Summary
B0402019
Building Permit - Commercial
Final Completion
CITY OF LEES SUMMIT
ALTERATION COMMERCIAL
FACADE REMODEL
10/19/2004
01/04/2005
07/03/2005
08/18/2005
Locations
Contacts
J & M CONTRACTING, Address:1712 E 123RD ST  
CITY OF LEES SUMMIT, Address:PO BOX 1600  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 04/17/2005 10/29/2010
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

Fire Department; IFC 1003.3.1.8 Egress doors shall be readily openable from the egress side without the use of akey or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
Correction

Fire Department; Exit signs shall be internally or externally illuminated. The face of an exit sign illuminated from an external source shall have an intensity of not less than 5 foot-candles (54 lux). Internally illuminated signs shall provide equivalent luminance and be listed for the purpose. IFC 1003.2.10.4 Exit sign illumination shall also be in accordance with the IBC.
Correction

Fire Department; Required means of egress components shall be maintained during construction and demolition.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $1,925.00 $1,925.00 Paid 01/04/2005
24 BLDG Plan Check Fees $52.05 $52.05 Paid 01/04/2005
25 Electrical Permit Fee $60.00 $60.00 Paid 01/04/2005
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 02/02/2005
Correction
Partial Correction
02/02/2005
GRADE BEAM @ SOUTH BUILDING WALL WHERIN A/E AMMENDS PERMIT DRAWINGS + SKETCHES ON SITE. CORRECTIONS/CLARIFICATIONS TO BE FAXED TO INSPECTOR 2/2/05 OK TO POUR PER DISCUSSION W/ A/E
Footing Inspection - Commercial Passed 02/04/2005
Correction
Resolved
02/04/2005
GRADE BEAM @ NORTH BUILDING WALL W 85' OF WALL; REMAINDER OF N WALL, LESS E 6' ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
02/04/2005
GRADE BEAM @ SOUTH BUILDING WALL
Footing Inspection - Commercial Partial 02/14/2005
Correction
Partial Correction
02/14/2005
GRADE BEAM @ EAST BLDG WALL ENSURE RE-BAR COVERAGE. OK TO POUR WHEN READY EAST 9' OF NORTH WALL + 30' ALONG EAST WALL
Correction
Resolved
02/14/2005
GRADE BEAM @ NORTH BUILDING WALL EXCLUDING EAST 9'
Rough Framing Inspection - Commercial Failed 02/15/2005
Correction
Corrective Action Required
02/15/2005
STEEL STUD FRAMING @ EXTERIOR WALLS SOUTH WALL NOT COMPLETE
Rough Framing Inspection - Commercial Request Complete 2/14/2005 2/15/2005 02/15/2005
Rough Framing Inspection - Commercial Partial 02/16/2005
Correction
Partial Correction
02/16/2005
STEEL STUD FRAMING @ EXTERIOR WALLS SOUTH WALL; OK TO COVER WHEN READY
Rough Framing Inspection - Commercial Request Complete 2/15/2005 2/16/2005 02/16/2005
Footing Inspection - Commercial Partial 02/17/2005
Correction
Partial Correction
02/17/2005
GRADE BEAM @ WEST ENTRANCE E-W WALL @ DRIVEWAY + TWO 15' OUTSIDE N-S SECTIONS + 8' E-W TO TIE IN @ NW CORNER; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 03/01/2005
Correction
Partial Correction
03/01/2005
None VESTBULE FOOTING APPROVED PER S1 DETAIL.
Correction
Partial Correction
03/01/2005
GRADE BEAM @ EAST BLDG WALL ENSURE RE-BAR COVERAGE. OK TO POUR WHEN READY EAST 9' OF NORTH WALL + 30' ALONG EAST WALL
Footing Inspection - Commercial Partial 03/08/2005
Correction
Resolved
03/08/2005
None VESTBULE FOOTING APPROVED PER S1 DETAIL.
