Permit Application Status

B0401133


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0401133
Building Permit - Commercial
Final Completion
PREMIERLIFE REAL ESTATE HOLDING
NEW COMMERCIAL
NEW COMMERCIAL BUILDING
06/18/2004
08/02/2004
01/29/2005
02/07/2005
Locations
Contacts
A L HUBER, Address:10770 EL MONTE  
GASTINGER WALKER HARDEN ARCHITECTS, Address:817 WYANDOTTE  
PREMIERLIFE REAL ESTATE HOLDING, Address:400 NW MURRAY RD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 12/15/2004 10/29/2010
Correction

Fire Department-Egress doors shall be readily openable from the egress side without the use of akey or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
Correction

Fire Department- Where required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. Access to exits shall be marked by readily visible exit signs in cases where the exit or the path of egress travel is not immediately visible to the occupants. Exit sign placement shall be such that no point in an exit access corridor is more than 100 feet (30 480 mm) from the nearest visible exit sign.
Correction

CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - 2000 IBC 1003.3.1.4 - Floor Elevation. There shall be a floor or landing on each side of a door. Such floor or landing shall be at the same elevation on each side of the door. Landings shall be level except for exterior landings, which are permitted to have a slope not to exceed 0.25 unit vertical in 12 units horizontal.
Correction

CA - 2000 IBC 1003.3.1.6 - Thresholds. Thresholds at doorways shall not exceed 0.75 inch in height for sliding doors serving dwelling units or 0.5 inch for other doors. Raised thresholds and floor level changes greater then 0.25 inch at doorways shall be beveled with a slope not greater than one unit vertical in two units horizontal (50-percent slope).
Correction

Fire Department; New and existing buildings shall have approved address numbers, building numbers, placed in a position to be plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background.
Correction

Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-7343.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department- 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection. Exceptions: 1. The supervisory signal at a constantly attended location is not required where duct smoke detectors activate the building’s alarm notification appliances. 2. In occupancies not required to be equipped with a fire alarm system, actuation of a smoke detector shall activate a visible and an audible signal in an approved location. 3. Smoke detector trouble conditions shall activate a visible or audible signal in an approved location and shall be identified as air duct detector trouble.
Correction

CA - 1999 NEC 250-104(a) - Metal water piping. The interior metal water piping system shall be bonded as required in (1), (2), (3), or (4) of this section. The bonding jumper shall be installed in accordance with Section 250-64(a), (b), and (e). The points of attachment of the bonding jumper(s) shall be accessible.
Correction

CA - 1999 NEC 250-104(b) - Metal gas piping. Each aboveground portion of a gas piping system upstream from the equipment shutoff valve shall be electrically continuous and bonded to the grounding electrode system.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

All backflow prevention assemblies must be tested and reports filed with the Lee's Summit Water Utilities Backflow Division (816-969-7636) within 30 days from the date installed.
Correction

Backflow prevention assembly must be located in an accessible location, min. 12" from floor, min. 6" from wall, max. 48" from floor.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

Codes Administration - Copies of the engineered truss package were not provided at the time of permit application.
Correction

CA - 2000 IBC 1704.1.1 - The permit applicant shall submit a statement of special inspections prepared by the registered design professional in responsible charge in accordance with Section 106.1 as a condition for permit issuance. This statement shall include a complete list of materials and work requiring special inspections by this section, the inspections to be performed and a list of the individuals, approved agencies or firms intended to be retained for conducting such inspections.
Correction

CA - 2000 IBC 1704.1.2 - Special inspectors shall keep records of inspections. The special inspector shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was done in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If the discrepancies are not corrected, the discrepancies shall be brought to the attention of the building official and the registered design professional in responsible charge prior to the completion of that phase of the work. A final report of inspections documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted periodically at a frequency agreed upon by the permit applicant and the building official prior to the start of work.
Correction

