Permit Application Status

B0401288


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0401288
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
PARTIAL COMMERCIAL
HOSPITAL FOUNDATION AND STRUCTURE PACKAGE
07/07/2004
07/21/2004
01/17/2005
11/03/2005
Locations
Contacts
JE DUNN CONSTRUCTION  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 01/03/2005 10/29/2010
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - 2000 IBC 1704.1.2 - Special inspectors shall keep records of inspections. The special inspector shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was done in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If the discrepancies are not corrected, the discrepancies shall be brought to the attention of the building official and the registered design professional in responsible charge prior to the completion of that phase of the work. A final report of inspections documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted periodically at a frequency agreed upon by the permit applicant and the building official prior to the start of work.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $1,109.00 $1,109.00 Paid 07/21/2004
24 BLDG Plan Check Fees $38.45 $38.45 Paid 07/21/2004
24 BLDG Permit Fees $7,503.00 $7,503.00 Paid 08/31/2004
24 BLDG Plan Check Fees $125.05 $125.05 Paid 08/31/2004
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Piers/Caissons Inspection - Commercial Partial 08/19/2004
Correction
Partial Correction
08/19/2004
DRILLED PIERS BETWEEN BLDGS A & B FIELD NUMBERED WEST-TO-EAST: 12; 11; 10; 9; INSP BY SEA & TERRACON OK TO POUR WHEN READY
Piers/Caissons Inspection - Commercial Partial 08/30/2004
Correction
Partial Correction
08/30/2004
DRILLED PIERS BETWEEN BLDGS A & B COMPLETE INSP BY SEA & TERRACON FIELD NUMBERED W-TO-E:
Footing Inspection - Commercial Partial 09/01/2004
Correction
Partial Correction
09/01/2004
ELEVATOR PIT SLABS S ELEVATOR -- WALL DOWELL PLACEMENT IN PROGRESS; ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 09/17/2004
Correction
Partial Correction
09/17/2004
NE ELEVATOR PIT SLAB ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
09/17/2004
ELEVATOR PIT SLABS
Rough Framing Inspection - Commercial Partial 09/20/2004
Correction
Partial Correction
09/20/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 09/21/2004
Correction
Partial Correction
09/21/2004
PREP FOR EXTERIOR & INTERIOR GRADE BEAMS SOUTH END APPROVED EARLIER BY KT; (B') FROM (17.3) TO (18.7); (C') FROM (16.7) TO (18.7); (D') FROM (16.7) TO (19); (17) FROM (B.3') TO (D'); (18) FROM (B') TO (D'); (18) FROM (C.3') TO (D'); ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
09/21/2004
NE ELEVATOR PIT SLAB
Correction
Resolved
09/21/2004
ELEVATOR PIT SLABS
Rough Framing Inspection - Commercial Partial 09/21/2004
Correction
Partial Correction
09/21/2004
PREP FOR C.I.P. CONCRETE WALL POUR ON (D') FROM (13) TO (14); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 09/22/2004
Foundation Inspection - Commercial Passed 09/22/2004
Correction
Resolved
09/22/2004
NE ELEVATOR PIT WALLS THEN OK TO POUR WHEN READY RE-BAR NEAR COMPLETE CLEAN + PLACE WATERSTOP