Correction
Partial Correction
03/08/2005
STEP FOOTING DOWN NORTH STAIRWELL ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
03/08/2005
GRADE BEAM @ WEST ENTRANCE TWO 15' OUTSIDE N-S SECTIONS + 8' E-W TO TIE IN @ NW CORNER; E-W WALL @ DRIVEWAY +
Correction
Resolved
03/08/2005
GRADE BEAM @ EAST BLDG WALL EAST 9' OF NORTH WALL + 30' ALONG EAST WALL
Rough Framing Inspection - Commercial Partial 03/10/2005
Correction
Partial Correction
03/10/2005
STEEL STUD FRAMING @ EXTERIOR WALLS OK TO COVER WHEN READY: SOUTH WALL; NORTH WALL EXCEPT AROUND DOORS/WINDOWS + MISC REPAIRS (STAIRWELL NOT READY); ENSURE BOTTOM FLANGES FULLY SCREWED TO TRACK
Rough Framing Inspection - Commercial Partial 03/11/2005
Correction
Partial Correction
03/11/2005
STEEL STUD FRAMING @ EXTERIOR WALLS OK TO COVER WHEN READY: SOUTH WALL; NORTH WALL EXCEPT ABOVE N ENTRANCE CANOPY + STAIRWELL (NOT READY); ENSURE BOTTOM FLANGES FULLY SCREWED TO TRACK
Rough Framing Inspection - Commercial Request Complete 3/10/2005 3/11/2005 03/11/2005
Rough Framing Inspection - Commercial Request Complete 3/10/2005 3/11/2005 03/11/2005
Rough Framing Inspection - Commercial Partial 03/15/2005
Correction
Partial Correction
03/15/2005
STEEL STUD FRAMING @ EXTERIOR WALLS OK TO COVER WHEN READY: SOUTH WALL; NORTH WALL; NORTH STAIRWELL (MID-HEIGHT BRACES TO BE INSTALLED WHEN SCAFFOLDING IS SET FOR SHEATHING); ENSURE BOTTOM FLANGES FULLY SCREWED TO TRACK
Rough Electrical Inspection - Commercial Not Ready 03/18/2005
Correction
Corrective Action Required
03/18/2005
LUMINAIRES IN ENTRANCE CANOPIES ENSURE CABLE ENTRY INTO FIXTURE IS NOT TUAT/STRESSED SOME NOT EXPOSED FOR INSPECTION
Rough Framing Inspection - Commercial Partial 03/18/2005
Correction
Partial Correction
03/18/2005
STEEL STUD FRAMING @ EXTERIOR WALLS OK TO COVER WHEN READY: SOUTH WALL; NORTH WALL; NORTH STAIRWELL; EAST WALL N OF O/H DOORS; ENSURE BOTTOM FLANGES FULLY SCREWED TO TRACK
Correction
Corrective Action Required
03/18/2005
BRICK TIES FOR NEW BRICK FACADE SPOT CHECK: SOME NOT SCREWED SECURE TO STUDS
Rough Plumbing Inspection - Commercial Partial 03/18/2005
Correction
Partial Correction
03/18/2005
FREEZE-PROOF HOSE BIB @ N WALL OK TO COVER WHEN READY PROJECTING THROUGH WALL NO ISSUES NOTED
Rough Electrical Inspection - Commercial Partial 03/23/2005
Correction
Partial Correction
03/23/2005
LUMINAIRES IN ENTRANCE CANOPIES OK TO COVER WHEN READY
Rough Framing Inspection - Commercial Partial 03/24/2005
Correction
Partial Correction
03/24/2005
STEEL STUD FRAMING @ EXTERIOR WALLS OK TO COVER WHEN READY: SOUTH WALL; NORTH WALL; NORTH STAIRWELL; EAST WALL N OF O/H DOORS; ENSURE BOTTOM FLANGES FULLY SCREWED TO TRACK
Correction
Resolved
03/24/2005
SEE TEXT
Correction
Partial Correction
03/24/2005
