Summary
B0500741
Building Permit - Commercial
Certificate of Occupancy
VILLE 36 INVESTMENT COMPANY LLC
CHANGE OF TENANT
TENANT FINISH
05/06/2005
06/23/2005
12/20/2005
11/07/2005
Locations
Contacts
HOFFMAN-CORTES CONTRACTING CO, Address:1600 BALTIMORE, SUITE 102  
HC KLOVER ARCHITECTS, Address:10955 LOWELL SUITE 700  
VILLE 36 INVESTMENT COMPANY LLC, Address:4740 ROANOKE PKWY  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 11/02/2005 10/29/2010
Correction

Codes Administration - 2003 IBC 1008.1.1 - Size of doors. The minimum width of each door opening shall be sufficient for the occupant load thereof and shall provide a clear width of not less than 32 inches. Clear openings of doorways with swinging doors shall be measured between the face of the door and the stop, with the door open 90 degrees. Where this section requires a minimum clear width of 32 inches and a door opening includes two door leaves without a mullion, one leaf shall provide a clear opening width of 32 inches. The maximum width of a swinging door leaf shall be 48 inches nominal. Means of egress doors in an occupancy in Group I-2 used for the movement of beds shall provide a clear width not less than 41.5 inches. The height of doors shall not be less than 80 inches.
Correction

Codes Administration - 2003 IBC 2406.1 - Human impact loads. Individual glazed areas, including glass mirrors, in hazardous locations as defined in Section 2406.3 shall comply with Sections 2406.1 through 2406.1.5.
Correction

Codes Administration - 2003 IBC 602.1 - General. Buildings and structures erected or to be erected, altered or extended in height or area shall be classified in one of the five construction types defined in Sections 602.2 through 602.5. The building elements shall have a fire-resistance rating not less than that specified in Table 601 and exterior walls shall have a fire-resistance rating not less than that specified in Table 602.
Correction

Codes Administration - LSCO 7-1102.1 - Demolition permit required. Unless otherwise approved by the building official, the demolition of structures or buildings, partial or complete, shall require a demolition permit. Fees for demolition permits shall be in accordance with the City of Lee's Summit, MO Fee Schedule.
Correction

Fire Department- Egress doors shall be readily openable from the egress side without the use of akey or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
Correction

Fire Department; Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Documents shall bear a State of Missouri architect/engineers seal..Construction documents shall include, but not be limited to, all of the following: 1. A floor plan. 2. Locations of alarm notification appliances.
Correction

Codes Administration - The address provided is incorrect.
Correction

Codes Administration - The occupant loads provided in the Code Review Information is incorrect and not consistant with what was provided on the information faxed to our department on March 23, 2005.
Correction

Codes Administration - Information is not provided regarding the roof system at the new mechanical installation.
Correction

Codes Administration - The plans indicate that there is an water dispenser that is connected to the water system. The plans also indicate that there is an ice maker in it.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

Fire Department; New and existing buildings shall have approved address numbers, building numbers, placed in a position to be plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background.
Correction

Fire Department. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. The plans and specifications shall bear a State of Missouri licensed engineers seal. This includes fire sprinkler systems, grease hood and duct suppression systems as well as other fire suppression system.
Correction

Fire Department: Fire protection systems shall be maintained in accordance with the original installation standards for that system. Required fire protection systems shall be extended, altered, or augmented as necessary to maintain and continue pro-tection whenever the building is altered, remodeled or added to.
Correction

Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-7343.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department- 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection. Exceptions: 1. The supervisory signal at a constantly attended location is not required where duct smoke detectors activate the building’s alarm notification appliances. 2. In occupancies not required to be equipped with a fire alarm system, actuation of a smoke detector shall activate a visible and an audible signal in an approved location. 3. Smoke detector trouble conditions shall activate a visible or audible signal in an approved location and shall be identified as air duct detector trouble.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

Codes Administration - 2003 IPC 403.6 - Public facilities. Customers, patrons and visitors shall be provided with public toilet facilites in structures and tenant spaces intended for public utilization. Public toilet facilities shall be located not more than one story above or below the space required to be provided with public toilet facilities and the path of travel to such facilities shall not exceed a distance of 500 feet (152 m).
Correction