Rough Framing Inspection - Commercial Partial 09/24/2004
Correction
Partial Correction
09/24/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; B'/18; C'/18; C'/17; D'/19; D'/18; D'/17; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 09/30/2004
Correction
Partial Correction
09/30/2004
PREP FOR EXTERIOR & INTERIOR GRADE BEAMS SOUTH END APPROVED EARLIER BY KT; (B') FROM (17.3) TO (18.7); (C') FROM (16.7) TO (18.7); (D') FROM (16.7) TO (19); (17) FROM (B.3') TO (D'); (18) FROM (B') TO (D'); (18) FROM (C.3') TO (D'); 10' EA(4) WAY @ (C')/(19); ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 10/04/2004
Correction
Resolved
10/04/2004
ELEVATOR PIT SLAB @ A'/16.5 OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 10/04/2004
Correction
Partial Correction
10/04/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/1; C/1; D/1; D/2; D/3; D/4; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Underslab Plumbing Inspection - Commercial Failed 10/05/2004
Correction
Corrective Action Required
10/05/2004
UNDER-SLAB DWV @ HOSPITAL-NORTH D'/17.6 TO B.8'/17.6 TO B.9'/17.9 + TO B.8'/19 TO B.5'/19; NOT FOUND IN PERMIT SET COVER AT RISK
Correction
Corrective Action Required
10/05/2004
UNDER-SLAB STORM PIPING @ HOSPITAL-NORTH D'/17.6 TO B.8'/17.6 TO B.9'/17.9; NOT FOUND IN PERMIT SET COVER AT RISK
Rough Framing Inspection - Commercial Partial 10/05/2004
Correction
Partial Correction
10/05/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/1; C/1; D/1; D/2; D/3; D/4; A/1; A/2; A/3; A/4; B/2; B/3; B/4; C/2; C/3; C/4; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 10/06/2004
Correction
Partial Correction
10/06/2004
GRADE BEAM @ WEST WALL OF HOSPITAL-TO-ASC TIE-IN FROM A.1' TO A.8'; INCL INTEGRAL COLUMN FTGS OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 10/11/2004
Correction
Partial Correction
10/11/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/1; C/1; D/1; D/2; D/3; D/4; A/1; A/2; A/3; A/4; B/2; B/3; B/4; C/2; C/3; C/4; A/5; B/5; C/5; D/5; A/6; B/6; C/6; D/6; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
10/11/2004
PREP FOR C.I.P. CONCRETE WALL POUR ON (D') FROM (13) TO (14);
Correction
Partial Correction
10/11/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; B'/18; C'/18; C'/17; D'/19; D'/18; D'/17;
Footing Inspection - Commercial Partial 10/13/2004
Correction
Partial Correction
10/13/2004
ARC GRADE BEAM FROM A/7 TO A'/13 ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 10/14/2004
Correction
Partial Correction
10/14/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; B'/18; C'/18; C'/17; D'/19; D'/18; D'/17; AA'/9.3; AA'/9.5; AA'/10.5; AA'/10.8; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 10/19/2004
Correction
Resolved
10/19/2004
ELEVATOR PIT SLAB @ A'/16.5
Correction
Resolved
10/19/2004
GRADE BEAM @ WEST WALL OF HOSPITAL-TO-ASC TIE-IN
Correction
Resolved
10/19/2004
ARC GRADE BEAM FROM A/7 TO A'/13
Correction
Partial Correction
10/19/2004
PREP FOR EXTERIOR & INTERIOR GRADE BEAMS SOUTH END; (B') FROM (17.3) TO (18.7); (C') FROM (16.7) TO (18.7); (D') FROM (16.7) TO (19); (17) FROM (B.3') TO (D'); (18) FROM (B') TO (D'); (18) FROM (C.3') TO (D'); 10' EA(4) WAY @ (C')/(19); REMAINDER OF EXT & INT GRD BM NORTH OF (14.3); ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 10/21/2004
