Permit Application Status

B0401940


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0401940
Building Permit - Commercial
Final Completion
CITY OF LEES SUMMIT
PARTIAL COMMERCIAL
FOUNDATION AND UNDERSLAB
10/05/2004
10/07/2004
04/05/2005
06/16/2005
Locations
Contacts
SHAUGHNESSY FICKEL AND SCOTT ARCHITECTS, Address:1150 GRAND BLVD SUITE 400  
TITAN CONSTRUCTION ORGANIZATION, Address:11865 S CONLEY  
CITY OF LEES SUMMIT, Address:PO BOX 1600  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 04/03/2005 10/29/2010
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Correction

Codes Administration - 2003 IBC 1704.1.2 - Report Requirement. Special inspectors shall keep records of inspections. The special inspector shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was done in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If the discrepancies are not corrected, the discrepancies shall be brought to the attention of the building official and to the registered design professional in responsible charge prior to the completion of that phase of the work. A final report documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted at a point in time agreed upon by the permit applicant and the building official prior to the start of work.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $902.00 $902.00 Paid 10/07/2004
24 BLDG Plan Check Fees $35.00 $35.00 Paid 10/07/2004
25 Plumbing Permit Fees $30.00 $30.00 Paid 10/07/2004
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Piers/Caissons Inspection - Commercial Partial 11/03/2004
Correction
Partial Correction
11/03/2004
PREP & PLACEMENT OF DRILLED CONCRETE PIERS ALL ON & SOUTH OF (11); OBSERVED BY TERRACON SPOT-CHECKED BY LSBI
Footing Inspection - Commercial Partial 11/03/2004
Correction
Partial Correction
11/03/2004
INITIAL GRADE BEAM POUR PREP POURED 11/2/04: (J) FROM (1) TO (2.3); (1) FROM (J) TO (G.3); (2) FROM (J) TO (G.7) NOT REQUESTED FOR INSPECT OBSERVED BY TERRACON
Correction
Partial Correction
11/03/2004
CONCRETE GRADE BEAM POUR PREP (J) FROM (2.3) TO (6.3); (2) FROM (G.7) TO (G.3); (5) FROM (J) TO (G); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/05/2004
Correction
Partial Correction
11/05/2004
CONCRETE GRADE BEAM POUR PREP (J): (2.3)TO(6.3); (2):(G.7)TO(G.3); (5):(J)TO(G); (F.5) FROM (4.8) TO (10.3); (4.8) FROM (F.5) TO (E.9); (1) FROM (F) TO (C); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Underslab Plumbing Inspection - Commercial Partial 11/09/2004
Correction
Partial Correction
11/09/2004
THREE FLOOR DRAINS PER AD3-M9 PER P-1.1 OK TO COVER WHEN READY
Footing Inspection - Commercial Partial 11/09/2004
Correction
Resolved
11/09/2004
INITIAL GRADE BEAM POUR PREP POURED 11/2/04: (J) FROM (1) TO (2.3); (1) FROM (J) TO (G.3); (2) FROM (J) TO (G.7) NOT REQUESTED FOR INSPECT OBSERVED BY TERRACON
Correction
Partial Correction
11/09/2004