P & D - All exterior mechanical equipment, whether roof mounted or ground mounted, shall be screened from view from off the property. The appearance of screens shall be coordinated with the building to maintain a unified appearance.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $1,502.00 $1,502.00 Paid 06/23/2005
24 BLDG Plan Check Fees $45.00 $45.00 Paid 06/23/2005
25 Electrical Permit Fee $84.12 $84.12 Paid 06/23/2005
25 Mechanical Permit Fees $30.50 $30.50 Paid 06/23/2005
25 Plumbing Permit Fees $23.00 $23.00 Paid 06/23/2005
89 Sewer Tap Fees $60.00 $60.00 Paid 06/23/2005
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Commercial Partial 08/05/2005
Correction
Partial Correction
08/05/2005
WALL FRAMING + IN-WALL SYSTEMS ROUGH ALL STUD FLANGES MUST BE SCREWED TO T&B TRACKS DEMISING WALL AT EAST OK TO TAPE/MUD EAST FACE
Rough Framing Inspection - Commercial Request Complete 8/4/2005 8/5/2005 08/05/2005
Underslab Plumbing Inspection - Commercial Passed 08/08/2005
Correction
Resolved
08/08/2005
UNDER-SLAB DWV PIPING OK TO COVER WHEN READY. NOTE 3" PIPING USED IN LIEU OF 4" PER DRAWING; NOT CONSIDERED CODE VIOLATION. NOTE TRAP PRIMER REQUIRED AT FLOOR DRAIN
All Rough Inspection - Commercial Partial 08/15/2005
Correction
Partial Correction
08/15/2005
WALL FRAMING + IN-WALL SYSTEMS ROUGH DEMISING WALL AT EAST: OK TO TAPE/MUD EAST FACE; OK TO COVER WEST FACE; EXISTING NORTH WALL OK TO COVER OK TO COVER WHEN READY COMPONENTS LISTED BELOW:
Electrical Service Inspection Passed 08/23/2005
Correction
Resolved
08/23/2005
ELECTRICAL SERVICE INSTALLATION 200 AMP RELEASE SERVICE
All Rough Inspection - Commercial Passed 09/08/2005
Correction
Resolved
09/08/2005
WALL FRAMING + IN-WALL SYSTEMS ROUGH OK TO COVER WHEN READY ALL WALLS
Correction
Resolved
09/08/2005
SOFFIT AT DIAMOND ROOM OK TO COVER WHEN READY
Gas Piping Inspection - Commercial Failed 09/16/2005
Correction
Corrective Action Required
09/16/2005
SUPPORT INTERVALS FOR ROOFTOP PIPING COMPLY WITH DRAWINGS ALSO, SUPPORT AT JOINTS
Correction
Corrective Action Required
09/16/2005
SUPPORT BLOCKS FOR ROOFTOP PIPING PROVIDE PER A/E DRAWINGS CLARIFY WITH A/E
Gas Service Inspection - Commercial Passed 09/16/2005
Correction
Resolved
09/16/2005
TEST PRESSURE LEVEL RELEASE GAS SERVICE HELD STEADY AT >10 PSI FOR >30 MIN
Above Ceiling Inspection Passed 10/06/2005
Correction
Resolved
10/06/2005
CEILING FRAMING + ABOVE-CEILING SYSTEMS ROUGH OK TO COVER WHEN READY SIGN CIRCUITS IN PROGRESS
Occupancy Inspection - Codes Commercial Failed 10/31/2005
Correction
Corrective Action Required
10/31/2005
Receive Fire Department approval SEE LIST PROVIDED
Correction
Corrective Action Required
10/31/2005
Receive Planning & Development Approval
Correction
Corrective Action Required
10/31/2005
CODES ADMININISTRATION ISSUES 1) ADHERE( NON-METALLIC) SLIPSHEETS TO WOOD BLOCKS SUPPORTING ROOFTOP GAS PIPING 2) AFFIX HANDICAPPED-ACCESSIBLE SIGN TO RESTROOM DOOR 3) SEAL ANY REMAINING PENETRATIONS OF OL465 EAST DEMISING WALL 4) PANIC BAR REQUIRED @ WEST DOOR STATED BELOW
Correction
Partial Correction
10/31/2005
OCCUPANCY APPROVAL STATUS OK FOR STAFFING &STOCKING NO PUBLIC UNTIL APPROVED
Occupancy Inspection - Codes Commercial Failed 11/03/2005
Correction
Resolved
11/03/2005
Receive Fire Department approval PER JIM EDEN 11/3/05
Correction
Corrective Action Required
11/03/2005
Receive Planning & Development Approval SCHEDULED TO INSPECT 11/3
Correction
Resolved
11/03/2005
CODES ADMININISTRATION ISSUES
Correction
Partial Correction
11/03/2005
OCCUPANCY APPROVAL STATUS SEE TEMPORARY OCCUPANCY
Occupancy Inspection - Codes Commercial Passed 11/04/2005
Correction
Resolved
11/04/2005
Receive Planning & Development Approval PER MIKE GORECKI 11/3/05
Correction
Resolved
11/04/2005
OCCUPANCY APPROVAL STATUS
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home