Correction
Partial Correction
10/21/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/1; C/1; D/1; D/2; D/3; D/4; A/1; A/2; A/3; A/4; B/2; B/3; B/4; C/2; C/3; C/4; A/5; B/5; C/5; D/5; A/6; B/6; C/6; D/6; B/7; C/7; D/7; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
10/21/2004
PREP FOR C.I.P. CONCRETE WALL POUR
Correction
Partial Correction
10/21/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; B'/18; C'/18; C'/17; D'/19; D'/18; D'/17; AA'/9.3; AA'/9.5; AA'/10.5; AA'/10.8; B'/15; C'/15; D'/15; B'/16; C'/16; D'/16; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Suspended Slab Inspection Partial 10/21/2004
Correction
Partial Correction
10/21/2004
PAN SLAB FLOOR DECK - SECOND FLOOR (7) TO (13); PER SEA INSPECTION OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 10/22/2004
Correction
Partial Correction
10/22/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/1; C/1; D/1; D/2; D/3; D/4; A/1; A/2; A/3; A/4; B/2; B/3; B/4; C/2; C/3; C/4; A/5; B/5; C/5; D/5; A/6; B/6; C/6; D/6; B/7; C/7; D/7; AA'/9.3; A/8; B/8; C/8; D/8; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 10/27/2004
Correction
Partial Correction
10/27/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/1; C/1; D/1; D/2; D/3; D/4; A/1; A/2; A/3; A/4; B/2; B/3; B/4; C/2; C/3; C/4; A/5; B/5; C/5; D/5; A/6; B/6; C/6; D/6; B/7; C/7; D/7; AA'/9.3; A/8; B/8; C/8; D/8; D/9; D'/11; C'/10.5; B.8/10.5; A.8/10.5; AA'/9.5; AA'/10.5; AA'/10.8; C'/11; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
10/27/2004
10" x 10" C.I.P. CONC. COLUMNS @ BLDG E-TO-HOSPITAL CONNECTOR 5 ON-LINE @ N WALL; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
10/27/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; B'/18; C'/18; C'/17; D'/19; D'/18; D'/17; AA'/9.3; AA'/9.5; AA'/10.5; AA'/10.8; B'/15; C'/15; D'/15; B'/16; C'/16; D'/16; ENSURE RE-BAR COVERAGE
Footing Inspection - Commercial Partial 10/27/2004
Correction
Partial Correction
10/27/2004
PREP FOR EXTERIOR & INTERIOR GRADE BEAMS S END; (B') FRM (17.3) TO (18.7); (C') FRM (16.7) TO (18.7); (D') FRM (16.7) TO (19); (17) FRM (B.3') TO (D'); (18) FRM (B') TO (D'); (18) FRM (C.3') TO (D'); 10' EA(4) WAY @ (C')/(19); BAL OF EXT & INT GRD BM N OF (14.3); (14) + 6' OF (A),(B),(C) @ (14) ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
10/27/2004
GRADE BEAM EXTENSION BETWEEN BLDGS A & B PER MC 10/25/04 PER DETAILS 19 & 20 DRAWING SHEET S11.2
Rough Framing Inspection - Commercial Partial 10/28/2004
Correction
Partial Correction
10/28/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; B'/18; C'/18; C'/17; D'/19; D'/18; D'/17; AA'/9.3; AA'/9.5; AA'/10.5; AA'/10.8; B'/15; C'/15; D'/15; B'/16; C'/16; D'/16; B'/19; C'/19; ENSURE RE-BAR COVERAGE
Correction
Resolved
10/28/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/1; C/1; D/1; D/2; D/3; D/4; A/1; A/2; A/3; A/4; B/2; B/3; B/4; C/2; C/3; C/4; A/5; B/5; C/5; D/5; A/6; B/6; C/6; D/6; B/7; C/7; D/7; AA'/9.3; A/8; B/8; C/8; D/8; D/9; D'/11; C'/10.5; B.8/10.5; A.8/10.5; AA'/9.5; AA'/10.5; AA'/10.8; C'/11; CONT'D ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
