Review Type |
Outcome |
Est. Completion Date |
Completed |
Internal Plan Review (Res)
|
Approved
|
03/28/2004
|
10/29/2010
|
|
|
|
Correction
CA - The Final Development Plan must be approved prior to issuing full building permits.
|
|
Correction
CA - 2000 IBC 1003.3.3.11 - Handrails. Stairways shall have handrails on each side. Handrails shall be adequate in strength and attachment in accordance with Section 1607.7.
|
|
Correction
CA - 2000 IBC 1003.3.3.11.1 - Handrail Height. Handrail height, measured above stair tread nosing, or finish surface of ramp slope, shall be uniform, not less than 34 inches and not more than 38 inches.
|
|
Correction
CA - 2000 IBC 1003.3.3.11.5 - Handrail extension. Handrails shall return to a wall, guard or the walking surface or shall be continuous to the handrail of an adjacent stair flight. Where handrails are not continous between flights, the handrails shall extend horizontally at least 12 inches beyond the top riser and continue to slope for the depth of one tread beyond the bottom riser.
|
|
Correction
CA - 2000 IBC 1003.3.1.4 - Floor Elevation. There shall be a floor or landing on each side of a door. Such floor or landing shall be at the same elevation on each side of the door. Landings shall be level except for exterior landings, which are permitted to have a slope not to exceed 0.25 unit vertical in 12 units horizontal.
|
|
Correction
CA - 2000 IBC 1003.3.1.6 - Thresholds. Thresholds at doorways shall not exceed 0.75 inch in height for sliding doors serving dwelling units or 0.5 inch for other doors. Raised thresholds and floor level changes greater then 0.25 inch at doorways shall be beveled with a slope not greater than one unit vertical in two units horizontal (50-percent slope).
|
|
Correction
Fire Department; New and existing buildings shall have approved address numbers, building numbers, placed in a position to be plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background.
|
|
Correction
Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
|
|
Correction
P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
|
|
Correction
A note should be provided indicating a Reduce Pressure Zone (RPZ) principal backflow prevention device will be placed inside the building on the domestic water service line prior to any point of use.
|
|
Correction
CA - 1999 NEC 250-104(b) - Metal gas piping. Each aboveground portion of a gas piping system upstream from the equipment shutoff valve shall be electrically continuous and bonded to the grounding electrode system.
|
|
Correction
CA - 1999 NEC 250-104(a) - Metal water piping. The interior metal water piping system shall be bonded as required in (1), (2), (3), or (4) of this section. The bonding jumper shall be installed in accordance with Section 250-64(a), (b), and (e). The points of attachment of the bonding jumper(s) shall be accessible.
|
|
Correction
CA - 2000 IPC 312.1 - Required tests. The permit holder shall make the applicable test prescribed in Sections 312.2 through 312.9 to determine compliance with the provisions of this code. The permit holder shall give reasonable advance notice to the code official when the plumbing work is ready for tests. The equipment, material, power and labor necessary for the inspection and test shall be furnished by the permit holder and the permit holder shall be responsible for determining that the work will withstand the test pressure prescribed in the following tests. All plumbing system piping shall be tested with either water or air. After the plumbing fixtures have been set and their traps filled with water, the entire drainage system shall be submitted to final tests. The code official shall require the removal of any cleanouts if necessary to ascertain if the pressure has reached all parts of the system.
Note: Testing of the plumbing system is not required to be witnessed by the Codes Administration Staff with the exception of gas piping.
|
|
Correction
CA - 2000 IPC 308.5 - Pipe shall be supported in accordance with Table 308.5.
|
|
Correction
CA - 2000 IBC 920.2 - Support. Suspended-type unit heaters shall be supported by elements that are designed and constructed to accomodate the weight and dynamic loads. Hangers and brackets shall be of noncombustible material. Suspended-type oil-fired unit heaters shall be installed in accordance with NFPA 31.
|
|
Correction
CA - 2000 IMC 920.1 - General. Unit heaters shall be installed in accordance with the listing and the manufacturer's installation instructions. Oil-fired unit heaters shall be tested in accordance with UL 731.
|
|
Correction
Fire Department; Extension cords and flexible cords shall not be a substitute for permanent wiring. Extension cords and flexible cords shall not be affixed to structures, extended through walls, ceilings or floors, or under doors or floor cove-ings, nor shall such cords be subject to environmental damage
or physical impact.
|
|
Correction
CA - 2000 IBC 1209.2 - Walls within 2 feet of urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture.
|
|
Correction
CA - 2000 IBC 1003.3.3.3 - Stair riser heights shall be 7 inches maximum and 4 inches minimum. Stair tread depths shall be 11 inches minimum. The riser height shall be measured vertically between the leading edges of adjacent treads. The tread depth shall be measured horizontally between the vertical planes of the foremost projection of adjacent treads and at right angle to the tread's leading edge.
|
|
Correction
CA - Erosion control devices shall be installed and maintained throughout the construction process in accordance with the City of Lee's Summit Design and Construction Manual. Failure to install or maintain erosion control devices may result in inspections not being performed, stop work orders being issued or court charges/action may be taken.
|
|
Correction
CA - Information was not provided on the water heater to be installed.
|
|
Correction
CA - Information is not provided on the boiler unit to be installed.
|
|
Correction
Fire Department- The non-use of hazardous materials will be verified at final inspection.
|
|
Correction
CA - ANSI A117.1-1998 404.2.7 - Door Hardware. Handles, pulls, latches, locks, and other operable parts on accessible doors shall have a shape that is easy to grasp with one hand and does not require tight grasping, pinching, or twisting of the wrist to operate. Such hardware shall be 34 inches minimum and 48 inches maximum above the floor or ground. Where sliding doors are in the fully open position, operating hardware shall be exposed and usable from both sides.
|
|
Correction
Backflow prevention assembly must be located in an accessible location, min. 12" from floor, min. 6" from wall, max. 48" from floor.
|
|
Correction
All backflow prevention assemblies must be tested and reports filed with the Lee's Summit Water Utilities Backflow Division (816-969-7636) within 30 days from the date installed.
|
|
|