Fire Derpartment; When fire apparatus access roads or a water supply for fire protection is required to be installed, such protection shall be installed and made serviceable prior to and during the time of construction except when approved alternative methods of protection are provided.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Fees
Paid Fees Amount Paid Owing Date Paid
25 Electrical Permit Fee $120.00 $120.00 Paid 08/02/2004
25 Mechanical Permit Fees $137.50 $137.50 Paid 08/02/2004
25 Plumbing Permit Fees $29.50 $29.50 Paid 08/02/2004
84 Water Meters $600.00 $600.00 Paid 08/02/2004
85 Water Taps $6,835.00 $6,835.00 Paid 08/02/2004
24 BLDG Permit Fees $2,822.00 $2,822.00 Paid 08/02/2004
24 BLDG Plan Check Fees $67.00 $67.00 Paid 08/02/2004
24 BLDG Permit Fees ($2,822.00) ($2,822.00) $0.00 N/A
24 BLDG Plan Check Fees ($67.00) ($67.00) $0.00 N/A
25 Electrical Permit Fee ($120.00) ($120.00) $0.00 N/A
25 Mechanical Permit Fees ($137.50) ($137.50) $0.00 N/A
25 Plumbing Permit Fees ($29.50) ($29.50) $0.00 N/A
84 Water Meters ($600.00) ($600.00) $0.00 N/A
85 Water Taps ($6,835.00) ($6,835.00) $0.00 N/A
24 BLDG Permit Fees $2,822.00 $2,822.00 Paid 08/02/2004
24 BLDG Plan Check Fees $67.00 $67.00 Paid 08/02/2004
25 Electrical Permit Fee $120.00 $120.00 Paid 08/02/2004
25 Mechanical Permit Fees $137.50 $137.50 Paid 08/02/2004
25 Plumbing Permit Fees $29.50 $29.50 Paid 08/02/2004
84 Water Meters $200.00 $200.00 Paid 08/02/2004
85 Water Taps $5,468.00 $5,468.00 Paid 08/02/2004
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Electrical Service Inspection Partial 07/30/2004
Correction
Partial Correction
07/30/2004
TEMPORARY ELECTRICAL SERVICE INSTALLATION 80 AMP RELEASE TEMPORARY SERVICE
Footing Inspection - Commercial Partial 08/06/2004
Correction
Partial Correction
08/06/2004
PERIMETER GRADE BEAM + INTEGRAL COLUMN FOOTINGS (A)/(2.5) SOUTH, THEN WEST TO (C)/(2.8); ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Passed 08/09/2004
Correction
Resolved
08/09/2004
INTERIOR COLUMN FOOTINGS OK TO POUR WHEN READY
Correction
Resolved
08/09/2004
PERIMETER GRADE BEAM + INTEGRAL COLUMN FOOTINGS (A)/(2.5) SOUTH, THEN WEST TO (C)/(2.8); REMAINDER OF PERIMETER ENSURE 3" RE-BAR COVERAGE OK TO POUR WHEN READY
Underslab Plumbing Inspection - Commercial Passed 08/16/2004
Correction
Resolved
08/16/2004
UNDER-SLAB DWV PIPING EXCAVATED; LAID; JOINED; SLOPED TO DRAIN. OK TO COVER WHEN READY PER PERMIT DRWGS
Underslab Electrical Inspection - Commercial Passed 08/17/2004
Correction
Resolved
08/17/2004
UNDER-FLOOR ELECTRICAL CONDUIT MATERIAL & WORKMANSHIP OK TO COVER WHEN READY
Sewer Service Inspection Partial 08/19/2004
Correction
Partial Correction
08/19/2004
SEWER SERVICE INSTALLATION FROM BUILDING ENTRY 100' SW; FROM SMH 120' E; 4" PVC; C.O.'S @ 100' OK TO COVER WHEN READY
Sewer Service Inspection - Commercial Request Complete 8/19/2004 8/19/2004 08/19/2004
Sewer Service Inspection Passed 08/20/2004
Correction
Resolved
08/20/2004
SEWER SERVICE INSTALLATION COMPLETE FROM BUILDING ENTRY TO SMH + FROM SMH NW TO ISLAND FOR FUTURE 4" PVC; C.O.'S @ ~100' OK TO COVER WHEN READY
Sewer Service Inspection - Commercial Request Complete 8/20/2004 8/20/2004 08/20/2004
Underground Plumbing Inspection - Commercial Not Ready 08/30/2004
Correction
Corrective Action Required
08/30/2004