STEEL STUD FRAMING @ EXTERIOR WALLS OK TO COVER WEST WALL WHEN READY. NOTE: PRIOR TO COVERING, PROVIDE WEATHER RESISTANT CAULK AT AUTO SPRINKLER AND TEST PIPE PENETRATIONS. ALSO, SCREW STUD TO BOTTOM TRACK SOUTH OF PIPES. DO NOT COVER ANY WALLS OF ENTRY CANOPY (NOT READY) ENSURE BOTTOM FLANGES FULLY SCREWED TO TRACK
Rough Framing Inspection - Commercial Request Complete 3/23/2005 3/24/2005 03/24/2005
Rough Plumbing Inspection - Commercial Partial 04/12/2005
Correction
Partial Correction
04/12/2005
FREEZE-PROOF HOSE BIB @ E WALL NEAR GAS METER SEAL WALL PENETRATION BEFORE FINAL INSPECTION PIPING INSIDE WALL + SHUT-OFF VALVE ABOVE CLG
Correction
Resolved
04/12/2005
FREEZE-PROOF HOSE BIB @ N WALL PROJECTING THROUGH WALL
Rough Electrical Inspection - Commercial Partial 04/12/2005
Correction
Partial Correction
04/12/2005
IN-WALL MC CABLE + BOXES @ VESTIBULE 100 OK TO COVER WHEN READY
Underground Electrical Inspection - Commercial Partial 04/15/2005
Correction
Partial Correction
04/15/2005
1/2" PVC CONDUIT S OF S BLDG LINE TO BE COVERED BY SIDEWALK OK TO COVER WHEN READY
Underground Electrical Inspection - Commercial Request Complete 4/14/2005 4/15/2005 04/15/2005
Footing Inspection - Commercial Passed 04/19/2005
Correction
Resolved
04/19/2005
GRADE BEAM @ SOUTH BUILDING WALL
Correction
Resolved
04/19/2005
GRADE BEAM @ NORTH BUILDING WALL
Correction
Resolved
04/19/2005
GRADE BEAM @ EAST BLDG WALL
Correction
Resolved
04/19/2005
GRADE BEAM @ WEST ENTRANCE
Correction
Resolved
04/19/2005
None
Correction
Resolved
04/19/2005
STEP FOOTING DOWN NORTH STAIRWELL
Correction
Resolved
04/19/2005
FOOTING FOR SCREENWALL @ NE CORNER ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Passed 05/03/2005
Correction
Resolved
05/03/2005
GRADE BEAMS AT WEST ENTRANCE VESTIBULE APPROVED PER PLAN
Rough Electrical Inspection - Commercial Passed 05/24/2005
Correction
Resolved
05/24/2005
LUMINAIRES IN ENTRANCE CANOPIES
Correction
Resolved
05/24/2005
IN-WALL MC CABLE + BOXES @ VESTIBULE 100
Correction
Resolved
05/24/2005
ABOVE-CEILING CAN LIGHTS & WIRING @ VESTIBULE 100 NO ISSUES FOUND ALREADY COVERED BUT PARTIALLY VISIBLE
Final Inspection - Commercial Passed 08/16/2005
Correction
Resolved
08/16/2005
Receive Fire Department approval PER N ULLERY 8/16/05
Underground Electrical Inspection - Commercial Passed 08/17/2005
Correction
Resolved
08/17/2005
1/2" PVC CONDUIT S OF S BLDG LINE
Rough Framing Inspection - Commercial Passed 08/17/2005
Correction
Resolved
08/17/2005
STEEL STUD FRAMING @ EXTERIOR WALLS
Correction
Resolved
08/17/2005
BRICK TIES FOR NEW BRICK FACADE
Correction
Resolved
08/17/2005
STEEL STUD FRAMING @ EXTERIOR WALLS
Rough Plumbing Inspection - Commercial Passed 08/17/2005
Correction
Resolved
08/17/2005
FREEZE-PROOF HOSE BIB @ N WALL
Correction
Resolved
08/17/2005
FREEZE-PROOF HOSE BIB @ E WALL NEAR GAS METER
Footing Inspection - Commercial Passed 08/17/2005
Correction
Resolved
08/17/2005
FOOTING FOR SCREENWALL @ NE CORNER
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home