10/28/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL CONT'D D'/12.9; A'/12.9; A'/12; B'/12; C'/12; D'/12; AA'/12; EL CONDUIT @ C'/19 & D'/15; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 10/29/2004
Correction
Partial Correction
10/29/2004
10" x 10" C.I.P. CONC. COLUMNS @ BLDG E-TO-HOSPITAL CONNECTOR 5 ON-LINE @ N WALL; 5 ON-LINE @ S WALL; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
10/29/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL CONT'D D'/12.9; A'/12.9; A'/12; B'/12; C'/12; D'/12; AA'/12; EL CONDUIT @ C'/19 & D'/15; A'/12.9; B'/12.9; C'/12.9; D'/12.9; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 11/03/2004
Correction
Partial Correction
11/03/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15; A'/16; A'/17; A'/18; A'/19; B'/17; B'/18; C'/18; C'/17; D'/19; D'/18; D'/17; AA'/9.3; AA'/9.5; AA'/10.5; AA'/10.8; B'/15; C'/15; D'/15; B'/16; C'/16; D'/16; B'/19; C'/19; A'/14; A'/15; A'/16; A'/17; A'/18; A'/19; B'/14; C'/14; D'/14; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
11/03/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL B/2; B/3; B/4; C/2; C/3; C/4; A/5; B/5; C/5; D/5; A/6; B/6; C/6; D/6; B/7; C/7; D/7; AA'/9.3; A/8; B/8; C/8; D/8; D/9; D'/11; C'/10.5; B.8/10.5; A.8/10.5; AA'/9.5; AA'/10.5; AA'/10.8; C'/11; CONT'D B/1; C/1; D/1; D/2; D/3; D/4; A/1; A/2; A/3; A/4;
Rough Framing Inspection - Commercial Partial 11/05/2004
Correction
Partial Correction
11/05/2004
C.I.P. CONCRETE COLUMNS - 3RD LEVEL B/3; B/4; B/5; B/6; B/7; C/3; C/4; C/5; C/6; C/7; STUB COLUMNS: ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Passed 11/12/2004
Correction
Resolved
11/12/2004
PREP FOR EXTERIOR & INTERIOR GRADE BEAMS S END; (B') FRM (17.3) TO (18.7); (C') FRM (16.7) TO (18.7); (D') FRM (16.7) TO (19); (17) FRM (B.3') TO (D'); (18) FRM (B') TO (D'); (18) FRM (C.3') TO (D'); 10' EA(4) WAY @ (C')/(19); BAL OF EXT & INT GRD BM N OF (14.3); (14) + 6' OF (A),(B),(C) @ (14)
Correction
Resolved
11/12/2004
GRADE BEAM EXTENSION BETWEEN BLDGS A & B
Correction
Resolved
11/12/2004
GRADE BEAM + FOOTING @ A'/17 OK TO POUR WHEN READY
Suspended Slab Inspection Partial 11/15/2004
Correction
Partial Correction
11/15/2004
PAN SLAB FLOOR DECK - 3RD LEVEL FROM (1) TO (7.5); FROM (7.5) TO (13); PER SEA APPROVAL OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 11/15/2004
Correction
Partial Correction
11/15/2004
C.I.P. CONCRETE COLUMNS - 1ST LEVEL A'/15;A'/16;A'/17;A'/18;A'/19;B'/17;B'/18;C'/18;C'/17;D'/19;D'/18;D'/17;AA'/9.3;AA'/9.5;AA'/10.5;AA'/10.8;B'/15;C'/15;D'/15;B'/16;C'/16;D'/16;B'/19;C'/19;A'/14;A'/15;A'/16;A'/17;A'/18;A'/19;B'/14;C'/14;D'/14; CC'/16.5; CC'/16.9; BB'/17.5; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Partial Correction
11/15/2004
10" x 10" C.I.P. CONC. COLUMNS @ BLDG E-TO-HOSPITAL CONNECTOR 5 ON-LINE @ N WALL; 5 ON-LINE @ S WALL; 2 FURTHEST EAST; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 11/17/2004
Correction
Partial Correction
11/17/2004