CONNECTION OF ROOF DRAIN PIPING INTO STORM WATER SYSTEM CALL FOR DISCUSS/INSPECT WHEN RESUMING INSTALL
Underground Electrical Inspection - Commercial Passed 09/02/2004
Correction
Resolved
09/02/2004
SECONDARY SERVICE CONDUIT TO BLDG + SITE LIGHTING/SIGN OK TO COVER WHEN READY
Underground Electrical Inspection - Commercial Request Complete 9/1/2004 9/2/2004 09/02/2004
Rough Framing Inspection - Commercial Partial 09/21/2004
Correction
Partial Correction
09/21/2004
None MED GUAGE METAL FRAMING PER 6 S.1 COMPLETE 4 #10 PER STUD IN NORTH WALL OK TO SHEATH WHEN READY PARAPET AND KNEE BRACING METAL FRAMING
Rough Framing Inspection - Commercial Request Complete 9/20/2004 9/21/2004 09/21/2004
Water Service Inspection Passed 09/27/2004
Water Service Inspection - Commercial Request Complete 9/27/2004 9/27/2004 09/27/2004
Gas Service Inspection - Commercial Failed 10/28/2004
Correction
Corrective Action Required
10/28/2004
Gas Test Pressure (IRC) EAST GAUGE HAS 40 PSI. WEST GAUGE HAS 8 PSI. NO ONE ON SIGHT. APPROVED PLANS REQUIRED TO BE ON SIGHT. PROVIDE A LADDER FOR ROOFTOP INSP. OF GAS PIPE
Gas Piping Inspection - Commercial Failed 10/28/2004
Correction
Corrective Action Required
10/28/2004
ACCESS PROVIDE A LADER FOR ROOF TOP INSP. OF GAS PIPE. APPROVED PLANS REQUIRED.
Rough Electrical Inspection - Commercial Failed 10/28/2004
Correction
Corrective Action Required
10/28/2004
NO APPROVED PLANS PAOVIDE APPROVED PLANS ON SIGHT. NO ONE ON SIGHT. UNKNOWN AS WHAT AREA TO INSP.
Miscellaneous Inspection Failed 10/29/2004
Correction
Corrective Action Required
10/29/2004
See Comment NOTE: VERTICLE PVC LINES ALONG EXTERIOR WALLS ARE JOINED WITH "FERNCO" TYPE FITTINGS. THESE JOINTS MUST BE ARE GLUED
Gas Piping Inspection - Commercial Failed 11/03/2004
Correction
Resolved
11/03/2004
ACCESS
Correction
Corrective Action Required
11/03/2004
DEBRIS & MATERIAL LEFT ON ROOF SURFACE REMOVE ALL METAL PRIOR TO FINAL INSPECTION
Correction
Corrective Action Required
11/03/2004
SLIP SHEETS UNDER PIPE SUPPORT BLOCKS TO PROTECT ROOF MEMBRANE NOT ADHERED TO BLOCKS WILL NOT STAY IN PLACE
Correction
Corrective Action Required
11/03/2004
PIPE SUPPORT BLOCK CONTACT WITH ROOF SOME NOT IN CONTACT WITH ROOF SURFACE
Correction
Corrective Action Required
11/03/2004
SUPPORT OF RIGID STEEL PIPING ENSURE ALL SPANS ARE WITHIN TABLE MAXIMUMS HORIZONTAL RUNS IFGC TABLE 415.1
Gas Service Inspection - Commercial Failed 11/03/2004
Correction
Resolved
11/03/2004
Gas Test Pressure (IRC) HELD STEADY AT >= 30 PSI FOR > 20 MIN
Correction
Corrective Action Required
11/03/2004
PERMIT DRAWINGS NO INSPECTION APPROVALS WITHOUT PERMIT DRAWINGS NOT FOUND ON SITE LSCO SEC 7-142; IBC 106
Gas Service Inspection - Commercial Passed 11/04/2004
Correction
Resolved
11/04/2004
Gas Test Pressure (IRC) RELEASE 2 GAS SERVICES HELD STEADY AT >= 30 PSI FOR > 20 MIN
Correction
Resolved
11/04/2004
PERMIT DRAWINGS
Electrical Service Inspection Partial 11/23/2004
Correction
Resolved
11/23/2004
TEMPORARY ELECTRICAL SERVICE INSTALLATION
Correction
Partial Correction
11/23/2004
ELECTRICAL SERVICE INSTALLATION PANEL "A" FOR 401 ONLY SERVICE TO PANEL "B" YET TO BE APPROVED + HOUSE METER "H" RELEASE TWO SERVICES
Electrical Service Inspection Passed 12/03/2004
Correction
Resolved
12/03/2004
ELECTRICAL SERVICE INSTALLATION TO PANEL "B" RELEASE SERVICE
Correction
Resolved
12/03/2004