CONCRETE GRADE BEAM POUR PREP (J): (2.3)TO(6.3); (2):(G.7)TO(G.3); (5):(J)TO(G); (F.5) FROM (4.8) TO (10.3); (4.8) FROM (F.5) TO (E.9); (1) FROM (F) TO (C); (G.4) TO (F.8) x (1.0) TO (2.1); ON (G) FROM (3) TO (4) + (6) TO (7) + (9) TO (10); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/10/2004
Correction
Resolved
11/10/2004
CONCRETE GRADE BEAM POUR PREP (5):(J)TO(G); (F.5) FRM (4.8)TO(10.3); (4.8)FRM(F.5)TO(E.9); (1)FRM(F)TO(C); (G.4)TO(F.8) x (1.0)TO(2.1); ON (G) FRM (3) TO (4) + (6) TO (7) + (9) TO (10); (1) TO (2) x (F) TO (F.7); + (F) FRM (2) TO (4.2); CONT'D (J): (2.3)TO(6.3); (2):(G.7)TO(G.3);
Correction
Partial Correction
11/10/2004
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J) FROM (6.2) TO (8.3); (8) FROM (J) TO (J.3); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
11/10/2004
BASE SLAB @ MECH RM ST-2A
Footing Inspection - Commercial Partial 11/12/2004
Correction
Partial Correction
11/12/2004
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J) FRM (6.2) TO (8.3); (8) FRM (J) TO (J.3); (C) FRM (1.0) TO (4.8); (4.8) FRM (C) TO (C.3); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/15/2004
Correction
Partial Correction
11/15/2004
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J) FRM (6.2) TO (8.3); (8) FRM (J) TO (J.3); (C) FRM (1.0) TO (4.8); (4.8) FRM (C) TO (C.3); (J) FRM (9.3) TO (11.3); (11.0) FRM (G.3) TO (J); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/16/2004
Correction
Partial Correction
11/16/2004
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J)FRM(6.2)TO(8.3);(8)FRM(J)TO(J.3);(C)FRM(1.0)TO(4.8);(4.8)FRM(C)TO (C.3);(J)FRM(9.3)TO(11.3);(11.0)FRM(G.3)TO(J); (J) FRM (8.3) TO (9.4); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
11/16/2004
ELEVATOR PIT BASE SLABS EL-2 PIT; EL-2 PIT OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 11/16/2004
Correction
Partial Correction
11/16/2004
STUB WALL + INTEGRAL PILASTERS PER 5/S3.3 ON (1.0) FROM (F) TO (C); ON (C) FROM (1.0) TO (4.8); ANCHOR BOLTS TO BE PLACED OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/17/2004
Correction
Partial Correction
11/17/2004
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J)FRM(6.2)TO(8.3);(8)FRM(J)TO(J.3);(C)FRM(1.0)TO(4.8);(4.8)FRM(C)TO (C.3);(J)FRM(9.3)TO(11.3);(11.0)FRM(G.3)TO(J); (J) FRM (8.3) TO (9.4); (4.8) FROM (C.3) TO (E.9); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 11/19/2004
Correction
Resolved
11/19/2004
EL-1 & EL-2 ELEVATOR PIT WALLS PLACE WATERSTOP @ KEYWAY OK TO POUR WHEN READY
Underslab Plumbing Inspection - Commercial Not Ready 11/23/2004
Correction
Corrective Action Required
11/23/2004
READINESS FOR INSPECTION PROPERTY LOCKED @ 3:45PM NO ACCESS FOR INSPECTION
Underslab Plumbing Inspection - Commercial Partial 11/29/2004
Correction
Partial Correction
11/29/2004
None ROOF DRAINS APPROVED- (2 LINE TO 5 LINE) 3" LINE IN TERMINATED AT (2 LINE) LOBBY DRAIN APPROVED 2" LINE IN AREA ADM 1.210 SOUTHSIDE BUILDING ROOF DRAIN
