Summary
B0501219
Building Permit - Commercial
Final Completion
LEES LANDING PROPERTIES LLC
NEW COMMERCIAL
NEW BUILDING
07/13/2005
08/05/2005
02/01/2006
12/28/2006
Locations
Contacts
HIRST AND ASSOCIATES PC, Address:621 NE WOODS CHAPEL RD  
MEMCO, Address:14219 KENNEDY RD  
LEES LANDING PROPERTIES LLC, Address:2270 NW SUMMERFIELD DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 01/31/2006 10/29/2010
Correction

Codes Administration - Wall construction details are not provided.
Correction

Codes Administration - The mechanical, electrical and plumbing plans are not signed and sealed.
Correction

Fire Department- Plans reviewed under the 2003 International Fire Code, not the 2000 edition indicated on the plans.
Correction

Fire Department- Egress doors shall be readily openable from the egress side without the use of akey or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

Codes Administration - Copies of the engineered truss package were not provided at the time of permit application.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

Codes Administration - All plans submitted for review on or after July 6, 2004 shall be designed to the requirements of the 2003 International Building Code, 2003 International Mechanical Code, 2003 International Plumbing Code, 2003 International Fuel Gas Code, 2003 International Fire Code, 2002 National Electric Code and the ANSI A117.1-1998 as amended and adopted by the City of Lee's Summit.
Correction

Fire Department; New and existing buildings shall have approved address numbers, building numbers, placed in a position to be plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

All backflow prevention assemblies must be tested and reports filed with the Lee's Summit Water Utilities Backflow Division (816-969-7636) within 30 days from the date installed.
Correction