ELECTRICAL SERVICE INSTALLATION PANEL "A" FOR 401 ONLY + HOUSE METER "H"
Gas Piping Inspection - Commercial Not Ready 12/22/2004
Correction
Corrective Action Required
12/22/2004
ACCESS TO ROOFTOP GAS PIPING NOT FOUND
Occupancy Inspection - Codes Commercial Not Ready 12/23/2004
Correction
Corrective Action Required
12/23/2004
ROOFTOP FINAL INSPECTION ADHERE ISOLATION PADS TO BOTTOM OF GAS PIPE SUPPORT BLOCKS CLEAR ALL METAL DEBRIS & EXCESS MATERIAL +
Gas Piping Inspection - Commercial Passed 12/29/2004
Correction
Resolved
12/29/2004
ACCESS TO ROOFTOP GAS PIPING NOT FOUND
Correction
Resolved
12/29/2004
DEBRIS & MATERIAL LEFT ON ROOF SURFACE REMOVE ALL METAL PRIOR TO FINAL INSPECTION
Correction
Resolved
12/29/2004
SLIP SHEETS UNDER PIPE SUPPORT BLOCKS TO PROTECT ROOF MEMBRANE NOT ADHERED TO BLOCKS WILL NOT STAY IN PLACE
Correction
Resolved
12/29/2004
PIPE SUPPORT BLOCK CONTACT WITH ROOF SOME NOT IN CONTACT WITH ROOF SURFACE
Correction
Resolved
12/29/2004
SUPPORT OF RIGID STEEL PIPING HORIZONTAL RUNS IFGC TABLE 415.1
Rough Framing Inspection - Commercial Passed 12/29/2004
Correction
Resolved
12/29/2004
None
Underground Plumbing Inspection - Commercial Passed 12/29/2004
Correction
Resolved
12/29/2004
CONNECTION OF ROOF DRAIN PIPING INTO STORM WATER SYSTEM
Miscellaneous Inspection Passed 12/29/2004
Correction
Resolved
12/29/2004
See Comment
Occupancy Inspection - Codes Commercial Failed 12/29/2004
Correction
Corrective Action Required
12/29/2004
Receive Public Works Approval UNDER SEPARATE COVER
Correction
Corrective Action Required
12/29/2004
Receive Planning & Development Approval UNDER SEPARATE COVER. CONTACT PLANNING & DEVELOPMENT FOR APPROVAL.
Correction
Corrective Action Required
12/29/2004
GAS PIPING BLOCKS NOT SECURED TO ROOFTOP. ISOLATE DISSIMILAR METALS USED FOR SECURING PIPING. CHECK SPANS FOR SUPPORT PER IFGC. ROOFTOP
Correction
Partial Correction
12/29/2004
ROOF DRAINAGE TO UNDERGOUND STORM ????? CHECK WITH JOHN BORNS.
Correction
Corrective Action Required
12/29/2004
LABEL GAS SERVICE PER ADDRESS
Correction
Corrective Action Required
12/29/2004
LABEL DISCONNECTS LABEL MAIN DISCONNECTS PER TENANT AND OTHER DISCONNECTS PER USE.
Correction
Corrective Action Required
12/29/2004
Receive Water Utilities Approval OBTAIN IRRIGATION PERMIT AND SUBMIT ALL BACKFLOW REPORTS FOR UNIT TO WATER UTILITIES
Occupancy Inspection - Codes Commercial Failed 01/05/2005
Correction
Corrective Action Required
01/05/2005
GAS PIPING BLOCKS NOT SECURED TO ROOFTOP. CHECK SPANS FOR SUPPORT PER IFGC. ROOFTOP
Rough Electrical Inspection - Commercial Passed 01/31/2005
Correction
Resolved
01/31/2005
NO APPROVED PLANS
Occupancy Inspection - Codes Commercial Partial 01/31/2005
Correction
Resolved
01/31/2005
Receive Public Works Approval
Correction
Resolved
01/31/2005
Receive Planning & Development Approval
Correction
Resolved
01/31/2005
GAS PIPING
Correction
Resolved
01/31/2005
ROOF DRAINAGE TO UNDERGOUND STORM
Correction
Resolved
01/31/2005
LABEL GAS SERVICE PER ADDRESS
Correction
Resolved
01/31/2005
LABEL DISCONNECTS
Correction
Resolved
01/31/2005
Receive Water Utilities Approval PER B BOICE 1/31/05
Correction
Partial Correction
01/31/2005
CLOSED UNDER FINAL BUILDING
Final Inspection - Commercial Passed 01/31/2005
Correction
Resolved
01/31/2005
CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home