Underslab Plumbing Inspection - Commercial Partial 12/03/2004
Correction
Resolved
12/03/2004
THREE FLOOR DRAINS PER AD3-M9 PER P-1.1
Correction
Resolved
12/03/2004
READINESS FOR INSPECTION
Correction
Resolved
12/03/2004
None ROOF DRAINS APPROVED- (2 LINE TO 5 LINE) 3" LINE IN TERMINATED AT (2 LINE) LOBBY DRAIN APPROVED 2" LINE IN AREA ADM 1.210 SOUTHSIDE BUILDING ROOF DRAIN
Correction
Partial Correction
12/03/2004
UNDER-SLAB DOWNSPOUT/STORM SEWER PIPING ALONG (H.2) FROM (5) TO (11.3); OK TO COVER WHEN READY
Correction
Partial Correction
12/03/2004
UNDER-SLAB DWV PIPING RR'S 1.203 & 1.204 + NORTH TO (5); OK TO COVER WHEN READY
Foundation Inspection - Commercial Partial 12/06/2004
Correction
Partial Correction
12/06/2004
STUB WALL + INTEGRAL PILASTERS PER 5/S3.3 ON (1.0) FROM (F) TO (C); ON (C) FROM (1.0) TO (4.8); ON (1.0) FROM (H.8) TO (J); ON (J) FROM (1) TO (5.3); ANCHOR BOLTS TO BE PLACED OK TO POUR WHEN READY
Correction
Resolved
12/06/2004
EL-1 & EL-2 ELEVATOR PIT WALLS PLACE WATERSTOP @ KEYWAY
Underslab Plumbing Inspection - Commercial Partial 12/07/2004
Correction
Partial Correction
12/07/2004
UNDER-SLAB DWV PIPING RR'S 1.203 & 1.204 + 4" W ON (G.2) NORTH TO (5); 4" W ON (G.2) N TO (11.2) + BRANCHES W @ (6.4) & (7.3); OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Partial 12/09/2004
Correction
Partial Correction
12/09/2004
UNDER-SLAB DWV PIPING RR'S 1.203 & 1.204 + 4" W ON (G.2) NORTH TO (5); 4" W ON (G.2) N TO (11.2) + BRANCHES W @ (6.4) & (7.3); W TRUNK ALONG (G.8) FRM (9.2) TO (11.2) + BRANCHES @ RMS 1.164 & 1.165; OK TO COVER WHEN READY
Underslab Electrical Inspection - Commercial Partial 12/13/2004
Correction
Partial Correction
12/13/2004
CONDUIT & BOXES SET IN AGGREGATE BASE (1) TO (4.5) x (G) TO (J); OK TO COVER WHEN READY AREAS INDICATED BELOW
Underslab Electrical Inspection - Commercial Partial 12/15/2004
Correction
Partial Correction
12/15/2004
CONDUIT & BOXES SET IN AGGREGATE BASE (1) TO (4.5) x (G) TO (J); ALL S OF (4.9); OK TO COVER WHEN READY AREAS INDICATED BELOW
Underground Electrical Inspection - Commercial Partial 12/15/2004
Correction
Partial Correction
12/15/2004
ELECTRICAL / DATA / COMMUNICATION ENTRY CONDUIT OK TO COVER WHEN READY UNDER EXT GRADE BEAM INTO RMS 1.157, 1.161, 1.62
Underground Electrical Inspection - Commercial Partial 12/20/2004
Correction
Partial Correction
12/20/2004
ELECTRICAL / DATA / COMMUNICATION ENTRY CONDUIT + FROM J/10 N/NW 75' TO NEAR STORM INLET "A"; OK TO COVER WHEN READY UNDER EXT GRADE BEAM INTO RMS 1.157, 1.161, 1.62
Correction
Partial Correction
12/20/2004
ELECTRICAL SERVICE GROUNDING FROM BLDG ENTRY @ J/10 -- ONE TO TWO DRIVEN GROUND RODS; ONE 75' N TO E OF STORM INLET "A"; 3/0 COPPER CONDUCTOR OK TO COVER WHEN READY
Correction
Resolved
12/20/2004
FOUR 3" CONDUIT FROM XFRMR-1 TO DP-1 OK TO COVER WHEN READY
Underground Electrical Inspection - Commercial Partial 12/23/2004
Correction
Partial Correction
12/23/2004