C.I.P. CONCRETE COLUMNS - 3RD LEVEL B/3; B/4; B/5; B/6; B/7; C/3; C/4; C/5; C/6; C/7; AA'/9.3; AA'/9.5; AA'/10.5; AA'/10.8; A.8/9.5; A.8/10.5; B.8/9.5; B.8/10.5; STUB COLUMNS: ENSURE ALL HAVE MIN 1-1/2" RE-BAR COVERAGE ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 11/23/2004
Correction
Partial Correction
11/23/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL CONT'D D'/12.9; A'/12.9; A'/12; B'/12; C'/12; D'/12; AA'/12; EL CONDUIT @ C'/19 & D'/15; A'/12.9; B'/12.9; C'/12.9; D'/12.9; A'/14; B'/14; C'/14; D'/14; A'/15; B'/15; C'/15; D'/15; A'/16; B'/16; C'/16; D'/16; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 12/02/2004
Correction
Partial Correction
12/02/2004
C.I.P. CONCRETE COLUMNS - 3RD LEVEL B/3; B/4; B/5; B/6; B/7; C/3; C/4; C/5; C/6; C/7; AA'/9.3; AA'/9.5; AA'/10.5; AA'/10.8; A.8/9.5; A.8/10.5; B.8/9.5; B.8/10.5; ALL STUB COLUMNS; A/7; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 12/09/2004
Correction
Partial Correction
12/09/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL CONT'D B'/12;C'/12;D'/12;AA'/12;ELCONDUIT@C'/19&D'/15;A'/12.9;B'/12.9;C'/12.9;D'/12.9;A'/14;B'/14;C'/14;D'/14;A'/15;B'/15;C'/15;D'/15;A'/16;B'/16;C'/16;D'/16; A'/17; B'/17; C'/17; D'/17; B'/18; C'/18; D'/18; CC'/16.5; CC'/16.9; CONT'D.. ENSURE RE-BAR COVERAGE D'/12.9;A'/12.9;A'/12;
Suspended Slab Inspection Partial 12/09/2004
Correction
Partial Correction
12/09/2004
PAN SLAB FLOOR DECK - SECOND FLOOR (7) TO (13); (16.5) TO (19) + CONNECTOR TO BLDG E; PER SEA INSPECTION OK TO POUR WHEN READY
Footing Inspection - Commercial Passed 12/10/2004
Correction
Resolved
12/10/2004
GRADE BEAM + FOOTING @ A'/17
Correction
Resolved
12/10/2004
CAPS ON TWO P-12 PIERS @ CANOPY AT REVOLVER ENTRANCE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 12/10/2004
Correction
Resolved
12/10/2004
C.I.P. CONCRETE COLUMNS - 2ND LEVEL CONT'D B'/12;C'/12;D'/12;AA'/12;CONDUIT@C'/19&D'/15;A'/12.9;B'/12.9;C'/12.9;D'/12.9;A'/14;B'/14;C'/14;D'/14;A'/15;B'/15;C'/15;D'/15;A'/16;B'/16;C'/16;D'/16;A'/17;B'/17;C'/17;D'/17;B'/18;C'/18;D'/18;CC'/16.5;CC'/16.9; A'/19; B'/19; C'/19; D'/19; A'/18; BB'/17.5 ENSURE RE-BAR COVERAGE D'/12.9;A'/12.9;A'/12;
Rough Framing Inspection - Commercial Partial 12/16/2004
Correction
Partial Correction
12/16/2004
C.I.P. CONCRETE COLUMNS - 3RD LEVEL B/3;B/4;B/5;B/6;B/7;C/3;C/4;C/5;C/6;C/7;AA'/9.3;AA'/9.5;AA'/10.5;AA'/10.8; A.8/9.5;A.8/10.5;B.8/9.5;B.8/10.5;ALL STUB COLUMNS; A/7; B'/13.1; C'/13.1; NOT ON PERMIT DRWGS>NOT APPROVED: B'/14; C'/14; B'/15; C'/15; B'/16; C'/16; ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Suspended Slab Inspection Partial 12/22/2004
Correction
Partial Correction
12/22/2004
PAN SLAB FLOOR DECK - 3RD LEVEL FROM (1) TO (7.5); FROM (7.5) TO (13); FROM (13) TO (16.5); FROM (16.5) TO (19); PER SEA APPROVAL OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 01/06/2005
Correction
Resolved
01/06/2005
C.I.P. CONCRETE COLUMNS - 1ST LEVEL C'/17;D'/19;D'/18;D'/17;AA'/9.3;AA'/9.5;AA'/10.5;AA'/10.8;B'/15;C'/15;D'/15;B'/16;C'/16;D'/16;B'/19;C'/19;A'/14;A'/15;A'/16;A'/17;A'/18;A'/19;B'/14;C'/14;D'/14; CC'/16.5; CC'/16.9; BB'/17.5; A'/15;A'/16;A'/17;A'/18; A'/19;B'/17;B'/18;C'/18;
Correction
Resolved
