2006
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
07/13/2006
|
|
Correction
|
|
Correction
Corrective Action Required
|
|
Correction
Corrective Action Required
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
|
07/19/2006
|
|
Correction
Corrective Action Required
|
|
Correction
|
Occupancy Inspection - Codes Commercial
|
Passed
|
|
|
08/29/2008
|
|
Correction
|
|
Correction
|