ELECTRICAL / DATA / COMMUNICATION ENTRY CONDUIT UNDER EXT GB INTO RMS 1.157, 1.161, 1.62; FROM J/10 N/NW 75' TO NEAR ST INLET "A"; DATA CONDUIT EXTENDED ~50' N OF STORM INLET "A"; OK TO COVER WHEN READY
Underslab Electrical Inspection - Commercial Partial 12/23/2004
Correction
Partial Correction
12/23/2004
CONDUIT & BOXES SET IN AGGREGATE BASE (1) TO (4.5) x (G) TO (J); ALL S OF (4.9); ALL N OF (1) TO (8.5); OK TO COVER WHEN READY AREAS INDICATED BELOW
Foundation Inspection - Commercial Partial 01/13/2005
Correction
Partial Correction
01/13/2005
FOUNDATION CAP WALL @ OUTER RADIUS OF CURVED RAMP OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/03/2005
Correction
Partial Correction
02/03/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J)FRM(6.2)TO(8.3);(8)FRM(J)TO(J.3);(C)FRM(1.0)TO(4.8);(4.8)FRM(C)TO (C.3);(J)FRM(9.3)TO(11.3);(11.0)FRM(G.3)TO(J); (J) FRM (8.3) TO (9.4); (4.8) FROM (C.3) TO (E.9); ON (11) FROM (G) TO (G.3); ON (G) FROM (11) TO (13); ON (13) FROM (G) TO (H); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/04/2005
Correction
Resolved
02/04/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J)FRM(6.2)TO(8.3);(8)FRM(J)TO(J.3);(C)FRM(1.0)TO(4.8);(4.8)FRM(C)TO (C.3);(J)FRM(9.3)TO(11.3);(11.0)FRM(G.3)TO(J); (J) FRM (8.3) TO (9.4); (4.8) FROM (C.3) TO (E.9); ON (11) FROM (G) TO (G.3); ON (G) FROM (11) TO (13); ON (13) FROM (G) TO (H); CONT'D
Correction
Partial Correction
02/04/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D ON (F.5) FROM (10.3) TO (12); ON (12) FROM (F.5) TO (E.3); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
02/04/2005
ISOLATED PIER CAP POUR PREP G/14; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/04/2005
Correction
Corrective Action Required
02/04/2005
None GRADE BEAM 11 @ (J LINE) FROM (12 LINE) TO (13 LINE) - APPROVED GRADE BEAM 5 @ (12 LINE) FROM (J LINE) TO (H.8 LINE) - APPROVED OK TO POUR
Footing Inspection - Commercial Partial 02/08/2005
Correction
Resolved
02/08/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D (J)FRM(6.2)TO(8.3);(8)FRM(J)TO(J.3);(C)FRM(1.0)TO(4.8);(4.8)FRM(C)TO (C.3);(J)FRM(9.3)TO(11.3);(11.0)FRM(G.3)TO(J); (J) FRM (8.3) TO (9.4); (4.8) FROM (C.3) TO (E.9); ON (11) FROM (G) TO (G.3); ON (G) FROM (11) TO (13); ON (13) FROM (G) TO (H);CONT'D
Correction
Partial Correction
02/08/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP ON (16) FROM (H.6) TO (G.3); ON (H.6) FROM (16) TO (15.2); REMAINDER OF PERIMETER OF TRASH ENCLOSURE ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/10/2005
Correction
Resolved
02/10/2005
INITIAL GRADE BEAM POUR PREP POURED 11/2/04: (J) FROM (1) TO (2.3); (1) FROM (J) TO (G.3); (2) FROM (J) TO (G.7) NOT REQUESTED FOR INSPECT OBSERVED BY TERRACON
Correction
Resolved
02/10/2005
ELEVATOR PIT BASE SLABS EL-2 PIT; EL-2 PIT
Correction
Resolved
02/10/2005
None GB 11 @ (J) FRM(12)TO(13) GB 5 @ (12) FRM(J)TO(H.8)
Correction
Partial Correction