Backflow prevention assembly must be located in an accessible location, min. 12" from floor, min. 6" from wall, max. 48" from floor.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $902.00 $902.00 Paid 08/05/2005
24 BLDG Plan Check Fees $35.00 $35.00 Paid 08/05/2005
25 Electrical Permit Fee $224.00 $224.00 Paid 08/05/2005
25 Mechanical Permit Fees $135.00 $135.00 Paid 08/05/2005
25 Plumbing Permit Fees $99.00 $99.00 Paid 08/05/2005
89 Sewer Tap Fees $360.00 $360.00 Paid 08/05/2005
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 09/12/2005
Correction
Partial Correction
09/12/2005
PERIMETER GRADE BEAM FROM NW BLDG CORNER TO NE BLDG CORNER TO SE BLDG CORNER TO 15 N OF SW CORNER RM 413; OK TO POUR WHEN READY SEGMENTS LISTED BELOW:
Footing Inspection - Commercial Partial 09/13/2005
Correction
Partial Correction
09/13/2005
PERIMETER GRADE BEAM FROM NW BLDG CORNER TO NE BLDG CORNER TO SE BLDG CORNER TO 15 N OF SW CORNER RM 413; REMAINDER OF PERIMETER OK TO POUR WHEN READY SEGMENTS LISTED BELOW:
Footing Inspection - Commercial Passed 09/14/2005
Correction
Resolved
09/14/2005
PERIMETER GRADE BEAM FROM NW BLDG CORNER TO NE BLDG CORNER TO SE BLDG CORNER TO 15 N OF SW CORNER RM 413; REMAINDER OF PERIMETER; CROSSWALL OK TO POUR WHEN READY SEGMENTS LISTED BELOW:
Water Service Inspection Passed 10/03/2005
Correction
Resolved
10/03/2005
WATER SERVICE FEEDER INSTALLATION TO BUILDING ENTRY FROM TAPPED SERVICE LINE PREVIOUSLY APPROVED
Sewer Service Inspection Passed 10/03/2005
Underslab Plumbing Inspection - Commercial Passed 10/03/2005
Correction
Resolved
10/03/2005
UNDER-SLAB DWV & WATER PIPING OK TO COVER WHEN READY
Sewer Service Inspection - Commercial Request Complete 10/3/2005 10/3/2005 10/03/2005
Water Service Inspection - Commercial Request Complete 10/3/2005 10/3/2005 10/03/2005
Underslab Electrical Inspection - Commercial Partial 10/11/2005
Correction
Partial Correction
10/11/2005
UNDER-FLOOR ELECTRICAL CONDUIT WEST 1/2 OF BUILDING; OK TO COVER WHEN READY PORTIONS LISTED BELOW:
Underground Electrical Inspection - Commercial Request Complete 10/10/2005 10/11/2005 10/11/2005
Electrical Service Inspection Partial 10/14/2005
Correction
Partial Correction
10/14/2005
TEMPORARY ELECTRICAL SERVICE INSTALLATION RELEASE TEMP SERVICE
Underslab Electrical Inspection - Commercial Passed 10/17/2005
Correction
Resolved
10/17/2005
UNDER-FLOOR ELECTRICAL CONDUIT WEST 1/2 OF BUILDING; EAST 1/2 OF BUILDING MATERIAL & WORKMANSHIP OK TO COVER WHEN READY
Rough Framing Inspection - Commercial Failed 01/23/2006
Correction
Corrective Action Required
01/23/2006
STUDS NOTCHED FOR SILL PLATE ANCHOR BOLTS REINFORCE BOTTOM OF STUDS
Correction
Corrective Action Required
01/23/2006
ANCHOR BOLT NUTS LOOSE NUTS ESPECIALLY AT EAST WALL SOME MISSING ENSURE ALL TIGHT
Rough Framing Inspection - Commercial Request Complete 1/20/2006 1/23/2006 01/23/2006
Rough Framing Inspection - Commercial Passed 01/25/2006
Correction
Resolved
01/25/2006
STUDS NOTCHED FOR SILL PLATE ANCHOR BOLTS
Correction
Resolved
01/25/2006
ANCHOR BOLT NUTS
Correction
Resolved
01/25/2006
FRAMING AT ROOF & EXTERIOR WALLS WHEN OTHER TRADES ARE COMPLETED NO REMAINING ISSUES SUBJECT TO RE-INSPECTION
Rough Framing Inspection - Commercial Request Complete 1/24/2006 1/25/2006 01/25/2006
Above Ceiling Inspection Partial 02/02/2006
Correction
Partial Correction
02/02/2006
ABOVE-CEILING SYSTEMS ROUGH ABOVE GWB UPPER CEILING OK TO COVER WHEN READY
All Rough Inspection - Commercial Partial 02/02/2006
Correction
Partial Correction
02/02/2006
WALL FRAMING + IN-WALL SYSTEMS ROUGH FURNACE ROOMS; OK TO COVER WHEN READY SPACES LISTED BELOW:
Electrical Service Inspection Not Ready 03/24/2006
Correction
Corrective Action Required
03/24/2006
READINESS FOR INSPECTION IBC 109.1, 109.5; IRC R109.3: PERMIT DRAWINGS REQUIRED FOR INSPECTION. NOT READY PROPERTY LOCKED INTERIOR NOT ACCESSIBLE
Electrical Service Inspection Passed 03/27/2006
Correction
Resolved
03/27/2006
TEMPORARY ELECTRICAL SERVICE INSTALLATION
Correction
Resolved
03/27/2006
READINESS FOR INSPECTION
Correction
Resolved
03/27/2006
ELECTRICAL SERVICE INSTALLATION AFFIX SUITE NUMBERS TO ENTRANCES BEFORE REQUESTING ACTIVATION. 600 AMP MAIN + 100 AMP H + SIX 100 AMP SUITE SVCS
Above Ceiling Inspection Passed 12/27/2006
Correction
Resolved
12/27/2006
ABOVE-CEILING SYSTEMS ROUGH ABOVE GWB UPPER CEILING
All Rough Inspection - Commercial Passed 12/27/2006
Correction
Resolved
12/27/2006
WALL FRAMING + IN-WALL SYSTEMS ROUGH
Final Inspection - Commercial Passed 12/27/2006
Correction
Resolved
12/27/2006
BUILDING SHELL FINAL INSPECTION CLOSE PERMIT ADVISE TO SEAL EXT WALLS SEAL ANY OPENINGS
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home