01/06/2005
PREP FOR C.I.P. CONCRETE WALL POUR
Correction
Resolved
01/06/2005
10" x 10" C.I.P. CONC. COLUMNS @ BLDG E-TO-HOSPITAL CONNECTOR
Correction
Partial Correction
01/06/2005
C.I.P. CONCRETE COLUMNS - 3RD LEVEL B/3;B/4;B/5;B/6;B/7;C/3;C/4;C/5;C/6;C/7;AA'/9.3;AA'/9.5;AA'/10.5;AA'/10.8; A.8/9.5;A.8/10.5;B.8/9.5;B.8/10.5; ALL STUB COLUMNS; A/7; B'/13.1; C'/13.1; B'/14; C'/14; B'/15; C'/15; B'/16; C'/16; B'/17; B'/18; C'/17; C'/18; A'/13.1 ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Passed 01/06/2005
Correction
Resolved
01/06/2005
CAPS ON TWO P-12 PIERS @ CANOPY AT REVOLVER ENTRANCE
Correction
Resolved
01/06/2005
CANOPY COLUMN FOOTINGS @ HOSP MAIN ENTRANCE 10 PER S10.2 & S11.1 OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Partial 01/25/2005
Correction
Partial Correction
01/25/2005
C.I.P. CONCRETE COLUMNS - 3RD LEVEL B/3;B/4;B/5;B/6;B/7;C/3;C/4;C/5;C/6;C/7;AA'/9.3;AA'/9.5;AA'/10.5;AA'/10.8; A.8/9.5;A.8/10.5;B.8/9.5;B.8/10.5; ALL STUB COLUMNS; A/7; B'/13.1; C'/13.1; B'/14; C'/14; B'/15; C'/15; B'/16; C'/16; B'/17; B'/18; C'/17; C'/18; A'/13.1 ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 02/02/2005
Correction
Partial Correction
02/02/2005
GRADE BEAM @ MAIN ENTRANCE RE-BAR MODIFICATIONS OVER PIERS PER SEA PER SECTION 13/S11.0 COMPLETE PERIMETER
Footing Inspection - Commercial Passed 11/02/2005
Correction
Resolved
11/02/2005
PREP FOR EXTERIOR & INTERIOR GRADE BEAMS
Correction
Resolved
11/02/2005
ELEVATOR PIT SLAB @ A'/16.5
Correction
Resolved
11/02/2005
GRADE BEAM @ WEST WALL OF HOSPITAL-TO-ASC TIE-IN
Correction
Resolved
11/02/2005
ARC GRADE BEAM FROM A/7 TO A'/13
Correction
Resolved
11/02/2005
GRADE BEAM EXTENSION BETWEEN BLDGS A & B
Correction
Resolved
11/02/2005
GRADE BEAM + FOOTING @ A'/17
Correction
Resolved
11/02/2005
CAPS ON TWO P-12 PIERS @ CANOPY AT REVOLVER ENTRANCE
Correction
Resolved
11/02/2005
CANOPY COLUMN FOOTINGS @ HOSP MAIN ENTRANCE
Correction
Resolved
11/02/2005
GRADE BEAM @ MAIN ENTRANCE
Piers/Caissons Inspection - Commercial Passed 11/02/2005
Correction
Resolved
11/02/2005
DRILLED PIERS BETWEEN BLDGS A & B INSP BY SEA & TERRACON
Underslab Plumbing Inspection - Commercial Passed 11/02/2005
Correction
Resolved
11/02/2005
UNDER-SLAB DWV @ HOSPITAL-NORTH
Correction
Resolved
11/02/2005
UNDER-SLAB STORM PIPING @ HOSPITAL-NORTH
Rough Framing Inspection - Commercial Passed 11/02/2005
Correction
Resolved
11/02/2005
C.I.P. CONCRETE COLUMNS - 1ST LEVEL
Correction
Resolved
11/02/2005
PREP FOR C.I.P. CONCRETE WALL POUR
Correction
Resolved
11/02/2005
C.I.P. CONCRETE COLUMNS - 2ND LEVEL
Correction
Resolved
11/02/2005
10" x 10" C.I.P. CONC. COLUMNS @ BLDG E-TO-HOSPITAL CONNECTOR
Correction
Resolved
11/02/2005
C.I.P. CONCRETE COLUMNS - 2ND LEVEL CONT'D
Correction
Resolved
11/02/2005
C.I.P. CONCRETE COLUMNS - 3RD LEVEL
Suspended Slab Inspection Passed 11/02/2005
Correction
Resolved
11/02/2005
PAN SLAB FLOOR DECK - SECOND FLOOR PER SEA INSPECTION
Correction
Resolved
11/02/2005
PAN SLAB FLOOR DECK - 3RD LEVEL PER SEA APPROVAL
Final Inspection - Commercial Passed 11/02/2005
Correction
Resolved
11/02/2005
CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home