02/10/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP ON (16) FROM (H.6) TO (G.3); ON (H.6) FROM (16) TO (15.2); REMAINDER OF PERIM OF TRASH ENCL; ON (16) FROM (HG.3) TO (G); ON (G) FROM (16) TO (15); ADJACENT PLANTER ENCLOSURE; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/11/2005
Correction
Resolved
02/11/2005
None (16) FROM (F.5) TO 10' WEST OF (E.1) (F.5) FROM (16) TO (14.7) (F) FROM (16) TO (12.6) OK POUR WHEN READY NORTH SIDE 1B EXT. WALL- GRD BEAM
Underslab Plumbing Inspection - Commercial Partial 02/15/2005
Correction
Partial Correction
02/15/2005
UNDER-SLAB DOWNSPOUT/STORM SEWER PIPING ALONG (H.2) FROM (5) TO (11.3); ALONG (H.2) FROM (11.3) TO OUTSIDE N WALL @ (16.0) + 8" BRANCH ALONG (15.0) TO (H.6); OK TO COVER WHEN READY
Correction
Partial Correction
02/15/2005
UNDER-SLAB DWV PIPING RR'S 1.203 & 1.204 + 4" W ON (G.2) NORTH TO (5); 4" W ON (G.2) N TO (11.2) + BRANCHES W @ (6.4) & (7.3); W TRUNK ALONG (G.8) FRM (9.2) TO (11.2) + BRANCHES @ RMS 1.164 & 1.165;
Underslab Plumbing Inspection - Commercial Partial 02/16/2005
Correction
Partial Correction
02/16/2005
UNDER-SLAB DOWNSPOUT/STORM SEWER PIPING ALONG (H.2) FROM (5) TO (11.3); ALONG (H.2) FROM (11.3) TO OUTSIDE N WALL @ (16.0) + 8" BRANCH ALONG (15.0) TO (H.6); 6" BRANCH ALONG (14.5) FROM 12" @ (H.2) TO (E.8); OK TO COVER WHEN READY
Correction
Partial Correction
02/16/2005
UNDER-SLAB DWV PIPING 4" W ON (G.2) NO TO (5); 4" W ON (G.2) N TO (11.2) + BRANCHES W @ (6.4) & (7.3); W TRUNK ALONG (G.8) FRM (9.2) TO (11.2) + BRANCHES @ RMS 1.164 & 1.165; 4" W ON (G.2) FROM (11) TO (13); JAN 1.150; OK TO COVER WHEN READY RR'S 1.203 & 1.204 +
Footing Inspection - Commercial Partial 02/16/2005
Correction
Partial Correction
02/16/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP ON (16) FROM (H.6) TO (G.3); ON (H.6) FROM (16) TO (15.2); REMAINDER OF PERIM OF TRASH ENCL; ON (16) FROM (HG.3) TO (G); ON (G) FROM (16) TO (15); ADJACENT PLANTER ENCLOSURE; COUNCIL CHAMBER RADIUS WALL FRM (E.3) TO (B.3); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 02/17/2005
Correction
Partial Correction
02/17/2005
STUB FOUNDATION WALL + INTEGRAL PIERS PER 13/S3.4 ON (16) FROM (G) TO (J); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
02/17/2005
STUB FOUNDATION WALL PER 1/S3.4 ON (H.6) FROM (16.0) TO (15.5); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/18/2005
Correction
Partial Correction
02/18/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP ON (16) FROM (H.6) TO (G.3); ON (H.6) FROM (16) TO (15.2); REMAINDER OF PERIM OF TRASH ENCL; ON (16) FROM (HG.3) TO (G); ON (G) FROM (16) TO (15); ADJACENT PLANTER ENCLOSURE; COUNCIL CHAMBER RADIUS WALL COMPLETED; CONT'D ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
02/18/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D ON (15.2) FROM (A) TO (E.1); ON (E.1) FROM (15.2) TO (16); ON (16) FROM (E.1) TO (F); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 02/18/2005
Correction
Resolved
