| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Internal Plan Review (Res)
|
Approved
|
06/02/2004
|
10/29/2010
|
|
|
|
|
|
Correction
CA - A Certificate of Occupancy will not be issued for a tenant finish until a minimum of a Temporary Occupancy has been issued for the shell building.
|
|
|
Correction
CA - 2000 IBC 1108.4 - Where kitchen, kitchenettes and wet bars are provided in accessible spaces or rooms, they shall be accessible in accordance with ICC/ANSI A117.1.
|
|
|
Correction
CA - 2000 IBC 803.5.1 - Textile wall coverings. Textile wall coverings shall have a Class A flame spread index in accordance with ASTM E 84 and be protected by automatic sprinklers installed in accordance with Section 903.3.1.1 or Section 903.3.1.2 or the covering shall meet the criteria of Section 803.5.1.1 or Section 803.5.1.2 when tested in the manner intended for use in accordance with NFPA 265 using the product mounting system, including adhesive.
|
|
|
Correction
Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance
testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-7343.
|
|
|
Correction
Fire Department; Construction documents for fire alarm systems shall be submitted for review
and approval prior to system installation. Documents shall bear a State of Missouri architect/engineers seal..Construction documents shall include, but not be limited to, all of the following:
1. A floor plan.
2. Locations of alarm-initiating and notification appli-
ances.
3. Alarm control and trouble signaling equipment.
4. Annunciation.
5. Power connection.
6. Battery calculations.
7. Conductor type and sizes.
8. Voltage drop calculations.
9. Manufacturers, model numbers and listing informa-
tion for equipment, devices and materials.
10. Details of ceiling height and construction.
11. The interface of fire safety control functions.
|
|
|
Correction
Fire Department- 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection.
Exceptions:
1. The supervisory signal at a constantly attended location is not required where duct smoke detectors activate the building’s alarm notification appliances.
2. In occupancies not required to be equipped with a fire alarm system, actuation of a smoke detector shall activate a visible and an audible signal in an approved location.
3. Smoke detector trouble conditions shall activate a visible or audible signal in an approved location and shall be identified as air duct detector trouble.
|
|
|
Correction
Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
|
|
|
Correction
Fire Department: Fire protection systems shall be maintained in accordance with the original installation standards for that system. Required fire protection systems shall be extended, altered, or augmented as necessary to maintain and continue pro-tection whenever the building is altered, remodeled or added to.
|
|
|
Correction
Fire Department; The required fire-resistance rating of fire-resistance-rated construction (including walls, fire stops, shaft enclosures, partitions and floors) shall be maintained. Such elements shall be properly repaired, restored or replaced when damaged, altered, breached or penetrated. Openings made therein for the passage of pipes, electrical conduit, wires, ducts, air transfer openings, and holes made for any reason shall be protected with approved methods capable of resisting the passage of smoke and fire. Openings through fire-resistance rated assemblies shall be protected by self-closing or automatic-
closing doors of approved construction meeting the fire protection requirements for the assembly.
|
|
|
Correction
CA - 1999 NEC 250-104(a) - Metal water piping. The interior metal water piping system shall be bonded as required in (1), (2), (3), or (4) of this section. The bonding jumper shall be installed in accordance with Section 250-64(a), (b), and (e). The points of attachment of the bonding jumper(s) shall be accessible.
|
|
|
Correction
Fire Department; New and existing buildings shall have approved address numbers, building numbers, placed in a position to be plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background.
|
|
|
Correction
CA - 2000 IBC 1108.12.3 - Point of sales and service counters. Where counters are provided for sales or distribution of goods or services, at least one of each type provided shall be accessible. Where such counters are dispersed throughout the building or facility, the accessible counters shall also be dispersed.
|
|
|
Correction
CA - 2000 IBC 1109.1 - Required accessible elements shall be identified by the International Symbol of Accessiblity at the locations listed in Section 1109.1.
1. Not applicable as the zoning ordinance is more restrictive.
2. Accessible passenger loading zones.
3. Accessible areas of refuge required by Section 1103.2.13.5.
4. Accessible rooms where multi single-user toilet or bathing rooms are clustered at a single location.
5. Accessible entrances where not all entrances are accessible.
6. Accessible check-out aisles where not all aisles are accessible. The sign, where provided, shall be above the check-out aisle in the same location as the check-out aisle number or type of check-out identification.
7. Unisex toilet and bathing rooms.
8. Accessible dressing, fitting, and locker rooms where not all such rooms are accessible.
|
|
|
Correction
CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
|
|
|
Correction
CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
|
|
|
Correction
CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
|
|
|
Correction
CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
|
|
|
Correction
CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
|
|
|
Correction
CA - 2000 IPC 504.6.1 - Discharge. The releif valve shall discharge full size to a safe place of disposal such as a floor, outside the building, or an indirect waste receptor. The discharge pipe shall not have any trapped sections and shall havve a visible air gap or air gap fitting located in the same room as the water heater. The discharge shall be installed ina manner that does not cause personal injury to occupants in the immediate area or structural damage to the building.
|
|
|
Correction
CA - A finish schedule was not provided.
|
|
|
Correction
CA - Construction Note 1 on Sheet A2.1 indicates that there are details on the reception counters but none are provided.
|
|
|
Correction
CA - A door schedule is not provided.
|
|
|
Correction
Fire Department- Egress doors shall be readily openable from the egress side without the use of a key or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
|
|
|
Correction
CA - ANSI A117.1-1998 404.2.7 - Door Hardware. Handles, pulls, latches, locks, and other operable parts on accessible doors shall have a shape that is easy to grasp with one hand and does not require tight grasping, pinching, or twisting of the wrist to operate. Such hardware shall be 34 inches minimum and 48 inches maximum above the floor or ground. Where sliding doors are in the fully open position, operating hardware shall be exposed and usable from both sides.
|
|
|
Correction
CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
|
|
|
Correction
CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
|
|
|
Correction
CA - 2000 IPC 504.7.2 - Pan drain terminiation. The pan drain shall extend full-size and terminate over suitably located indirect waste receptor or floor drain or extend to the exterior of the building and terminate not less than 6 inches (152 mm) and not more than 24 inches (610 mm) above the adjacent ground surface.
|
|
|
Correction
CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
|
|
|
Correction
CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
|
|
|
Correction
P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
|
|
|
|