02/18/2005
STUB WALL + INTEGRAL PILASTERS PER 5/S3.3 ON (1.0) FROM (F) TO (C); ON (C) FROM (1.0) TO (4.8); ON (1.0) FROM (H.8) TO (J); ON (J) FROM (1) TO (5.3);
Correction
Resolved
02/18/2005
EL-1 & EL-2 ELEVATOR PIT WALLS
Correction
Resolved
02/18/2005
FOUNDATION CAP WALL @ OUTER RADIUS OF CURVED RAMP
Correction
Partial Correction
02/18/2005
STUB FOUNDATION WALL + INTEGRAL PIERS PER 13/S3.4 ON (16) FROM (G) TO (J);
Correction
Partial Correction
02/18/2005
FOUNDATION WALL PER 4/S3.4 E SIDE OF N ENTRANCE; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Electrical Service Inspection Not Ready 02/22/2005
Correction
Partial Correction
02/22/2005
GROUND JUMPER FROM GRADE BEAM RE-BAR TO ABOVE POUR LINE AT (J/13) FOR CONNECTION TO SUPERSTRUCTURE STEEL
Underslab Electrical Inspection - Commercial Partial 02/22/2005
Correction
Partial Correction
02/22/2005
CONDUIT & BOXES SET IN AGGREGATE BASE (1) TO (4.5) x (G) TO (J); ALL S OF (4.9); ALL N OF (1) TO (8.5); (9.3)-(12.3) x (F.5)-(J); OK TO COVER WHEN READY AREAS INDICATED BELOW
Footing Inspection - Commercial Partial 02/23/2005
Correction
Partial Correction
02/23/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D ON (15.2) FROM (A) TO (E.1); ON (E.1) FROM (15.2) TO (16); ON (16) FROM (E.1) TO (F); ON& W OF (H.6) FROM (12.3) TO (15.2); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/25/2005
Correction
Resolved
02/25/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP REMAINDER OF PERIM OF TRASH ENCL; ON (16) FROM (HG.3) TO (G); ON (G) FROM (16) TO (15); ADJACENT PLANTER ENCLOSURE; COUNCIL CHAMBER RADIUS WALL COMPLETED; CONT'D ON (16) FRM (H.6)TO(G.3); ON(H.6) FRM (16)TO(15.2);
Correction
Resolved
02/25/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D ON(16)FRM(E.1)TO (F); ON& W OF (H.6) FRM (12.3) TO (15.2); ON (16) FROM (A) TO (F); ON (H.6) FROM (16) TO (12.5); ON (J) FROM (13) TO (12.5) INCL BOXOUT & ANGLED WALL BUT EXCL (12.5) FROM (H) TO (J); CONT'D ON(15.2)FRM (A)TO(E.1); ON(E.1)FRM(15.2)TO(16);
Correction
Partial Correction
02/25/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 03/01/2005
Correction
Resolved
03/01/2005
None OK TO POUR COMPLETE NORTHERN FOOTING ON NORTH END OF BUILDING- FROM (F.8) TO (G.6) @ (16.2) LINE AND FROM (16.2) LINE TO (15.7) LINE @ (F.8) HANDI-CAP RAMP
Foundation Inspection - Commercial Partial 03/01/2005
Correction
Resolved
03/01/2005
None WALL APPROVED FROM (H.6) TO (J) @ (12.3) LINE
Underslab Plumbing Inspection - Commercial Partial 03/04/2005
Correction
Partial Correction
03/04/2005
None APPROVED UNDERSLAB FROM (12.6) TO (13.6) FROM (A) LINE TO (J) LINE
Sewer Service Inspection Passed 03/04/2005
Correction
Resolved
03/04/2005
None PLIMBING CONTRACTOR PLACED CLEAN OUTSIDE AND INSIDE OF BUILDING ABOVE REQUIREMENTS OF PRINTS - I FELT THAT THIS ADDITION WAS WARRANTED
Underslab Plumbing Inspection - Commercial Partial 03/08/2005
Correction
Resolved
03/08/2005
UNDER-SLAB DOWNSPOUT/STORM SEWER PIPING ALONG (H.2) FROM (5) TO (11.3); ALONG (H.2) FROM (11.3) TO OUTSIDE N WALL @ (16.0) + 8" BRANCH ALONG (15.0) TO (H.6); 6" BRANCH ALONG (14.5) FROM 12" @ (H.2) TO (E.8); REMAINEDER @ N END OF BLDG OK TO COVER WHEN READY
Correction
Partial Correction
03/08/2005
UNDER-SLAB DWV PIPING 4" W ON (G.2) NO TO (5); 4" W ON (G.2) N TO (11.2) + BRANCHES W @ (6.4) & (7.3); W TRUNK ALONG (G.8) FRM (9.2) TO (11.2) + BRANCHES @ RMS 1.164 & 1.165; 4" W ON (G.2) FROM (11) TO (13); JAN 1.150; 1.129; 1.132; 1.133; 1.143 OK TO COVER WHEN READY RR'S 1.203 & 1.204 +
Correction
Resolved
03/08/2005
None APPROVED UNDERSLAB FROM (12.6) TO (13.6) FROM (A) LINE TO (J) LINE
Foundation Inspection - Commercial Partial 03/09/2005
Correction
Partial Correction
03/09/2005
STUB WALLS @ N END OF BLDG ON (15.3) FROM (C.8) TO (E.1); ON (E.1) FROM (15.3) TO (16); ON (16) FROM (E.1) TO (F.1); ON (F.1) FROM (16) TO (14.9); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 03/11/2005
Correction
Partial Correction
03/11/2005
STUB WALLS @ N END OF BLDG ON (15.3) FROM (C.8) TO (E.1); ON (E.1) FROM (15.3) TO (16); ON (16) FROM (E.1) TO (F.1); ON (F.1) FROM (16) TO (14.9); ON (15.2) FROM (A) TO (C.3) ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
03/11/2005
FOUNDATION WALL AT RADIUS WALL OF COUNCIL CHAMBER FROM (E.2) TO (15.2) ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Underslab Electrical Inspection - Commercial Partial 03/15/2005
Correction
Partial Correction
03/15/2005
CONDUIT & BOXES SET IN AGGREGATE BASE (1) TO (4.5) x (G) TO (J); ALL S OF (4.9); ALL N OF (1) TO (8.5); (9.3)-(12.3) x (F.5)-(J); (12)-(16) x (F.5)-(J); OK TO COVER WHEN READY AREAS INDICATED BELOW
Foundation Inspection - Commercial Partial 03/24/2005
Correction
Partial Correction
03/24/2005
None SHEET S1.2 LINE 16 FROM A TO D.5 BOX AT LINE A X LINE 15.5 (PLANTER WALLS) BOX AT LINE B.5 X LINE 15.5 (PLANTER WALLS)
Footing Inspection - Commercial Partial 03/30/2005
Correction
Resolved
03/30/2005
FOOTING + SHORT WALL ABOVE PER (10) ON S3.5 ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Underslab Electrical Inspection - Commercial Partial 04/06/2005
Correction
Partial Correction
04/06/2005
CONDUIT & BOXES SET IN AGGREGATE BASE (1) TO (4.5) x (G) TO (J); ALL S OF (4.9); ALL N OF (1) TO (8.5); (9.3)-(12.3) x (F.5)-(J); (12)-(16) x (F.5)-(J); COUNCIL CHAMBER AREA OK TO COVER WHEN READY AREAS INDICATED BELOW
Electrical Service Inspection Passed 04/08/2005
Correction
Resolved
04/08/2005
GROUND JUMPER FROM GRADE BEAM RE-BAR TO ABOVE POUR LINE 4/8/05: CAD-WELDED TO STEEL WF COLUMN. THIS INSPECTION OF PART OF ELECT SERVICE SYSTEM NOT FOR RELEASE OF SERVICE. SEE SUPERSTRUCTURE PERMIT. AT (J/13) FOR CONNECTION TO SUPERSTRUCTURE STEEL
Underslab Electrical Inspection - Commercial Partial 04/19/2005
Correction
Partial Correction
04/19/2005
CONDUIT & BOXES SET IN AGGREGATE BASE (1) TO (4.5) x (G) TO (J); ALL S OF (4.9); ALL N OF (1) TO (8.5); (9.3)-(12.3) x (F.5)-(J); (12)-(16) x (F.5)-(J); COUNCIL CHAMBER 1.109; COUNCIL CHAMBER DIAS 1.110; RMS 1.111; 1.113; 1.114; 1.115; OK TO COVER WHEN READY AREAS INDICATED BELOW
Rough Plumbing Inspection - Commercial Partial 06/14/2005
Correction
Partial Correction
06/14/2005
WASTE & VENT PIPING ALL 1ST & 2ND FLOOR FROM (1) TO (8); VISUAL + PRESSURE TEST SUBSYSTEMS LISTED BELOW:
Rough Plumbing Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
WASTE & VENT PIPING
Footing Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
INITIAL GRADE BEAM POUR PREP
Correction
Resolved
06/15/2005
CONCRETE GRADE BEAM POUR PREP
Correction
Resolved
06/15/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D
Correction
Resolved
06/15/2005
BASE SLAB @ MECH RM ST-2A
Correction
Resolved
06/15/2005
ELEVATOR PIT BASE SLABS
Correction
Resolved
06/15/2005
None
Correction
Resolved
06/15/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP
Correction
Resolved
06/15/2005
None
Correction
Resolved
06/15/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D
Correction
Resolved
06/15/2005
CONCRETE GRADE BEAM + INTEGRAL PIER CAP POUR PREP, CONT'D
Correction
Resolved
06/15/2005
None
Correction
Resolved
06/15/2005
FOOTING + SHORT WALL ABOVE PER (10) ON S3.5
Piers/Caissons Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
PREP & PLACEMENT OF DRILLED CONCRETE PIERS OBSERVED BY TERRACON SPOT-CHECKED BY LSBI
Underslab Plumbing Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
THREE FLOOR DRAINS PER AD3-M9
Correction
Resolved
06/15/2005
READINESS FOR INSPECTION
Correction
Resolved
06/15/2005
None
Correction
Resolved
06/15/2005
UNDER-SLAB DOWNSPOUT/STORM SEWER PIPING
Correction
Resolved
06/15/2005
UNDER-SLAB DWV PIPING
Correction
Resolved
06/15/2005
None
Underslab Electrical Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
CONDUIT & BOXES SET IN AGGREGATE BASE
Foundation Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
STUB WALL + INTEGRAL PILASTERS PER 5/S3.3
Correction
Resolved
06/15/2005
EL-1 & EL-2 ELEVATOR PIT WALLS
Correction
Resolved
06/15/2005
FOUNDATION CAP WALL @ OUTER RADIUS OF CURVED RAMP
Correction
Resolved
06/15/2005
STUB FOUNDATION WALL + INTEGRAL PIERS PER 13/S3.4
Correction
Resolved
06/15/2005
STUB FOUNDATION WALL PER 1/S3.4
Correction
Resolved
06/15/2005
FOUNDATION WALL PER 4/S3.4
Correction
Resolved
06/15/2005
None
Correction
Resolved
06/15/2005
STUB WALLS @ N END OF BLDG
Correction
Resolved
06/15/2005
FOUNDATION WALL AT RADIUS WALL OF COUNCIL CHAMBER
Correction
Resolved
06/15/2005
None
Underground Electrical Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
ELECTRICAL / DATA / COMMUNICATION ENTRY CONDUIT
Correction
Resolved
06/15/2005
ELECTRICAL SERVICE GROUNDING
Correction
Resolved
06/15/2005
FOUR 3" CONDUIT FROM XFRMR-1 TO DP-1
Final Inspection - Commercial Passed 06/15/2005
Correction
Resolved
06/15/2005
CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home